1. SCOPE
1.1 The Scope covers the procedures for installation of chillers and chilled water
pumps
2. PURPOSE
2.1 The purpose of this procedure is to detail the necessary criteria for installation work
of chillers & chilled water pumps, as per approved shop drawings and manufacturers
recommendations, to produce a quality installation conforming to relative standards
and project specifications.
3. INSTALLATION PROCEDURE
3.1 GENERAL
3.1.1. All equipment/material received at site shall be inspected by the
engineers representative, handled and stored upon receipt.
3.1.2. All installation / Construction works shall be carried out in compliance
with the contract specifications, approved shop drawings and project
safety manual.
3.1.3. Inspection and testing shall be conducted by the site supervisor and/or be
co-ordinated with Mechanical representative / Engineer (as applicable).
3.1.4. All equipment provided shall be inspected to ensure that it is free from
any physical damages
3.2 CHILLER
3.2.1. Ensure the location where the chiller to be installed is exactly as per
approved shop drawing.
3.2.2. Examine upstands, plinths to receive chillers for completeness with
specification, drawing and manufacturers recommended installation
requirements. Proper bases with isolating pads/inertia bases as specified
in the specification, etc., Must be completed prior to installation.
3.2.3. Mark positions for mounting springs on the concrete foundation
3.2.4. Position mounting springs according to identification numbers or colour
code
3.2.5. Ensure that the mounting springs installed are of correct capacity
according to manufacturer and at proper location.
3.2.6. Lift the chiller on to its pre-positioned mounting spring. Lifting shall be
as per manufacturers recommendations.
3.2.7. Position spring bolts through the chiller designated base holes
3.2.8. Support piping as per approved shop drawings, do not use chiller as a
support for piping
3.2.9. Level and alignment tolerances will be according to manufacturers
recommendations
3.2.10. Do not connect chilled water pipe line until the chiller level and
alignment operations have been completed.
3.2.11. Inspect all water piping for flow direction and correct connections
METHOD STATEMENT FOR THE MSM : 003 part-1
INSTALLATION OF CHILLER & Rev. :0
Page : 2 of 3
CHILLED WATER PUMPS Date : 29.01.01
3.3.7. Ensure the pipework connected to the pumps, are as indicated on the
approved drawings..
3.3.8. Install thermometers, pressure gages and other pipe line accessories as
shown on the approved shop drawing, ensuring all are installed
square & plumb, with sufficient space for operation & maintenance
and with minimum obstructions to take readings.
3.3.9. Prior to electrical connection, Check foundation bolts, Check strainers
are cleaned, Check valve positions, Gauges etc., Check level and
alignment of pumps, Check pump casing is vented, Check pump shafts
rotate freely.
3.3.10. Support all valves independently from piping
3.3.11. Check rotating parts are lubricated. Ensure all electrical power
connections have been completed.
3.3.12. Ensure that emergency lock-off isolator switch is located at a; clear
visible, easily accessible and close location
3.3.13. Ensure all areas that require touch-up painting (scratches etc) on all
pumps have been completed. Upon completion of touch-up ensure the
pumps & accessories have been cleaned.
3.3.14. Enclose in polyethylene sheet to preserve from surrounding debris until
commissioning
4. SAFETY
4.1 All personnel shall employ good & safe working practice according to project
safety plan
4.2 Proper precautions (warning boards, etc.) will be taken to ensure that no
unauthorized personnel are present during the time of crane lifting and
positioning.
4.3 All areas shall be cleaned of any waste material and normalised after completion
of the job
4.4 Safety equipment, i.e., safety helmets, safety shoes, coveralls, gloves etc., should
always be worn always
4.5 Contacts with live electric components is prohibited.
4.6 Ensure sufficient task lighting is available during all stages of work
4.7 Be alert to the conditions in the work area. Protection shall be taken to insure a
safe working place.
4.8 Special attention shall be given to the use of safety belts and harnesses, secured
ladder, proper scaffolding(supplied and installed by the main contractor), good
housekeeping, etc to be followed
***