Vous êtes sur la page 1sur 26

Line estimate for widening of Pipe culvert:

Project: Four laning of NH 47 - Salem to Coimbatore section)


Str. No: 7/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 21.51 1.40 1.60 48.19

2 Cum 5.40 1.70 1.60 29.38

77.56

2 M10 Grade concrete PCC in foundation 1 Cum 21.51 1.40 0.10 3.01

2 Cum 5.40 1.70 0.10 1.84

4.85

3 M15 Grade concrete PCC in Cradle 1 Cum 21.51 1.20 0.50 12.91

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.34 1.50 21.72

2 Cum 5.40 0.70 3.03 22.93

44.65

5 Class NP4 pipes 1 Rm 21.51 - - 21.51

6 Selected fill between cradle bed to Road top level 1 Cum 13.26 1.40 3.88 71.97

1 Cum 21.51 Area = 0.95 -15.33

56.64

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 5.00 1.40 - 7.00

12 HYSD bars 1.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 7/2

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 10.60 1.40 1.60 23.74

2 Cum 5.40 1.70 1.60 29.38

53.12

2 M10 Grade concrete PCC in foundation 1 Cum 10.60 1.40 0.10 1.48

2 Cum 5.40 1.70 0.10 1.84

3.32

3 M15 Grade concrete PCC in Cradle 1 Cum 10.60 1.20 0.50 6.36

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.22 1.50 19.70

2 Cum 5.40 0.51 0.60 3.28

22.98

5 Class NP4 pipes 1 Rm 10.60 - - 10.60

6 Selected fill between cradle bed to Road top level 1 Cum 7.95 1.40 1.07 11.96

1 Cum 10.60 Area = 0.95 -7.56

4.41

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 5.30 1.40 - 7.42

12 HYSD bars 0.70


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 12/5

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 48.70 1.40 1.60 109.08

2 Cum 5.40 1.70 1.60 29.38

138.46

2 M10 Grade concrete PCC in foundation 1 Cum 48.70 1.40 0.10 6.82

2 Cum 5.40 1.70 0.10 1.84

8.65

3 M15 Grade concrete PCC in Cradle 1 Cum 48.70 1.20 0.50 29.22

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.24 1.50 20.09

2 Cum 5.40 0.54 0.89 5.21

25.30

5 Class NP4 pipes 1 Rm 48.70 - - 48.70

6 Selected fill between cradle bed to Road top level 1 Cum 44.72 1.40 1.74 108.76

1 Cum 48.70 Area = 0.95 -34.71

74.05

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 40.75 1.40 - 57.05

12 HYSD bars 0.77


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 14/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 16.52 1.40 1.60 37.01

1 Cum 5.40 1.70 1.60 14.69

51.70

2 M10 Grade concrete PCC in foundation 1 Cum 16.52 1.40 0.10 2.31

1 Cum 5.40 1.70 0.10 0.92

3.23

3 M15 Grade concrete PCC in Cradle 1 Cum 16.52 1.20 0.50 9.91

4 M15 Grade concrete PCC in Head wall 1 Cum 5.40 1.22 1.50 9.85

1 Cum 5.40 0.51 0.60 1.64

11.49

5 Class NP4 pipes 1 Rm 16.52 - - 16.52

6 Selected fill between cradle bed to Road top level 1 Cum 14.01 1.40 1.01 19.73

1 Cum 16.52 Area = 0.95 -11.78

7.96

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 2 Cum Area = 17.77 0.30 10.66

2 Cum Area = 17.77 0.15 5.33


15.99

9 Dismantling of existing head wall 1 Cum 4.50 0.4 1.05 1.89

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 11.50 1.40 - 16.10

12 HYSD bars 0.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 15/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 16.00 1.40 1.60 35.84

