RAWDHAT AL KHAIL (RAK) HC CONSTRUCTION - PLAN A (OPTION 1)

PROGRESS UPDATE AS ON 17-JUL-17

Original BL Project BL Project Total


Activity ID Activity Name Start Finish
Duration Start Finish Float
RAWDHAT AL KHAIL (RAK) HC CONSTRUCTION - PLAN A (OPTION 1) 312 8-Jan-17 9-Oct-17 04-Feb-17 A 28-Dec-17 -80
Statutory Permits and Approvals 126 8-Jan-17 26-Jan-17 05-Feb-17 A 20-Feb-17 A
A0003 RAK Plan A - BP File Open 0 17-Jan-17 20-Feb-17 A
A0001 RAK Plan A - Receive RAK Stamped Docs from PHCC 16 8-Jan-17 25-Jan-17 05-Feb-17 A 16-Feb-17 A
A0002 RAK Plan A - Verify Docs 0 26-Jan-17 18-Feb-17 A
BP Process Timeline 183 28-Jan-17 18-Jun-17 04-Feb-17 A 21-Sep-17 -65
DC2 Approvals & Building Permit 12 5-Jun-17 18-Jun-17 9-Sep-17 21-Sep-17 -65
A0023 DC2 Approval 7 5-Jun-17 12-Jun-17 9-Sep-17 16-Sep-17 -65
A1000 RAK Plan A - BPermits Complete 0 18-Jun-17 21-Sep-17 -65
A0024 Building Permit 5 13-Jun-17 18-Jun-17 17-Sep-17 21-Sep-17 -65
Service Approvals 56 1-Apr-17 4-Jun-17 04-Jul-17 A 7-Sep-17 -65
A0021 Submission of QCDD FF/FA/ACMV Package 1 1-Apr-17 1-Apr-17 04-Jul-17 A 04-Jul-17 A
A0022 Approval of QCDD FF/FA/ACMV Package 55 2-Apr-17 4-Jun-17 05-Jul-17 A 7-Sep-17 -65
Detailed Design 146 28-Jan-17 8-Mar-17 04-Feb-17 A 07-Jun-17 A
A0004 Preparation of Design 16 28-Jan-17 14-Feb-17 04-Feb-17 A 08-May-17 A
A0005 Submission of Design 1 15-Feb-17 15-Feb-17 09-May-17 A 09-May-17 A
A0006 Confirmation from PHCC on MECH/ELECT Load 4 16-Feb-17 20-Feb-17 10-May-17 A 14-May-17 A
A0007 Review by PHCC 6 16-Feb-17 22-Feb-17 10-May-17 A 16-May-17 A
A0008 Comments on Design from PHCC 1 23-Feb-17 23-Feb-17 17-May-17 A 17-May-17 A
A0009 Updation of Comments 4 25-Feb-17 28-Feb-17 18-May-17 A 28-May-17 A
A0010 Resubmission of Uodated Design 1 1-Mar-17 1-Mar-17 29-May-17 A 01-Jun-17 A
A0011 Review and Approval by PHCC 6 2-Mar-17 8-Mar-17 03-Jun-17 A 07-Jun-17 A
DC1 Approvals 38 9-Feb-17 25-Mar-17 01-Jun-17 A 04-Jul-17 A
A0012 Submission of Architecture DC1 Drawings online 0 9-Feb-17 01-Jun-17 A
A0013 DC1 Comments from Baladiya 2 11-Feb-17 12-Feb-17 04-Jun-17 A 05-Jun-17 A
A0014 Re-Uploading of DC1 Drawings 7 14-Feb-17 21-Feb-17 06-Jun-17 A 12-Jun-17 A
A0015 DC1 Clearance from Baladiya 6 22-Feb-17 28-Feb-17 13-Jun-17 A 17-Jun-17 A
A0016 Submission of QCDD Life Safety Drawings 1 2-Mar-17 2-Mar-17 01-Jun-17 A 01-Jun-17 A
A0018 Submission of Kharama Package 2 2-Mar-17 4-Mar-17 01-Jun-17 A 01-Jun-17 A

