P3M3 Project Model

5. Project Management Maturity Model

This model is based on best practice guidance and Effective engagement with the stakeholder
OGCs PRINCE2 publications, along with experience environment, focusing on achieving stakeholder
gained from the Project Management Maturity Model requirements.
and the original version of P3M3.
Projects should contribute to business objectives.
Typically, their funding is identified as part of overall
Definition of project management
business planning. They may be part of an wider
OGC defines a project as a unique set of coordinated
programme of business change.
activities, with definite starting and finishing points,
undertaken by an individual or team to meet specific
Attributes of project management
objectives within defined time, cost and performance
The following sections set out the attributes for
parameters as specified in the business case.
each of the seven Process Perspectives within the
Project management guides a project through a visible Project Management Maturity Model, at each of
set of activities, from controlled start-up, through the five Maturity Levels, along with a description
delivery, to controlled closure, and review. There will of each attribute.
be visible milestones and well-managed resources,
stakeholders and interdependencies, with all parties
involved being clear about their goals and individual
responsibilities.

Characteristics of project management


Good project management will be expected to have
the following characteristics.
A finite and defined lifespan
Defined and measurable business deliverables that
contribute towards the achievement of business
objectives
A defined amount of resources
Delivery of capabilities from which business benefits
and performance improvements can be leveraged
An organizational structure, with defined roles and
responsibilities
Focus on management and coordination
Delivery of outputs within time and cost constraints
Quality management, focusing on fit-for-purpose
outputs based on requirements
Business cases containing an accurate budget for
output delivery
Risk management focused on costs, quality and
timescales for delivery
Issue management is proactive and focused on
ensuring successful delivery
Project plans that are both product and activity
orientated

P3M3 is a Registered Trade Mark of the Office of Government Commerce


The OGC logo is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom

2 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

PjM3 - Management Control Level 1 2. Issues resolved locally with little consultation
Description with other areas
Project management terminology is used by some
3. Some change control but only at local level
members of the organization but not consistently and
possibly not understood by all stakeholders. 4. Project monitoring and control may be
sufficiently robust to provide adequate visibility
Projects will be conducted and managed according to
of actual project progress and enable effective
individual preferences.
action to be taken if project performance
deviates significantly from project plan
Specific Attributes
1. Some projects recognized and some specific 5. Work may be ongoing to establish an
objectives organization-wide project management
approach through recognition of a project life
2. Ad hoc configuration management
cycle, supported by document templates, tools
3. Some projects may have a person designated as and techniques, but is yet to be established
project manager
6. Key documents and other assets recognized
4. Some projects will be subject to some throughout project life cycle
rudimentary management activities, such as
7. Each project has a recognized framework but
outline planning, and recognition of key activities
standard project management processes and
and resources undertaking those activities
fully supported methods not yet adopted across
5. Projects poorly documented with poorly entire organization
defined end-point
8. Little impact assessment on business operations
6. Some projects may be considered to have been a prior to transition
success, but there is little on which to build and
9. Tool and method selection may be localized
reduce the risk for new projects
10. Localized information structures with some
Generic Attributes information sharing between teams
1. Training provision is uncoordinated, with little or
11. Local configuration management arrangements
no knowledge sharing
defined, perhaps with file-naming conventions
2. Key individuals lack experience and local storage arrangements
3. No standard roles, and responsibilities are not
Generic Attributes
defined or are generic
1. Localized information structures, with some
4. Some information available but is outdated, information sharing between teams
unstructured and dispersed
2. Focus on documentation during start-up and
5. Limited, if any, formal checking or review definition, but not maintained over initiatives
life cycle
6. Plans, if any, are conceptual or merely sequences
of events with rough timescales 3. Limited localized information controls, with no
formal release management arrangements
7. Planning, if any, likely to be an initial activity with
little maintenance of ownership or tracking 4. Local reviews, with some corrective actions
undertaken within the group
PjM3 - Management Control Level 2 5. Generic training may be provided in key
Description concepts, and there may be individuals
The concepts of project management will have been undertaking qualification training
grasped by the organization, and there may be local
6. Local sharing of knowledge may exist but
experts, such as experienced project managers,
mostly ad hoc
working on key projects.
7. Key individuals may have practical delivery
Specific Attributes experience and track record
1. Evidence of project framework used to facilitate
8. Roles, responsibilities and competencies defined
planning and in change management, but not
in some areas but not consistently across the
consistent across the organization
organization

Portfolio, Programme and Project Management Maturity Model (P3M3) 3


P3M3 Project Model

9. Plans exist but are not underpinned by consistent 12. There will be active consideration of transition
development methodology, yet may still be management to ensure that project deliverables
effective locally are capable of being exploited by the user
10. Planning seen as activity tracking rather than
Generic Attributes
proactive/forecasting
1. Information has a refresh cycle or is regularly
11. Estimation is more guesstimation and does accessed
not use standard techniques
2. Organization-wide information standards on
confidentiality, availability and integrity
PjM3 - Management Control Level 3
3. Formal information release management
Description
procedures
There is a centrally defined and documented approach
to a project management life cycle and controls, and it 4. Independent reviews take place
is applied in all projects by capable staff who support
5. Scrutiny largely for compliance reasons,
project teams.
identifying failures rather than opportunities
for improvement
Specific Attributes
1. Fully documented and supported project life 6. Plans developed to a central and consistent
cycle across the organization, with gates or standard that is output- or goal-based
stage reviews to maintain control followed
7. Plan development takes into account a range
by all projects
of relevant factors
2. Issue management and change control
8. Evidence of effective estimating techniques
procedure integrated and consistent across
the organization 9. Dependencies are identified, tracked and
managed effectively
3. Project managers accustomed to tailoring
standard project framework to meet needs of 10. Training is focused on the organizations
specific projects approaches and raising competence of
individuals in specific roles
4. Projects ensure that it is feasible to deliver
solutions that satisfy relevant requirements 11. Forums exist for sharing organizational
experience to improve individual and
5. Variations to project deliverables subject to
organizational performance
change control procedures and approved
as appropriate 12. Centrally managed role definitions and
sets of competencies defined and used to
6. Standard processes, procedures and templates
support appointments
to enable consistent management control
of projects
PjM3 - Management Control Level 4
7. Decisions to begin transition signed off by key
Description
business managers
Project management is seen as a key tool for the
8. Project deliverables accord with product delivery mechanism of change.
descriptions and are reviewed against agreed
Within the project environment the focus is on
quality criteria that match strategic objectives
improvement of delivery through measurement and
and are traceable throughout project life cycle
analysis of performance.
9. Product or service handover to operational staff
planned at early stage Specific Attributes
1. Evidence of projects being stopped or diverted to
10. Project Boards with business representation exist
gain better alignment with other initiatives and
and have clearly defined purposes, based on
optimize project delivery environment
standard model
2. Knowledge management is a central function
11. Formal reviews planned and undertaken at
and is used to help improve performance
appropriate stages in project life cycle, perhaps
involving members of other teams, the business 3. Succession plans for key roles
and external reviewers
4. Development plans for all team members

