Vous êtes sur la page 1sur 23

Published in July 2011 by the Workplace Safety and Health

Council in collaboration with the Ministry of


Manpower. These guidelines are co-developed by the
Workplace Safety and Health Council and the Ministry of
Manpower.

All rights reserved. This publication may not be reproduced or


transmitted in any form or by any means, in whole or in part,
without prior written permission. The information provided in
this guidebook is accurate as at time of printing. As a guide, this
booklet has no legal standing. The Workplace Safety and Health
Council and the Ministry of Manpower do not accept any
liability or responsibility to any party for losses or damage
arising from following the guidelines.

Guidelines on Design for Safety


in Buildings and Structures
contents

Introduction 01

Intro
Roles and Responsibilities 03

The GUIDE Process 13

Implementation 16

Record Keeping 20

duction
Glossary 23

Appendices 25

Appendix A : Design Hazards 26

Appendix B : Sample GUIDE-1 29


Appendix C : Sample GUIDE-2 32

Appendix D : Sample GUIDE-3 38

Appendix E : Safety and Health 41
Risk Assessment Form

Year of issue: 2008


First revision: 2011
2

Objective
Design and planning is an essential component in every construction work.
In line with the Workplace Safety and Health Act ( WSH Act), reducing risk
at source is one of the components to improving site safety. To address risk
Roles&
Respon
at source, there is a need to look at who creates the risk and address the
issue from there. While the WSH Act imposes a duty on the occupiers,
employers and principals, the risks inherent in the design also need to be
addressed and means to mitigate the risks identified. In addition, accidents
are often a result of either poor planning or lack of communication between

sibilities
the designer and occupier, resulting in loss of information. The process to
ensure transfer of relevant information and documents are therefore recorded
here as well.

This guideline serves to assist key stakeholders on the process of design safety
and the transfer of vital safety and health information along the construction
process chain. To facilitate this, duties of the various stakeholders are
specified, as well as Design Reviews stipulated, creating a framework which
allows every stakeholder to participate in making vital safety and health
decisions.
4 5

Duties of the Maintain the permanent fixtures


and fittings of a building or
Designer structure;

The duties of designers are as


Use the structure designed as a
follows:
place of work; and
Assess the design so as to review
the safety and health risks that
May be affected by such work,
the design creates;

Designers
for example customers or the
general public.
Eliminate the hazards as far as
reasonably practicable. Where
hazards cannot be eliminated,
designers should assess the
resultant risks by looking at
the severity and probability of
In line with the WSH Act, the person who creates the risk must be responsible
occurrence. The resultant risks
to mitigate it. This is applicable to the designers (architects and engineers), should be reduced by:
who should ensure that the risks created as a result of their design, be - Proposing alternative solutions;
- Providing the coordinator,
reviewed through a systematic process and the resultant mitigated risk be contractors and end users
passed to the contractor. with adequate information
so as to prevent accidents
from happening. The designer
In specifying the design of a building or structure, the designer should
should
understand how the building or structure can be constructed, cleaned, The consideration to remove the
safety and health risks from the
understand
maintained, and decommissioned or demolished safely. He must therefore how the
design is not to limit designers in
study the design and look at the risks to those carrying out the proposed works terms of their creativity but to building or
and others affected by it, such as the public or people using the building or ensure that the designer in structure can
preparing a design avoids
structure in the future. be constructed,
foreseeable risks to the safety and
health of those who:
cleaned,
Carry out construction work maintained
including demolition; and
decommissioned
Clean any window or transparent
or demolished
or translucent wall, ceiling or roof
in or on a building or structure;
safely.
6 7

With regard to the structure being Competence of the


used as a workplace, the designer
should note that the WSH Act
Designer
imposes certain duties on the
Depending on the scope of works
occupier of a workplace.
required, a professional engineer
or an architect is required to be
While these duties are not imposed

Design for Safety


responsible for the design under
on the designer, he should
the Building Construction Act
consider such requirements in his
regulated by the Building and
design.

Coordinator
Construction Authority.
A competent designer therefore
A list of typical design hazards is
should:
included in Appendix A. The list
Have relevant qualifications as
serves as a reference for designers
required by the Professional
when doing design work, but does
Engineers Board or the Board of
not limit possible hazards to only In many construction projects, coordination between the client, the designer
Architects; and
those listed there.
and contractor is lacking, resulting in miscommunication of vital information
Have safety and health that could affect safety and health risks in the project.
experience.

