Académique Documents
Professionnel Documents
Culture Documents
MANUAL
The Table of Contents list shows that the Hayward Tyler Manuals are for guidance
manual is divided into sections. Paragraph only and we reserve the right to update,
references are consecutive throughout each revise and modify this manual in accordance
section, and are preceded by the with our continuous research and
appropriate section number. For example development programme.
6.1. designates:-
Revised manuals will not automatically be
Section 6, Commissioning. issued, however, should they be required,
6.1. Pre-Start Check List. Hayward Tyler may be contacted and
arrangements can be made.
The major illustrations of the Pump and
Motor are included at the rear of Section 8.
Additional illustrations of particular features
are incorporated in the text.
REVISION HISTORY
CONTACT DETAILS
Hayward Tyler Ltd.
1 Kimpton Road
Luton
Bedfordshire
ENGLAND
LU1 3LD
Telephone :-
+44 (0) 1582 731144
Fax :-
+44 (0) 1582 452198
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -i-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
WARRANTY Hayward Tyler is committed to delivering
The unit(s) is/are subject to a warranty as excellent aftersales service. As part of the
specified within the original sales contract. warranty process, all claims will be
The unit warranty does not cover motor acknowledged within 1 working day and
burnouts due to internal dry running, actioned within 5 working days from initial
insufficient cooling, lightening strikes, notification. In order to assist Hayward Tyler
improper installation, control or operation. In to address the claim effectively, please
the unlikely event of a unit ceasing to provide the following information when
operate normally please refer in the first reporting a warranty issue:
instance to the fault matrix included in this
manual. If the issue still cannot be resolved Unit Serial Number
then contact Hayward Tyler using the details Primary contact details
below: Details of the issue including the date issue
was first observed
HTS Customer Services Coordinator Commissioning Date
Hayward Tyler Ltd (Services) Last Service Date (Service Agency)
1 Kimpton Road Previous Warranty Claims
Luton
Bedfordshire Dependant on the nature of the fault, it may
ENGLAND be necessary to strip and inspect the unit
LU1 3LD prior to issuing a report. Any work
undertaken on a unit that has failed under
Telephone: +44 1582 731144 circumstances not deemed to be covered
Email: warranty@haywardtyler.com under warranty will be chargeable to the unit
end user.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - ii -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 1 Table of Contents
1 Table Of Contents
FOREWORD ..................................................................................................................................... i
REVISION HISTORY ........................................................................................................................ i
CONTACT DETAILS ......................................................................................................................... i
WARRANTY ..................................................................................................................................... ii
1 Table Of Contents ................................................................................................................... 1
2 Technical Data ........................................................................................................................ 3
2.1 General........................................................................................................................... 3
2.2 Pump / Motor Design Characteristics............................................................................. 3
2.3 Operating Points............................................................................................................. 3
2.4 Clearances & Settings .................................................................................................... 4
2.5 Instrumentation............................................................................................................... 4
2.6 Torque Loading .............................................................................................................. 4
2.7 Weights (Approximate) ................................................................................................... 4
3 Storage.................................................................................................................................... 9
3.1 Environment ................................................................................................................... 9
3.2 Storage General .......................................................................................................... 9
3.3 Inhibitor........................................................................................................................... 9
3.4 Heat Exchanger............................................................................................................ 11
3.5 Exterior Surfaces .......................................................................................................... 11
3.6 Standard Storage Checks For Storage Up To 3 Years................................................ 11
3.7 Storage Periods Greater Than Three Years ................................................................ 12
3.8 Preparation For Storage After Use............................................................................... 12
3.9 Inspection Record Card ............................................................................................... 14
4 Description ............................................................................................................................ 16
4.1 General......................................................................................................................... 16
4.2 Pump ............................................................................................................................ 16
4.3 Motor ............................................................................................................................ 16
4.4 Terminal Boxes ............................................................................................................ 20
4.5 Heat Exchanger............................................................................................................ 20
4.6 Alarm Systems ............................................................................................................. 20
5 Installation ............................................................................................................................. 21
5.1 General......................................................................................................................... 21
5.2 Pump Case Installation (Fig 5.1) .................................................................................. 22
5.3 Preparation For Motor Installation ................................................................................ 23
5.4 Motor Installation (Fig 5.2) ........................................................................................... 23
5.5 Fitting The Heat Exchanger (Customer supplied) ........................................................ 27
5.6 Filling The Circulator With Boiler Cold ......................................................................... 27
5.7 Hydrotesting Boiler With Circulator Installed ................................................................ 28
5.8 Electrical Connections .................................................................................................. 30
5.9 Motor Protection ........................................................................................................... 31
6 Commissioning ..................................................................................................................... 33
6.1 Pre-Start Check ............................................................................................................ 33
6.2 Initial Starting - Cold Boiler Condition .......................................................................... 33
6.3 Stopping ....................................................................................................................... 35
7 Operation .............................................................................................................................. 36
7.1 Starting The Circulator ................................................................................................. 36
7.2 Shutting Down The Circulator ...................................................................................... 37
7.3 Routine Checks And Operation Conditions ................................................................. 38
7.4 Fault Finding (Fig 7.1) .................................................................................................. 41
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -1-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 1 Table of Contents
8 Maintenance ......................................................................................................................... 42
8.1 Motor Removal ............................................................................................................. 42
8.2 Disassembly ................................................................................................................. 45
8.3 Inspection Of Components........................................................................................... 45
8.4 Assembly Notes ........................................................................................................... 48
8.5 Re-Installation Of Motor ............................................................................................... 50
8.6 Parts Lists..................................................................................................................... 52
8.7 Drawing List.................................................................................................................. 56
9 Stud Tensioning Equipment .................................................................................................. 66
9.1 Introduction................................................................................................................... 66
9.2 Application .................................................................................................................... 66
9.3 Description (Fig. 9.1) .................................................................................................... 66
9.4 Assembling The Stud Tensioner (Fig. 9.3) ................................................................. 68
9.5 Replenishing The Pump Tank ...................................................................................... 74
9.6 Indexing ........................................................................................................................ 74
9.7 Safety Procedures ........................................................................................................ 74
9.8 Tightening Flange Nuts ................................................................................................ 74
9.9 Releasing Flange Nuts ................................................................................................. 75
9.10 Parts List ...................................................................................................................... 77
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -2-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 2 - Technical Data
2 Technical Data
2.1 General
EP/09/11104 A, B, C
Unit Serial Nos:
EP/09/11105 A, B, C
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -3-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 2 - Technical Data
2.5 Instrumentation (See Sections 4.6 and 8.7 for more detail)
Instrument No. Located Type
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -4-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
#"
$
'
4
$
!"!