4 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

5. Project management metrics used to monitor 7. Evidence of interventions to avoid conflicts and
and control projects in quantitative terms take advantage of opportunities
6. Project Boards show high degree of engagement 8. Mentoring and individual development is used to
and active decision-making to improve delivery improve organizational performance
7. The organization routinely collects performance 9. Succession plans exist for key roles
data from projects and uses it to characterize
process capability
PjM3 - Management Control Level 5
8. Inter-project dependencies actively managed Description
Management controls ensure that the project
9. Projects maintain business focus and alignment
approach delivers the change objectives of the
through a sponsor or project executive fully
organization.
conversant with project management methods
and techniques Acceptance of project management as the optimal
approach to change delivery is organization-wide.
10. Project reports used to inform management on
There is evidence of continual improvement.
risk and provide assurance that projects are on
track towards desired outcome
Specific Attributes
11. Project Boards have appropriate business 1. Underlying causes of project issues and
representation, including supply chain, where recognized problems are identified and changes
appropriate implemented to minimize recurrence in future
projects
12. Project Board membership perceived as providing
opportunity to improve, and is consequently well 2. Common causes of product defects and process
supported by senior management non-compliance analyzed and action taken to
prevent recurrence
13. Project reviews centrally managed and conducted
at appropriate value assurance points 3. Objective achievement by projects reviewed by
the organization and lessons learned fed into
14. Assets stored in secure repository, with access by
other projects
those with appropriate clearance
4. Guidance available to project managers and
15. Dynamic configuration management system with
teams routinely reviewed and updated to reflect
audit trails and ability to revert to earlier builds
indicators from previous experience
and baselines
5. Established sizing measures and complexity
16. Controls on entry into, and exit from,
indicators for projects used to adjust risk profile
configuration management system
and signal requisite level of control to be applied
Generic Attributes 6. Overarching timetable of project plans, reviewed
1. Information is current and extensively referenced by Executive Board
for better decision-making
7. Configuration management embedded in
2. Trend analysis and measurement undertaken all activities, with extensive consultation
on performance information to identify and consideration
improvement opportunities
8. Referencing and storage systems integrated with
3. Knowledge management is a central function organizational approaches
and is used to help improve performance
and planning Generic Attributes
1. Information is valued, with continual
4. Reviews focus on opportunities to improve as
maintenance and reference
well as compliance
2. Evidence of extensive intelligence-gathering
5. Plans kept up to date, with the application
processes, with information disseminated
of sophisticated planning techniques and
through a variety of channels
recognition of interdependencies
3. Review and improvement is continual and
6. Extensive training is provided, focusing on
proactive, with lessons being shared openly
personal development and performance
improvement

Portfolio, Programme and Project Management Maturity Model (P3M3) 5


P3M3 Project Model

4. Planning inherent in decision-making process, Specific Attributes


with adjustments and implications managed 1. Evidence in some projects of understanding of
and deployed differences between product features, outputs
and outcomes
5. Active management of interdependencies
between initiative plans and other business plans 2. Responsibility for benefits may be assigned
within some project business cases but outside
6. Estimations are accurate and used effectively to
project team
ensure delivery
3. Role of sponsor or project executive in benefits
7. High levels of competence embedded in all roles
management and realization may be articulated
and seen as part of career paths
in some projects
8. Knowledge transfer is an inherent behaviour
4. May be some benefit measurement criteria
within the organization
5. Different areas manage and account for benefits
9. Skills embedded into organizational leadership
in different ways
and management development programmes
6. Post-project reviews focused on project activities
and deliverables rather than achievement
PjM3 - Benefits Management Level 1
of benefits
Description
There is some recognition that the concept of benefits
Generic Attributes
can be differentiated from project outputs.
1. Localized information structures, with some
information sharing between teams
Specific Attributes
1. Requirements defined in terms of features and 2. Focus on documentation during start-up
results rather than measurable performance and definition, but not maintained over
improvement initiatives life cycle
2. Benefits seen as justification rather than core 3. Limited localized information controls, with no
element of projects delivery formal release management arrangements
3. Little or no recognition of how benefits are to be 4. Local reviews, with some corrective actions
managed and realized undertaken within the group
5. Generic training may be provided in key
Generic Attributes
concepts, and there may be individuals
1. Training provision is uncoordinated, with little or
undertaking qualification training
no knowledge sharing
6. Local sharing of knowledge may exist but
2. Key individuals lack experience
mostly ad hoc
3. No standard roles, and responsibilities are not
7. Key individuals may have practical delivery
defined or are generic
experience and track record
4. Some information available but is outdated,
8. Roles, responsibilities and competencies defined
unstructured and dispersed
in some areas but not consistently across the
5. Limited, if any, formal checking or review organization
6. Plans, if any, are conceptual or merely sequences 9. Plans exist but are not underpinned by consistent
of events with rough timescales development methodology, yet may still be
effective locally
7. Planning, if any, likely to be an initial activity with
little maintenance of ownership or tracking 10. Planning seen as activity tracking rather than
proactive/forecasting
PjM3 - Benefits Management Level 2 11. Estimation is more guesstimation and does
Description not use standard techniques
Benefits are recognized as an element within project
business cases. There may be some documentation
regarding who is responsible for particular benefits
and their realization, but this is unlikely to be followed
through or consistent.