To ensure continuity in information flow, the client should appoint a


suitably qualified Design for Safety Coordinator. The Design for Safety
A professional
Coordinator should follow through with the project from the design stage,
engineer or
to the construction stage until the handover to the client for maintenance.
an architect is
required to be
responsible As such, the Design for Safety Coordinator should be on-board
for the design the team as early as the concept design stage so as to facilitate the design
under the review.
Building
Control Act
regulated by
the Building
and Construction
Authority.
8 9

Duties of the Competence of the


Design for Safety Design for Safety
Coordinator Coordinator
They are: Before the engagement of any
Facilitate the process to involve coordinator, the competence
all stakeholders to review the of the coordinator should be
design and mitigate the risks; assessed. The coordinator should:
Have relevant experience
Maintain records of safety
and health issues arising from
the Design Review Process and
pertaining to the type of
construction works stipulated:
A total of 10 years of both
Client
actions taken; and design and construction
experience in any combination;
Ensure the relevant safety and The client plays a very important role in the process of the whole project. As
health information is passed Have relevant construction related
on to the contractor for his academic degree acceptable by a result of the client financing the project, he is able to influence many major
tendering and work purpose. recognised construction-related decisions in the project such as the engaging of the designers, coordinators,
institutions; and
contractors, etc., as well as type of design and materials used.
The Design for Safety Coordinator
should not be in-charge of Have safety and health
safety and health at the site, experience. As such, it is important to emphasize that the clients role is to ensure that
The coordinator nor should he take over the
adequate resources (time and finances) are provided for the design and
is a role that safety and health responsibilities The coordinator is a role that may
of the designer and the contractor. be undertaken by an independent construction of a safe building or safe workplace.
may be
individual or a person within the
undertaken However, he should ensure project team that is assigned to
by an relevant information on safety carry out the task of a coordinator.
independent and health is passed on to the In addition, he may take up more
individual or a designers, contractors and all than one project at any one time.
other relevant stakeholders at the
person within
appropriate time. In situations where coordinators
the project are taking on more than one
team that is project, they should still fulfill
assigned to their individual roles duties as
carry out the stipulated for each and every
project.
task of a
coordinator.
10 11

Duties of the Client Accidents are more prone to


happen if sufficient time is not
The client first fulfills his role allocated to address risks by
by choosing a competent implementing suitable control
coordinator and designer to measures.
undertake his project. The client
must demonstrate that he has The time allocated for the project

Main
checked the competence of the should be deemed sufficient by
coordinator and designer and not the designer and coordinator and

Contractor
merely appoint them based on the agreed by the contractor when
fees quoted. tendering for the project. This
should be supplemented by some
In addition, while the client has form of project planning by
the right to specify the type of any stakeholder to show the
construction and materials he practicality of the time frame.
requires for the project, he has Where identified hazards or risks are not eliminated/mitigated at the design
to be advised by the coordinator The client should also provide
phase, the residual risks must be addressed and managed by the main
and designer on the safety and relevant information that is needed
by the project team to enable them contractors and sub-contractors during the construction phase.
health aspects of the design. This
does not mean the client is limited to carry out their duties properly
to making choices that limit the at different stages of the project.
Main contractors, being responsible for the planning, management and
creativity of the designer, but all For the concept design stage, the
information could include as-built co-ordination of construction works, play a critical role in ensuring that
risks and hazards arising from the
The client must drawings of existing buildings on
design should be mitigated. hazards identified, both prior to and during the actual construction works,
demonstrate site, topographical surveys, soil
are properly addressed. To enable the effective management of safety and
that he has As such, it is vital that the client investigation reports and existing
checked the participates in the Design Review utility services. This information health during the construction phase, it is essential that relevant information
Process so as to be kept informed could be passed on to the project pertaining to risks identified during the design stage be provided to main
competence of
on the basis of the design and team in the form of a Site Risk
the coordinator Register. contractors. Where possible, main contractors should be involved in identifying
other important design or safety
and designer decisions. and through design mitigating the occupational safety and health risks at the
and not merely Finally, when appointing a contractor
concept or detailed design phase, e.g. a main contractor may be involved in the
appoint them Besides being advised by the for the project, the client must
ensure he selects the contractor detailed design phase of a design and build project.
based on the coordinator and designer on the
safety and technical aspects of the based on some form of assessment
fees quoted. based on both the price and
design, the client should also be
advised on the time required for quality. BCAs Price Quality Method
the completion of the project. is one method that could be used.
12

