Revision History
Rev Date Summary Remarks
Method Statement for the Chlorination &
0 02-08-2017 Disinfection of Drinking water networks in Area As per the site requirement
01, Package 5
1
2
1. Scope of Work: a brief description of the activity / work being addressed by the Method Statement
Actual Location: Expand Dhahran Residential Community Project, Area 01, Package 5
Start date: 02/12/2017 Finish date:02/16/2017
Number of operatives & manpower with trade:
Civil Engineer-1
Service Engineer 1
Technician - 1
Field Safety Officer-1
Work permit receiver-1
First Aider-1
Surveyor-1
Site Foreman-1
Laborer-6
2.Prestart requirements: Attendances by others, permits, etc.
Secure work permit approval from SAPMT/UD prior to start with commencing the activity.
Coordinate with the other trades prior to commence the work, for provision of facilities.
Ensure all approved IFC drawings and material submittals will be in place
Ensure necessary shop drawings, tools, materials, equipment and manpower required for the work to
be on site.
Plan and prepare schedule of activities to be conducted.
All site personnel involved in doing the chemical preparation will be competent and trained.
Coordinate with Safety Manager / Safety Officer regarding the risks associated to the activity.
Barricade the area, provide basic need for facilities & hygiene for people viz. shelter, toilet, drinking
water
Page 1 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
3. Plant & equipment: Tools, PPE, Lifting equipment & appliances, special requirements for work at
height, confined space ,boots overalls etc.
Chlorination Skid Equipment
1 Centrifugal pump,
2 x 20 filter set,
Accumulated water is drained. ( In any cases there is 100% filled up water inside, drain
completely including the networks inside the villas )
While the system is draining, set up the Chlorination skid in DVB-2042 as the injection point
serving the Area 01 Villas.
Open DVB 2030, DVB-2029 (Zone 2), DVB-2026 (Zone 1), DVB-2028 (Zone 5), DVB-2063
(Zone 3), DVB-2044 (Zone 4)
Set up the hose of the water tanker in the Chemical Tank of the Chlorination Skid
Wearing PPE, slowly fill the chemical tank with the initial 100 kg of Berkobio 369. At the same
time adding fresh water from the water tanker at the same flow rate 1 liter/min ( Make sure the
Page 2 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
injection line valve is open and the discharge valve after the transfer pump of the Chlorination
Skid )
Once finished, Continue filling fresh water with chlorine injection pump to pressurize the
system until 2 bars, 50% filled up system lines.
After 2 bar is reached, again inject the remaining 100 kg Berkobio 369 same time adding
fresh water continuously.
Once the solution is injected, supply with fresh water to pressure the system. While doing this,
open the Drinking water faucets in end point of villas in each zone. This to make sure the
chlorinated solution will reach the end point in all villas.
During this period, M/s. Wetico Service Engineer will go to the drinking water faucets of end
villas in each zone to conduct chlorine test to confirm if the chlorine have reached.
Once confirmed that the all chlorinated solution is in the system. Drinking water faucets will be
closed. And continue pressurizing the lines until 4 bars, 100% completely filled.
WETICO Service engineer will now conduct Chlorine test to check the concentration of the
chlorine in end villas of each zone.
The chlorine residual should 100 ppm. Any villa found to have less than 100ppm
concentration, the lines shall be injected with additional required Berkobio 369 in the nearest
valve box. Relocate the Chlorine Skid equipment to the injection line. (Zone 1 DVB 2026,
Zone 2 DVB-2029, Zone 3 DVB-2063, Zone 4 DVB-2044, Zone 5 DVB-2028)
After checking all villas in Area 01 drinking water network has 100 ppm Chlorine
concentration, start retention time of 24 hrs.
Wearing PPE, First check the residual Chlorine concentration in the system network.
Using sterilized sampling bottles, take samples at each discharge point inside the villa (drinking
water faucet)
Using Wetico Chlorine test kits, check for the residual chlorine.
After getting the residual Chlorine, calculate for the quantity of Berkoclean 553 to be used for
neutralization.
Make sure chemical tank of chlorination skid is cleaned and free of Berkobio 369. If still have
traces of chlorine, rinse with Berkoclean 553 solution @1% solution and final rinse of water.
