2
Personnel on a Coatings Project
Authority Roles
The specific duties of the QC and the QA will vary from project to
project. The coating inspection process typically dictates that after
certain activities (e.g. surface preparation), work should be halted,
inspected, rework performed as necessary and accepted by the QC and
QA, before the contractor can move on to the next step of the painting
process. These specific inspection items are typically referred to as
A rule of thumb is that the QC inspection should occur first and any
non-conforming items identified by the QC should be corrected, re-
inspected and accepted by the QC. The QA observations should only
occur after the work (hold point) has been accepted by the QC. The
QA should then verify that the work that the QC accepted meets the
requirements of the specification. If the QA identifies non-conforming
items, they should be repaired and re-inspected before the QA accepts
the work and the contractor proceeds to the next step of the painting
process. It is often helpful, if not necessary, to have the QC or
foreman present during the QA observations, so that any deficiencies
can be identified and confirmed by both parties. This also allows the
contractor to clearly identify areas requiring rework to his workers.
Roles of QA and QC
In the 1990s and 2000s, Owners began to recognize that while third
party inspection was still desirable, it was not intended to replace QC
by the contractor. With the increased recognition of SSPC QP1, ISO,
ASQ and other certifications, more and more companies are moving to
the concept of a total quality system involving a clear division between
QC and QA responsibilities.
and more organizations and end users are attempting to better define
their expectations for both the QC and QA.
The SSPC QP-1 program states that hold point inspections should be
performed during six primary stages of the coatings project. That is
pre-cleaning, surface preparation, primer application, intermediate
application, top coat application and cure.
The SSPC QP-1 Annual Internal Audit Report / Checklist for SSPC
Certified Contractors (Rev 02/04), specifically requires that the
QC representative prepare daily reports that include the following
information (at minimum):
Existing
Quality Control Points Purpose New Steel Steel
1. Solvent Cleaning Remove asphalt cement, oil,grease, etc. Yes Yes
2. Grinding Flange Edges Remove sharp corners Yes Yes
3. Abrasive Blasting Blast surfaces to receive paint Yes Yes
4. Containment/Waste Contain, collect, & dispose of No Yes
Disposal abrasive blasting debris
5. Prime Coat Application Check surface cleanliness, apply
prime coat, check coating thickness Yes Yes
6. Remove Fins, Tears, & Remove surface defects and Yes Yes
Slivers slivers
7. Washing of Shop Primer Remove all water soluble Yes No
materials (salt, dirt, etc.)
8. Intermediate Coat Check surface cleanliness, apply Yes Yes
Application intermediate coat, check coating thickness
9. Caulking Caulk areas not sealed by the Yes Yes
intermediate coat
10. Finish Coat Application Check surface cleanliness, apply Yes Yes
intermediate coat, check coating
thickness
11. Final Review Acceptance and check total Yes Yes
system thickness
A. Compliance programs
i. QC program
ii. Worker Protection Program
iii. Environmental Protection Program
iv. Containment Program
v. Waste Management Program
B. Location of Equipment
i. Dust collector
ii. Hygiene facilities
iii. Recycling equipment (on or off site)
iv. Waste storage
C. Work schedule
5 Lighting
6 Product Information
7 Visual Standard
can also be a key element in the event that the coating failure results
in litigation against the coating contractor or the coating supplier. Just
like homeowner or car insurance, you may never use it, but when you
need it, youre glad you have it.
Each entry should contain the date and start with, The writer arrived
on-site at (time).... Note that the diary is discoverable during the
litigation process.
Paint Inspection
Documentation Acknowledgement
Project: Project #: Copy to:
Location: Office Estimating
QC Sup HSO
Company Name: Start Date: Proj Mgr Inspector
Contact: Finish Date: Other
This is to acknowledge receipt of one or more of the following documents:
Specifications Revisions Correspondence Reports
Drawings Test Results Other
Receipt of all documentation is to be recorded in the project documentation log
Date Documentation, Specifications, Prints, and Revisions Description and Title
Update all specifications and procedures and record in appropriate revision logs
Issued to: Company:
Receipt Acknowledge by: Signature: Date:
Return this form with signature to:
Inspection Equipment
Calibration Record
Project: Case #: Copy to:
Location: Office
Issued to: Inspector
Issue Date: Return Date: Other
Document all equipment requiring calibration Other
Inspection Equipment
Copy to:
Issuance Sheet Office
Location:
Attachments:
Issued to: Issued Date: Calibration Certificates
Inspection Equipment
Operation Date of Calibration
Item Model # Serial # Procedure Calibration Verification
Environmental Conditions
Surface Preparation
Application
The following desginated inspector has been issued the above listed inspection equipment, certifications, and calibration standards required to perform the
intended inspection as required by contract. The inspector is required to keep all issued equipment in a safe place and in good working order. The inspector will
document required calibrations and maintain all records per job specifications. Upon completion of the project, the inspector will return all equipment to the QC
manager. The inspector is responsible for negligence and understands and accepts to replace damaged or stolen equipment.
