This Testing and Commissioning (T & C) Procedure aims to lay down the minimum
testing and commissioning requirements to be carried out on fire service installation in
Government Buildings of the Hong Kong Special Administrative Region (HKSAR). Such
requirements are applicable to both new installations upon completion and existing ones
after major alteration.
The present edition was developed based on its 2001 edition by the Fire Service,
LPG, Catering and Plumbing Specialist Support Group that was established under the
Building Services Branch Technical Information and Research & Development Committee.
With the benefit of information technology, electronic version of this new edition is to be
viewed on and free for download from the Architectural Services Department (ArchSD)
Internet homepage. As part of the Governments efforts to limit paper consumption, hard
copies of this T & C Procedure will not be put up for sale.
This T & C Procedure is solely compiled for use on fire service installation carried
out for or on behalf of the ArchSD in Government buildings of the HKSAR.
1. Introduction 1
6. Calibrated Equipment 11
Part 2 : Declaration
3.3 Manual and Automatic Fire Alarm System and Fire Alarm
Control System
Annex B 1-5
Testing and commissioning progress chart fire service installation
Annex C 1-2
Abbreviations
Table of Contents FS_TCP
Page 3 of 3 2007 Edition
B.S.B. Testing and Commissioning Procedure Fire Service Installation
1. Introduction
1.1 This procedure is intended to lay down the minimum testing and
commissioning requirements to be carried out by the Contractor on a new
Fire Service Installation upon completion or on an existing Fire Service
installation after alteration. Additional testing and commissioning (T & C)
requirements and procedures may be proposed by the Contractor as
appropriate and agreed by the Project Building Services Engineer (PBSE),
e.g. for special equipment supplied and/or installed by the Contractor.
1.2 This procedure is also written to facilitate the PBSE and Project Building
Services Inspector (PBSI) in carrying out the following aspects of work
with respect to T & C.
(i) To vet and approve the T & C procedures proposed and submitted
by the Contractor.
(iii) To receive the T & C reports, record forms, certificates and other
supporting data.
1.3 This procedure shall be read in conjunction with the General Specification
for Fire Service Installation in Government Buildings of The Hong Kong
Special Administrative Region issued by the Building Services Branch,
Architectural Services Department (Fire Service General Specification or
General Specification), particularly on Part D of Fire Services General
Specification. The PBSE and PBSI in this procedure are Architect's
representatives as advised by the Architect from time to time.
(iii) to verify the presence and proper functioning of safety, protection and
alarm devices;
and
(iv) to capture and record performance data of the whole installation as the
baseline for future operation and maintenance.
All the test results shall be recorded by the Contractor in the appropriate test
record forms, the reference of which is shown against each individual test. A
complete set of these forms is included in Part 3 and Part 4 of Annex A.
FS_TCP
Page 1 of 11 2007 Edition
3. Scope of the T & C Works
3.1.1 The Contractor shall submit the T&C procedures together with the
proposed Testing and Commissioning programme, and Testing and
Commissioning Progress Chart shown in Annex B to the PBSE/PBSI for
approval. This procedure only indicates the minimum T&C requirements.
The Contractor shall add and include additional installations, T&C
procedures, and details not included in this procedure in his submitted
T&C procedures. The submission shall be made within the time limit
stated in the Particular Specification or the Fire Service General
Specification and shall be no later than three months before the
commencement of relevant T&C.
3.1.2 Where tests are required to be witnessed by the PBSE/PBSI, the Contractor
shall give due advance notice (usually not less than four calendar days) and
provide details of date, time and type of tests to be performed. PBSE/PBSI
in this procedure shall deem to include Project E&M Engineer/Project
E&M Inspector (PEME/PEMI) or any other person(s) as required by the
Architect.
3.1.3 Upon completion of such inspections and tests in T & C procedures, the
Contractor shall complete and sign a testing and commissioning certificate
by an authorised person approved by the PBSE as in Annex A, to the effect
that the agreed T & C procedures have been duly carried out and
satisfactorily completed. The requirements are detailed in the Fire Service
General Specification.
3.1.4 Before carrying out any test, the Contractor shall ensure installations
comply with the statutory requirements and regulations, particularly on the
safety and protection requirements.
