Sucesoras Factor Metrado Precio Parcial Rendimiento 03 sep '17 10 sep '17 17 sep '17 24 sep '17 01 oct '17 08 oct '17 15 oct '17 22 oct '17 29 oct '17 05 nov '17 12 nov '17
cuadrillas Unitario J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L
1 INSTALACIONES ELECTRICAS 43.64 das vie 01/09/17 jue 09/11/17 S 223,656.00
3 01.01 GIGANTOGRAFIA DE 5,00 x 3,50 m 1 da sb 02/09/17 lun 04/09/17 5 4 1 1832.8 1832.8 1 S 1,782.20
4 01.02 TRAZO Y REPLANTEO TOPOGRAFICO 0.28 das lun 04/09/17 lun 04/09/17 3 9 0.7 1067.48 747.24 2.5 S 205.73
9 02.02 EXCAVACION DE HOYO EN TERRENO ROCOSO 7 das lun 04/09/17 vie 15/09/17 4 8 3 21 2250.47 47259.87 1 S 46,150.27
10 02.03 POSTE DE CONCRETO 9 m/200 Kg 1.88 das lun 18/09/17 jue 21/09/17 8 11 15 1105.29 16579.35 8 S 16,061.95
11 02.04 POSTE DE CONCRETO 9 m/300 Kg 0.75 das jue 21/09/17 vie 22/09/17 10 12,15 6 1139.68 6838.08 8 S 6,089.86
12 02.05 CIMENTACION DE POSTE DE CONCRETO 0.32 das vie 22/09/17 sb 23/09/17 11 8.09 192.28 1555.55 25 S 1,136.98
13 02.06 CODIFICACION DE POSTES DE B.T. 1.4 das jue 02/11/17 dom 05/11/17 6 48 21 50.23 1054.83 15 S 767.74
14 03 SUMINISTRO E INSTALACION DE RETENIDAS 10.46 das vie 22/09/17 lun 09/10/17 S 38,797.85
15 03.01 EXCAVACION DE HOYO EN TERRENO ROCOSO 7.17 das vie 22/09/17 mi 04/10/17 11 16 2 14.34 2250.47 32271.74 1 S 30,127.42
16 03.02 RETENIDA INCLINADA SIMPLE B.T. 0.57 das mi 04/10/17 jue 05/10/17 15 17 4 515.5 2062 7 S 1,871.59
17 03.03 RETENIDA VERTICAL B.T. 1.8 das jue 05/10/17 dom 08/10/17 16 18 9 714.36 6429.24 5 S 6,252.34
19 04 MONTAJE DE ARMADOS DE ESTRUCTURAS 10.88 das lun 09/10/17 vie 27/10/17 S 1,220.29
20 04.01 ARMADO TIPO S1 0.34 das lun 09/10/17 mar 10/10/17 21 24 12 46.92 563.04 35 S 371.53
21 04.02 ARMADO TIPO S2 0.04 das lun 09/10/17 lun 09/10/17 23 20 1 128.06 128.06 28 S 99.05
22 04.03 ARMADO TIPO S2.S 0.07 das jue 26/10/17 vie 27/10/17 24,37 44 2 230.66 461.32 28 S 405.11
23 04.04 ARMADO TIPO S3 0.17 das lun 09/10/17 lun 09/10/17 18 21 5 65.73 328.65 30 S 211.57
24 04.05 ARMADO TIPO S6 0.12 das mar 10/10/17 mar 10/10/17 20 22,26,30 3 74.13 222.39 25 S 133.03
27 05.02 CABLE ELECTRICO NYY 3-1x6 + 1x6mm2 0.53 das mi 11/10/17 jue 12/10/17 26 99.8 13.33 1330.33 190 S 1,174.40
28 05.03 CABLE ELECTRICO NYY T/1x6mm2 0.05 das mi 01/11/17 mi 01/11/17 42 9 5.73 51.57 190 S 23.73
29 06 SUMINISTRO E INSTALACION DE DUCTOS 9.92 das mar 10/10/17 jue 26/10/17 S 10,870.33
31 06.02 EXCAVACION EN TERRENO NORMAL 7.04 das mar 10/10/17 dom 22/10/17 30 32CC+2 das,37 2 28.15 70.49 1984.29 2 S 1,773.75
37 07.01 MANHOLES DE C.A. 0.80x0.80x1.20m INTERIOR 3 das dom 22/10/17 jue 26/10/17 31 22 3 878.31 2634.93 1 S 2,553.64
39 08.01 EXCAVACION DE HOYO EN TERRENO ROCOSO 8 das mar 10/10/17 lun 23/10/17 30 40 3 24 2250.47 54011.28 1 S 52,743.17
40 08.02 PUESTA A TIERRA TIPO VARILLA PARA B.T. 1.6 das lun 23/10/17 jue 26/10/17 39 41 8 893.18 7145.44 5 S 6,929.37
42 08.04 SEALIZACION DE PUESTA A TIERRA 0.53 das mar 31/10/17 mi 01/11/17 41 6,28 8 55.05 440.4 15 S 274.80
43 09 SUMINISTRO DE TABLERO DE BOMBAS. 2.33 das vie 27/10/17 lun 30/10/17 S 4,851.47
44 09.01 MURETE DE LADRILLO 0.33 das vie 27/10/17 vie 27/10/17 22 45 1 376.88 376.88 3 S 235.73
46 09.03 TABLERO DE DISTRIBUCION DE 24 POLOS 1 da dom 29/10/17 lun 30/10/17 45 48 1 1957.87 1957.87 1 S 1,957.87
48 10.01 PRUEBAS ELECTRICAS 1 da dom 05/11/17 lun 06/11/17 13,46 49 1 1572.46 1572.46 1 S 1,537.88
Proyecto: Cronograma Tarea Divisin Progreso Hito Resumen Resumen del proyecto Tareas externas Hito externo Fecha lmite
Fecha: lun 04/09/17
Pgina 1