Issued by: Issued to:
QC Manager Signature: Inspector Signature:
Date: Date:
SSPC QCS 2-13 Revision 1 09/2005
Project/Client: Contr
Location: Attachments:
Description: DFT Sheet NCR/CAR
Requirements:
Contractor: Spec #: Revision #:
Description of Areas and Work Performed Hold Point Inspections Performed
1. Pre Surface Preparation/Condition and Cleanliness
2. Surface Preparation Monitoring
3. Post Surface Preparation/Cleanliness and Profile
4. Pre Application Prep/Surface Cleanliness
5. Application Monitoring/Wet Film Thickness (WFT)
6. Post Application/Application Defects
7. Post Cure/Dry Film Thickness (DFT)
8. Nonconformance/Corrective Actions Follow-Up
9. Final Inspection
Approved by:
Surface Conditions Ambient Conditions
New Maint Primer/Paint Age/Dry/Cure Time (Indiciate AM or PM) : : : :
Abrasive Blast Abrasive Type Sample Kit Sz/Cond: Sweat-In Time: Min/Hrs
Blast Hose Size Nozzle Size/PSI Shelf Life: Pot Life: Min/Hrs
Profile Check Disc Tape Gage Airless/Conv Spray Brush Roller Other
Specified mils avg/Achieved mils Pump Pot: Hose Diameter: Air Check:
Surface Effect on DFT Gage/BMR mils Ratio/Size: Hose Length: SEP/Trap:
Dry Film Thickness (DFT) Gage Calibration Record GPM/CFM: Spray Gun: Filter:
Gage Type/ Gage Plate/Shim Gage Adj Spec Avg DFT Last DFT This
Model Serial # Mils/m +/ DFT Coat Coat PSI: Tip Size: Agitator:
Inspector Signature: Date:
SSPC QCS 2-06 Revision 1 09/2005
Project/Client: Contr
Location: Spec #:
Description: Revision #:
Item: Item:
Spot Readings Spot Readings
Location Area %
Location Area %
1 2 3 Total Min/Max Avg 1 2 3 Total Min/Max Avg
A A
B B
C C
D D
E E
Approx Approx
Sq Ft Specified DFT mils/m Total avg mils/m Sq Ft Specified DFT mils/m Total avg mils/m
Reference Inspection Report # for application record Reference Inspection Report # for application record
Item: Item:
Spot Readings Spot Readings
Location Area %
Location Area %
1 2 3 Total Min/Max Avg 1 2 3 Total Min/Max Avg
A A
B B
C C
D D
E E
Approx Approx
Sq Ft Specified DFT mils/m Total avg mils/m Sq Ft Specified DFT mils/m Total avg mils/m
Reference Inspection Report # for application record Reference Inspection Report # for application record
Item: Item:
Spot Readings Spot Readings
Location Area %
Location Area %
1 2 3 Total Min/Max Avg 1 2 3 Total Min/Max Avg
A A
B B
C C
D D
E E
Approx Approx
Sq Ft Specified DFT mils/m Total avg mils/m Sq Ft Specified DFT mils/m Total avg mils/m
Reference Inspection Report # for application record Reference Inspection Report # for application record
DFT Gage Calibration Record Comments:
Gage Type/ Gage Plate/Shim Gage Adj Spec Avg DFT Last DFT This
Model Serial # Mils/m +/ DFT Coat Coat
Inspector Signature: Date:
Project/Client: Contr
Location: Attachments:
Description: Stop Work Order
Requirements:
Contractor: Spec #: Revision #:
Time and Location Name/Company/Title
Final Approval
Authorized Contractor Signature: Inspector Signature:
Title: Date: Date:
SSPC QCS 2-08 Revision 1 09/2005
Location: Camera:
Camera Time/Date Verified: Yes No N/A Permission Req: Yes No Exposures:
Film Developer: # Date: Roll/Disc #:
# Location Area Comment
Inspector Signature:
Date:
SSPC QCS 2-10 Revision 1 09/2005
Ethics
Documentation
Charging time to a project that was not actually spent performing work
activities on the project is unethical. Padding (i.e. adding additional
expenses such as increased mileage or time) on time or expenses
reports, is considered fraudulent and unethical.
