Removing G.I. or A.C. sheet roofing including purlins, principal rafters etc.
1 15.48 38.26 BDR including sorting serviceable and unserviceable materials, stacking the same 43.05 SQ.MT 666.41
as and where directed in the compound including scaffolding etc. complete.
Dismantling brick masonry in lime or cement mortar and stacking the materials
2 115.31 46.09 BDW 8 135.45 Cu.M. 15618.47
as directed with all leads, lifts etc. complete.
Removing lime or lean cement concrete including stacking the spoils as
3 68.32 46.13 BDW 8 435.75 Cu.M. 29771.31
directed with all leads, lifts etc. complete.
Removing doors and windows with frames and stacking the materials as
4 30.00 46.15 BDW 8 64.05 Nos. 1921.50
directed with all leads, lifts etc. complete.
Removing ventilators and small windows with frame and stacking the materials
5 4.00 46.16 BDW 8 64.05 Nos. 256.20
with all leads lifts etc. complete.
Removing cement or lime plaster including disposing of the spoils as directed
6 30.000 46.22 BDW 8 12.60 SQ.MT 378.00
with all leads, lifts etc. complete.
Removing earthen, stoneware pipes and stacking them as directed with all
7 30.00 46.27 BDW 8 9.45 RMT 283.50
leads, lifts etc. complete.
Removing cast iron or wrought iron or A.C. pipe and stacking them as directed
8 91.31 46.28 BDW 8 9.45 RMT 862.87
with all leads, lifts etc. complete.
Dismantling the R.C.C. work 1:2:4 and sorting out the materials such as steel
9 4.00 46.29 BDW 8 etc. as directed and stacking them within the specified lead as directed etc. 645.75 Cu.M. 2583.00
complete.
Removing Urinal Pans or Wash hand basin with frame including disconnecting
the sanitary and water supply connections. removing the same carefully and
10 4.00 46.40 BDW 52.50 Nos. 210.00
stacking the serviceable materials as and where directed including throwing
the unserviceable materials out side etc. complete.
Removing W.C. Pan including disconnecting the sanitary and water supply
connections, removing and breaking flooring and bed con-crete around pan
11 4.00 46.41 BDW removing the same carefully and stacking the service-able materials as and 110.25 Nos. 441.00
where directed including throwing the unserviceable materials out side etc.
complete.
Dismantling existing brick bat coba in the W/C and toilets including removing
12 4.00 46.42 BDW the dismantelled stuff outside the rooms, including stacking and cleaning 1023.75 Nos. 4095.00
surface etc. complete.
Total Cost of Work Portion 57087.26
Add 5% for contingencies charges on (A):- 2854.36
59941.63
Add 2% for work charged establishment charges on (B):- 1198.83
TOTAL 61140.46
Say Rs 61140.46
.
Junior Engineer Deputy Engineer Executive Engineer
E WARD ,.P.C.M.C.,Pimpri-18 E WARD,.P.C.M.C.,Pimpri-18 E WARD.PCMC Pimpri. 18.
City Engineer
P.C.M.C
PIMPRI CHINCHWAD MUNICIPAL CORPORATION , PIMPRI - 18.
NAME OF WORK - AANASAHEB MAGAR KANYA PRTHAMIK SHALA, BHOHRADEWADI BHOSARI
SUMMERY STATEMENT
Memorandum showing the items of work to be carried out
City Engineer
P.C.M.C
Pimpri - Chinchwad Municipal Corporation , Pimpri, -18.
NAME OF WORK - AANASAHEB MAGAR KANYA PRTHAMIK SHALA, BHOHRADEWADI BHOSARI
MEASUREMENT SHEET
1 30.00 30 RMT
Total Net Qty 30.00 RMT
Dismantling existing brick bat coba in the W/C and toilets including
11 removing the dismantelled stuff outside the rooms, including
stacking and cleaning surface etc. complete.
4.00 4.00
Total Net Qty 4.00 Cum