!!
!
!
& "
&
! !
1*2
!
0
!
0"
&
! !
1*%
2
!
$
%
1332
!
$ $
$
"
%
!
"
0
$
"
$
$
1!!2
'
!
%
$
'
!
00!"
&
!
& "
&
& !
& "
0
!
! "!
0 0 !
00!" & %
!
" 0 %
#"
!
&&"
78
0
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -6-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
!"#$%
&' (') *
8
8
8
7
6
76
7
6
6
6
6
8
8
#34
7
7
6
6
8
7
6
.
!"
9!"
+,-,.
/01 %%% 232
-1 ,4,5 %
!'*(
+
(,(%,(!(
%/*,01"!'2
!
!
+,3+
!
( *(( !((( !*(( ((( *(( "((( "*(( '((( '*(( *(((
/(
$(
*(
%&
'("$(
)"
*+
'(
450+6
7!(#
"(
(
"8
+
#
!(
(
,-$.
!/01
1) The pump case internal surfaces and all 2) The motor apertures must be blanked
machined faces must be cleaned and a off with flanges secured with studs, bolts
suitable removable solvent rust and nuts.
preventative, with a minimum effective
life of 6 months, applied. 3) The motor and transit assembly must be
Recommended rust preventatives are, filled to the top of the transit canister
Jenolac J400 or Shell Ensis Fluid 264, with inhibitor of the appropriate
or their equivalents. concentration, through the filling
connector located in the temporary
2) All pump case openings must be closed transit flange, sealing off the motor heat
with covers. These covers to be exchanger bottom outlet.
secured to the weld preparations with
steel banding and the pump case main 3.3 Inhibitor
flange with the existing studs and nuts
supplied on the pump flange. Inhibitor is to be produced from a pre-mixed
concentration of mono-propylene glycol and
distilled water in a 50/50 solution by volume.
The mono-propylene glycol must contain
corrosion inhibitors and meet BS6580 or
equivalent. A tolerance of 5% on the
normal glycol/water mix may be applied.
Figure 3.1 : Pump Case Storage Details 55% MPG /45% Water 1.040
MPG = Mono-propylene Glycol
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD -9-
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 10 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 11 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
Figure 3.3 : Inhibitor Filling Valve 3) Check all fittings and clearances and
general condition. Fit spare parts as
necessary.
3.6.2 Pump Case and Transit
Assemblies 4) Reassemble the motor as described in
Section 8.
Inspect the pump assembly and check the
following: - 5) Using a socket wrench on the impeller
nut, check that the shaft rotates freely,
1) No extensive corrosion has occurred on approximately seven revolutions in an
the internal pump machined areas. anti-clockwise direction.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 12 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
8) Seal off all apertures with appropriate 11) Re-check the insulation resistance of
transit flanges and gaskets. the motor windings.
9) Fill the motor with a pre-mixed 12) Check that the storage conforms to Para
concentration of inhibitor, in accordance 3.2.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 13 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
Signed
Fourth Check
Date
Signed
Third Check
Date
Signed
Second Check
Order No ..
Date
Signed
First Check
W.S.U Storage Record
Date
Date put
in store
Check Requirements
Exchanger
Unit Nos
Others
Heat
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 14 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 3 Storage
SITE
UNIT NO
DATE.
UNITS STOPPED AT..
Interconnection
Assembly
Assembly
Pipework
ASSEMBLY IN STORAGE AREA
STORED IN SAFE POSITION
IDENTIFICATION LABELS ATTACHED
PAINTWORK IN GOOD CONDITION
ASSEMBLIES HAVE INCURRED NO PHYSICAL DAMAGE (SEE NOTE 1)
STUDS, NUTS AND BOLTS ARE IN A SOUND CONDITION X X
STUDS, NUTS AND BOLTS FITTED IN THE CORRECT NUMBER X X
STUD PROTECTORS FITTED TO MAIN FLANGE STUDS X X X
BLANK FLANGES FITTED SECURELY X X X X
NO LEAKAGE OF THE INHIBITOR VISIBLE X
ROTATING ASSEMBLY ROTATED 6-7 TIMES X X X X
INHIBITOR LEVEL CORRECT X
INHIBITOR COMPOSITION CORRECT X
NO CORROSION ON PUMP CASE PROTECTED AREAS X X X X
WOODEN COVERS SECURED TO PUMP CASE OPENINGS X X X X
RUBBER BUNGS SECURELY FITTED X X
HEAT EXCHANGER SECURELY FITTED TO WOODEN CRADLE X X X X
KEY : ACCEPTABLE
O REQUIRES ACTION
NOTE 1 : DETAILS OF OBESERVATIONS SHOULD BE NOTED ON THE REVERSE SIDE OF CHECK LIST
WITNESSED BY OF.....