Duties of the He should also ensure that all


sub-contractors are provided with
Main Contractor the required information to enable
them to carry out the works safely.
The main contractor must be
competent to carry out the work
Upon being awarded the contract,
that he is engaged to do in a safe
the main contractor should
manner.
arrange with the Design for
Safety Coordinator along with
In addition, the main contractor
the designers for temporary
should ensure that sub-contractors
works, specialist designers, etc. to
and designers engaged to carry
carry out a design review prior to
out the works are competent and
commencement of works.

the
adequately resourced.

The main contractor should, in


discussion with sub-contractors
carrying out the works, take

GUIDE
reasonable steps to ensure that
risks identified are properly
managed.

The main

Process
contractor
must be
competent to
carry out the
work that he is
engaged to do
in a safe
manner.
14 15

Steps in Steps 3 and 4 should be iterative


and repeated until the review team
Conducting GUIDE is satisfied that the design can
no longer be changed to totally
1. G Group together a review
eliminate all risks.
team consisting of major
stakeholders.

The 2.

U Understand the full design
concept by looking at the

Guide Process

drawings and calculations,
or have the designers elaborate
on the design.
Communication between
3. I Identify the risks that arise stakeholders is key to safe design.

as a result of the design or


To ensure the design is safe, a Design Review Process is introduced in the
construction method. The risks
project flow. The safety and health (SH) review committee should consist should be recorded and
of the main key stakeholders, such as the client, design engineer, architect, analysed to see if they can be
eliminated by changing the
Design for Safety Coordinator and contractor if he is on board design.
already. The SH review committee should be chaired and facilitated by the
4. D Design around the risks
Design for Safety Coordinator. There should also be a systematic
identified to eliminate or to There should
process whereby the risks of the design are highlighted, reviewed and mitigate the risks.
also be a
recorded.
5. E Enter all the information
systematic
including vital design change process
The outcome of the review process should be a safe design endorsed by information affecting safety whereby the
all parties and a record of the resultant hazards or vital safety and health and health or remaining risks risks of the
to be mitigated into the Safety
information. To assist the stakeholders in reviewing the design, a process design are
and Health Risk Register.
called GUIDE is recommended. highlighted,
The GUIDE Process should be reviewed and
chaired by the Design for Safety recorded.
Coordinator who should be
suitably qualified in both safety
and technical aspects so as to
guide the review team to identify
and manage the hazards.
17

Implementation

Imple
The design of the project is often done in two stages, the concept design
stage and the detailed (final) design stage. In order to influence the design
and identify the risks as early as possible, it is proposed that the GUIDE
Process be done in the various stages of the project. In addition, doing the
GUIDE Process in different phases also ensures that the review team can
concentrate on a smaller scope during each process, thereby reducing the

mentation
possibility of missing out on any significant item.

It is recommended that the GUIDE Process be done in three phases:


GUIDE-1: Concept Design Review
GUIDE-2: Detailed Design, Maintenance and Repair Review
GUIDE-3: Pre-Construction Review
18 19

Guide 1 - Concept Design Review


Guide 2 - Detailed Design,
Key Focus for GUIDE A sample of topics that can be
Maintenance and Repair Review discussed for GUIDE-1, GUIDE-2
Guide 3 - Pre-Construction
Design Review The key aspects to be covered, and GUIDE-3 are enclosed in
when doing GUIDE, are suggested Appendix B, Appendix C and
(but not limited) as follows: Appendix D, respectively. The
Site Risk Concept Detailed Tender Construction Maintenance
Register Design Design Stage Stage Stage General Design Concept hazards highlighted then should be
singled out and addressed in the
Accessibility Safety and Health Risk Assessment
Form covered in Appendix E.
Confined Space The residual hazards should be
Client Designer Coordinator Contractor
highlighted to the contractor to
Emergency ensure that they will be dealt with.