6 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

PjM3 - Benefits Management Level 3 10. Training is focused on the organizations


Description approaches and raising competence of
There is a centrally managed and consistent individuals in specific roles
framework for defining and tracking the realization
11. Forums exist for sharing organizational
of benefits from project outputs.
experience to improve individual and
organizational performance
Specific Attributes
1. Measures of project success are becoming 12. Centrally managed role definitions and
defined and explicit sets of competencies defined and used
to support appointments
2. Common approach and processes that ensure
consistency across all projects in relation to
benefits measurement and realization PjM3 - Benefits Management Level 4
Description
3. Benefits management process described within
Benefits management is embedded within the
project business case
project management approach and there is a focus
4. Changes to project considered against impact on delivery of business performance from project
on benefits outputs.
5. Common set of tools and templates used for Project performance metrics are collected and
benefits management activities, including their analyzed.
detailed description
Specific Attributes
6. Benefits documents stored centrally and subject
1. Processes in place to identify and resolve double
to change control
counting of benefits
7. Detailed statements explaining how benefits will
2. Benefits defined at programme level and may be
be achieved from project deliverables
cascaded down to projects
8. Benefits calculated in financial terms against
3. Benefit reviews undertaken regularly and action
centrally managed assessment criteria
taken to leverage opportunities
9. Clear responsibilities for benefits realization cited
4. Complex variety of benefits measures designed
in business cases
and applied according to circumstances (e.g.
10. Post-project benefit reviews used to report Balanced Scorecard)
formally on outcomes and benefit realization
5. Common, performance-based benefits
measurement and assessment mechanisms
Generic Attributes
in place
1. Information has a refresh cycle or is regularly
accessed 6. Clear and active ownership of plans to improve
performance from project outputs
2. Organization-wide information standards on
confidentiality, availability and integrity 7. Processes for management of benefits realization
owned, reviewed and being improved
3. Formal information release management
procedures 8. The organization ensures that claimed benefits
are realistic and endorsed by the sponsor or
4. Independent reviews take place
project executive
5. Scrutiny largely for compliance reasons,
identifying failures rather than opportunities Generic Attributes
for improvement 1. Information is current and extensively referenced
for better decision-making
6. Plans developed to a central and consistent
standard that is output- or goal-based 2. Trend analysis and measurement undertaken
on performance information to identify
7. Plan development takes into account a range
improvement opportunities
of relevant factors
3. Knowledge management is a central function
8. Evidence of effective estimating techniques
and is used to help improve performance
9. Dependencies are identified, tracked and and planning
managed effectively

Portfolio, Programme and Project Management Maturity Model (P3M3) 7


P3M3 Project Model

4. Reviews focus on opportunities to improve 4. Planning inherent in decision-making process,


as well as compliance with adjustments and implications managed
and deployed
5. Plans kept up to date, with the application
of sophisticated planning techniques and 5. Active management of interdependencies
recognition of interdependencies between initiative plans and other business plans
6. Extensive training is provided, focusing on 6. Estimations are accurate and used effectively to
personal development and performance ensure delivery
improvement
7. High levels of competence embedded in all roles
7. Evidence of interventions to avoid conflicts and and seen as part of career paths
take advantage of opportunities
8. Knowledge transfer is an inherent behaviour
8. Mentoring and individual development is used within the organization
to improve organizational performance
9. Skills embedded into organizational leadership
9. Succession plans exist for key roles and management development programmes

PjM3 - Benefits Management Level 5 PjM3 - Financial Management Level 1


Description Description
Benefits management is embedded within the There is little or no financial control at project level.
organizational approach to change and is assessed as There is a lack of accountability and monitoring of
part of the development of organizational strategy. project expenditure.
Business performance metrics are linked to, and
Specific Attributes
underpin, the recognition of benefits realization.
1. Projects poorly defined and difficulties
There is evidence of continual improvement.
experienced in setting realistic budgets or
cost envelopes
Specific Attributes
1. Clear links between strategic decision-making 2. No process for projects to bid for funds
and benefits realization
3. Projects lack control mechanisms to track costs
2. Evidence of development and innovation of and project expenditure
techniques based on experience of realizing
4. Little formal project investment appraisal,
a variety of benefits in several different
with formal business cases rarely submitted
environments
and monitored
3. Active management of opportunities to enhance
5. Operational input costs assumed and not
benefits realization
accounted for
4. Decisions taken to balance benefits and
dis-benefits based on statistical measures Generic Attributes
1. Training provision is uncoordinated, with little
5. Strategic priorities affect benefit measures (e.g.
or no knowledge sharing
changes to strategic Key Performance Indicators
are filtered down into projects) 2. Key individuals lack experience
6. Post-project benefit reviews studied, trends 3. No standard roles, and responsibilities are not
established, and lessons learned fed back defined or are generic
into benefits realization planning and other
4. Some information available but is outdated,
management activities
unstructured and dispersed
Generic Attributes 5. Limited, if any, formal checking or review
1. Information is valued, with continual
6. Plans, if any, are conceptual or merely sequences
maintenance and reference
of events with rough timescales
2. Evidence of extensive intelligence-gathering
7. Planning, if any, likely to be an initial activity with
processes, with information disseminated
little maintenance of ownership or tracking
through a variety of channels
3. Review and improvement is continual and
proactive, with lessons being shared openly

8 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

PjM3 - Financial Management Level 2 11. Estimation is more guesstimation and does
Description not use standard techniques
Project business cases are produced in various forms
and the better and more formal cases will present
PjM3 - Financial Management Level 3
the rationale on which to obtain organizational
Description
commitment to the project. Overall cost of the project
There are centrally established standards for the
is not monitored or fully accounted for.
preparation of business cases and processes for their
management throughout the project life cycle.
Specific Attributes
1. Project business case approval processes at local Project managers monitor costs and expenditure
level only in accordance with organizational guidelines and
procedures, with defined interfaces with other
2. Some projects have business cases and there is
financial functions within the organization.
occasional reporting of progress and
costs incurred
Specific Attributes
3. Some project business cases contain more 1. Standardized approach to project business
than one option to justify the design intent or case development
preferred solution
2. Business cases approved centrally, making
4. Budgeting cost management at project level budget limitations explicit
is inconsistent across projects and unlikely to
3. Issues and risks assessed in financial terms
be well integrated with the organizations
financial processes 4. Guidelines exist on costs to be included in, and
excluded from, budgets
5. Budgets for funding changes as well as project
outputs not included in business cases 5. Projects have distinct budgets and expenditure
against budget is tracked and reported on
Generic Attributes
6. Clearly defined authorities for expenditure levels,
1. Localized information structures, with some
with cost and expenditure reported on using
information sharing between teams
agreed templates or pro-forma reports
2. Focus on documentation during start-up and
7. Contract placement using professional
definition, but not maintained over initiatives
procurement support to ensure best value
life cycle
for money
3. Limited localized information controls, with no
8. Standard financial estimation and value for
formal release management arrangements
money techniques deployed consistently
4. Local reviews, with some corrective actions across projects
undertaken within the group
9. Business cases reviewed at explicit stages in
5. Generic training may be provided in key project life cycle and actions taken to put
concepts, and there may be individuals projects back on track
undertaking qualification training
10. Evidence of operational sign-off for any
6. Local sharing of knowledge may exist but additional costs imposed by project
mostly ad hoc
11. Capital and revenue costs accounted
7. Key individuals may have practical delivery for differently
experience and track record
12. Centrally agreed project budgets, making it clear
8. Roles, responsibilities and competencies defined when and where funding will be available
in some areas but not consistently across
the organization Generic Attributes
1. Information has a refresh cycle or is regularly
9. Plans exist but are not underpinned by consistent
accessed
development methodology, yet may still be
effective locally 2. Organization-wide information standards on
confidentiality, availability and integrity
10. Planning seen as activity tracking rather than
proactive/forecasting 3. Formal information release management
procedures