COMPILED BY OF.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 15 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 4 Description
The motor is suspended beneath the pump Within the pump cavity rotates a key driven,
casing and is filled with cold boiler water at mixed flow type impeller, mounted on the
full system pressure. No seal exists end of the extended motor shaft.
between the pump and motor, but provision
is made to thermally isolate the pump from 'Renewable wear rings are fitted to both the
the motor in the following respect: - impeller and the diffuser. The impeller wear
ring is the harder component to prevent
1) Thermal Conduction. Because the galling.
pump temperature is so high, usually
above 340C and the motor temperature
is limited to about 55C, a simple
4.3 Motor
restriction, in the form of a 'neck', is The motor is a squirrel cage, wet stator,
provided to minimise heat conduction. induction motor, the stator wound with a
special water tight insulated cable. The
2) Hot Water Diffusion. To minimise phase joints and lead connections are also
diffusion of boiler water, a narrow moulded in an insulated material. The motor
annulus surrounds the rotor shaft, is joined to the pump casing by a pressure
between the hot and cold regions. A tight flange joint and a motor cover
baffle ring restricts solids entering the completes the pressure tight shell.
annulus.
The motor shell contains all the moving
3) Motor Cooling. The motor cavity is parts, except for the impeller. Below the
maintained at a low temperature by a impeller is situated an integral heat baffle
heat exchanger in a closed loop water which reduces the heat flow, a combination
circulation system, thus extracting the of convection and conduction, down the unit.
heat conducted from the pump. A baffle wear ring-cum-sleeve above the
baffle forms a labyrinth with the underside of
In addition, this water circulates through the impeller to limit sediment penetration
the stator and bearings, extracting the into the motor. Should foreign matter
heat generated in the windings and manage to pass the labyrinth device into the
providing bearing lubrication. An motor enclosure, a filter located at the base
internal filter is incorporated in the of the cover end bearing housing strains it
circulating system. out.
4) In emergency conditions, if low pressure Lifting lugs are supplied to secure hoists
coolant to the heat exchanger fails, or is when raising and lowering the motor.
inadequate to cope with heat flow from
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 16 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 4 Description
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 17 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 4 Description
The thrust disc is also designed to operate as 4.3.5 Terminal Gland (Fig 4.2)
an auxiliary impeller to circulate the internal The electrical supply to the motor is taken
water content of the motor. through special high pressure single lead
cable terminal glands of the high
4.3.2.3 Reverse Thrust Bearing temperature, safety type.
The weight of the rotating assembly, as well as
the down thrust imposed at start-up and shut- The seal is effected by a terminal gland
down, are taken by a reverse thrust bearing moulding, together with o-rings located
located on a reverse thrust housing which between an insulating sleeve and an inner
forms the bottom of the cover housing casing, and between the inner casing and
cylinder. the motor case. The addition of a cone-
shaped collar within the terminal
The reverse thrust housing also includes a moulding, plus the design of the inner
composite reverse thrust wear ring and is the casing, prevents any possibility of a gland
mounting for the internal filter. blowout at high temperatures. However, if
the motor is subjected to sustained
4.3.3 Internal Filter overheating, a slight leakage may occur
into the terminal boxes.
A stainless steel woven wire strainer, fitted at
the base of the reverse thrust seat, filters the
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 18 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 4 Description
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 19 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 4 Description
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 20 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
NOTE:
5 Installation Two long lift hoists should be used to raise
5.1 General the pump or motor, each hoist being capable
of taking the full weight of the pump or motor
WARNING:
The Hayward Tyler boiler circulating 4) The pump should be positioned so that
pump is a precision piece of heavy the nett positive suction head (N.P.S.H.)
machinery. available exceeds the N.P.S.H.
specified in the Technical Data - Section
It should only be installed under the 2).
supervision of a qualified professional
engineer who should ensure that the NOTE:
staff directly concerned are adequately When operating at temperature, sub cooling
trained and have read and understood of the inlet water is normally present and this
this manual. gives a considerable increase in the
N.P.S.H. available. The worst condition is
When installing the circulators the following normally operating cold.
conditions MUST be observed.
5) Fit a suitable gland (not supplied) to the
1) The system pipe work should be cable entry of each terminal box.
adequately supported to accept the
weight of the circulator. 5.1.1 Installation Notes
2) When mounted, the pump should The following conditions must be observed
accommodate movement in the pipe when installing the circulator:
work due to thermal expansion without
imposing excessive loads on the casing 1) Ensure that the main system is free from
and branches, associated pipework and solids before mounting the circulators.
cables.
2) Permanent insulation should be applied
3) Sufficient clearance should be allowed only to the pump case. No insulating
beneath the motor to permit lowering of material must be applied to the motor
the motor from the pump case for case or to the main flange studs and
maintenance. (See Section 8 for the nuts, as this will cause the motor to
General Arrangement drawing). If overheat.
removable floors or girders etc. are fitted
after the motor is installed, ensure that 3) The cables leading to the motor, should
the terminal boxes or low pressure be flexible and looped immediately prior
cooling water supply lines will not foul to entering the terminal boxes. The
them when the boiler is on load and the looping should be sufficient to
circulator moves downwards due to accommodate unit movement caused by
thermal expansion. expansion and contraction of the boiler
pipe work.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 21 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
5.2 Pump Case Installation the system pipe work and re-check the
(Fig 5.1) horizontal limits.