1 Cum 5.40 1.70 1.60 14.69

50.53

2 M10 Grade concrete PCC in foundation 1 Cum 16.00 1.40 0.10 2.24

1 Cum 5.40 1.70 0.10 0.92

3.16

3 M15 Grade concrete PCC in Cradle 1 Cum 16.00 1.20 0.50 9.60

4 M15 Grade concrete PCC in Head wall 1 Cum 5.40 1.22 1.50 9.85

1 Cum 5.40 0.51 0.60 1.64

11.49

5 Class NP4 pipes 1 Rm 16.00 - - 16.00

6 Selected fill between cradle bed to Road top level 1 Cum 13.35 1.40 1.07 20.09

1 Cum 16.00 Area = 0.95 -11.40

8.69

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 2 Cum Area = 17.77 0.30 10.66

2 Cum Area = 17.77 0.15 5.33


15.99

9 Dismantling of existing head wall 1 Cum 4.50 0.4 1.05 1.89

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.70 1.40 - 14.98

12 HYSD bars 0.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 15/2

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 16.04 1.40 1.60 35.94

1 Cum 5.40 1.70 1.60 14.69

50.63

2 M10 Grade concrete PCC in foundation 1 Cum 16.04 1.40 0.10 2.25

1 Cum 5.40 1.70 0.10 0.92

3.16

3 M15 Grade concrete PCC in Cradle 1 Cum 16.04 1.20 0.50 9.63

4 M15 Grade concrete PCC in Head wall 1 Cum 5.40 1.22 1.50 9.85

1 Cum 5.40 0.51 0.60 1.64

11.49

5 Class NP4 pipes 1 Rm 16.04 - - 16.04

6 Selected fill between cradle bed to Road top level 1 Cum 13.77 1.40 0.89 17.08

1 Cum 16.04 Area = 0.95 -11.44

5.65

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 2 Cum Area = 17.77 0.30 10.66

2 Cum Area = 17.77 0.15 5.33


15.99

9 Dismantling of existing head wall 1 Cum 4.50 0.4 1.05 1.89

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 11.50 1.40 - 16.10

12 HYSD bars 0.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 17/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 46.91 1.40 1.60 105.07

2 Cum 5.40 1.70 1.60 29.38

134.45

2 M10 Grade concrete PCC in foundation 1 Cum 46.91 1.40 0.10 6.57

2 Cum 5.40 1.70 0.10 1.84

8.40

3 M15 Grade concrete PCC in Cradle 1 Cum 46.91 1.20 0.50 28.14

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.22 1.50 19.70

2 Cum 5.40 0.51 0.60 3.28

22.98

5 Class NP4 pipes 1 Rm 46.91 - - 46.91

6 Selected fill between cradle bed to Road top level 1 Cum 44.15 1.40 1.13 69.67

1 Cum 46.91 Area = 0.95 -33.43

36.23

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 41.40 1.40 - 57.96

12 HYSD bars 0.70


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 18/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 20.39 1.40 1.60 45.68

1 Cum 5.40 1.70 1.60 14.69

60.37

2 M10 Grade concrete PCC in foundation 1 Cum 20.39 1.40 0.10 2.85

1 Cum 5.40 1.70 0.10 0.92

3.77

3 M15 Grade concrete PCC in Cradle 1 Cum 20.39 1.20 0.50 12.24

4 M15 Grade concrete PCC in Head wall 1 Cum 5.40 1.22 1.50 9.85

1 Cum 5.40 0.51 0.60 1.64

11.49

5 Class NP4 pipes 1 Rm 20.39 - - 20.39

6 Selected fill between cradle bed to Road top level 1 Cum 17.55 1.40 1.17 28.81

1 Cum 20.39 Area = 0.95 -14.53

14.28

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 2 Cum Area = 17.77 0.30 10.66