S and H Risk Register


(SHRR)
Lighting The project team should note that
while the lists for GUIDE-1, GUIDE-2
Excavation and GUIDE-3 serve as a reference,
there may be other topics not
Guide Process For Design and Build contracts
Fall Prevention
where the contractor is in-charge discussed in the lists that are
Flow Diagram of the design of the project, specific to the project itself. The
Working Platforms project team should therefore
GUIDE-2 should be done with the
GUIDE-1: Concept design review diligently consider other safety
contractors input. He can then
should look at general location of Hoisting/ Weight
highlight constraints that he and health risks that could exist as
the project, traffic and vehicular a result of the design.
will face when constructing the Layout
flow in the surroundings, type of
building or structure. This would
building, and other general
further help in the GUIDE process. Maintenance
constraints.

GUIDE-3: Pre-construction design Material Handling/ Storage


GUIDE-2: Detailed design,
review should examine temporary
maintenance and repair review Adequate provisions
works design and design by Means/ Methods
should look at the detailed for temporary works
specialist contractors not covered during the design
architectural and structural stage minimises risks
during the concept and detailed Operation
design. The review should also during construction.
design phases.
determine the risks involved in
Physical Hazards
the construction methods, the
access and egress, whether the Sequence
design will create confined space Designing a structure
or other hazards. The risks related so that work does not
Standardisation need to be performed
to maintenance and repair of the at height will prevent
building, such as the cleaning Weather fall incidents e.g.
lifting and erection of
methods, should also be studied.
a hangars roof truss.
21

Safety and Health


Risk Register

Record
The Safety and Health Risk Register should be a live document whereby risks
identified from the design stage are recorded and kept for future reference. It
should also record risks that cannot be removed through design changes and
highlight them to the contractor during the tendering stage.

Keeping
Such a document will bring about transparency in the tender process so
that the contractor is pre-warned of the project hazards and the difficulties
faced. He will then be able to accurately price for the project, reducing
possibilities of any under-pricing and therefore inability to complete the
project.
22

The items that should be in the The Safety and Health Risk Register
Safety and Health Risk Register are should be kept by the
as follows: Design for Safety Coordinator
Records of GUIDE-1, 2 and 3 before handing over to the client.
and records of the resultant
changes or risks to be mitigated. The Design for Safety Coordinator
should be responsible for ensuring
Relevant safety and health that relevant information is
information that the contractor recorded and made available to
and the client should take the stakeholders for their work.
note of.

Construction method advisory


notes by the designers as

Gloss
guidance notes to the
contractor for building and
demolition in the future.

Maintenance method advisory


notes by the designer and/or

ary
contractor as guidance notes to
the owner.

The Safety Safe Operating Procedures


and Health for use and maintenance of
Risk Register equipment / machinery of
should be a the completed building e.g.
gondolas, scissor lifts, etc.
live document
whereby risks
identified from
the design
stage are
recorded and
kept for future
reference.
24

Term DEFINITION

Designer Anyone who creates or contributes to the complete design or the


partial design of a road, a building, a bridge, a tunnel, a dam or any
other civil engineering works.

Principal A person who, in connection with any trade, business, profession or


undertaking carried on by him, engages any other person otherwise
than under a contract of service
- to supply labour for gain or reward; or
- to do work for any gain or reward.

Risk Likelihood that a hazard will cause a specific harm or injury to someone

Appen
or something. More specifically, it is the likelihood of accidents or
ill-health occurring at work and the consequences of such occurrences.

Design Plans, calculations and drawings that dictate what the end product of
the project should be.

Concept Design The initial planned design of the projects layout, type of building or

dices
structure, etc.

Detailed Design The final design of the projects outlook, the layout, the supporting
structures and the materials.
26 27

Eliminating materials that could be installed.


