DAILY ACTIVITIES REPORT

CLIENT : SMGP DATE : 10 Juli 2017


CONTRACTOR : PT. Cipta Bangun Nusantara REPORT NO. : 28/DAR/CBN-SMGP/VII/2017
PROJECT : Sorik Marapi WORKING HOUR : Hours
CONTRACT NO : CODE AREA : SM-A & SM-E
WEATHER 07:00-08:00 08:00-09:00 09:00-10:00 10:00-11:00 11:00-12:00 12:00-13:00 13:00-14:00 14:00-15:00 15:00-16:00 16:00-17:00 17:00-18:00
Clear
Cloudy
Tiny Rain
Heavy Rain
PRODUCTION
NO. TODAY ACTIVITIES NO. TOMORROW ACTIVITIES PLAN
start date finish date TODAY Total day
HSE
1
Monitoring Land Slide E 200
Safety briefing before start work
1. Continue 2 Monitoring Drainage Land slide E 200

3 Flow test A -103 to atmohperic separator

CIVIL WORK: 4 Well A-105 & 106 waitting fitting 12"


Fabricate of pipe support for flow testingg line 105 & 106 at
1 Land Slide SM-E200 Continue 5 CBN work shop

Monitoring Land Slide well Pad E-200 Continue


6 Fabricate pipe support for LECM - A 104
Monitoring and repair drainage land slide E 200 Continue 7 Fabricte 12" p

WELL TESTING A -103

1 Monitoring

1.1 Take sampling brine at weir box, quenching separator

1.2 Take sampling NCG, brine and steam Condensate


continue
1.3 Take sampling brine at weir box

Download data WHP well SM-A 104 & stroking +greasing valve in
1.4
the flow line pad A
Compare WHP Well SM-A 104 with Madge Tech and Pressure
1.5 Gauge

1.6 Download data WHP Well SM - A & Stand By location

1.7 Monitoring WHP Well A 101,102, 104 & 105 after Well A 104 shsut in Continue

MECHANICAL & PIPELINE WORK

2 Rebuilt scafolding A-105 for PT Survey Tiger - SMGP Done


3 Fabricate pipe support for welltesting line 105 continue

4 Moving 24" pipe from base camp for under ground 104 LECM done

5 Pumping at underground pit A-103 before


6 Fabricate pipe support for welltesting line A 106
NO. TOOLS QTY
7 Fabricate pipe support for weltesting line a - 104 LECM

8 1 Scafolding

2 Strinking Wrench

Big Hammer
3

4 Safety Body Harness

5 infra red meter

6 Ph meter

Body Harness
7
Laptop for download data
8

Pressure Gauge
9
NUMBER
NO. DETAIL MANPOWER
Overall Previous Today

1 Leader + supervisor 1 1 1

2 QC 1 1 1

3 Logistik 1 1 1

4 Welder 2 2 2

5 Pipe Fitter 2 2 2

6 General Labour 6 6 6

7 HSE 2 2 2

8 Project Control 1 1 1

9 Material Man 2 2 2

10 Well test 6 6 6

11 sampling 1 1 1

12 Time Keeper 1 1 1

Total 26

NO. EQUIPMENT UNIT QTY NO. MATERIAL UNIT QTY

1 Welding truck UNIT 1 1. welding root 7018 10 Kgr

2 bom truck unit 1 2 acytelin 2 Btl

3 truck (engkel) unit 1 3 Oksigen 3 Btl

4 Welding Machine unit 3 4 argo stick

5 Cutting rools unit 1 5 Grinding disc and cutting disc 20 Ea

6 Tools set welder Set 3

Tools set fitter set 3


Mon

Attachment Photos

All service company, coordination meeting and safety briefing before work activity

Continue flow test well - A 103 take sample and monitoring weir box flow test - A 103
Preparation pipes 12" for A - 105, 104 LECM and moving 24' pipe from base camp to well pad A for chasing ander ground 104 LECM
Land slide E 200 monitoring Drainage land slide E 200 monitoring

Fabricate of pipe support for well A-105 and 106 Fabricate of pipe support for A 104 LECM

TITTLE SIGNATURE DATE

Pepared by : Admin Devi Anike Putri Lubis 10 July 17

Reviewed by : Project Manager Agus Gunawan 10-Jul-17