Académique Documents
Professionnel Documents
Culture Documents
R.Seshadri
Larsen & Toubro Limited
Mysore works
Rev.1: P K Sharma
-1-
1.0 Introduction :
Following sections describe a typical scheme for auto Load sharing of 3 nos.
DG sets connected in parallel to a common bus in a plant. The load sharing
scheme described can be envisaged for a building / hospital /hotel complex or
any industry. The plant equipments are :
Under normal conditions the plant will be operating from the local SEB
supply. When the SEB supply fails, the three DG sets will be synchronized to
the plant bus and they will start feeding the plant load.
When the three DGs are in parallel, and are feeding the same load, any of the
following events can happen – if the load sharing scheme is not in place :
………………….2
-2-
a) Cascaded Tripping : One of the DGs , can get over loaded and trip –
causing the remaining DGs to get over loaded and trip . This happens
due to mis-match in DG makes, age, and size. The most efficient /
largest DG will try and swallow the entire plant load – will get over
loaded in the process- will trip on over load and cause cascaded tripping
of remaining DGs.
b) Hunting of DGs : It should be noted that the plant load may not remain
constant – it would normally be fluctuating. The operator may stabilize
the DGs ( by setting the kW & kVAR outputs) at one level of plant
load – if the load changes, the operator is required to stabilize the DGs
again.
As can be seen this is a continuous process – the operator will be busy
handling the DG controls with every fluctuation in plant load. If the
fluctuations are frequent, then the DGs may under go hunting – rapid
rise/ fall in speed till the operator arrives at correct out put settings. If
the operator does not respond quickly , there can be reverse power into
DGs and may result in heavy damage to DGs.
d) Poor power factor : One or more generators may run on a poor PF,
depending upon the ratio of its kw output to kVAR output.
Following sections give a more detailed idea on how the proposed system
achieves the above scope of work.
a) 3 nos. Load sharing Relays , for active power kW ( one per DG)
b) 3 nos. Load sharing Relays, for reactive power kVAR ( one per DG)
c) 1 no. Auto / Manual Switch
d) 9 nos. PBs – for inc / dec signals of Voltage & frequency of each DG
set
e) 2 nos. comprehensive measuring instrument QUASAR
The heart of the system is the Auto load sharing relay (LSR) type RRS. This
relay has the following features (please refer fig.3).
a) RRS continuously measures the power out put of each DG. If set in kW
mode , it will measure active power. If set in kVAR mode, it will
measure reactive power.
b) RRS gives three relay out put contacts. One is increase pulse . The
second is decrease pulse. The third is over power contact. If RRS is
used as kW controller, the inc / dec pulses are given to the governor
controls of DG set. If RRS is used as kVAR controller, the inc / dec
pulses are given to the exciter controls of the DG set. The over power
contact is used as a over power monitor / protection.
………….6
-6-
Please see fig. 4 which shows typical connection of two RRS relays, one for
each DG. Both RRS relays are for kW control. Please note that the DC
voltage out put terminals of each RRS (14 & 15) are connected as a DC bus.
Under this condition, the status of the RRS out puts will be as shown in the
table in fig .4. Points to be noted are :
5.0 Frequency Control: The system also ensures that load sharing is performed
at 50 Hz( + or – 0.5Hz), when the frequency control is enabled. The master
DG will run at 50 HZ and the slaves DGs will follow the the master, to
maintain the speed of the system at 50Hz equivalent.
In this case all RRS relays are totally disabled. The relays will not give any
pulse out puts. The operator has to maintain the output levels of each DG by
means of front panel inc/dec push buttons.
The above sections explain the general guidelines, control actions and
hardware required for auto load sharing scheme. There can be minor
variations, additional requirements based on the specific needs of an actual
installation. On receipt of an order, L&T will be pleased to provide all
customers an elaborate control circuit wiring diagram for implementing the
entire scheme.
oooooOOOOO&$&OOOOOooooo