1) Remove the pump case flange and 5) Complete the weld to the procedure
branch covers and clean the pump approved by the boiler manufacturer
branches. and test radiographically for flaws.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 22 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 23 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
taking care to avoid damage to the contact with the pump case face. At
terminal boxes. this stage, the gap between the
flange faces should be
12) Fit the motor to the pump case as approximately 2.5mm and should be
follows: equal all round the flange.
f) Check the gaps every 10 mm, or 13) If, after fitting the heat exchanger:
less, during the last 100 mm of the
motor raising sequence to ensure a) running is not reasonably imminent,
that the motor does not 'cock' or the motor and heat exchanger
rotate as it is raised. Adjust the gap circuit must be refilled immediately
as necessary. with inhibitor.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 24 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 25 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
MOTOR ASSEMBLY
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 26 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
d) Place the Flexitallic gasket at the top 5.6 Filling The Circulator
high pressure flange joint of the With Boiler Cold
motor and coat the bolt threads with
silicone grease, leave the gasket Filling the circulator correctly is a
clean. Bolt the top high pressure prerequisite to ensure satisfactory operation.
connection together. If air is present in the motor it could affect
bearing lubrication and precipitate bearing
NOTE: failure.
On high pressure / temperature applications,
guide ring type gaskets are used at the If air pockets are present in the stator this
auxiliary flange joints; tighten the flanges would affect dissipation of heat generated in
about the guide ring, metal-to-metal. the windings, creating hot spots and
consequent degrading of the insulating
e) Ensure the motor / heat exchanger material, and ultimately cause winding
interconnecting pipe work assembly failure.
is correct for the circulator. The
correct pipe work is stamped with Due to the complexity of the passages in the
the serial number. motor through which water must flow to
displace all air, it is necessary to fill the
f) Place a Flexitallic gasket at each motor very slowly. The maximum filling rate
joint at the bottom of the motor case is 2 litres /min.
and heat exchanger for the bottom
high pressure connection. Coat the The motor must NOT be filled via the pump
flange fastener threads with silicone casing, but only through the filling connector
grease. located at the motor cover.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 27 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 28 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 29 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
7) Fit the bursting discs to the terminal 1) Pump suction and discharge pressure
boxes as follows: - gauges.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 30 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
NOTE:
4) Ground leakage relay to warn of very Overload relays are now typically calibrated
low winding resistance in order to in motor full load current (FLC) where the
prevent winding insulation failure. relay trips with a current 10% above the FLC
setting point. Hence the overload relay of
5) Indication and record of downcomer this type should have a setting point of the
temperature and pump case cold duty current.
temperature. This is required to avoid
thermal shocks when starting a pump on Maximum current at nominal voltage:
a hot boiler. See Technical Data, Section 2.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 31 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 5 Installation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 32 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 6 Commissioning
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 33 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 6 Commissioning
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 34 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 6 Commissioning
c) Check all flanges, glands and valves 2) Close the discharge valves.
for leaks.
3) Maintain the low pressure cooling water
d) As the boiler water temperature supply to the heat exchanger.
increase, its specific gravity
decreases and the amount of NOTE 1:
N.P.S.H., available increases. The If the circulator is to stand idle for some
temperature of the high pressure considerable time with the boiler cold, the
water to the heat exchanger may low pressure cooling water to the heat
alter due to lower losses in the exchanger may be turned off, especially on
motor, or because of increased heat systems where the cooling water runs to
flow from the pump. waste.
NOTE: NOTE 2:
It is normal procedure to commission On hot boilers, and whenever the circulator
circulators separately, but if required, before is run, the low pressure cooling water to the
the last circulator is stopped, the others may heat exchanger must always be on.
be energised and their recordings taken
after each one is brought on-line. CAUTION:
If the circulator is to be idle for an
6.3 Stopping extended period, and be subjected to
freezing temperatures, make sure that
1) Press the stop button on the control provision is made to protect the motors
console. The run-down time is from freezing (see Section 3.2.2.)
approximately 2.5 seconds.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 35 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 36 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
7.2 Shutting Down The a) Cooling rate too fast: - If the pump
case cooling rate is too fast, slow
Circulator the cooling rate by partially opening
CAUTION: the by-pass valves as necessary.
Low pressure cooling water flow and
motor temperatures must always be b) Cooling rate too slow: - If the pump
within the specified limits, whenever the case cooling rate is too slow,
circulator is on hot standby. increase the rate by injecting a high
pressure purge as detailed in Para.
7.2.1 Boiler Hot - Circulator to go 7.3.8.
on Hot Standby 5) When the pump case has cooled to
1) Press the stop button on the control 43C de-pressurise the circulator as
console. follows: -
2) Ensure that the low-pressure cooling a) Ensure the pump discharge by-pass
line valves are open. valves and shut-off valve are closed.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 37 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
d) Re-check that the pressure does not temperature reaches 65C. If desired,
increase. Should it increase, check the aforementioned alarm temperature
the following: - settings may be lowered, on the
temperature alarm thermometer, to suit
i) Make sure that all valves normal operation but only after the boiler
between the circulator and high- and circulator has been operated long
pressure system are closed. enough to stabilise.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 38 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 39 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
7.3.7 Low Pressure Cooling prevent the ingress of harmful fluids and
Water Supply Failure solids into the motor.