2 Cum Area = 17.77 0.15 5.33


15.99

9 Dismantling of existing head wall 1 Cum 4.50 0.4 1.05 1.89

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 14.70 1.40 - 20.58

12 HYSD bars 0.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 18/3

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 66.90 1.40 1.60 149.86

2 Cum 5.40 1.70 1.60 29.38

179.23

2 M10 Grade concrete PCC in foundation 1 Cum 66.90 1.40 0.10 9.37

2 Cum 5.40 1.70 0.10 1.84

11.20

3 M15 Grade concrete PCC in Cradle 1 Cum 66.90 1.20 0.50 40.14

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.38 1.50 22.30

2 Cum 5.40 0.76 4.63 37.81

60.11

5 Class NP4 pipes 1 Rm 66.90 - - 66.90

6 Selected fill between cradle bed to Road top level 1 Cum 55.45 1.40 5.48 425.02

1 Cum 66.90 Area = 0.95 -47.68

377.34

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 44.00 1.40 - 61.60

12 HYSD bars 1.81


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 20/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 30.48 1.40 1.60 68.28

2 Cum 5.40 1.70 1.60 29.38

97.65

2 M10 Grade concrete PCC in foundation 1 Cum 30.48 1.40 0.10 4.27

2 Cum 5.40 1.70 0.10 1.84

6.10

3 M15 Grade concrete PCC in Cradle 1 Cum 30.48 1.20 0.50 18.29

4 M15 Grade concrete PCC in Head wall 2 Cum 5.40 1.25 1.50 20.25

2 Cum 5.40 0.56 1.02 6.16

26.41

5 Class NP4 pipes 1 Rm 30.48 - - 30.48

6 Selected fill between cradle bed to Road top level 1 Cum 26.24 1.40 1.87 68.70

1 Cum 30.48 Area = 0.95 -21.72

46.97

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 4 Cum Area = 17.77 0.30 21.33

4 Cum Area = 17.77 0.15 10.66


31.99

9 Dismantling of existing head wall 2 Cum 4.50 0.4 1.05 3.78

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 22.00 1.40 - 30.80

12 HYSD bars 0.80


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 21/2

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 16.94 5.45 1.60 147.70

1 Cum 10.80 1.70 1.60 29.38

177.08

2 M10 Grade concrete PCC in foundation 1 Cum 16.94 5.45 0.10 9.23

1 Cum 10.80 1.70 0.10 1.84

11.07

3 M15 Grade concrete PCC in Cradle 1 Cum 16.94 5.25 0.50 44.46

4 M15 Grade concrete PCC in Head wall 1 Cum 10.80 1.22 1.50 19.70

1 Cum 10.80 0.51 0.60 3.28

22.98

5 Class NP4 pipes 4 Rm 16.94 - - 67.75

6 Selected fill between cradle bed to Road top level 1 Cum 14.04 5.45 1.20 91.62

4 Cum 16.94 Area = 0.95 -48.29

43.33

7 Bed pitching 1 Cum 10.80 5.00 0.30 16.20

1 Cum 10.80 5.00 0.15 8.10


24.30

8 Side slope pitching 2 Cum Area = 31.79 0.30 19.07

2 Cum Area = 31.79 0.15 9.54


28.61

9 Dismantling of existing head wall 1 Cum 8.50 0.4 1.05 3.57

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 11.15 5.45 - 60.77

12 HYSD bars 0.69


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 22/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 14.51 2.75 1.60 63.85