Portfolio, Programme and Project Management Maturity Model (P3M3) 9


P3M3 Project Model

4. Independent reviews take place 10. May be an Investment Board overseeing all
project financial performance
5. Scrutiny largely for compliance reasons,
identifying failures rather than opportunities 11. Analysis of expenditure across projects used
for improvement to release and constrain funds in a
sophisticated way
6. Plans developed to a central and consistent
standard that is output- or goal-based 12. Structured approach to handing over financial
assets and costs to operational groups
7. Plan development takes into account a range of
relevant factors 13. Formal business reviews undertaken at various
stages in project life cycle to ensure that business
8. Evidence of effective estimating techniques
cases continue to present an accurate picture of
9. Dependencies are identified, tracked and desirability, viability and feasibility of projects
managed effectively
Generic Attributes
10. Training is focused on the organizations
1. Information is current and extensively referenced
approaches and raising competence of
for better decision-making
individuals in specific roles
2. Trend analysis and measurement undertaken
11. Forums exist for sharing organizational
on performance information to identify
experience to improve individual and
improvement opportunities
organizational performance
3. Knowledge management is a central function
12. Centrally managed role definitions and sets
and is used to help improve performance
of competencies defined and used to support
and planning
appointments
4. Reviews focus on opportunities to improve as
well as compliance
PjM3 - Financial Management Level 4
Description 5. Plans kept up to date, with the application
The organization is able to prioritize investment of sophisticated planning techniques and
opportunities effectively in relation to the availability recognition of interdependencies
of funds and other resources.
6. Extensive training is provided, focusing on
Project budgets are managed effectively and project personal development and performance
performance against cost is monitored and compared. improvement
7. Evidence of interventions to avoid conflicts and
Specific Attributes
take advantage of opportunities
1. Funds for use by projects scheduled optimally
8. Mentoring and individual development is used to
2. Business cases at core of decision-making
improve organizational performance
3. Financial tolerances monitored effectively across
9. Succession plans exist for key roles
all projects
4. Financial appraisals of project viability
PjM3 - Financial Management Level 5
routinely conducted
Description
5. Cost management at project level fully Project financial controls are fully integrated with
integrated with the organizations financial those of the organization. Cost estimation techniques
management functions used at the project level are continually reviewed
in terms of actual versus estimate comparisons to
6. Auditing of project expenditure routinely
improve estimation throughout the organization.
undertaken
There is evidence of continual improvement.
7. Risks evaluated in financial terms and
economically viable response plans formulated
Specific Attributes
and agreed
1. Project budget estimates reviewed at all planning
8. Earned value concepts of project activity may be checkpoints and refreshed accordingly
deployed, as appropriate
2. Changes in overall project cost and stage cost
9. Lessons on cost estimation shared across projects profiles escalated to, and reviewed by, senior
management

10 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

3. Costs incurred used to forecast future costs and PjM3 - Stakeholder Engagement Level 1
budgetary impact Description
Stakeholder engagement and communication is rarely
4. Project financial approvals process integrated
used by projects as an element of the delivery toolkit.
into organizational financial approvals process
5. Project financial risks escalated as appropriate, Specific Attributes
with effective mitigation and solutions sought 1. Concept of stakeholder engagement may be
acknowledged but is undefined
6. High degree of accuracy in forecasting project
costs within agreed tolerance allowances 2. Projects communicate with stakeholders on ad
hoc basis, relying on individuals within the team
7. Project costs integrated with organizational
taking the initiative
financial plans
3. No structured approach to stakeholder
8. Objective and regular assessment of the optimal
engagement and communications
use of finances, and review of opportunities
to identify better value from supply chain and
Generic Attributes
market place
1. Training provision is uncoordinated, with little or
9. Investment Board overseeing all project no knowledge sharing
financial performance
2. Key individuals lack experience
10. Value for money tracking of all projects
3. No standard roles, and responsibilities are not
defined or are generic
Generic Attributes
1. Information is valued, with continual 4. Some information available but is outdated,
maintenance and reference unstructured and dispersed
2. Evidence of extensive intelligence-gathering 5. Limited, if any, formal checking or review
processes, with information disseminated
6. Plans, if any, are conceptual or merely sequences
through a variety of channels
of events with rough timescales
3. Review and improvement is continual and
7. Planning, if any, likely to be an initial activity with
proactive, with lessons being shared openly
little maintenance of ownership or tracking
4. Planning inherent in decision-making process,
with adjustments and implications managed
PjM3 - Stakeholder Engagement Level 2
and deployed
Description
5. Active management of interdependencies Projects will be communicated to stakeholders, but
between initiative plans and other business plans this is linked more to the personal initiative of project
managers than to a structured approach being
6. Estimations are accurate and used effectively to
deployed by the organization.
ensure delivery
7. High levels of competence embedded in all roles Specific Attributes
and seen as part of career paths 1. Evidence may exist of more sophisticated analysis
and communications planning for some projects
8. Knowledge transfer is an inherent behaviour
within the organization 2. Most stakeholder analysis is basic and
inconsistent, limited to the issue of what
9. Skills embedded into organizational leadership
stakeholders are interested in
and management development programmes
3. Projects recognize stakeholder groupings but are
limited to local knowledge
4. Some projects have their own communications
plans but they focus on merely transmitting
information
5. Outgoing communications channels from
projects are limited, with focus on email
or websites

