VALORIZACION AGROVISION II ETAPA - 1 COMPONENTE

VALORIZACION ANTERIOR VALORIZACION N 01


Item Descripcin Und. Metrado Precio $ Parcial $ METRADO VALORIZADO AVANCE % METRADO VALORIZADO AVANCE %

OBRAS PRELIMINARES 3,472.98 2,896.31 83.40%


ELEMENTOS DE SEGURIDAD 1,514.26 757.13 50.00%
ENSAYOS DE LABORATORIO 470.33
CONSTRUCCION DE CAMARA ROMPE PRESION (01 UNID) 2,133.62
CONSTRUCCION DE FLOCULADOR 26,189.24 11,172.27 42.66%
CONSTRUCCION DE RESERVORIO DE 25 MIL M3 (02 UNID) 169,711.72 117,087.72 68.99%
ESTRUCTURAS EN CONCRETO RESERVORIOS
CONSTRUCCION DE TOMA FLOTANTE (02 UNID) 6,351.55
CONSTRUCCION DE VERTEDEROS (02 UNID) 13,258.38
CONSTRUCCION DE POZA DE LODOS 8,961.66 8,520.81 95.08%
ESTRUCTURA DE INGRESO POSA DE LODOS (01 UNID) 1,399.20
LINEA ADUCCION 22,099.66
COSTO DIRECTO 255,562.61 0.00 140,434.24
GASTOS GENERALES 11,500.32 0.00 6,319.54
UTILIDAD 12,778.13 0.00 7,021.71
SUBTOTAL 279,841.05 0.00 153,775.49
IMPUESTO (IGV 18%) 50,371.39 0.00 27,679.59
TOTAL PRESUPUESTO 330,212.44 0.00 0.00% 181,455.08 54.95%
AMORTIZACION DE ADELANTO 30% 99,063.73 49,531.87

TOTAL A FACTURAR INCLUIDO IGV (USD $) 0.00 131,923.21

VALORIZACION AGROVISION II ETAPA - 2 COMPONENTE


VALORIZACION ANTERIOR VALORIZACION N 01
Item Descripcin Und. Metrado Precio $ Parcial $ METRADO VALORIZADO AVANCE % METRADO VALORIZADO AVANCE %

OBRAS PRELIMINARES Y PROVISIONALES 1,851.00 0.00 0.00 0.00%


ELEMENTOS DE SEGURIDAD 286.96 0.00 0.00 0.00%
ENSAYOS DE LABORATORIO 136.35 0.00 0.00 0.00%
LOZA DE HIDRANTES (1 UNID) 2,752.05 0.00 0.00 0.00%
CAMARA DE INSPECCIN (01 UNID) 1,994.37 0.00 0.00 0.00%
CAMARA DE HIDRANTE A FLOCULADOR (01 UNID) 8,408.48 0.00 0.00 0.00%
CAMARA DE HIDRANTE A LOSA DE FILTRADO (01 UNID) 7,722.98 0.00 0.00 0.00%
CAJA DE VALVULAS DE CONTROL RESERVORIOS (02 UNID) 8,173.79 0.00 0.00 0.00%
MURO PERIMETRAL 47 X 5,9 H 23,396.37 0.00 0.00 0.00%
MURO PERIMETRAL 30 X 3,5 H 11,522.88 0.00 0.00 0.00%
COSTO DIRECTO 66,245.24 0.00 0.00
GASTOS GENERALES 2,981.04 0.00 0.00
UTILIDAD 3,312.26 0.00 0.00
SUBTOTAL 72,538.54 0.00 0.00
IMPUESTO (IGV 18%) 13,056.94 0.00 0.00
TOTAL PRESUPUESTO 85,595.47 0.00 0.00% 0.00 0.00%
AMORTIZACION DE ADELANTO 30% 25,678.64 0.00

TOTAL A FACTURAR INCLUIDO IGV (USD $) 0.00 0.00

VALORIZACION AGROVISION II ETAPA - 3 COMPONENTE


VALORIZACION ANTERIOR VALORIZACION N 01
Item Descripcin Und. Metrado Precio $ Parcial $ METRADO VALORIZADO AVANCE % METRADO VALORIZADO AVANCE %

OBRAS PRELIMINARES Y PROVISIONALES 2,521.37 1,628.49 64.59%


ELEMENTOS DE SEGURIDAD 289.85 144.93 50.00%
ENSAYOS DE LABORATORIO 75.75 0.00 0.00%
MOVIMIENTO DE TIERRAS 2,620.45 1,772.77 67.65%
OBRAS DE CONCRETO 33,419.40 4,944.62 14.80%
ALBAILERIA 3,882.59 1,768.79 45.56%
REVOQUES 1,679.72 0.00 0.00%
VIDRIERIA 540.00 0.00 0.00%
CARPINTERIA MADERA 396.84 0.00 0.00%
CARPINTERIA METALICA 6,416.00 0.00 0.00%
INSTALACIONES ELECTRICAS Y SANITARIAS 1,601.88 0.00 0.00%
PINTURA 1,146.19 0.00 0.00%
COSTO DIRECTO 54,590.03 0.00 18,890.69
GASTOS GENERALES 2,183.60 0.00 755.63
UTILIDAD 2,729.50 0.00 944.53
SUBTOTAL 59,503.13 0.00 20,590.85
IMPUESTO (IGV 18%) 10,710.56 0.00 3,706.35
TOTAL PRESUPUESTO 70,213.70 0.00 0.00% 24,297.20 34.60%
AMORTIZACION DE ADELANTO 30% 21,064.11 10,532.05

TOTAL A FACTURAR INCLUIDO IGV (USD $) 0.00 13,765.14