3.1.5 The Contractor shall carry out his/her own adjustment, testing and
commissioning to ensure installations comply with the requirements prior
to inviting the PBSE/PBSI to witness the testing and commissioning.
FS_TCP
Page 2 of 11 2007 Edition
3.2 Testing and Inspection
3.2.1 The requirements are in general as specified in the Fire Service General
Specification and this procedure. If there is any discrepancy between this
procedure and the Fire Service General Specification, the Fire Service
General Specification shall take precedence.
3.2.2 The Contractor shall carry out the tests and inspections as shown in Part 3
and record the test results on Part 4 of Annex A and as agreed between the
PBSE/PBSI and the Contractor. Where required in the Particular
Specification or Fire Service General Specification, the Contractor shall
also carry out inspection, witness the testing and/or arrange his own testing
on related fire service installations and related fire service provisions
installed by others in order to check and certify their compliance with the
fire service requirements. All interfacing of the fire service installation
with related fire service installation and related fire service provisions
such as firemans lift, etc. installed by others and the functioning of the
interfacing equipment when a fire signal is initiated shall be checked,
tested and certified by the Contractor.
3.3.3 The Contractor shall provide all the necessary staff, labour, consumable
and non-consumable materials for carrying out testing and commissioning
works at their expenses. Electricity supply, water, diesel, chemicals, LP
gas, town gas, fire extinguishing gases/media, lubricants, and other fuel oil
for engine-driven pumps and generators for carrying out testing and
commissioning works shall be arranged and provided by the Contractor at
no cost to the Employer, as detailed in the General Specification.
FS_TCP
Page 3 of 11 2007 Edition
3.3 Documentation and Deliverables
The Contractor shall submit his proposed T & C procedures together with the
proposed Testing and Commissioning programme, and Testing and
Commissioning Progress Chart shown in Annex B to PBSE for approval.
The Contractor shall record all commissioning information and testing results at
the witness of the PBSE/PBSI or his representatives. All inspection and T & C
results shall be recorded in the data record forms shown in Part 3 and 4 of Annex
A. Data recorded in other formats may also be accepted subject to the approval
by the PBSE given before the test, or the agreement between PBSE/PBSI and the
contractor during the test. Immediately after each test, the Contractor's
Commissioning Engineer in Charge (CEIC) shall sign the test/data record sheet,
and obtain the endorsement of the PBSE or PBSI who has witnessed the test on
site, irrespective of whether the test is successful or not, and submit a copy of the
test/data record sheet to the PBSE.
For testing that is required during the construction period, the Contractor shall
also submit a formal testing and commissioning report endorsed by the CEIC
within fourteen (14) calendar days after the completion of the whole test for any
part of the installation.
Upon completion of all the required T&C procedures, the Contractor shall
complete and sign a testing and commissioning certificate by an authorised
person as shown in Part 1 and 2 of Annex A to the effect that the agreed T & C
works have been duly carried out and satisfactory completed.
The Contractor shall submit full testing and commissioning report to the
Architect within fourteen (14) calendar days after completion of testing and
commissioning of the installation. All testing and commissioning report shall be
properly checked and certified by Contractors CEIC before submission. For
testing that is required during construction period, the Contractor shall submit
testing and commissioning report endorsed by CEIC within 14 calendar days
after the completion of the whole test for any part of the installation.
The full testing and commissioning report shall cover all measured data, data
sheets, and a comprehensive summary describing the operation of the system at
the time of the functional and performance tests. Deviations in performance
from the Particular Specification or Fire Service General Specification or the
design intent shall be recorded, with a description and analysis included.
FS_TCP
Page 4 of 11 2007 Edition
4. T & C Procedures
All pipework shall be thoroughly cleaned and flushed before test. The
Contractor shall ascertain that there is adequate drainage nearby to
discharge by large hose in order to ensure flooding of low level areas
will not occur. Where necessary, the Contractor shall provide chemical
cleaning to the pipes. After flushing out the pipework, a flow test shall
be performed on the hydrant/hose reel system in accordance with the
requirements of the Code of Practice for Minimum Fire Service
Installations and Equipment.
