Vous êtes sur la page 1sur 3

Company Job

Mellitah Oil & Gas BV


Saipem S.p.A. GAS DIVISION
C/584/ME/08
LIBYAN BRANCH

Plant Contractor Job No. .


MELLITAH COMPLEX
Production Enhancement Project 032074

ENGINEERING DOSSIER Sh. 1 of 6 .

Pre COMMISSIOING MANUAL

SECTION 7
Company Job
Saipem S.p.A. Mellitah Oil & Gas BV
GAS DIVISION
C/584/ME/08
LIBYAN BRANCH

Plant Contractor Job No.


MELLITAH COMPLEX
Production Enhancement Project 032074

Sh. 2 of 6
MECHANICAL COMPLETION

7 GENERAL

The job documents relevant the precommissioning of the plant and of the new Air Dryer
Package are listed in the following section.

Company Number rev Contractor Number Title

402382-063-M-N-0004 00 C1 40460-MG-E-30533 Installation & precommissioning manual


CONTENTS OF PRECOMMISSIONING &
G-50-P-Z-0004 00 P2 50-000-ZA-E-03071 COMMISSIONING MANUALS FOR MELLITAH
PLANT
PRECOMMISSIONING AND COMMISSIONING
G-50-P-Z-0009 00 A1 50-000-ZA-E-03900
MANUAL FOR MELLITAH PLANT

_______________________________

Form code: MDT.GG.QUA.0004 Sh. 01/Rev. 3.96 File code: agipspcve.dot Data file: 365605536.doc
This document is CONFIDENTIAL and the sole property of the WLGP. It shall neither be shown to third parties nor used for other purposes than those for
which it has been issued/sent. Any unauthorized attempt to reproduce it, in any form, is strictly prohibited.
Company Job
Mellitah Oil & Gas BV
Saipem S.p.A. GAS DIVISION
C/584/ME/08
LIBYAN BRANCH

Plant Contractor Job No. .


MELLITAH COMPLEX
Production Enhancement Project 032074

ENGINEERING DOSSIER Sh. 3 of 6 .

Vous aimerez peut-être aussi