Page : 1 of 3
Original BL Project BL Project Total
Activity ID Activity Name Start Finish
Duration Start Finish Float
A0017 Approval of QCDD Life safety Drawings 12 4-Mar-17 16-Mar-17 04-Jun-17 A 04-Jul-17 A
A0019 Approval of Kharama Package 12 4-Mar-17 16-Mar-17 04-Jun-17 A 17-Jun-17 A
A0020 DC1 Clearance (Arch-Elect-LifeSafety) 7 18-Mar-17 25-Mar-17 04-Jun-17 A 04-Jul-17 A
PHCC Permits 10 5-Jun-17 15-Jun-17 26-Feb-17 A 16-Mar-17 A
A0025 Apply Internal Permits 5 5-Jun-17 10-Jun-17 26-Feb-17 A 02-Mar-17 A
A0026 Approvals for Internal Permits 5 11-Jun-17 15-Jun-17 04-Mar-17 A 16-Mar-17 A
Materials 46 24-Jan-17 3-Apr-17 04-Mar-17 A 20-Aug-17 -68
A0027 RAK Plan A - Submissions 46 24-Jan-17 18-Mar-17 04-Mar-17 A 9-Aug-17 -68
A0028 RAK Plan A - Approval 45 11-Feb-17 3-Apr-17 08-Apr-17 A 20-Aug-17 -68
Shop Drawings 108 26-Mar-17 29-Jul-17 08-May-17 A 18-Nov-17 -68
A0030 RAK Plan A - Method Statement 10 26-Mar-17 5-Apr-17 10-Jun-17 A 27-Jul-17 -68
A0029 RAK Plan A - Submissions 20 26-Mar-17 17-Apr-17 08-May-17 A 8-Aug-17 -58
A0031 RAK Plan A - Approval 20 6-Apr-17 29-Apr-17 20-May-17 A 20-Aug-17 -68
A0032 RAK Plan A - Procurement of Materials 77 1-May-17 29-Jul-17 10-Jul-17 A 18-Nov-17 -68
Construction 52 7-Jun-17 13-Aug-17 11-Sep-17 1-Nov-17 -50
Civil Works 39 7-Jun-17 7-Aug-17 11-Sep-17 25-Oct-17 -67
A0033 Fixing Barricades, Signs, Coordoning Off 1 7-Jun-17 7-Jun-17 11-Sep-17 11-Sep-17 -64
A0035 Removal of Existing Utilities 2 8-Jun-17 10-Jun-17 12-Sep-17 13-Sep-17 -64
A0036 Removal of Existing Ceiling 4 11-Jun-17 14-Jun-17 14-Sep-17 18-Sep-17 -64
A0034 Removal of Existing Flooring 2 15-Jun-17 17-Jun-17 19-Sep-17 20-Sep-17 -64
A0037 Installation of Partition Walls 12 19-Jun-17 9-Jul-17 23-Sep-17 5-Oct-17 -65
A0038 Installation of Lead Lining 10 1-Jul-17 11-Jul-17 27-Sep-17 8-Oct-17 -65
A0039 Installation of Ceiling 10 13-Jul-17 29-Jul-17 4-Oct-17 15-Oct-17 -67
A0041 Installation of Doors 6 9-Jul-17 30-Jul-17 19-Oct-17 25-Oct-17 -67
A0040 Installation of Floor Finishes 8 30-Jul-17 2-Aug-17 16-Oct-17 24-Oct-17 -67
A0042 Installation of Fixed Furnitures 8 20-Jul-17 7-Aug-17 17-Oct-17 25-Oct-17 -67
A0043 Installation of Loose Furniture 4 3-Aug-17 7-Aug-17 22-Oct-17 25-Oct-17 -67
MEP Works 45 8-Jun-17 7-Aug-17 12-Sep-17 26-Oct-17 -80
A1001 Cable trunking from sub station 6 8-Jun-17 13-Jun-17 12-Sep-17 17-Sep-17 -72
A0044 Conduiting 4 19-Jun-17 24-Jun-17 26-Sep-17 30-Sep-17 -68
A0046 Installation of A/c Ducts 7 27-Jun-17 4-Jul-17 1-Oct-17 8-Oct-17 -68
A0047 Installation of A/c Units 2 5-Jul-17 6-Jul-17 9-Oct-17 10-Oct-17 -68