A water supply test with the drain and test valves fully opened shall be
made on the sprinkler system in accordance with the requirements of the
LPC Rules for Sprinkler Installations. An alarm test for at least 30
seconds on the water gong shall also be carried out by opening the test
valve to ensure that it shall sound continuously after water flow in the
system is detected. All controls and air supply system for the pre-action
system, recycling pre-action system and dry pipe system shall be tested.
For street hydrant system without pumps, the Contractor shall test the
incoming water supply pressure at a nearby supply point and at such
time as agreed with the PBSE/PBSI before the commencement of the
installation works to establish the adequacy of the water supply
pressure. If the supply pressure is inadequate, the Contractor shall
propose remedial measures for the approval of the PBSE. The
Contractor shall find and select the most appropriate nearby supply point
for the test.
FS_TCP
Page 5 of 11 2007 Edition
- Date of test
- Apparatus or section under test
- Makers number (if any)
- Nature, duration and conditions of test
- Result of test
- Name of Contractors representative (in block letter) in charge
of test
- Name of Employers representative at witness the test
Soak test of least 1 week shall be carried out for all automatic detectors
at the time after the completion of all works including fitting-out works
and the whole area is cleaned up, normally at the time of occupation by
users or immediately after. Such test shall deemed to be successful only
if during such period no false fire alarm is occurred or necessary action
has been taken to rectify the causes.
FS_TCP
Page 6 of 11 2007 Edition
The Contractor shall arrange power failure load tests to prove proper
functioning of the fire service installation and the associated power
supply changeover control during power failure and fire mode.
For fire alarm direct link to the FSD or FSD's approved centre, the
Contractor shall, unless approved by the PBSE, initiate the fire alarm
direct link applications to the appropriate agencies within 3 months after
commencement of the Contract so that the fire alarm direct link will be
connected and tested before the fire service inspections. The Contractor
shall submit a copy of the application document to the PBSE/PBSI for
record.
The Contractor shall co-ordinate and shall closely monitor the status of
completion of fire alarm direct link and the telephone line before the fire
service inspections by the FSD. The Contractor shall apply for and
provide at the Contractor's own cost the required telephone point for
connection of the fire alarm direct link as required. If the Contractor
cannot complete the fire alarm direct link by the date of fire service
inspection by the FSD, the Contractor shall be responsible to provide all
necessary manpower and telephone equipment, at the Contractor's own
expenses, solely for the purpose for a 24-hour/day full attendant service
to substitute the fire alarm direct link, to the approval of the FSD and the
PBSE, up to the date of the completion of the fire alarm direct link.
The Contractor shall allow carrying out on-site full discharge test after
completion of the installation when required by the FSD to confirm the
design conditions can be met and to the satisfaction of the FSD and
approval of the PBSE. The Contractor shall follow relevant FSD
Requirements and Circular Letters on the requirements of discharge
tests. The Contractor shall refill the gas cylinders with the design agents
after the tests and reset all the equipment after the discharge test.
FS_TCP
Page 7 of 11 2007 Edition
4.4 EMERGENCY LIGHTING AND EXIT SIGN TESTS
For emergency lighting system and exit signs provided with central
monitoring, testing and logging system, the system shall be tested in
accordance with the manufacturer's specification and to meet the
requirements in the FSDCoP, EE_TC and this procedure.
FS_TCP
Page 8 of 11 2007 Edition
4.5 EMERGENCY GENERATORS TESTS
The Contractor shall carry out full visual inspection, safety check,
functional and performance test for the emergency generator
installation. The tests shall include measurement on noise confirming
compliance with the statutory requirements and/or as required by the
Environmental Protection Department, the HKSAR. Emergency
generators for fire service installation shall be located in separate room
unless otherwise agreed by the FSD and approved by the PBSE.
When the emergency generator has gained its capacity and is ready to
accept the fire service load, each fire service installation shall be
switched on until all installations are in operating conditions. If an
automatic starting programme or device is provided for controlling the
starting sequence of the equipment using emergency power supply, the
programme or device shall be allowed to operate and test. A
'simultaneous running' test shall then take place and shall last for a
continuous period of 1 hour. During this period, the performance of each
fire service installation shall be monitored and recorded.