Portfolio, Programme and Project Management Maturity Model (P3M3) 11


P3M3 Project Model

6. Some stakeholders advised or consulted, and PjM3 - Stakeholder Engagement Level 3


feedback processed Description
There is a centrally managed and consistent approach
7. Key messages delivered inconsistently, with no
to stakeholder engagement and communications used
audit trails
by all projects.
8. Key individuals have practical experience and are
the source of most communications activity Specific Attributes
1. Centrally defined and consistent approach,
9. Communications interdependency tracking
and supporting process, for identifying and
between initiatives is limited
analyzing stakeholders
10. Structured approach beginning to evolve,
2. Projects consider stakeholder needs and
but based on good practice of one or two
stakeholders are actively involved in
key individuals
decision-making
Generic Attributes 3. Corporate communications (or equivalent)
1. Localized information structures, with some are involved in development of stakeholder
information sharing between teams engagement processes and procedures
2. Focus on documentation during start-up and 4. Stakeholders have authority and clearly defined
definition, but not maintained over initiatives roles within project
life cycle
5. Audit trails of communications maintained for
3. Limited localized information controls, with no all projects
formal release management arrangements
6. Structured, centrally managed communications
4. Local reviews, with some corrective actions plan balances communications from all projects
undertaken within the group
7. Communications channels vary and are used to
5. Generic training may be provided in key target and deliver messages effectively
concepts, and there may be individuals
8. Communications budget exists
undertaking qualification training
9. Much of this approach is provided by the
6. Local sharing of knowledge may exist but
permanent Project Office
mostly ad hoc
7. Key individuals may have practical delivery Generic Attributes
experience and track record 1. Information has a refresh cycle or is regularly
accessed
8. Roles, responsibilities and competencies
defined in some areas but not consistently 2. Organization-wide information standards on
across the organization confidentiality, availability and integrity
9. Plans exist but are not underpinned by consistent 3. Formal information release management
development methodology, yet may still be procedures
effective locally
4. Independent reviews take place
10. Planning seen as activity tracking rather than
5. Scrutiny largely for compliance reasons,
proactive/forecasting
identifying failures rather than opportunities
11. Estimation is more guesstimation and does for improvement
not use standard techniques
6. Plans developed to a central and consistent
standard that is output- or goal-based
7. Plan development takes into account a range
of relevant factors
8. Evidence of effective estimating techniques
9. Dependencies are identified, tracked and
managed effectively

12 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

10. Training is focused on the organizations 5. Plans kept up to date, with the application
approaches and raising competence of of sophisticated planning techniques and
individuals in specific roles recognition of interdependencies
11. Forums exist for sharing organizational 6. Extensive training is provided, focusing
experience to improve individual and on personal development and performance
organizational performance improvement
12. Centrally managed role definitions and sets 7. Evidence of interventions to avoid conflicts and
of competencies defined and used to support take advantage of opportunities
appointments
8. Mentoring and individual development is used to
improve organizational performance
PjM3 - Stakeholder Engagement Level 4
9. Succession plans exist for key roles
Description
Sophisticated techniques are used to analyze
and engage the project stakeholder environment PjM3 - Stakeholder Engagement Level 5
effectively, and quantitative information is used to Description
underpin the assessment of effectiveness. Communications are being optimized from extensive
knowledge of the project stakeholder environment,
Specific Attributes to enable the projects to achieve their objectives.
1. Sophisticated approach to analyzing,
There is evidence of continual improvement.
segmenting and maintaining stakeholder
perspective information
Specific Attributes
2. Extensive range of communications channels 1. Stakeholder engagement embedded in the
and techniques used to deliver messages organizations culture
3. Effectiveness of communications and stakeholder 2. Communications active, bi-directional and
engagement is measured, and is high embedded in decision-making process
4. Critical stakeholders embedded in decision- 3. Stakeholders fully engaged in change process
making process at all levels
5. Stakeholder reactions analyzed, and evidence 4. Communications recognized by project leaders
of proactive communications management as a key leadership tool
to influence stakeholder attitudes and levels
5. Communications measured, relevant and trusted
of support
6. Project leaders engaged with and supporting Generic Attributes
communications activities 1. Information is valued, with continual
maintenance and reference
7. Stakeholder identification and analysis covers
internal and external groups, with information 2. Evidence of extensive intelligence-gathering
maintained centrally processes, with information disseminated
through a variety of channels
8. Projects with high levels of market or community
consultation are common at this level 3. Review and improvement is continual and
proactive, with lessons being shared openly
Generic Attributes
4. Planning inherent in decision-making process,
1. Information is current and extensively referenced
with adjustments and implications managed
for better decision-making
and deployed
2. Trend analysis and measurement undertaken
5. Active management of interdependencies
on performance information to identify
between initiative plans and other business plans
improvement opportunities
6. Estimations are accurate and used effectively
3. Knowledge management is a central function
to ensure delivery
and is used to help improve performance
and planning 7. High levels of competence embedded in all roles
and seen as part of career paths
4. Reviews focus on opportunities to improve as
well as compliance

Portfolio, Programme and Project Management Maturity Model (P3M3) 13


P3M3 Project Model

8. Knowledge transfer is an inherent behaviour PjM3 - Risk Management Level 2


within the organization Description
Risk management is recognized and used on projects,
9. Skills embedded into organizational leadership
but there are inconsistent approaches, which result in
and management development programmes
different levels of commitment and effectiveness.

PjM3 - Risk Management Level 1 Specific Attributes


Description 1. Different areas and projects manage risk in
There is minimal evidence of risk management being different ways
used to any beneficial effect on projects.
2. Some projects recognize different categories
There may be evidence of risks being documented but of risk (e.g. distinguishing between project and
little evidence of active management. operational risks)
3. Risk response strategies and plans are likely to
Specific Attributes
have been ineffective in the past
1. Some risks may be identified and associated
with particular projects, but are not described 4. Inconsistency of approach to the assessment
or registered consistently, and there will be of risks
little, if anything, in terms of an effective risk
5. Risk register based on an organizational template
management process
may be used, but escalation and communication
2. Focus of management attention is on dealing on risks outside the project may be ineffective
with issues as they arise, with a reactive rather
6. Local risk management processes in place and
than proactive approach
managed by Project Board and teams
3. Risks arbitrarily classified and rarely, if ever,
7. Risk management not aligned with other project
quantified
life cycle activities (e.g. project planning)
4. Risk identification likely to be a one-off activity
8. Risk status reported to Project Board on ad hoc
and risks unlikely to be tracked or re-assessed
basis, if at all
during project life cycle
9. Key project managers understand and
5. Foreseeable threats likely to impact on projects
articulate the purpose and importance of
6. Little, if any, communication with other parts of risk management, but inconsistent levels of
the organization concerning project risk commitment and understanding across all
projects or the organization
Generic Attributes
1. Training provision is uncoordinated, with little Generic Attributes
or no knowledge sharing 1. Localized information structures, with some
information sharing between teams
2. Key individuals lack experience
2. Focus on documentation during start-up and
3. No standard roles, and responsibilities are not
definition, but not maintained over initiatives
defined or are generic
life cycle
4. Some information available but is outdated,
3. Limited localized information controls, with no
unstructured and dispersed
formal release management arrangements
5. Limited, if any, formal checking or review
4. Local reviews, with some corrective actions
6. Plans, if any, are conceptual or merely sequences undertaken within the group
of events with rough timescales
5. Generic training may be provided in key
7. Planning, if any, likely to be an initial activity with concepts, and there may be individuals
little maintenance of ownership or tracking undertaking qualification training
6. Local sharing of knowledge may exist but
mostly ad hoc
7. Key individuals may have practical delivery
experience and track record

