Académique Documents
Professionnel Documents
Culture Documents
CPM-PERT
Activity-On-Node (AON) Example
With Project Crashing
2014
2014
Pearson
Pearson
Education,
Education,
Inc.Inc. 3-1
AON Example
Table 3.1 Milwaukee Paper Manufacturings Activities and Predecessors
IMMEDIATE
ACTIVITY DESCRIPTION PREDECESSORS
A Build internal components
B Modify roof and floor
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G
1
07/03/17
Activity A
A (Build Internal Components)
Start
Activity B
Start B (Modify Roof and Floor)
Activity
Figure 3.5
A C
Start
B D
2
07/03/17
F
A C
E
Start H
B D G
H
Dummy 7
E
1 6
Activity (Inspect/
Test)
G l
al
st n
I( n llutio e)
ic
3
D
5 Po ev
D
(Pour Figure 3.8
Concrete/
Install Frame)
2014 Pearson Education, Inc. 3-6
3
07/03/17
4
07/03/17
Activity Name
or Symbol
A Earliest
Earliest ES EF Finish
Start
Latest LS LF Latest
Start 2 Finish
Activity Duration
2014 Pearson Education, Inc. 3 - 10
5
07/03/17
Forward Pass
Begin at starting event and work forward
Forward Pass
Begin at starting event and work forward
EF = ES + Activity time
6
07/03/17
ES EF = ES + Activity time
Start
0 0
7
07/03/17
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
2014 Pearson Education, Inc. 3 - 15
2 2
Start
0 0
B
0 3
8
07/03/17
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
2014 Pearson Education, Inc. 3 - 17
2 2
Start
0 0
B D
0 3 3 7
3 4
9
07/03/17
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Figure 3.10
2014 Pearson Education, Inc. 3 - 19
Backward Pass
Begin with the last event and work backwards
Latest Finish Time Rule:
10
07/03/17
Backward Pass
Begin with the last event and work backwards
Latest Start Time Rule:
LS = LF Activity time
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B LS = LF
D Activity timeG
0 3 3 7 8 13
3 4 5 LF = EF
of Project
2014 Pearson Education, Inc. 3 - 22
11
07/03/17
10 13
2 2 3
Start E H
0 0
LF 4= Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
12
07/03/17
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Slack = LS ES or Slack = LF EF
13
07/03/17
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
14
07/03/17
ES EF Gantt Chart
for Milwaukee Paper
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
LS LF Gantt Chart
for Milwaukee Paper
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution
device
H Inspect and test
15
07/03/17
t = (a + 4m + b)/6
Variance ofoftimes:
Probability
1 in 100 of Probability of
Probability
< a occurring
v = [(b a)/6]2 1occurring
in 100 of > b
Activity
Time
Computing Variance
TABLE 3.4 Time Es.mates (in weeks) for Milwaukee Papers Project
MOST
OPTIMISTIC LIKELY PESSIMISTIC EXPECTED TIME VARIANCE
ACTIVITY a m b t = (a + 4m + b)/6 [(b a)/6]2
A 1 2 3 2 .11
B 2 3 4 3 .11
C 1 2 3 2 .11
D 2 4 6 4 .44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 .11
16
07/03/17
Probability of Project
Completion
Project variance is computed by
summing the variances of critical
activities
p2 = Project variance
= (variances of activities
on critical path)
Probability of Project
Completion
Project variance is computed by
summing the variances of critical
Project variance
activities
2p = .11 + .11 + 1.00 + 1.78 + .11 = 3.11
17
07/03/17
Probability of Project
Completion
Figure 3.12
Standard deviation = 1.76 weeks
15 Weeks
(Expected Completion Time)
Probability of Project
Completion
What is the probability this project can
be completed on or before the 16 week
deadline?
Due
Z = date Expected date
of completion /p
= (16 weeks 15 weeks)/1.76
18
07/03/17
Probability of Project
Completion
From Appendix I (Z table)
What is the probability
.00 .01 this project
.07 can
.08
be completed on or before
.1 .50000 .50399
the 16 week
.52790 .53188
deadline?.2 .53983 .54380 .56749 .57142
due
.5 Z.69146
= date expected
.69497
date
.71566 /
of completion .71904
p
.6 .72575 .72907 .74857 .75175
= (16 wks 15 wks)/1.76
Probability of Project
Completion
0.57 Standard deviations
Probability
(T 16 weeks)
is 71.57%
15 16 Time
Weeks Weeks
Figure 3.13
19
07/03/17
Determining Project
Completion Time
Probability
of 0.99
Probability
of 0.01
2.33 Standard Z
From Appendix I deviations
0 2.33
Figure 3.14
20
07/03/17
21
07/03/17
$30,000
Normal
Normal
Cost
| | |
1 2 3 Time (Weeks)
Figure 3.15
Crash Time Normal Time
2014 Pearson Education, Inc. 3 - 43
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
0 0 4 8 13 15
0 4 2
B D Slack = 0 G Slack = 0
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
22