1 Cum 7.20 1.70 1.60 19.58

83.44

2 M10 Grade concrete PCC in foundation 1 Cum 14.51 2.75 0.10 3.99

1 Cum 7.20 1.70 0.10 1.22

5.21

3 M15 Grade concrete PCC in Cradle 1 Cum 14.51 2.55 0.50 18.50

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 14.51 - - 29.02

6 Selected fill between cradle bed to Road top level 1 Cum 11.51 2.75 1.25 39.65

2 Cum 14.51 Area = 0.95 -20.69

18.96

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 8.50 2.75 - 23.38

12 HYSD bars 0.46


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 23/2

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 21.09 2.75 1.60 92.80

1 Cum 7.20 1.70 1.60 19.58

112.39

2 M10 Grade concrete PCC in foundation 1 Cum 21.09 2.75 0.10 5.80

1 Cum 7.20 1.70 0.10 1.22

7.02

3 M15 Grade concrete PCC in Cradle 1 Cum 21.09 2.55 0.50 26.89

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.28 1.50 13.85

1 Cum 7.20 0.61 1.55 6.80

20.65

5 Class NP4 pipes 2 Rm 21.09 - - 42.18

6 Selected fill between cradle bed to Road top level 1 Cum 15.80 2.75 2.40 104.17

2 Cum 21.09 Area = 0.95 -30.07

74.10

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.50 2.75 - 28.88

12 HYSD bars 0.62


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 24/3

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 63.24 2.75 1.60 278.25

1 Cum 7.20 1.70 1.60 19.58

297.83

2 M10 Grade concrete PCC in foundation 1 Cum 63.24 2.75 0.10 17.39

1 Cum 7.20 1.70 0.10 1.22

18.61

3 M15 Grade concrete PCC in Cradle 1 Cum 63.24 2.55 0.50 80.63

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.35 1.50 14.62

1 Cum 7.20 0.72 3.50 18.15

32.76

5 Class NP4 pipes 2 Rm 63.24 - - 126.48

6 Selected fill between cradle bed to Road top level 1 Cum 54.04 2.75 4.35 646.06

2 Cum 63.24 Area = 0.95 -90.15

555.91

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 44.85 2.75 - 123.34

12 HYSD bars 0.99


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 24/4

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 37.73 2.75 1.60 165.99

1 Cum 7.20 1.70 1.60 19.58

185.58

2 M10 Grade concrete PCC in foundation 1 Cum 37.73 2.75 0.10 10.37

1 Cum 7.20 1.70 0.10 1.22

11.60

3 M15 Grade concrete PCC in Cradle 1 Cum 37.73 2.55 0.50 48.10

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.35 1.50 14.59

1 Cum 7.20 0.72 3.39 17.51

32.10

5 Class NP4 pipes 2 Rm 37.73 - - 75.45

6 Selected fill between cradle bed to Road top level 1 Cum 28.74 2.75 4.24 335.40

2 Cum 37.73 Area = 0.71 -40.33

295.07

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 19.75 2.75 - 54.31

12 HYSD bars 0.97


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 25/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 14.17 2.75 1.60 62.34

1 Cum 7.20 1.70 1.60 19.58

81.92

2 M10 Grade concrete PCC in foundation 1 Cum 14.17 2.75 0.10 3.90

1 Cum 7.20 1.70 0.10 1.22

5.12

3 M15 Grade concrete PCC in Cradle 1 Cum 14.17 2.55 0.50 18.06

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 14.17 - - 28.34

6 Selected fill between cradle bed to Road top level 1 Cum 12.08 2.75 0.79 26.32

2 Cum 14.17 Area = 0.71 -15.15

11.17

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.00 2.75 - 27.50

12 HYSD bars 0.46


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 26/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 89.44 2.75 1.60 393.54

2 Cum 7.20 1.70 1.60 39.17

432.71

2 M10 Grade concrete PCC in foundation 1 Cum 89.44 2.75 0.10 24.60

2 Cum 7.20 1.70 0.10 2.45

27.04

3 M15 Grade concrete PCC in Cradle 1 Cum 89.44 2.55 0.50 114.04

4 M15 Grade concrete PCC in Head wall 2 Cum 7.20 1.42 1.50 30.77

2 Cum 7.20 0.83 9.17 109.93

140.70

5 Class NP4 pipes 2 Rm 89.44 - - 178.88

6 Selected fill between cradle bed to Road top level 1 Cum 68.90 2.75 10.02 1899.00

2 Cum 89.44 Area = 0.71 -95.62

1803.37

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 4 Cum Area = 22.00 0.30 26.39

