15 February 2011
Dear Sirs,
The Accepted Contract Amount shall be Rp. 48.500.000.000,- (Rupiahs Forty Eight Billion
Five Hundred Million Only) inclusive ofPPN and PPh.
The Accepted Contract Amount is a fixed unit rate Contract with provisional quantities. The
quantities shall be remeasured on completion.
The scope of work, in general terms, comprises the construction of bored piles and the
. construction of soldier piled earth retaining structure as specified in the Contract Documents.
The Accepted Contract Amount is based on the specification, drawings and other documents
issued at the time of tender, and provides for all materials and plant to be supplied as
specified.
- The Commencement Date, in accordance with Sub Clause 3.1 of the Conditions of Contract,
shall be 20 March 2012. ~ ~ "ij(
PT. Sarananeka lndahpancar
Jl. Prof. DR. Satrio Kav.ll
Jakarta 12930, INDONESIA
Telp. : (62-21) 520 2585
Fax. : (62-21) 529 22846
,.'
CIPUTRA
The Completion Date, in accordance with Sub Clause 3.1 ofthe Conditions of Contract, shall
be 150 (one hundred fifty) calendar days calculated from the Commencement Date, that is 17tl!
August 2012.
4. Delay Damages
The amount of delay damages, in accordance with Clause 3 of the Conditions of Contract,
shall be 0.1% of the Accepted Contract Amount per day up to a limit of 5% of the Accepted
Contract Amount.
5. Payment
In accordance with Clause 5 of the Conditions of Contract, payments to the Contractor shall
be made as follows:
(i) An advance payment with Total Amount Rp. 7.160.000.000,- (Rupiah Seven Billion and
One Hundreds Sixty Million) inclusive of PPN and PPh for a down payment of works
and rebar price.
(ii) Monthly progress,
(iii) Retention of 5% of the Accepted Contract Amount withheld for the six (6) month
Defects Liability Period.
In respect of the advance payment, the payment to the Contractor shall be made upon receipt
by the Employer of an unconditional bank guarantee in an equivalent amount issued by an
approved bank devisa, the form of the bank guarantee shall be substantially in the form as set
forth in Appendix A of the 1.00 Form of Tender. In any event, the terms of the bank guarantee
or advance payment guarantee shall be approved by or be to the satisfaction of the Employer.
The target date for the issue of the Quantity Surveyor's Valuation shall be Fourteen (14 No)
calendar days from receipt of the Contractor's Application for Payment. Payment by the
Employer shall be made within 21 (twenty one) working days of the receipt of invoice. All
bank charges or other costs arising from the transfer of funds to the Contractor' s account shall
be borne by the Contractor.
In accordance with Clause 4 of the Conditions of Contract, the defects liability period shall be
six (6) calendar months from the date of the Taking-Over Certificate issued by the Project
Manager.
7. Insurances
Insurance of the Works and Third Party Liability insurances in accordance with Clause 11 of
the Conditions of Contract will be placed by the Employer.
PT.Sarananekalndahpancar
Jl. Prof. DR. Satrio Kav.11
Jakarta 12930, INDONESIA
Telp. : (62-21) 520 2585
Fax. : (62-21) 529 22846 2
~ CIPUTRA
The Contractor shall be responsible for insuring his own construction equipment, his own
workpeople and for payment of all premiums or Jamsostek contributions in respect thereof.
8. Performance Bond
The Contractor shall provide a performance bond in amount Rp. 2.425.000.000,- (Rupiah
Two Billion Four Hundred Twenty Five Million Only) to PT. Sarananeka Indahpancar
issued by a reputable local bank or bank licensed (Bank Devisa) for due performance of the
contract, in accordance with Clause 16 of the Conditions of Contract, in an amount equivalent
to 5% of the Accepted Contract Amount. The form of the performance bond shall be
substantially in the form as set forth in Appendix B of the 1.00 Form of Tender. In any event,
the terms of the performance bond shall be approved by or be to the satisfaction of the
Employer.
9. Contract Documents
The following letters and documents shall constitute integral parts of the Contract Documents:
(Y
PT.Sarananekalndahpancar
Jl. Prof. DR. Satrio Kav.11
Jakarta 12930, INDONESIA
Telp. : (62-21) 520 2585
Fax. : (62-21) 529 22846 3
~ CIPUTRA
Pending the execution of a formal agreement, this Letter of Award (SPK) shall constitute
sufficient authority for the Contractor to proceed with the Works. Following the execution of the
formal agreement, this SPK shall constitute part of the Contract Documents and the Contractor
shall fully comply with and be bound by the terms and conditions of the Contract Documents.