If the cooling water to the heat exchanger is 1) Flush down the fill and purge system to
lost while the circulator is at operating ensure the line is clean.
temperature, the motor will be de-energised
as soon as the motor temperature reaches 2) Check that the low pressure cooling
the trip setting of 65C by the temperature water supply valves are open.
controller. Prior to this an alarm will be
initiated by the low pressure cooling water 3) Introduce high pressure purge through
flow monitor indicating that the low pressure the filling valves. Check that the purge
cooling water supply has been lost and a temperature does not exceed 49C and
further alarm will be initiated by the that the purge pressure is above the
temperature controller when the motor boiler pressure.
temperature reaches 60C.
7.3.9 Extended Shut-Down
CAUTION :
Damage to the windings may occur if the When the circulator remains shutdown for
motor remains in operation after 5 an extended period: -
minutes from the loss of cooling water.
1) Check regularly that it remains full of
CAUTION : water.
Do not attempt to operate the motor by
overriding the temperature controller trip 2) Run the circulator for a minimum of ten
mechanism and restore the low pressure minutes every two months.
cooling water as quickly as possible.
Damage to the windings may occur if the CAUTION
cooling water is not restored before the If the motor is to be subjected to extreme
motor temperature rises above 70C. low temperature, the motor must be
prevented from freezing, see section 3.2.
NOTE:
Before re-starting a circulator after an If the boiler is laid-up under a nitrogen
emergency shutdown, low pressure cooling blanket, take necessary precautions to
water must be supplied to the pump to prevent damage to the motor through
reduce the motor temperature to at least gaseous water. Any pump start-up, when
38C. the boiler is in this condition, must be
undertaken and initial start and the full
fill and vent procedure, as detailed in
7.3.8 High Pressure Purge section 5.6, must be followed.
Supply To Motor
Purge water applied to the motor through 7.3.10 Boiler Cleaning
the high pressure fill line, in an emergency,
During any boiling-out or acid cleaning
will limit motor temperature, so protecting
operation of the boiler, the de-energised
the motor until inspection and rectification
circulators must be isolated completely prior
are possible. The flow of purge water must
to introducing any chemicals to the boiler.
be sufficient to stabilise the temperature of
The circulators must be continuously purged
the motor to overcome any water loss due to
with clean cool water at a pressure of
leakage, etc., as follows: -
approximately 7 bar in excess of the existing
drum pressure to eliminate infiltration of
NOTE:
contaminated water into the bearing and
Continuous purging of the motor during
motor components. . A purge rate of 3.8
operation is recommended only during
litres / min., is normally sufficient to prevent
boiling-out and acid cleaning. A purge rate
the ingress of harmful fluids and solids into
of 3.8 litres / min., is normally sufficient to
the motor.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 40 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 7 Operation
REDUCED QUANTITY
EXCESSIVE POWER CONSUMPTION
REDUCED HEAD
SYSTEM
ELECTRICAL
CIRCULATOR
SYSTEM
CIRCULATOR
SYSTEM
ELECTRICAL
CIRCULATOR
SYSTEM
ELECTRICAL
CIRCULATOR
SYSTEM
SECONDARY COOLING
WATER FAILURE
ACTION
CHECK TEMPORARY
FILTER FOR BLOCKAGE
CHECK DIRECTION OF
ROTATION, IF INCORRECT
REVERSE ANY TWO
SUPPLY LEADS
CHECK THAT FLOW VALVES
BLOCKAGE OR
CONSTRUCTIONAL
CHANGE
PIPE STRAIN OR
INADEQUATE CASING
SUPPORT
CHECK DISCHARGE
VALVES EQUALLY OPEN
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 41 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
1) Isolate the electrical supply; disconnect a) Disconnect and the remove the
all instrument cables from the motor bottom outlet high pressure
identifying the connections and leads. interconnecting pipework between
the motor and heat exchanger by
2) Remove the terminal box covers and removing the flange nuts and
disconnect the external power supply washers from the flange bolts and/or
cables from each terminal box, studs. Discard the flange gaskets.
identifying each lead for reassembly.
b) Disconnect the top inlet high
3) Using a 1000v megger, check that the pressure connection between the
insulation resistance to ground of the motor and heat exchanger as
motor leads conforms to Winding above.
Resistance Diagram, Section 2, Fig 2.2
when measured at the terminal stems c) Take the weight of the heat
with the unit full of water at 20C or the exchanger with adequate lifting gear
normal ambient temperature. Record and remove the nuts and bolts
the reading. securing the heat exchanger to the
motor brackets.
4) If suction valves are not fitted, the boiler
system must be cooled, depressurised d) Remove the heat exchanger to an
and drained before motor removal. inspection area.
CAUTION: 11)
The low pressure cooling water flow and a) Fit the removable lifting lugs to the
motor temperature must be maintained brackets on the motor casing. Set
within the specified limits whenever the up two chain hoists and rigging, of
motor is in contact with a hot pump case. sufficient capacity for each to take
the full weight of the motor, and
5) Check that the circulator is connect to the lifting lugs.
depressurised and isolated from the
boiler and fill system. WARNING:
Normally two hoists are used for
6) Drain the pump casing using the drain removing the motor and because the
valves in the discharge pipework and /or load can shift from one hoist to the other
the pump case drain valve. during the removal, each hoist must be
capable of taking the full weight of the
WARNING: motor.
Never drain the pump casing through the
motor fill & drain line as this could cause b) Take the initial strain of the motor.
contamination of the motor.
