1.0 PROJECT SCOPE STATEMENT
To install Air Pollution Control System and Device at SIRIM Foundry, Rasa Hulu Selangor with duration of
completion not more than 61 days at cost not exceed than RM 186,000
1.2 Deliverables
1.3 Milestones
Site visit
Build internal components
Modify roof and floor
Construct collection stack
Pour concrete and install frame
Build Hi-Temperature burner
Install Control System
Install Air-Pollution Control Device
Inspection and Testing
3
1.4 Technical Requirements
Air-Pollution Control System and Device capable tomeet requirement of emission from DOE
Malaysia as stipulated in the Environmental Quality (Clean Air) Regulations 1978
The workers must comply the OHSAS safety requirements during installation
Site work is limited on Monday to Friday from 8.00 a.m. to 5 p.m.
Achieve main goals of the project in maximum ways.
4
2.0 PROJECT MANGEMENT PLANNING
Project Maintenance
Team & Inspection
5
2.2 Risk Analysis
6
2.3 Resource Requirement
Equipment &
Financial People Human resources Marketing
Device
2.3.1 Budget
The budget for each activities of the project are described in table below:
Total 186,000
Table 3: Budget
7
2.4 Work Breakdown Structure
Build and set up Modifying the Construction Installation of Control Installation of Air
the internal roof and floor works including System which involves Control Device,
components pour concrete in assembling the Regenerative
and assemble the Centrifugal exhaust Thermal
frame blower, hoods, gas duct Oxidizers (RTO)
and stacks
8
2.5 Project Network Schedule
Durations
Activity Descriptions Predecessor
(Days)
9
2.5.1 Forward and Backward Pass
0 A 2 2 B 9 9 D 16 16 F 23
0 2 2 16 16 7 23 23 7 30
9 7
2 C 16 16 E 30 16 G 30
2 14 16 16 14 30 44 14 58
30 H 58
Install Air-
0 Pollution Control 0
Device
30 28 58
LEGEND
ES ID EF 58 I 61
Inspection and
SL DESCRIPTION SL 0 Testing 0
LF DUR LF 58 3 61
Critical Path
10
2.5.2 Gantt Chart
B. Build internal
components
2-9
C. Modify roof
and floor
2-16
D. Construct
collection stack
9-16
E. Pour concrete
and install frame
16-30
F. Build Hi-
Temperature 16-23
burner
G. Install Control
System
16-30
H. Install Air-
Pollution Control 30-58
Device
I. Inspection and
Testing
58-61
Legend :
Critical Path
11
3.0 BASELINE BUDGET CONTROL PLAN AND STATUS REPORT
The total budget for the Installation of Air Pollution Control System and Device for Air Purifier Sdn.Bhd. is
RM 186,000.00. The budget will be allocated in some units of activities of the project.
Time Period
ACT DUR ES LF SL Total PV
0 1 2 3 4 5 6
A 2 0 2 0 2 2
B 7 2 16 7 32 16 16
C 14 2 16 0 16 8 8
D 7 9 23 7 14 14
E 14 16 30 0 18 8 10
F 7 16 30 7 30 30
G 14 16 58 28 32 14 18
H 28 30 58 0 34 14 10 10
I 3 58 61 0 8 8
Total PV by period 26 46 54 32 10 18
12
3.2 Status Report
13
Status Report: Ending Period 5 (Day 421-51)
Task % complete EV AC PV CV SV
A Finished 2,000 2,500 2,000 - 500 0
B Finished 32,000 30,000 32,000 2,000 0
C Finished 16,000 14,000 16,000 2,000 0
D Finished 14,000 19,500 14,000 - 5,500 0
E Finished 18,000 17,000 18,000 1,000 0
F Finished 30,000 32,500 30,000 - 2,500 0
G Finished 32,000 29,000 32,000 3,000 0
H 90% 30,600 28,800 24,000 1,800 6,600
Cumulative Totals 174,600 173,300 168,000 1,300 6,600
14
3.4 Summary Graph
EV, AC, PV
200000
180000
160000
140000
120000
RM
100000 EV
80000 AC
60000 PV
40000
20000
0
1 2 3 4 5 6
Period
15
4.0 CONCLUSION
Based on the data obtained, it was found that the objective of the proposal can be achieved within 61 days total
project duration and cost not more than RM 186,000 at the end of Period 6. This was supported by the SPI Index
value equivalent to 1.00, which indicates the project durations are completed on time. While for CPI, the
index value showed 1.02 which is more than 1.00, indicates that the project is under cost. The usage of
functional structure in this projects organization would enhance the productivities and efficiencies of each
workers and their employees. On the other hand, the application of this project scheduling and work
breakdown structure would also be able to ensure the project durations for all of the activities are
completed within time frame and maintained reasonable budget control plan.
5.0 RECOMMENDATIONS
Based on CPI Index for Period 2 and 3, the value showed less than 1.00 which indicates that the cost
was over budget. There are several recommendations that can be proposed to improve the cost of this
project during the period 2 and 3. First, the project management team should reduce the cost by
identifying the parts, raw materials, equipment and etc from reliable and valid suppliers that can offer
much cheaper price and at the same time capable to meet the technical requirements for the project.
Secondly, the project team need to consider the currency exchange loss in the budget if the parts, raw
materials and equipment were purchased from other countries. The currency loss must be include in
order to avoid any burst in allocated budget.
16
REFERENCES
1. Clifford F. Grey, Erik W. Larson, Project Management; The Managerial Process, published by
The McGraw-Hill Companies, 2008
2. https://en.wikipedia.org/wiki/Regenerative_thermal_oxidizer
3. http://epp.co.in/eppchemical/air-pollution-control-system.htm
4. http://www.doe.gov.my/eia/wp-content/uploads/2012/03/A-Guide-For-Investors1.pdf
17