create a significant fire risk during
Appendix A construction. 6. D e s i g n t o s i m p l i f y s a f e
construction by:
4. Consider prefabrication to Providing lifting points on
minimise hazardous work on prefabricated elements and
To aid the designers in carrying disturbance of existing site, for example: marking the weight and the
out the guide process, this section asbestos, cutting chases in Designing elements like steel centre of gravity of heavy
identifies some areas over which brickwork and concrete, breaking structures so that they can be or bulky items both on the
the designer has direct influence. down cast-in-situ piles to level, prefabricated and assembled drawings and on the items
Designers should note that the list scabbling concrete, manual on ground and then lifted to themselves;
is not exhaustive, nor is every item digging of tunnels, flame cutting position for installation;
relevant to every project. or sanding areas coated with Making provision for temporary
lead paint or cadmium; and Specifying cutting of steel works required during
Items that the designer should members to be done off-site, construction;
note are as follows: Specifying materials that under controlled conditions, to
1. The design of buildings or are easier to handle, e.g. reduce the amount of dust Designing joints in vertical
structures should consider risk lightweight building blocks, created; and steel structure members such
from site hazards such as: limiting the weight of formwork that bolting can be easily done
Underground services; for easier handling. Reducing site welding so as to by someone standing on the
reduce fire or burn risks and floor using seating angles to
Vehicular traffic movements to 3. Safety hazards should be using prefabricated bolt and provide support while bolting
and within the site; designed out by: nuts as connections. is being done;
Remove the Removing the need to work Features that
need to work Pedestrian movements within at height wherever possible, 5. Fe a t u re s t h a t re d u c e o r Designing connections to reduce or
and around the site; and particularly where it requires eliminate the risk of falling minimise risk of incorrect
at height eliminate the
work from ladders or where should be introduced where it assembly and providing clear
wherever Condition and proximity of safe means of access cannot be risk of falling
is not possible to remove the directions on drawings; and
possible, adjacent buildings. provided; should be
need to work at height:
particularly Early installation of permanent Designing for safe installation introduced
where it 2. Health hazards should be Removing fragile roofing access, such as stairs, to reduce of external cladding i.e. where it is not
designed out by: materials or designing access the use of ladder or scaffolds; installation of cladding from the
requires work possible to
Specifying less hazardous route to the roof including a inside of the building.
from ladders materials, e.g. solvent-free or working platform; remove the
Edge protection or other
or where safe low solvent adhesives and need to work
features that increase the safety 7. Identify worst case scenarios
means of water-based paints; Eliminating deep or long of access and construction; and and implement the preventive at height.
access cannot excavations in public areas or control measures, such as:
Avoiding processes that create on highways; and Anchor points for installation Designing adequate safety
be provided.
hazardous fumes, vapors, dust, of life-line or safety harnesses factors such that overloading
noise or vibration, including when a work platform cannot (static, dynamic and impact)
28 29

and collapse of permanent or system for easy access and


temporary structure are not maintenance; design should be
possible; flexible to accommodate minor Appendix B
changes to building usage; and
Putting in place monitoring
instrumentation that provide Considering safe movement of
early warning of possible pedestrian and vehicular traffic Sample GUIDE-1: Concept Design Review
collapse or ground movements; flow during occupancy.
and The purpose of GUIDE-1 is to review the conceptual design and identify the critical risks
9. Identify unusual demolition associated with the construction, maintenance, repair and demolition of the project. By
Emergency route for mass hazards for future plans: identifying and understanding the risks very early in the life cycle of the project, risk controls
evacuation in the event of Sources of substantial stored can be established to ensure that these risks are managed either by eliminating or controlling
emergency. energy, such as pre- or them.
post-tension cables;
8. Design to simplify future Sometimes, risks identified in GUIDE-1 can only be addressed later in the project when more
maintenance and cleaning work Unusual stability concepts; of the project details are known. However, the highlighting of the risk aids the designer
by: in understanding the feasibility as well as the hazards associated with the project. The
Making provision for safe Alterations that have changed designer may be well-informed but not equipped with WSH knowledge. As such, GUIDE-1
permanent access; the structure significantly; and should be done by a group of key stakeholders and not only by the designer in isolation.
The contribution of the various people will therefore help to ensure that safety at every
Specifying windows that can be Embedded materials, utilities, stage and level is examined and discussed. The primary concern of GUIDE-1 will be on
cleaned from the inside; or artefacts whose exposure the safety issues related to the LOCATION of the project. LOCATION determines several
or removal may introduce new major considerations such as soil assessment, the public, the existing services and the
The designer Placing all controls and electrical hazards. placement of major machinery. GUIDE-1 therefore needs to examine the issues associated
need not boxes at accessible locations; and highlight the risks and hazards arising.
design out The designer is to note that their
every single Designing safe access to the creativity should not be limited by To aid the GUIDE-1 Review Team, a series of questions are tabulated. While the questions
roof; the above, but safety and health may highlight important issues, they serve only as a reference for the team and may not be
hazard
requirements should still be comprehensive. As such, the team should still have a brainstorming session which will be
identified, Making provision for safe evaluated. The designer need not more effective in highlighting the hazards and concerns of the key stakeholders.
but he should temporary access to allow design out every single hazard
weigh the risk for painting and maintenance identified, but he should weigh the Details / Hazards
Considerations
level of the of facades, etc.; risk level of the hazards and as far Identified
as reasonably possible, design out
hazards and Has the soil profile of the site of the proposed
Using paints or materials the risks either by eliminating the
as far as project been studied by the QP?
that require less frequent hazards or incorporating control
Solid
reasonably maintenance or replacement; measures to reduce the risks to
Are there buildings or structures that may have
possible design acceptable levels.
shallow foundation in the vicinity of the proposed
out the risks. Designing the ventilation
project?
30 31