12) Loosen the pump/motor flange stud nuts
7) When the pump case has cooled. in accordance with the hydraulic stud
isolate and disconnect the low pressure tensioning instructions in Section 9.
cooling water inlet and outlet flanges
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 42 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
14) Lower the motor to the horizontal 16) Seal off the pump case opening by
position, (Figure 8.2), remove the lifting fitting the blank off plate refer to
tackle and cover all joint faces and Section 5 for details.
openings with clean rags.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 43 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 44 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
8.2.2 Main Impeller (Fig 8.2) 8.3.1.1 Stud Inspection at each Flange
Breakdown
Remove the impeller from the rotor
assembly as follows:- Whenever either the pump case/ motor case
or the motor case/motor cover flange joint is
4) Unlock the punch marks and remove the broken, the exposed portion of all the flange
impeller cap screw. studs must be thoroughly inspected visually
for indications of damage or corrosion,
5) Remove the LEFT-HAND threaded mainly in the form of pitting and cracks etc.
impeller nut using the special spanner Pitted or cracked studs must be renewed.
and tommy bar provided in the tool kit.
8.3.1.2 Stud inspection at Pump
NOTE: Overhaul
Do not use any leverage in the water At each convenient circulator overhaul
passages of the impeller to oppose force period, approximately 4 - 5 years, a
exerted on the special spanner; the weight percentage of the studs must be given a
of the rotor will oppose rotation if the tommy- non-destructive examination, as follows:
bar is given a few heavy blows with a
leadfaced hammer. 1) Remove two random studs from both
the pump case/motor case joint and any
If the nut shows any tendency to seize on one stud from the motor case/motor
the shaft, do not continue to exert force, but cover joint.
drill and split the nut to remove.
2) Clean up the studs, and using a liquid
6) Carefully withdraw the impeller, then dye penetrant and/or magnetic particle
remove the impeller washer and remove examination, examine for surface
the impeller key. cracks, particularly in the stud threads
and thread run out areas.
7) Immediately refit a serviceable impeller
nut to permanently protect the shaft NOTE:
threads. If there has been a history of leakage in
service from the joints and/or previous
recorded damage, remove and inspect at
least 10% of each flanges studs.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 45 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
8.3.1.3 Studs on Extended Circulator 2) Subtract the impeller wear ring outer
Service Life diameter from the diffuser wear ring
bore, allowing for any temperature
If at the end of the circulator nominal service difference and compare with the
life, or as otherwise defined, an extension of clearance specified in Section 2,
circulating pump life is proposed, it is Technical Data.
recommended that all studs should be
renewed. However, should a request be 3) Check the hardened surface of the
made for an extension to the life of the impeller wear ring.
existing studs, then the following points must
be satisfied:- 4) If the diffuser wear ring requires
renewal, fit the new ring and secure
1) The general condition and surface using the socket head cap screws and
integrity of the studs must be lock washers. Tighten the screws in
satisfactory. accordance with the torque figures
detailed in Section 2.
2) There should be adequate residual
fatigue life in the studs for the extended
life proposed; this can be obtained by
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 46 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 47 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
a) Screw the stud into the case, until Figure 8.4 : Assembly of Flange Studs
the last thread of the stud is (Pump /Motor Case)
recessed within the tapped hole
5mm nominal, that is, one full casing 8.4.1.2 Motor Case/Cover Studs
thread left exposed above the stud
1) Assemble the motor case/ cover studs
metal end as shown in Figure 8.4.
as follows:
b) In conjunction with the stud
a) Screw the stud into the case, until
recessing, maintain the squared end
dimension L measures 236 mm in
of the stud on a common plane to
the motor case.
adjacent studs within 3mm. This is
essential to prevent fouling of the
b) Maintain the ends of the stud on a
Hydraulic Stud Tensioner on the
common plane to adjacent studs
studs either side of the stud being
within 2mm. This is essential to
tensioned.
prevent fouling of the Hydraulic Stud
Tensioner on the studs either side of
the stud being tensioned.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 48 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
NOTE:
The impeller nut has a left handed thread.
Do not use any leverage in the water
passages of the impeller to oppose force
exerted by the spanner, the weight of the
rotor will oppose rotation if the spanner is
given a few heavy blows with a lead-faced
hammer.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 49 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
10) Using a 1000V megger, check that the with the installation procedure described in
insulation resistance to ground of the Section 5.
motor leads is above 200 megohms
when measured at the terminal stems WARNING:
with the unit full of water below Reinstallation is only possible with the
approximately 20C, if possible, or at boiler cold, de-pressurised and drained.
normal ambient temperature. Record Fit a temporary gauge to check the
Reading. pressure inside the pump casing. Blow
down and cool as required before
8.4.4 Heat Exchanger removing the casing blank.
Ensure that the heat exchanger is 1) Remove the casing blank and fit a new
serviceable and if removed, re-fit in flexitallic gasket to the motor flange.
accordance with installation procedures as
described in Section 5. 2) Fit the motor, heat exchanger, inter-
connecting pipe work, fill and high
8.5 Re-Installation Of Motor pressure purge lines and the secondary
cooling water pipe work.
The re-installation of the motor assembly to
the pump case is carried out in accordance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 50 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 51 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 52 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 53 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 54 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 55 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 8 Maintenance
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 56 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
%%
#//
%)&&4(%%
!55
)*%%!!*&
&(*(!%
&
% %
!&%
&
/ /
"$$$ / /
-%&*&
7"&
4(
)%&
#
$$
%& %
"
$!!
&
%6$
)
4)
!%%
$ &%&
&)(
&(%
&%&
$
#//
/
$$
#
!%%
&%&-
%)(
)3!
!!*&
!!%/"3 !""6 $ "#"$%"" "%"" $%$&'%
""#
%!2)(/#3 $,) ' ,)
/
/
" $$$*!"#$"%&'#()%*+,
!"#$"%&'#()%*+, &*&%!(&%&&!!($
"3 (9
#
$,), ' ,) 4+) &(*(!%--)--
/
12 6 ,)
44, 5+$,)
%%()
, .