14 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

8. Roles, responsibilities and competencies defined 5. Scrutiny largely for compliance reasons,
in some areas but not consistently across the identifying failures rather than opportunities
organization for improvement
9. Plans exist but are not underpinned by consistent 6. Plans developed to a central and consistent
development methodology, yet may still be standard that is output- or goal-based
effective locally
7. Plan development takes into account a range
10. Planning seen as activity tracking rather than of relevant factors
proactive/forecasting
8. Evidence of effective estimating techniques
11. Estimation is more guesstimation and does
9. Dependencies are identified, tracked and
not use standard techniques
managed effectively
10. Training is focused on the organizations
PjM3 - Risk Management Level 3
approaches and raising competence of
Description
individuals in specific roles
Project risk management is based on a centrally
defined process that is cognizant of the organizations 11. Forums exist for sharing organizational
policy for the management of risks and is used experience to improve individual and
consistently. organizational performance
12. Centrally managed role definitions and sets
Specific Attributes
of competencies defined and used to support
1. Standard risk management templates and tools
appointments
used extensively and consistently
2. Risks identified, assessed and controlled in
PjM3 - Risk Management Level 4
accordance with recognized procedures,
Description
across all projects
Project risk management is working effectively, is
3. Regular reviews, addressing broader embedded, and the value of risk management can be
opportunities for improvement as well demonstrated.
as compliance
There is evidence of opportunity management and
4. Reviews seen as a positive opportunity to management of risk aggregation.
improve, not a threat
Specific Attributes
5. Risk management interventions embedded
1. Projects able to demonstrate resource and
within project life cycle
budgetary implications of risks throughout
6. Risks consistently categorized by type project life cycle
(e.g. commercial, operational or strategic)
2. Cost effectiveness and feasibility of response
7. Audits of risk within projects measures demonstrable across all projects
8. Processes exist for escalation of project risks 3. Audits of risk management effectiveness
9. Risks not limited to internal impact on 4. Aggregated risk levels across projects tracked
project goals and managed
10. Risk assessment techniques defined and 5. Clear understanding of level of risk exposure
deployed consistently from projects being undertaken
6. Evidence of lessons being learned from project
Generic Attributes
reviews and assurance reviews
1. Information has a refresh cycle or is regularly
accessed 7. Risk management seen as organizational
process, with clear ownership
2. Organization-wide information standards on
confidentiality, availability and integrity 8. May be a risk manager, providing guidance
and controls
3. Formal information release management
procedures 9. Evidence of decision-making based on risk
assessment
4. Independent reviews take place

Portfolio, Programme and Project Management Maturity Model (P3M3) 15


P3M3 Project Model

10. The business and project stakeholders generally 8. Strong links and integration with financial
feel comfortable with the management of management, planning, estimating, project
project risks, and are involved as appropriate control and governance processes, and risks to
project benefits are highlighted and examined
Generic Attributes
1. Information is current and extensively referenced Generic Attributes
for better decision-making 1. Information is valued, with continual
maintenance and reference
2. Trend analysis and measurement undertaken
on performance information to identify 2. Evidence of extensive intelligence-gathering
improvement opportunities processes, with information disseminated
through a variety of channels
3. Knowledge management is a central function
and is used to help improve performance 3. Review and improvement is continual and
and planning proactive, with lessons being shared openly
4. Reviews focus on opportunities to improve as 4. Planning inherent in decision-making process,
well as compliance with adjustments and implications managed
and deployed
5. Plans kept up to date, with the application
of sophisticated planning techniques and 5. Active management of interdependencies
recognition of interdependencies between initiative plans and other business plans
6. Extensive training is provided, focusing on 6. Estimations are accurate and used effectively to
personal development and performance ensure delivery
improvement
7. High levels of competence embedded in all roles
7. Evidence of interventions to avoid conflicts and and seen as part of career paths
take advantage of opportunities
8. Knowledge transfer is an inherent behaviour
8. Mentoring and individual development is used within the organization
to improve organizational performance
9. Skills embedded into organizational leadership
9. Succession plans exist for key roles and management development programmes

PjM3 - Risk Management Level 5 PjM3 - Organizational Governance Level 1


Description Description
Risk management is embedded in the organizational Some informal governance of projects exists but has
culture and underpins all decision-making within undefined links to broader organizational controls.
projects. There is evidence of continual improvement. Roles are unlikely to be formally defined.

Specific Attributes Specific Attributes


1. Accountability for management of risk at 1. Projects start up without business control, and
Executive Board level no evidence of sign-off at project closure
2. Executive Board has clear visibility of risk 2. Project manager may exist but no clear authority
exposure to the organization from projects and may be part-time
3. Risk assessment underpins all decision-making 3. Project management activities likely to be
restricted, with confusion as to what is
4. Projects ensure adequate consideration
happening within projects on a day-to-day basis
of business continuity, especially on
and who controls what
business handover
4. Projects struggle to gain commitment and
5. Evidence of opportunity risks being actively
resources when required
managed
5. Minimal business ownership of project or
6. Risk management policy and supporting
representation on project team
governance arrangements periodically
reviewed for effectiveness
7. Business intelligence informs risk management
process and has clear cascade and
escalation route

16 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

Generic Attributes 3. Limited localized information controls, with no


1. Training provision is uncoordinated, with little formal release management arrangements
or no knowledge sharing
4. Local reviews, with some corrective actions
2. Key individuals lack experience undertaken within the group
3. No standard roles, and responsibilities are not 5. Generic training may be provided in key
defined or are generic concepts, and there may be individuals
undertaking qualification training
4. Some information available but is outdated,
unstructured and dispersed 6. Local sharing of knowledge may exist but
mostly ad hoc
5. Limited, if any, formal checking or review
7. Key individuals may have practical delivery
6. Plans, if any, are conceptual or merely sequences
experience and track record
of events with rough timescales
8. Roles, responsibilities and competencies defined
7. Planning, if any, likely to be an initial activity with
in some areas but not consistently across the
little maintenance of ownership or tracking
organization
9. Plans exist but are not underpinned by consistent
PjM3 - Organizational Governance Level 2
development methodology, yet may still be
Description
effective locally
Project management from an organizational
perspective is beginning to take shape but with 10. Planning seen as activity tracking rather than
ad hoc controls and no clear strategic control. proactive/forecasting
Roles and responsibilities will be inconsistent,
11. Estimation is more guesstimation and does
as will reporting lines.
not use standard techniques
Specific Attributes
1. Projects initiated based on local needs PjM3 - Organizational Governance Level 3
Description
2. Decisions taken in projects not always referred
Centrally defined organizational controls are applied
upwards for verification
consistently to all projects, with decision-making
3. Community of project management practice may structures in place and linked to organizational
exist, but with limited effectiveness in prioritizing governance.
and coordinating process improvement across
the organization Specific Attributes
1. Common definition of Project Boards (or
4. Not all projects will have project managers
equivalent) and their key roles and responsibilities,
5. Some projects may be undertaken outside the which are in place on most projects unless there is
organizations governance framework and are a clear reason for them not to be
not fully accountable
2. Central body that monitors and influences
6. Projects and initiatives report progress locally progress of all projects and the optimal balance
of current projects
7. Changes to projects not always delivered
through project manager route 3. Consolidated progress reporting on all projects
8. Project Boards may exist, but with ad hoc 4. All key roles and responsibilities documented
membership, acting more as consultation groups within individual terms of reference
than delivery groups
5. Project ideas evaluated against consistent criteria
prior to approval
Generic Attributes
1. Localized information structures, with some 6. Centralized decision-making ensures that
information sharing between teams projects fit the organizations ongoing needs
2. Focus on documentation during start-up and 7. Functional activities of sponsor or project
definition, but not maintained over initiatives executive can be demonstrated for all projects
life cycle