Having answered the above list of questions and highlighting the hazards, the hazards
identified should then be transferred to a Safety and Health Risk Assessment Form (Appendix E).
Will there be possible lowering of ground water
table as a result of the proposed construction? The form allows for the hazards and control measures to be indicated and the Review Team
should then agree on the party to be assigned to take the actions to further address the hazard.
Will there be possible settlement due to the A follow-up review should be done to ensure that the hazards to be addressed are not merely
proposed project? shelved and filed away for information. Other considerations by the review team or actions
done to mitigate the risks should be documented in the Safety and Health Risk Assessment form
Are there any possible preventive measures to so as to ensure that all relevant information is captured.
ensure settlement is minimised?
At concept design stage, unless the exercising of GUIDE-1 proves that a redesign/relocation
of the project is required, all issues can be addressed in the detailed design stage. As such
Will the commencement of the project typically GUIDE-1 needs only to be performed once.
affect the public in any way?
Public

Design issues highlighted in GUIDE-1 should be addressed by the designers when doing the
Will the commencement of the project detailed design. GUIDE-2 will hence be a session to identify the new hazards as well as
affect the traffic in any way? ensure hazards raised in GUIDE-1 are followed through and mitigated.

Are there underground services in the site that


need to be removed for the project?
Services

Will the removal of these services, if any, be a


hazard to the workers or the public?

Are there any special features that require special


arrangements during construction?

Can the method of construction/sequence be


identified at present?
Others

Are there any hazards associated with the method


of construction/ sequence that can be dealt with
at present?

Are there any foreseeable hazards that can be


identified and eliminated?
32 33

Can prefabricated elements be provided with

Appendix C designed lifting points, and the weight, the centre-


of-gravity marked on the drawings and on the items?

If the prefabricated structure is required to be


temporarily suspended for a period of time before
Sample GUIDE-2: Detailed Design, Maintenance and Repair Review final installation, are there means to ensure the
hazards arising are removed?
GUIDE-2 serves to assist designers to review the detailed design where most of the design
is in process but still subject to possible modifications. By the time GUIDE-2 is implemented Can joints in vertical steel structure members be
the design intent should have been finalised, making the identification of hazards easier. In designed such that bolting can be done while on
addition, the maintenance and repair methodology should also be reviewed at this stage, the ground?
such that required maintenance or repair issues can be addressed.
Can connections be designed to minimise risk
While GUIDE-2 serves to address these new hazards, the issues raised during GUIDE-1 should of incorrect assembly (e.g. unique bolt layout for
also be reviewed and closed out if possible. each connection) and clear instructions provided
on drawings?
GUIDE-2 should be done by the key stakeholders and not just the designer in isolation. It
is important that proper documentation be done so as to ensure relevant information are
Consider the work process and the equipment
passed on and kept in the Safety and Health Risk Register (SHRR).
required for heavy lifting. Can the position for
parking of these equipment be finalised and
A series of questions are tabulated below to aid the GUIDE-2 Review Team. While the
cordoned off?

Heavy Lifting
questions may highlight important issues, they serve only as a reference for the team
and may not be comprehensive. As such, the team should still have a brainstorming
Does a foundation for these lifting equipment
session which will be more effective in highlighting the hazards and concerns of the key
need to be designed so as to minimise settlement
stakeholders.
and failure of support?
Details / Hazards
Considerations
Identified
Consider the worst case scenario. Can this scenario
Can elements such as steel structures be be prevented or managed to minimise injuries?
prefabricated, assembled on ground and then
lifted to position for installation?
Can the need to work at height be removed?