!"""#"$%"" "%""
&%!
%)%& % &%!2
"#9 0%4(1
9
#
#9
"#9
#
&%! 9
!!% #9 #9
+
$
"#9 "#9
#
&%& +
$
/
"
" #/
# "#
/" /"
# #
"#
"
9
"/
/
"#9 9
/"
#/
/
/"
//
"#9
""
""
#
#
"9 "9
9 9
*!! *!!
%&)%&- %)%&-
!""6 $ "#"$%"" "%"" $%$&'%
""#
$,) '
/ " $$$*!"#$"%&'#()%*+,
,) /
!"#$"%&'#()%*+, &*&%!(&%&&!!($
$,), '
,)
4+)
#
&(*(!%--)-- (:
12 /
44, 5+$,) 6 ,)
%%()
, .
!"""#"$%"" "%""
/
!"!#$%"&'#()*
+,-). !"!#$%"&'#()* '
*(0
$+-+ ' +- 4*-
11
1
1
28 6 +-
44+ 5*$+-
,--.-- )
!"""#"$%"" "%""
0
5 0
0 0'
0
0
5
)
0
0
0
3
0 5
0
0
85
)
0
' 0
3
0
0
3
0
3
0
00
0
0
% 22
0
85
)
0
6775
0
0
0 0
0 8 0 0
0
8
8
2
2
0
02
0
0'
0
;(<<
0
022
3
0
05 0
9
0 '5 '
0
0
''0'
0
'5
9'
0
5
6
0
77
6 775
0 3
0
0 ''
3
0
0
5
3
0 '
0
0'
0
0
0'
0
0 ''
)
0 5
0
02
0
0' 2
0
'' 3
0
0' 2
0
0
0'2
0
0
0
0
56
0
0
0'2
77
4
4
/
!"!#$%"&'#()*
+,-). !"!#$%"&'#()* '
*(0
$+-+ ' +- 4*-
11
1
1
28 6 +-
44+ 5*$+-
,--.-- )
!"""#"$%"" "%""
88.5
5
1
X
23 7
9 10 11
10 9 6
12
22 20 16 17 18 19 21 8
152
WRAPPED LAYER TO BE OFFSET BY HALF THE TAPE WIDTH. 19 37917-169 BURSTING DISC 2
4.2. PHASE MARKING TO PROCESS SPECIFICATION 36613/111 12 42774-2705 GASKET - TERMINAL BOX SUPPORT 1
5. BILL OF MATERIAL INDICATED FOR ONE PHASE TERMINAL BOX ONLY, TYPICAL FOR 10 17207M10 M10 SPRING WASHER 42
REMAINING TWO PHASES 9 16501M10 M10 FULL NUT 42
USE .......................................... BOILER WATER CIRCULATING PUMPS WITH MOTORS * Not Applicable for Pitching Holes
GEOMETRIC TOLERANCE SYMBOLS
HAYWARD TYLER
TEL. +441582 731144
FAX. +441582 452198
TITLE:
HAYWARD TYLER ENGINEERED PRODUCTS LTD 6.6 KV FAULT RATED TERMINAL BOX
MACHINING TOLERANCES EXCEPT WHERE OTHERWISE STATED mm
Straightness Parallelism
Over 0 50 150 300 600 1200 Flatness Squareness
SIZE
To 50 150 300 600 1200
Roundness Angularity NAME DATE
380-P-453-3300-210 GMP UNIT
Cylindricity Position
Outside
B 9822 CHANGE TO DRAWING NOTE AND TITLE. K. JONES 05/05/10 A. JONES 05/05/10 Diameter 0.12 0.25 0.50 0.75 1.25 1.50 Profile of a line Concentricity DRAWN T. BOLTON 30/03/2010
Profile of a surface Symmetry
A
Inside
Diameter
0.12 0.25 0.50 0.75 1.25 1.50 Run out M Maximum - CHECKED A.S. JONES 31/03/2010 DRG NO. ISSUE
42938-003 Sheet 1 of 1 B
* Boxed dimension - Metal Condition
MODIFIED APPROVAL APPROVED A.S. JONES 31/03/2010
REV. ECR CHANGE DESCRIPTION MODIFIED BY APPROVED BY Length 0.25 0.50 0.50 1.00 1.00 1.00 *Dimm. which defines true position
DATE DATE
*
2
*
&& #
&& #
3
&
"&
$ " #
&
2
!
#
"
()* (
)*
(
" #
!!"" ! !
,
"
-.
- * ! 1
$ $%&'
!
- " !
"
#
4
+! (2
3
% #
*+! ,!- .!
/
0
"#
!!""
1 /
#$%&
/0 ( )
#
3!
- !!!
#5
' ( ) 6
+! 7
/
"7!
7 -
!
& $
Tolerance to Recommended
0-800 deg C
Thermocouple Motor Cavity 3 42938/007 TC Ltd 12-K-289-118-8.0-2ID-3P11/IP67-165MM IEC60584.2:1993 3/4" NPT 3/4" NPT N/A 60 deg C alarm,
Class 2 65 deg C trip
2 Adjustable
Flow Switch / LP Cooling Water 1 1/2" ANSI /
1 42401/201 Flotech Solutions Ltd M16SSMP3EE3EESL1cS12F300S1D1 0-100% of 16m3/hr +/- 2% of full scale 20 mm conduit SPDT 0-100%
Indicator Pipework 300#RF
(3 wire) switches
Temperature
Motor Case 1 42401/205 Dresser/Ashcroft 600A-02-C27-B01-A1-L07-BS-XNG 0-120 deg C 1% FSD 1/2" NPT N/A N/A N/A
Indicator
InstrumentScheduleRev027Oct2010
Figure 8.11 : Instrumentation Schedule -63-
!)