/'}?urs faithfully,
& rorand behalfofPT. SARANANEKA INDAHPANCAR ~'
Signed Signed
Date Date
Countersigned and chopped in acknowledgement of this Letter of A ward (SPK) and its contents.
INDONESIA
SPECIALIST
Signed
Date
PT.Sarananekalndahpancar
Jl. Prof. DR. Satrio Kav.ll
Jakarta 12930, INDONESIA
Telp. : (62-21) 520 2585
Fax. : {62-21) 529 22846 4
0 .11/476: CIPUTRA Lot 11 Davis Langdon & Seah Indonesia pt
Package 02: Piling and Earth Retaining Structure
PRELIMINARIES
6/1
0 .11/476: CIPUTRA Lot 11 Davis Langdon & Seah Indonesia pt
Package 02: Piling and Earth Retaining Structure
General
A Allow for site clearance (site vegetation , loose rubbish and 10.000 m2 7.000 70.000.000
debris) (Provisional)
B Allow for providing all plant and equipment on site for the 1 Is 270.000.000 270.000.000
installation of the piles including moving the plant and
equipment about the site, the provision of temporary
supports as required during the execution of the works and
for removing the plant and equipment from site on
completion of the works
c Allow for submission of records in triplicate of all bored piles 1 Is 5.000.000 5.000.000
installed, duly signed by the Contractor and deliver to the
Project Manager as the work proceeds
D Allow for the submission of a drawing showing the final plan 1 Is incl in bill no 1
position of each pile reference by a serial number and the
levels of the bottom and top of each pile as installed
6/2
0 .11/476: CIPUTRA Lot 11 Davis Langdon & Seah Indonesia pt
Package 02: Piling and Earth Retaining Structure
ALL PROVISIONAL
Note:
Bored pile, 1200mm diameter (318 no)
.
Bored pile, 1OOOmm diameter (170 no)
A Boring, 1200mm diameter from ground level to proposed 14.630 m 395.000 5.778.850.000
bored pile level (46 m)
B Boring, 1000mm diameter from ground level to proposed 7.480 m 355.000 2.655.400.000
bored pile level (44 m)
Concrete filling (fc=30 Mpa), to 1200mm diameter pile (32 11 .520 m3 960.000 11.059.200.000
m)
E Ditto, to 1000mm diameter pile (33.5 m) 4.480 m3 960.000 4.300.800.000
G Remove surplus excavated material/soil disposal from site 16.000 m3 70.000 1.120.000.000
6/3
0 .11/476: CIPUTRA Lot 11 Davis Langdon & Seah Indonesia pt
Package 02: Piling and Earth Retaining Structure
Collection
6/4
0 .11/476: CIPUTRA Lot 11 Davis Langdon Seah Indonesia pt.
Package 02: Piling and Earth Retaining Structure
General
A Allow for providing all plant and equipment on site for the 1 Is incl in bill no.2
installation of the piles including moving the plant and
equipment about the site, the provision of temporary
supports as required during the execution of the works and
for removing the plant and equipment from site on
completion of the works
\
B Allow for submission of records in triplicate of all bored piles 1 Is 6.000.000 6.000.000
installed, duly signed by the Contractor and deliver to the
Project Manager as the work proceeds
c Allow for the submission of a drawing showing the final plan 1 Is incl in bill no.1
position of each pile reference by a serial number and the
levels of the bottom and top of each pile as installed
6/5
0 .11/476: CIPUTRA Lot 11 Davis Langdon Seah Indonesia pt.
Package 02: Piling and Earth Retaining Structure
ALL PROVISIONAL
B Concrete filling (fc=30 Mpa), to 800mm diameter pile 2.280 m3 960.000 2.188.800.000
c General reinforcing bar (rebar ratio = 110 kg/m3) 250.800 kg 8.650 2.169.420.000
E Remove surplus excavated material/soil disposal from site 3.030 m3 70.000 212.100.000
6/6
0 .11/476: CIPUTRA Lot 11 Davis Langdon Seah Indonesia pt.
Package 02: Piling and Earth Retaining Structure
Collection
..
617
0.11/476: CIPUTRA Lot 11 Davis Langdon & Seah Indonesia pt
Package 02: Bored Pile
FINAL SUMMARY
Rupiahs
CIPUTRA Lot 11
Cilandak Commercial Estate 110 NGW Cilandak Commercial Estate 110 NGW
7/1