Portfolio, Programme and Project Management Maturity Model (P3M3) 17


P3M3 Project Model

8. Evidence of sponsor or project executives PjM3 - Organizational Governance Level 4


ensuring that projects maintain alignment Description
with organizational strategy, with interventions There will be clearly aligned project decision-making
as appropriate processes that adopt and integrate with broader
organizational governance and which are transparent
9. Decisions are auditable
to those involved. Project management responsibilities
10. Clear reporting lines set and maintained are embedded within broader role descriptions.
11. Legislative and regulatory requirements built
Specific Attributes
into guidelines
1. Decision-making balances need for
12. Evidence of structured start-up and closure of organizational performance and continuity
projects under clear business control with need for change
2. Decision-making includes approvals from key
Generic Attributes
governance groups at key critical points (gates)
1. Information has a refresh cycle or is regularly
throughout project life cycle
accessed
3. Directors with project responsibilities exhibit
2. Organization-wide information standards on
appropriate knowledge and behaviours
confidentiality, availability and integrity
4. Decision-making effectiveness reviewed and
3. Formal information release management
improvements sought
procedures
5. Strategic changes communicated to Project
4. Independent reviews take place
Board effectively
5. Scrutiny largely for compliance reasons,
6. Senior management sponsor, and demonstrate
identifying failures rather than opportunities
their commitment to, improvement initiatives
for improvement
7. Business performance measured against historic
6. Plans developed to a central and consistent
trends and impact of projects on business
standard that is output- or goal-based
performance is fully understood
7. Plan development takes into account a range
8. Evidence of ideas and requirements being
of relevant factors
scheduled and built into organizational
8. Evidence of effective estimating techniques strategic planning
9. Dependencies are identified, tracked and 9. Decisions to launch projects made against impact
managed effectively assessment on current initiatives
10. Training is focused on the organizations
Generic Attributes
approaches and raising competence of
1. Information is current and extensively referenced
individuals in specific roles
for better decision-making
11. Forums exist for sharing organizational
2. Trend analysis and measurement undertaken
experience to improve individual and
on performance information to identify
organizational performance
improvement opportunities
12. Centrally managed role definitions and sets
3. Knowledge management is a central function
of competencies defined and used to support
and is used to help improve performance
appointments
and planning
4. Reviews focus on opportunities to improve as
well as compliance
5. Plans kept up to date, with the application
of sophisticated planning techniques and
recognition of interdependencies
6. Extensive training is provided, focusing on
personal development and performance
improvement

18 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

7. Evidence of interventions to avoid conflicts and 14. Project management embedded as core
take advantage of opportunities change management technique
8. Mentoring and individual development is used to 15. Regular periodic reviews of effectiveness
improve organizational performance of governance arrangements, based on
lessons learned
9. Succession plans exist for key roles
Generic Attributes
PjM3 - Organizational Governance Level 5 1. Information is valued, with continual
Description maintenance and reference
The governance arrangements for projects are a core
2. Evidence of extensive intelligence-gathering
aspect of organizational control, with demonstrable
processes, with information disseminated
reporting lines to Executive Board level and with clear
through a variety of channels
ownership and control responsibilities embedded
within the organization. 3. Review and improvement is continual and
proactive, with lessons being shared openly
There is evidence of continual improvement.
4. Planning inherent in decision-making process,
Specific Attributes with adjustments and implications managed
1. Projects signed off at Executive Board level, and deployed
as appropriate
5. Active management of interdependencies
2. Organizational governance and accountabilities between initiative plans and other business plans
reflected throughout the organization,
6. Estimations are accurate and used effectively to
down to specific project responsibilities and
ensure delivery
accountabilities
7. High levels of competence embedded in all roles
3. Legal and regulatory responsibilities have
and seen as part of career paths
visible compliance
8. Knowledge transfer is an inherent behaviour
4. Decisions on priorities and major conflict
within the organization
resolution resolved by reference to strategic
priorities and Executive Board 9. Skills embedded into organizational leadership
and management development programmes
5. Pre-emptive and rational project closure
based on business decisions other than
project performance PjM3 - Resource Management Level 1
Description
6. Lessons learned contribute to development of
There is some recognition within the organization of
guidance on conduct of specific roles
the need to manage resources effectively to enable
7. Projects aligned to organizations strategic plans successful delivery of projects, but little evidence of
resource acquisition, planning or management.
8. Formal ideas management process exists,
with ideas deferred or built into strategy
Specific Attributes
where appropriate
1. Project resources allocated on ad hoc basis, but
9. Executive Board-level reaction to, and may be some awareness of core skills necessary
management of, business performance to deliver projects
relating to project-initiated activities
2. Minimal reporting on resource utilization
10. High levels of competence in project and change
3. Project documentation does not include
management evident at Executive Board level
resourcing profiles
11. Leadership development programme includes
project management education Generic attributes
1. Training provision is uncoordinated, with little or
12. Structured management of knowledge, with
no knowledge sharing
lessons being learned and embedded
2. Key individuals lack experience
13. Business performance actively tracked and
managed, with timely interventions 3. No standard roles, and responsibilities are not
defined or are generic