Gifts
The Roles of Quality Assurance Comprehension of Module Two will enable the
participant to:
and Quality Control Inspection
Describe the differences between quality assurance
Personnel on a Coatings Project and control
Describe the common duties of quality assurance and
control personnel
Describe the purpose and content of a pre-
pre-job
conference
Explain the purpose of an inspection procedure/plan
Explain the importance of ethics of inspection
personnel
Quality Assurance vs
Quality Control
Quality Control
Differences Performs necessary observations,
QA works for the testing and documentation (routine,
facility owner systematic inspection)
QC works for the
painting contractor Verifies that each phase of the work is
in compliance with the specification
1
Coatings Inspector
Quality Assurance
Representation and Roles
QA by the facility owner verifies that Inspectors can represent various entities,
the QC accurately inspects, reports Inspectors can serve different roles based
on the contractual relationship
and documents the work performed)
QC for the painting contractor (hired as a
consultant on a contract basis)
Audit
Audit function QC for the painting contractor
QA for the prime contractor, subcontracting the
painting work
QA for a facility owner
QA for a coating manufacturer
Distinctions Between
QC and QA Caution Regarding QA
Both owner
owners and third party QA
Authority Roles: must exercise care not to unduly
Directing operations interrupt contractor operations
Exerting control (by withholding Potential legal liability
payment)
Advising contractor or owner
Documenting non-
non-conformities
QA does not relieve QC responsibilities
2
Coatings Inspection
Total Quality System Duties & Responsibilities
The International Standards Specific duties will vary from project
Organization (ISO) and the American to project based on the specification
Society for Quality (ASQ) advocate the General duties are common to most
use of both QC and QA to achieve a projects
total quality system. Most specifications invoke inspection
Hold Points
Points
3
Rules of Thumb QA Process
QC inspection should occur first
Typically a review of tests or
Non-
Non-conforming items identified by QC
documentation provided by the QC
should be corrected, reinspected and
accepted by QC Duplicate testing at certain hold
points (i.e., DFT measurements
measurements)
QA observations occur when the work
has been completed and accepted by
QC
4
SSPC-QP1 Certification SSPC-QP1 QC Reports
Program
For painting contractors QC is required to prepare daily
Hold points should be performed after: reports on the following:
Pre-
Pre-cleaning 1. Compressed air cleanliness
Surface Preparation
2. Dry film thickness
Primer Application
Intermediate Application
3. Air temperature
Topcoat Application 4. Humidity
Cure 5. Dew point temperature
9. Surface profile
10. Batch numbers of paint used
11. Batch numbers of thinner used
12. Mixing according to specification
5
State Specific QC and QA Pre-Construction
Responsibilities (Pre-Job) Conference
Occurs prior to
Illinois DOT project start-
start-up
Introduced contractor certification The facility owner,
requirements 2002 - 2003 contractor, coating
Developed a new coating specification supplier and the
inspector attend
Developed different forms for QC and
QA
Daily QA Report
Establish roles in Pre-
Pre-Job Conference
6
Pre-Job Conference Inspection Procedures
7
Work Plans & Process Work Plans & Process
Control Procedures Control Procedures
Work Plans Process Control Procedures (PCPs)
Description of processes & critical factors Contract-
Contract-specific
affecting quality and safety
Reference project specification
Require formal approval process
Include accept/reject criteria & authority May require pre-
pre-approved format
Includes project schedule
Lists equipment, mobilization plans, control of
materials
Indicate frequency of project meetings
8
Work Plans & Process
Documenting & Reporting
Control Procedures
Work Plans and Process Control Critical responsibility of the coatings
Procedures (PCPs) inspector
Submitted in advance of production Must be timely and accurate
QA may review for completeness and Can be key in problem solving or litigation if
conformance to the specification a failure occurs
May require revisions and re-
re-approval No standard
standard inspection form
Logbook or diary
diary of daily, project-
project-related
events should also be maintained
9
Ethics Defined Ethics of the Inspector
10
Other Ethical Breaches Other Ethical Breaches
Charging time to a project that was Receiving gifts or gratuities from the
not actually spent performing work contractor or the coating manufacturer
activities on the project Cash, loans, airline tickets, etc.
Padding of time or expenses Loans of personal equipment
Allowing the contractor to do work at
your home (for free)
Many companies require inspectors to Participants must read and sign prior
sign documents promising to uphold to sitting for PCI Course Examinations
professional ethics on the job Indicates Protective Coating
Inspector
Inspectors acknowledgement of
requirement for ethical behavior
11
Summary Summary, cont.
Pre-
Pre-job conferences: Inspection Procedures
Occur prior to project start-
start-up Aid in identifying inspection checkpoints and
acceptance criteria
Enable discussion of specification, List inspection checkpoint, inspection methods
schedule, inspection points, etc. and acceptance criteria
Attended by facility owner, contractor, Documentation and Reporting
coating manufacturer, QA and QC Critical responsibility of a coatings inspector
inspectors, others Key element in problem solving or litigation
12
Summary, cont. Module 2 Workshop
13