4 Cum Area = 22.00 0.15 13.20


39.59

9 Dismantling of existing head wall 2 Cum 6.00 0.4 1.05 5.04

10 M15 Grade concrete PCC in Pillars 4 Cum 0.40 0.40 0.40 0.26

11 Wearing coat 1 Sqm 48.35 2.75 - 132.96

12 HYSD bars 4.23


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 26/3

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 17.96 2.75 1.60 79.04

1 Cum 7.20 1.70 1.60 19.58

98.63

2 M10 Grade concrete PCC in foundation 1 Cum 17.96 2.75 0.10 4.94

1 Cum 7.20 1.70 0.10 1.22

6.16

3 M15 Grade concrete PCC in Cradle 1 Cum 17.96 2.55 0.50 22.90

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.22

1 Cum 7.20 0.52 0.69 2.58

15.80

5 Class NP4 pipes 2 Rm 17.96 - - 35.93

6 Selected fill between cradle bed to Road top level 1 Cum 14.38 2.75 1.54 60.95

2 Cum 17.96 Area = 0.71 -19.21

41.74

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.80 2.75 - 29.70

12 HYSD bars 0.48


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 28/3

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 17.77 2.75 1.60 78.17

1 Cum 7.20 1.70 1.60 19.58

97.75

2 M10 Grade concrete PCC in foundation 1 Cum 17.77 2.75 0.10 4.89

1 Cum 7.20 1.70 0.10 1.22

6.11

3 M15 Grade concrete PCC in Cradle 1 Cum 17.77 2.55 0.50 22.65

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.24 1.50 13.43

1 Cum 7.20 0.55 0.93 3.67

17.10

5 Class NP4 pipes 2 Rm 17.77 - - 35.53

6 Selected fill between cradle bed to Road top level 1 Cum 13.71 2.75 1.78 67.06

2 Cum 17.77 Area = 0.71 -18.99

48.07

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 9.65 2.75 - 26.54

12 HYSD bars 0.52


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 28/4

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 18.84 2.75 1.60 82.89

1 Cum 7.20 1.70 1.60 19.58

102.47

2 M10 Grade concrete PCC in foundation 1 Cum 18.84 2.75 0.10 5.18

1 Cum 7.20 1.70 0.10 1.22

6.40

3 M15 Grade concrete PCC in Cradle 1 Cum 18.84 2.55 0.50 24.02

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.26 1.50 13.66

1 Cum 7.20 0.58 1.23 5.17

18.83

5 Class NP4 pipes 2 Rm 18.84 - - 37.68

6 Selected fill between cradle bed to Road top level 1 Cum 14.17 2.75 2.08 81.23

2 Cum 18.84 Area = 0.71 -20.14

61.09

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 9.50 2.75 - 26.13

12 HYSD bars 0.57


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 29/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 17.10 2.75 1.60 75.26