Falling from Height


Prefabrication

E.g. removing the need to work from ladders,


Can the cutting of steel members be done
removing the need to work where a safe means of
off-site, under controlled conditions to reduce
access cannot be provided.
the dust created?

Can fragile roofing materials be removed or an


Can site welding be reduced so as to reduce fire or
burn risks and prefabricated nuts and bolts used alternative access route (including a work
as connections? platform) to the roof be designed?
34 35

Can there be early installation of permanent Can the layout be optimised to prevent any
access, such as stairs, to reduce the use of ladders accidents from the flow of traffic, pedestrian,
or scaffolds? equipment, etc. within and around the site during
the construction stage?
Can edge protection or other features that increase
the safety of access and construction be designed Consider the flow of traffic, pedestrian, equipment

Layout
and installed? within and around the site during the permanent
stage. Can the layout be optimised to prevent any
Can anchor points for installation of life-line accidents?
or safety harnesses be mounted where work
platforms cannot be installed? Is there a need to designate specific material,
equipment, vehicular and human traffic flow
Can floor openings, if any, be minimised? diagram?

Can a safer means of access or egress be used


instead of the temporary means required? Does the design create any confined space in the
permanent or temporary stage?

Confined Space
Can the permanent staircase and lifts be completed
first and used during the construction stage? Can the confined space be removed from the
design?
Will the design affect the work process and stages
Can the requirement to enter the confined space
Temporary Works and Sequencing

during construction?
be minimised by removal of vital equipment or
Can temporary works required during construction controls from the confined space?
be planned for? E.g. specifying the type and position
of the temporary works so as to ensure spatial

Emergency Route
Is the emergency route for both the temporary and
considerations have been considered.
permanent stages the shortest and most direct?

Are there special construction considerations that


In the emergency route, is there adequate
need to be highlighted to the contractor for his
lighting, directions, warning and backup power
construction?
for mass evacuation of people?

Does the sequence of construction create any


temporary unstable working platform, which

Health Hazards
requires additional bracing? Can less hazardous materials be specified?
E.g. solvent-free or low solvent adhesives and
Can adequate safety factors be incorporated in the water-based paints.
design such that overloading or collapse of the
permanent or temporary structure is not possible?
36 37

Can processes that create hazardous fumes, Can alterations that have changed the structure
vapors, dust, noise or vibration be avoided? significantly be highlighted?
E.g. disturbing existing asbestos, cutting chases
in brickwork and concrete, breaking down Can disruptions to existing utilities within
cast-in-situ piles to level, scrabbling concrete, occupied buildings be avoided?
hand-digging tunnels, flame cutting or sanding
areas coated with lead paint or cadmium.

Can materials that are easier to handle be
specified? E.g. lightweight building blocks, Having answered the above list of questions and highlighting the hazards, the hazards
limiting the weight of formwork components to identified should then be transferred to a Safety and Health Risk Assessment Form (Appendix E).
less than 25kg. The form allows for the hazards and control measures to be indicated and the Review
Team should then agree on the party to be assigned to take the actions to further address
Is there a possibility of floods in the site? If so, how the hazard. A follow-up review should be done to ensure that the hazards to be addressed are
can the hazard be minimised in the temporary and not merely shelved and filed away for information. Other considerations by the review team
permanent stages? or actions taken to mitigate the risks should be documented in the Safety and Health Risk
Assessment form so as to ensure that all relevant information is captured.
Is there a possibility of lightning strike in the site?
If so, how can the hazard be minimised in the As mentioned previously, design issues highlighted in GUIDE-1 should be addressed by the
Weather

temporary and permanent stages? designers when doing the detailed design. GUIDE-2 will hence be a session to identify
the new hazards as well as ensuring hazards raised in GUIDE-1 are followed through and
Are there any other adverse weather conditions that mitigated.
can affect the ability to safely construct the work?

What are the effects of extreme temperature or


humidity on instrumentation?

Can monitoring instrumentation that provides


early warning of possible collapse or ground
movements be installed?
Others

Are there any other major hazards that need


to be dealt with? Can materials that can create
significant fire risk be removed?