!!"
# $
"
$ # %&
# %&'
%&!(
&&
# &&
# )%&
&
&
&
$ #
&
$ !""*+
!
")
%
"
!!3
#
$$$!"#$"%&'#()%*
& 45 &
- * ! 1
$ !"#$"%&'#()%*
"
!
- " !
#
# "
22)
2
2
14
+! (2
3
0
!
*+! ,!- .!
6
)
76
#$%&
/0 ( )
#
3!
- !!!
#5 )
$
#"
! $+#
# #
$
.
*! 1
* $
$ *
2
$#
!** !
$ $ !!! !
,
/
%-.$ %-
,.$
,
&'
'()
* !
7$
!"#
!!
&'(") !"#
#"
# $
#
$$
'() %
*
!,
"#
# $# #% % #% #% # ) /''0
*
!
4'6
%
*
,,1
(
% 7
2 ' )' 3)' 4'' 5'' 3/''
#!
+
-
)' 3)' 4'' 5'' 3/''
!$
!" %
"$"
!$
'(3/ '(/) '()' '(0) 3(/) 3()'
!
"
""
* $% ! $
!! ! $
$
'(3/ '(/) '()' '(0) 3(/) 3()'
!
!
%&!
% + #
'(/) '()' '()' 3('' 3('' 3(''
*
.&$
$
$
*(
+
$
!
,
, $ !
Figure 8.13 : Tool Kit List -65-
Section 9 Stud Tensioning Equipment
When working on a circulator flange joint, all The pump body contains the oil reservoir,
the heads are employed simultaneously, incorporating an oil filter plug and oil
each being diametrically opposed. The pressure return valve for variable pressure
heads are positioned on the studs in a release, the pump handle, gauge and quick
prescribed sequence, and are pressurised to release high pressure hoses complete the
a specified limit in accordance with each of assembly. All the pump components are
five consecutive stud tensioning easy to dismantle for servicing.
programmes. As the studs are
progressively tensioned, the mating flanges 9.3.3 Stud Tensioner Heads
are drawn together, so allowing the
circulator flange nuts to be tightened or The stud tensioner heads each comprise a
released. bridge that fits over the stud and stud nut to
seat on the flange and is retained by the
bridge retainer. A tensioner body
9.3 Description (Fig. 9.1) incorporating a seal, sits on the bridge and
9.3.1 General is held in position by the threaded insert,
The Hydraulic Stud Tensioner Equipment screwed on the stud. The head is
comprises three principal components: - hydraulically pressurised via a quick release
coupling and high pressure hose.
1) Tensioner head assembly, including the
bridge, tensioner body and piston and Three of the four heads have two
threaded inserts (see Fig. 9.2). connectors fitted. The fourth head has one
connector and one blanking plug. The
2) Hand-pump - including oil reservoir. fourth head is always the last in line in the
system, the other heads are interconnected.
3) High Pressure Couplings, hoses and
pressure gauge.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 66 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 67 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
9.4 Assembling The Stud normal for the bridge window to face
radially outwards from the centre of the
Tensioner (Fig. 9.3) circular flanged joint.
The hand pump and its accessory hoses are
normally provided, in the toolbox, already NOTE:
assembled needing only to be connected to The bridge base circumference should sit
the tensioning heads. However for flatly against the surface against which it is
information purposes, the assembly of the being tensioned.
stud tensioner kit is as follows: -
5) Attach each threaded insert into the bolt
1) tensioners by screwing onto the threads
a) Remove the hand pump, complete protruding above each nut. Screw down
with pressure gauge, high pressure the inserts using the tommy bars
hoses and hose couplings from the supplied with the equipment, until
hydraulic pump tool box. contact with the load cells is achieved.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 68 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 69 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 70 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 71 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 72 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 73 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 74 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 75 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
one half () turn using the appropriate 4) If the nuts are still in contact with the
bar. Repeat for every stud on each pass. flange and cannot be removed with the
system at absolute pressure, consult
3) Should the nuts fail to move, a slow Hayward Tyler for advice.
gradual increase in pressure should be
made until the nut lifts of the flange face. 5) Repeat the stud tensioning and nut
At this stage, a further increase in unscrewing sequences diametrically until
pressure is un-necessary and will not all flange nuts are released.
assist in freeing a tight nut.
6) After use, thoroughly clean, examine for
CAUTION: damage and lubricate each component of
Never exceed the maximum system the stud tensioner equipment. Wrap all
pressure when removing the nuts. components in suitable water-proof
material then store in a clean, dry area in
their respective tool boxes.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 76 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401
Section 9 Stud Tensioning Equipment
Figure 9.6 : Stud Tensioner Assembly (Hose connection position may vary)
Also included: - Hand Pump complete with 1500 bar Pressure Gauge
Hydraulic Harness manufactured from flexible hose and quick release couplings to tension 4 tools
simultaneously.
Harness consisting of 5m Lead Hose and 1.5m Interconnecting Hoses
Tommy Bars, Oil Pack, Spare Seals, Storage Box for Tensioning Heads, Storage Box for Pump
and Harnesses, Manuals for Tensioner and Hand Pump.
Rev 0 Sep 10 Hayward Tyler Ltd, 1 Kimpton Road, Luton, England. LU1 3LD - 77 -
Telephone: + 44 (0) 1582 731144 Fax: + 44 (0) 1582 393401