1 Cum 7.20 1.70 1.60 19.58

94.84

2 M10 Grade concrete PCC in foundation 1 Cum 17.10 2.75 0.10 4.70

1 Cum 7.20 1.70 0.10 1.22

5.93

3 M15 Grade concrete PCC in Cradle 1 Cum 17.10 2.55 0.50 21.81

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 17.10 - - 34.21

6 Selected fill between cradle bed to Road top level 1 Cum 14.80 2.75 0.90 36.68

2 Cum 17.10 Area = 0.71 -18.29

18.39

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 12.50 2.75 - 34.38

12 HYSD bars 0.46


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 29/2

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 13.26 2.75 1.60 58.35

1 Cum 7.20 1.70 1.60 19.58

77.94

2 M10 Grade concrete PCC in foundation 1 Cum 13.26 2.75 0.10 3.65

1 Cum 7.20 1.70 0.10 1.22

4.87

3 M15 Grade concrete PCC in Cradle 1 Cum 13.26 2.55 0.50 16.91

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 13.26 - - 26.52

6 Selected fill between cradle bed to Road top level 1 Cum 11.93 2.75 0.42 13.63

2 Cum 13.26 Area = 0.71 -14.18

-0.55

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.60 2.75 - 29.15

12 HYSD bars 0.46


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 29/3

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 12.96 2.75 1.60 57.04

1 Cum 7.20 1.70 1.60 19.58

76.63

2 M10 Grade concrete PCC in foundation 1 Cum 12.96 2.75 0.10 3.57

1 Cum 7.20 1.70 0.10 1.22

4.79

3 M15 Grade concrete PCC in Cradle 1 Cum 12.96 2.55 0.50 16.53

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 12.96 - - 25.93

6 Selected fill between cradle bed to Road top level 1 Cum 12.08 2.75 0.19 6.35

2 Cum 12.96 Area = 0.71 -13.86

-7.51

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 11.20 2.75 - 30.80

12 HYSD bars 0.46


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 29/4

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 14.84 1.40 1.60 33.25

1 Cum 5.40 1.70 1.60 14.69

47.93

2 M10 Grade concrete PCC in foundation 1 Cum 14.84 1.40 0.10 2.08

1 Cum 5.40 1.70 0.10 0.92

3.00

3 M15 Grade concrete PCC in Cradle 1 Cum 14.84 1.20 0.50 8.91

4 M15 Grade concrete PCC in Head wall 1 Cum 5.40 1.22 1.50 9.85

1 Cum 5.40 0.51 0.60 1.64

11.49

5 Class NP4 pipes 1 Rm 14.84 - - 14.84

6 Selected fill between cradle bed to Road top level 1 Cum 13.15 1.40 0.60 11.01

1 Cum 14.84 Area = 0.71 -7.93

3.07

7 Bed pitching 1 Cum 5.40 5.00 0.30 8.10

1 Cum 5.40 5.00 0.15 4.05


12.15

8 Side slope pitching 2 Cum Area = 17.77 0.30 10.66

2 Cum Area = 17.77 0.15 5.33


15.99

9 Dismantling of existing head wall 1 Cum 4.50 0.4 1.05 1.89

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 11.45 1.40 - 16.03

12 HYSD bars 0.35


Line estimate for widening of Pipe culvert:
Project: Four laning of NH 47 - Salem to Coimbatore section)
Str. No: 30/1

Sl No Description Nos Unit L B D Quantity


1 Earthwork excavation for foundation 1 Cum 14.48 2.75 1.60 63.70

1 Cum 7.20 1.70 1.60 19.58

83.29

2 M10 Grade concrete PCC in foundation 1 Cum 14.48 2.75 0.10 3.98

1 Cum 7.20 1.70 0.10 1.22

5.21

3 M15 Grade concrete PCC in Cradle 1 Cum 14.48 2.55 0.50 18.46

4 M15 Grade concrete PCC in Head wall 1 Cum 7.20 1.22 1.50 13.13

1 Cum 7.20 0.51 0.60 2.19

15.32

5 Class NP4 pipes 2 Rm 14.48 - - 28.96

6 Selected fill between cradle bed to Road top level 1 Cum 12.36 2.75 0.81 27.44

2 Cum 14.48 Area = 0.71 -15.48

11.96

7 Bed pitching 1 Cum 7.20 5.00 0.30 10.80

1 Cum 7.20 5.00 0.15 5.40


16.20

8 Side slope pitching 2 Cum Area = 22.00 0.30 13.20

2 Cum Area = 22.00 0.15 6.60


19.80

9 Dismantling of existing head wall 1 Cum 6.00 0.4 1.05 2.52

10 M15 Grade concrete PCC in Pillars 2 Cum 0.40 0.40 0.40 0.13

11 Wearing coat 1 Sqm 10.25 2.75 - 28.19

12 HYSD bars 0.46


Summary of line estimates for widening of Pipe culverts (PACKAGE - I):
Project: Four laning of NH 47 - Salem to Coimbatore section)

Sl No Description Unit Quantity

1 Earthwork excavation for foundation Cum 2944.12

2 M10 Grade concrete PCC in foundation Cum 184.01

3 M15 Grade concrete PCC in Cradle Cum 679.31

4 M15 Grade concrete PCC in Head wall Cum 652.77

5 Class NP4 pipes Rm 1081.76

6 Selected fill between cradle bed to Road top level Cum 3610.38

7 Bed pitching with stone Cum 245.70

Bed pitching with granular material Cum 122.85

8 Side slope pitching with stone Cum 385.10

Side slope pitching with granular material Cum 192.55

9 Dismantling of existing head wall Cum 70.98

10 M15 Grade concrete PCC in Pillars Cum 4.10

11 Wearing coat Sqm 961.63

12 HYSD bars MT 19.75