Can sources of substantial stored energy, such


as pre- or post-tension cables be specified in the
drawings and highlighted for future demolition?
38 39

Appendix D
Can temporary works required during
construction be planned for? E.g. specifying the
type, position of the temporary works so as to
Sample GUIDE-3: Pre-Construction Review ensure spatial considerations have been
considered.
Temporary works design and design for elements provided by specialist contractors are
often included as part of the scope of works in construction contracts. Where such design Are there special construction considerations that
elements are not covered during the concept design and detailed design stages of the need to be highlighted to the contractor for his
project, risks and hazards associated with the design and methods of construction should construction?
be identified and addressed prior to commencement of works.
Does the sequence of construction create
GUIDE-3 aims to provide coordinators with a tool to identify and address risks associated any temporary unstable stage, which requires
with temporary works design and designs provided by specialist contractors. additional bracing?

Along with the key stakeholders involved in GUIDE-1 and GUIDE-2, the main contractor and Can adequate safety factors be incorporated in
his appointed designers and specialist contractors should be a part of the GUIDE-3 process the design such that overloading or collapse of
Review Team. Similar to GUIDE-2, it is important that proper documentation be done so the permanent or temporary structure is not
as to ensure that relevant information is passed on and documented in the Safety and possible?
Health Risk Register (SHRR).
Will there be possible basal heave and piping
To aid the GUIDE-3 Review Team, a series of questions are tabulated. While the questions during excavation?
may highlight important issues, they serve only as a reference for the team and may not be
comprehensive. As such, the team should still have a abrainstorming session which will be Will there be possible settlement due to the
more effective in highlighting the hazards and concerns of the key stakeholders. proposed project?

Details / Hazards
Considerations
Identified
Has a proper schedule for monitoring of
instrumentation been provided?

Can a safer means of access or egress be used


Will there be any adverse effects on
Temporary Works and

instead of the temporary means required?


adjacent structures during the removal of
Sequencing

temporary works?
Can the permanent staircase and lifts be completed
first and used during the construction stage?
Are there any alternatives or measures that could
reduce or minimise such adverse effects?
Will the design affect the work process and stages
during construction?
40 41

Are there any safety concerns on elements of


Specialist Design specialist design to be considered by the main
contractor?
Appendix E
Sample Safety and Health Risk
Assessment Form
Can alternative safe work practices be employed
to mitigate such concerns?

Action
By
required?
Further
review
Others

Have the risks and hazards identified in GUIDE-1


and GUIDE-2 been addressed or mitigated?

hood Level
Likeli- Risk
Residual Risk Level
SAFETY AND HEALTH RISK ASSESMENT FORM

Severity
Having answered the above list of questions and highlighted the hazards, the hazards
identified should then be transferred to a Safety and Health Risk Assessment Form (Appendix E).

Proposed Control
Measures
The form allows for the hazards and control measures to be indicated and the Review

Conducted by:
Team should then agree on the party to be assigned to take the actions to further address
the hazard. A follow-up review should be done to ensure that the hazards to be addressed
are not merely shelved and filed away for information. Other considerations by the review

designed out?
hazards be
Can these
team or actions done to mitigate the risks should be documented in the Safety and Health Risk
Assessment form so as to ensure that all relevant information is captured.

Level
After going through the GUIDE-3 process, a session should be held to identify the new hazards

Risk
Risk Assessment
as well as ensure hazards raised in GUIDE-1 and GUIDE-2 are followed through and mitigated.

Likeli-
hood
Severity

Attachment: GUIDE 1, GUIDE 2, GUIDE 3

Project Safety and Health Coordinator


Identified
Hazards
Risks
Process/ Location:
Next review date:

Consider-
Review date:

Endorsed by:
Design
Project Title

ation
Company:
Review:

S/No.
42

Acknowledgements

We wish to thank the following organisations for the images used in this publication:
Bovis Lend Lease Pte Ltd
Dragages Singapore Pte Ltd

Contributors
Association of Consulting Engineers Singapore
Building and Construction Authority
Institution of Engineers Singapore
Land Transport Authority
Lend Lease
Ministry of Manpower
Real Estate Developers Association of Singapore
Singapore Contractor Association Limited
Singapore Institute of Architects
Singapore Institute of Surveyors and Valuers
The Institution of Engineers Singapore
Woh Hup Pte Ltd
Workplace Safety and Health Council

Vous aimerez peut-être aussi