Page : 2 of 3
Original BL Project BL Project Total
Activity ID Activity Name Start Finish
Duration Start Finish Float
A0049 Installation of FA/FF 8 3-Jul-17 12-Jul-17 1-Oct-17 9-Oct-17 -67
A0048 Installation of A/c Grills 6 8-Jul-17 20-Jul-17 14-Oct-17 19-Oct-17 -68
A0045 Trunking and cabling 8 25-Jun-17 25-Jul-17 1-Oct-17 9-Oct-17 -67
A0051 Installation of Switches and Sockets 12 1-Jul-17 31-Jul-17 2-Oct-17 15-Oct-17 -64
A0050 Installation of Light Fittings 5 30-Jul-17 3-Aug-17 12-Oct-17 17-Oct-17 -63
A0052 Testing and Commissioning 4 1-Aug-17 5-Aug-17 21-Oct-17 24-Oct-17 -68
A0053 Integrating Power/NW to Existing Power/NW Sources 2 6-Aug-17 7-Aug-17 25-Oct-17 26-Oct-17 -68
RAK Plan A - Construction Complete 0 7-Aug-17 7-Aug-17 26-Oct-17 26-Oct-17 -68
A0054 RAK Plan A - Construction Complete 0 7-Aug-17 26-Oct-17 -68
RAK Plan A - Snag Lists Completion 5 8-Aug-17 13-Aug-17 28-Oct-17 1-Nov-17 -43
A0055 RAK Plan A - Snag Lists Completion 5 8-Aug-17 13-Aug-17 28-Oct-17 1-Nov-17 -43
Equipment Transition Plans "B" to "A" 56 10-Jun-17 13-Aug-17 28-Aug-17 1-Nov-17 -43
A0056 RAK Plan A - Shifting of Equipment from "B" or to Procure 15 10-Jun-17 26-Jun-17 28-Aug-17 16-Sep-17 -43
A0057 RAK Plan A - PHCC Decision/Plan on New Equipment 40 28-Jun-17 13-Aug-17 17-Sep-17 1-Nov-17 -43
A0058 RAK Plan A - PHCC Decision/Plan on Shifting Equipment from "B" 40 28-Jun-17 13-Aug-17 17-Sep-17 1-Nov-17 -43
Equipment Mounting and Fixing - Transition 18 13-Aug-17 4-Sep-17 1-Nov-17 22-Nov-17 -43
A0059 RAK Plan A - Allow and Approve Transition 0 13-Aug-17 1-Nov-17 -43
A0060 RAK Plan A - Fixing of Hardware and Equipments 18 14-Aug-17 4-Sep-17 2-Nov-17 22-Nov-17 -43
A0061 RAK Plan A - Equipment Available 0 4-Sep-17 22-Nov-17 -43
Site Trials 5 5-Sep-17 10-Sep-17 23-Nov-17 28-Nov-17 -43
A0062 RAK Plan A - Site Trials - Adjustments/Changes 5 5-Sep-17 10-Sep-17 23-Nov-17 28-Nov-17 -43
Branding and Signages 22 9-Aug-17 4-Sep-17 29-Oct-17 22-Nov-17 -38
A0063 RAK Plan A - Marketing/Branding 22 9-Aug-17 4-Sep-17 29-Oct-17 22-Nov-17 -38
A0064 RAK Plan A - Signages 22 9-Aug-17 4-Sep-17 29-Oct-17 22-Nov-17 -38
Civil Defence Process 50 12-Aug-17 9-Oct-17 31-Oct-17 28-Dec-17 -68
A0065 RAK Plan A - Screening Center QCDD Approval 50 12-Aug-17 9-Oct-17 31-Oct-17 28-Dec-17 -68
A0066 RAK Plan A - Screening Center Ready 0 9-Oct-17 28-Dec-17 -68
Process for Licensing by MoE 26 8-Aug-17 7-Sep-17 26-Oct-17 25-Nov-17 -40
A0067 RAK Plan A - Inspection and Approval Process by MoE 26 8-Aug-17 7-Sep-17 26-Oct-17 25-Nov-17 -40
Site Ready for Go-Live Preperation 0 9-Oct-17 9-Oct-17 28-Dec-17 28-Dec-17 -68
A0068 RAK Plan A - Site Ready for Go-Live Preperation 0 9-Oct-17 28-Dec-17 -68