From the injection point DVB 2042 fill the chemical tank with the required quantity of Berkoclean
553
(Note: At the worksheet above, the quantity of Berkoclean 553 is only estimated when the chlorine
residual is 50-70 ppm after 24hrs. retention time . This is based on the chlorination projects Wetico
carried out earlier. However actual quantity can be determined after getting the actual residual Chlorine
on-site )
Page 3 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
Start injection of Berkoclean 553 with the required quantity in the DVB-2042 pressurizing the
system. At some point, drinking water faucets in end villas shall be opened for 5 10 minutes to
pull the neutralizing solution at the end to de-chlorinate the system.
After 10 minutes, closed all Drinking water faucets, and continue injecting the neutralizing solution
until finished.
Wearing PPE, check the residual Chlorine concentration in the system network. It should be zero
ppm Chlorine.
Using sterilized sampling bottles, take samples at each discharge point (drinking water faucet)
Using Wetico Chlorine test kits, check for the residual chlorine. (If in case, there is >0ppm chlorine
detected. Inject additional required Berkoclean 553 at location where the chlorine is above 0ppm)
After all system is found to have zero ppm Chlorine flush out directly to drain line the waste
solution or neutralized solution shall be collected by a tanker. Place the suction pump in DVB-
2042.
Refill the system networks (main & branch) and all villas with fresh water. Open the
source from main lines passing the DVB-2042. Open all valve box DVB 2038, DVB-2040,
DVB-2041, DVB-2043, DVB-2044 to pass though all fresh water. Open also DVB 2030, DVB-
2029 (Zone 2), DVB-2026 (Zone 1), DVB-2028 (Zone 5), DVB-2063 (Zone 3), DVB-2044
(Zone 4)
While filling up, open the raw water faucets of all villas or end villas of each zone.
Wetico Service Engineer will make some test if neutralizing solution has totally discharge.
Presence of residual chlorine 0.5 ppm 1.5 ppm is an indicator that the system is disinfected
Wearing PPE, water samples will be taken using non-reactive sterilized sampling bottles by
random (villas at the end and beginning per zone).
Water samples collected are shipped to Subcontractor laboratory and Aramco accredited
laboratory within 24hrs. for analysis. Standard method of sampling Water for Microbiological
analysis is followed.
Subcontractor will submit the completion report along with bacteriological analysis results
Page 4 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
10. Specific training / induction to be given to those executing the work (where required)
(All employees) Engineer, Supervisor, Foreman,
Hazard Identification
Labors, helpers, WPR, FSO for the job.
(All employees) Engineer, Supervisor, Foreman, Labors,
Risk Assessment
helpers, WPR, FSO for the job.
Confined Space Awareness & (All employees) Engineer, Supervisor, Foreman, Pipe
Rescue training fitters,
Page 5 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
12. First Aid Name & contact details of First Aider and Location of First Aid Box
- Mr. Alex Monsunny First Aider # 059-152-3714 @ site
- First Aid box Placed in car along with first aider.
Call
059-152-3714 Alex Monsunny First Aider
059-776-3598 Khalid Saifullah HSE Manager
055-390-9990 Housam Nakouzi Project Manager
056-120-8888 Fahad Al-Mansoor Construction Manager
054-636-7776 Saleh Selim Lead Mechanical Engineer
Remain Claim
Say this is an Emergency
Describe your Location
Describe the Incident
Report Injuries if any
Give your Name and Telephone / Mobile Number
Repeat the above information
Stay on line. Do Not Hang Up, Until Help Arrives.
Page 6 of 7
UNCONTROLLED WHEN PRINTED
Job Specific Method Statement
Title: Chlorination & Disinfection of Drinking water networks
MS #:MS-YC-PKG2-213 Rev #. 00
in Area 01, Package 5
16. Supporting Documentation e.g. risk assessment, plans, permits, drawings etc.
Document Ref #
JSA
I have read the site specific Method Statement, Risk Assessments and all supporting documentation for
my task or had it explained to me. I fully understand its contents and confirm that I will adhere to all
instructions contained within. I agree that NO ATTEMPT will be made to carry out any other works not
detailed on this Method Statement.
Furthermore, I agree to abide by all site rules and will stop work and report any site conditions that have
potential to cause injury, accident or ill health to myself or others.