Portfolio, Programme and Project Management Maturity Model (P3M3) 19


P3M3 Project Model

4. Some information available but is outdated, 8. Roles, responsibilities and competencies defined
unstructured and dispersed in some areas but not consistently across the
organization
5. Limited, if any, formal checking or review
9. Plans exist but are not underpinned by consistent
6. Plans, if any, are conceptual or merely sequences
development methodology, yet may still be
of events with rough timescales
effective locally
7. Planning, if any, likely to be an initial activity with
10. Planning seen as activity tracking rather than
little maintenance of ownership or tracking
proactive/forecasting
11. Estimation is more guesstimation and does
PjM3 - Resource Management Level 2
not use standard techniques
Description
Resources are being deployed across the organization
and individual projects have an approach to resource PjM3 - Resource Management Level 3
acquisition, planning or management. However, there Description
is little evidence of consistency of approach. The organization has a centrally defined and adopted
set of procedures and management processes for
Specific Attributes acquiring, planning and managing project resources.
1. Resources assigned locally to specific project
activities, possibly with some recognition of Specific Attributes
particular skills and competencies 1. Centrally defined and adopted set of procedures
in place for resource management
2. Resource utilization locally tracked and reported
on to some extent, but little evidence of 2. Work to be carried out by third parties or
resulting actions contractors defined and planned in accordance
with documented procedures and reviewed at
3. Little evidence of resource forecasting in terms of
key milestones or project stages
skills and competency requirements tailored to
project complexity or risk 3. Frameworks in place with external market for
provision of resources to meet shortages and
4. Resource plans do not adequately consider
expertise peaks
project handover and downstream support
requirements 4. Resource utilization tracking and productivity
monitoring occasionally undertaken, using
5. Some resource overstretch in key or pivotal
industry standard techniques
positions
5. Resource planning undertaken in broadest sense,
Generic Attributes not limited to human resources
1. Localized information structures, with some
6. Some collaboration between project teams
information sharing between teams
or recognition at organizational level of
2. Focus on documentation during start-up and opportunities for sharing critical or
definition, but not maintained over initiatives limited resources
life cycle
7. Potential issues arising from resource availability
3. Limited localized information controls, with no identified and escalated
formal release management arrangements
8. Evidence of induction planning and activities
4. Local reviews, with some corrective actions when joining project teams
undertaken within the group
Generic Attributes
5. Generic training may be provided in key
1. Information has a refresh cycle or is regularly
concepts, and there may be individuals
accessed
undertaking qualification training
2. Organization-wide information standards on
6. Local sharing of knowledge may exist but
confidentiality, availability and integrity
mostly ad hoc
3. Formal information release management
7. Key individuals may have practical delivery
procedures
experience and track record
4. Independent reviews take place

20 Portfolio, Programme and Project Management Maturity Model (P3M3)


P3M3 Project Model

5. Scrutiny largely for compliance reasons, 8. Induction and extraction plans for individuals
identifying failures rather than opportunities joining and leaving project teams
for improvement
Generic Attributes
6. Plans developed to a central and consistent
1. Information is current and extensively referenced
standard that is output- or goal-based
for better decision-making
7. Plan development takes into account a range
2. Trend analysis and measurement undertaken
of relevant factors
on performance information to identify
8. Evidence of effective estimating techniques improvement opportunities
9. Dependencies are identified, tracked and 3. Knowledge management is a central function
managed effectively and is used to help improve performance
and planning
10. Training is focused on the organizations
approaches and raising competence of 4. Reviews focus on opportunities to improve as
individuals in specific roles well as compliance
11. Forums exist for sharing organizational 5. Plans kept up to date, with the application
experience to improve individual and of sophisticated planning techniques and
organizational performance recognition of interdependencies
12. Centrally managed role definitions and sets 6. Extensive training is provided, focusing on
of competencies defined and used to support personal development and performance
appointments improvement
7. Evidence of interventions to avoid conflicts and
PjM3 - Resource Management Level 4 take advantage of opportunities
Description
8. Mentoring and individual development is used
Resource management for projects is considered at a
to improve organizational performance
strategic level within the organization.
9. Succession plans exist for key roles
There is evidence of resource capacity management,
through capacity planning, in order to meet project
delivery needs. PjM3 - Resource Management Level 5
Description
Specific Attributes Resources are deployed optimally. There is clear
1. Resource utilization and efficiency is tracked evidence of load balancing and the effective use of
and measured both internal and external resources across projects.
2. Training and mentoring focused on performance There is evidence of continual improvement.
improvement rather than qualifications
Specific Attributes
3. Minimal dependence on key individuals,
1. Active strategies for development of internal
with resource risks managed using defined
capacity and capability
response plans
2. The organization will have an explicit policy for
4. Active leveraging of supply chain to optimize
improving its technical capability and will have
resource utilization between internal and
improvement plans that recognize business
external resource pools
demands and constraints
5. Central resource management tools in place,
3. Flexible resource availability and movement
maintained and supporting projects
between projects, programmes and operations
6. Resource availability and utilization quantitatively
4. Resource allocation based on resource availability
measured
and competency requirements across projects
7. Senior management attempting to understand
5. Project managers have an understanding of
business demand for project resources and,
business processes and objectives and are able
through forecasts, attempting to influence
to ensure that project resources are sufficiently
demand and prioritize projects
focused on business needs

Portfolio, Programme and Project Management Maturity Model (P3M3) 21


P3M3 Project Model

6. Senior management ownership of capability


building and associated risks
7. Active supply chain collaboration to deploy and
utilize optimal set of skills in projects

Generic Attributes
1. Information is valued, with continual
maintenance and reference
2. Evidence of extensive intelligence-gathering
processes, with information disseminated
through a variety of channels
3. Review and improvement is continual and
proactive, with lessons being shared openly
4. Planning inherent in decision-making process,
with adjustments and implications managed
and deployed
5. Active management of interdependencies
between initiative plans and other business plans
6. Estimations are accurate and used effectively to
ensure delivery
7. High levels of competence embedded in all roles
and seen as part of career paths
8. Knowledge transfer is an inherent behaviour
within the organization
9. Skills embedded into organizational leadership
and management development programmes

22 Portfolio, Programme and Project Management Maturity Model (P3M3)


Feedback concerning the model should be sent to
P3M3model@ogc.gsi.gov.uk
Feedback concerning the self-assessment should be sent to
P3M3assessment@ogc.gsi.gov.uk

OGC 1 Horse Guards Road, The Service Desk will also


London SW1A 2HQ channel queries to the
appropriate second-line
About OGC support. We look forward
The Office of Government to hearing from you.
Commerce is an independent
You can contact the Service
office of HM Treasury.
Desk 8am 6pm Monday
The OGC logo is a registered to Friday:
trademark of the Office of
T: 0845 000 4999
Government Commerce
E: ServiceDesk@ogc.gsi.gov.uk
in the United Kingdom and
www.ogc.gov.uk
other countries.
Press enquiries
OGC Service Desk
T: 020 7271 1318
OGC customers can contact
F: 020 7271 1345
the central OGC Service Desk
about all aspects of
OGC business.
CP0258/01/10

This is a Crown copyright value added product, reuse of which


requires a licence which is issued by OGC. Please contact the
OGC Service Desk for further details. Crown copyright 2010

Vous aimerez peut-être aussi