Académique Documents
Professionnel Documents
Culture Documents
PPP Modelling
Scenarios
March 2014
TCV has considered four Baseline Models with four scenarios modelled for each. The four models are based
on the following assumptions:
Baseline 1 - is based on a typical availability payment/social infrastructure PPP with a capital component
of the projects QSP of 60%
Baseline 2 - is more capital cost intensive (capital component of the QSP is around 85%)
Baseline 3 - is more operationally cost intensive (capital component of the QSP is around 40%)
Baseline 4 includes a capital contribution at the end of construction.
TCV has modelled the impact on the NPC of the QSP for each Baseline under the following scenarios:
Scenario 1 - reducing construction cost in the model by 5%, 10% and 20% (noting that reduced
construction cost will have a flow on impact on other cost line items)
Scenario 2 - reducing the financing fees and margins by 5%, 10% and 20% (noting what the equivalent
basis point change is)
Scenario 3 - reducing the operating costs by 5%, 10% and 20%
Scenario 4 reducing equity returns by 5%, 10% and 20%.
Each of these scenarios has been analysed based on two discount rates:
an example PPP bid discount rate of 7.18% (risk free rate plus systematic risk premium)
an example risk free rate of 4.98%.
The results of our modelling for the 5% sensitivity are shown below.
Under the Baseline 1 Model, the results of the analysis show that reductions to the hypothetical projects
construction cost have the greatest NPC sensitivity. The sensitivities to changes in financing fees and
margins, equity returns and Facilities Management (FM)/consortium costs have a lesser impact.
In addition, while a lower discount rate increase the costs associated with the project on an NPC basis, when
the discount rate is varied to the risk free rate the results of the analysis are similar in relative terms.
Description Value
The following pie chart shows the break-down of cash-flows (uses of funds) associated with the hypothetical
projects NPC of its QSP (Baseline 1).
Scenario 1 was modelled by re-solving the hypothetical model by adjusting the construction cost along
the construction S-curve down by 5%, 10% and 20% respectively, keeping the other key general inputs
from Table 1 constant
Scenario 2 was modelled by re-solving the hypothetical model by adjusting the four major financing cost
components (Construction Margin, Commitment Fee, Upfront Debt Underwriting Fee and Operating
Margin) down by 5%, 10% and 20% respectively, keeping the other key general inputs from Table 1
constant
Table 2 below summarises the impact on the NPC of the QSP that was achieved through the model re-
solves under each scenario described above.
Scenario 2 Financing Fees & Margins down 5% $412.9m -0.6 $549.0m -0.6
Scenario 2 Financing Fees & Margins down 10% $410.3m -1.3 $545.7m -1.2
Scenario 2 Financing Fees & Margins down 20% $405.3m -2.6 $539.0m -2.4
Table 3 below summarises the NPC of the QSP that was achieved through the model re-solves under each
scenario described above.
Scenario 2 Financing Fees & Margins down 5% $295.5m -0.9 $390.2m -0.9
Scenario 2 Financing Fees & Margins down 10% $292.9m -1.8 $387.2m -1.7
Scenario 2 Financing Fees & Margins down 20% $287.7m -3.5 $380.5m -3.4
Table 4 below summarises the NPC of the QSP that was achieved through the model re-solves under each
scenario described above.
Scenario 2 Financing Fees & Margins down 5% $633.7m -0.4 $847.0m -0.4
Scenario 2 Financing Fees & Margins down 10% $631.2m -0.8 $844.0m -0.8
Scenario 2 Financing Fees & Margins down 20% $626.2m -1.6 $837.5m -1.6
Table 5 below summarises the NPC of the QSP that was achieved through the model re-solves under each
scenario described above.
Scenario 2 Financing Fees & Margins down 5% $402.7m -0.4 $514.2m -0.5
Scenario 2 Financing Fees & Margins down 10% $400.7m -0.9 $511.7m -0.9
Scenario 2 Financing Fees & Margins down 20% $397.1m -1.8 $506.6m -1.9
This is driven by the fact that the projects construction cost is directly correlated with the amount of capital
required (both debt and equity). This in turn drives the required amounts to be serviced under the structure,
and hence reductions in constructions costs reduce both debt and equity outstanding and the flow on to
consequential interest and equity distributions required.
Under the Baseline 2 Model, where a more capital intensive project is considered, the hypothetical projects
sensitivity to construction costs is increased from the Baseline 1 Model. As there is a greater amount of debt
in the structure than Baseline 1, the sensitivity to financing fees and margins and equity returns is also
increased from the Baseline 1 Model, while as expected, the FM/consortium costs sensitivity is reduced.
Under the Baseline 3 Model, the projects FM/consortium costs provide the greatest sensitivity to the
Projects NPC. The construction cost sensitivity is reduced and the sensitivity split between construction and
FM/Consortium costs is broadly in proportion to the 40/60 capital/operating composition, when compared
with Baseline 1s 60/40 Capital/Operating composition.
Under the Baseline 4 Model, where a State capital contribution is introduced, the sensitivity to construction
costs and FM/consortium costs is similar to Baseline 1 where there is no State capital contribution. The
major point of differentiation is as expected, the projects NPC is less sensitive to changes to financing fees
and margins as the amount of debt in the structure has been reduced on construction completion.
In addition, while a lower discount rate increase the costs associated with the project on an NPC basis, when
the discount rate is varied to the risk free rate the results of the analysis are similar in relative terms.
DISCLAIMER
This Public Private Partnership Modelling Scenarios (PPP Financial Modelling Paper) has been prepared by
Treasury Corporation of Victoria (TCV) at the request of the Victorian Department of Treasury and Finance.