FS_TCP
Page 9 of 11 2007 Edition
4.6 HOT SMOKE TEST
Hot smoke test shall be carried out where specified or required by the
FSD. The Contractor shall arrange, co-ordinate and carry out the hot
smoke test to meet the purpose for simulating the prototype of a real fire
under specific dynamic buoyant flow of smoke and heat intensity in a
controlled manner and for assessing the performance of smoke
management system, smoke control system and smoke extraction
system with the given building geometry. Hot smoke test shall follow
FSD Circular Letter No. 2/2002, Australian Standard AS 4391-1999
"Smoke Management System Hot Smoke Test" or approved
international standards and practices and to the satisfaction of the FSD
and the PBSE. The Contractor shall obtain comments from the FSD and
all relevant parties on the detailed requirements and arrangement for the
hot smoke test at early stage of the Contract.
FS_TCP
Page 10 of 11 2007 Edition
measures.
Details of the hot smoke test requirement shall refer to the Fire Service
General Specification and FSDCoP.
5.1 After the proper testing and commissioning of the Fire Service
Installation, the Contractor shall notify the appropriate Authority,
through the PBSE, on the completion of the installation and its readiness
for inspection and testing. The Contractor shall arrange all necessary
inspections and tests as required by the Authority.
5.2 Before notifying the appropriate Authority for inspection, the Contractor
shall arrange a mock up inspection and test with the PBSE/PBSI to
demonstrate the readiness of the fire service installation for statutory
inspection. The mock up test shall be a full inspection test same as the
statutory inspection to be conducted for appropriate Authority. The
Contractor shall prepare and make ready all documents required for
statutory inspection that will be examined during the mock up inspection
and statutory inspection.
6. Calibrated Equipment
FS_TCP
Page 11 of 11 2007 Edition
Annex A
Testing and Commissioning Certificate
on Fire Service Installation
1.4 *Contractor/Sub-Contractor :
1.6 PBSE :
1.7 PBSI :
Part 2 : Declaration
3.1.2.1 Check:
a) Pipings are suitably connected to the fire pumps, fire *Yes/No/N.A. *Yes/No/N.A.
hydrants, hose reels and fire service inlets.
c) Size of the inter-connection header pipe(s) for fire service *Yes/No/N.A. *Yes/No/N.A.
inlets is correct.
b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.
e) Does the size of the water pump suction water pipe from *Yes/No/N.A. *Yes/No/N.A.
the tank match the size of the pump suction inlet?
h) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.1.3.2 Pipework
b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
w) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
y) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?
ab) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
ac) Are sprinkler heads provided at top of refuse chutes? *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
ae) Are equipotential earth bondings provided for all *Yes/No/N.A. *Yes/No/N.A.
sections of the pipeworks?
3.1.3.3 Hydrant
a) Do the layouts of the hydrant tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?
f) Are the hydrant outlets between 800 mm and 1200 mm *Yes/No/N.A. *Yes/No/N.A.
above finished floor level?
g) Is the outlet not obstructing any door opening, or any *Yes/No/N.A. *Yes/No/N.A.
existing route?
k) Are the hydrant outlet provided with bronze caps *Yes/No/N.A. *Yes/No/N.A.
complete with chains?
a) Do the layouts of the hose reels tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Is the internal bore of tubing not less than 19mm in *Yes/No/N.A. *Yes/No/N.A.
diameter?
d) Is the hose reel drum not less than 150mm in diameter? *Yes/No/N.A. *Yes/No/N.A.
e) Is nozzle fitted with simple two-way on/off valve and the *Yes/No/N.A. *Yes/No/N.A.
valve is not spring loaded?
f) Are the control valves of gate type or of simple two-way *Yes/No/N.A. *Yes/No/N.A.
ball type?
g) Are the gates valves are closed by clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.
h) Are the rising mains and associated pipework not less *Yes/No/N.A. *Yes/No/N.A.
than 40mm nominal bore?
i) Are the pipes feeding individual hose reel are not less *Yes/No/N.A. *Yes/No/N.A.
than 25mm nominal bore.
j) Are the doors of the hose reel cabinets or recesses *Yes/No/N.A. *Yes/No/N.A.
provided without any locks?
k) Are manual fire alarm call points sited at a prominent *Yes/No/N.A. *Yes/No/N.A.
position near to the hose reels?
l) Are the doors clearly bear FIRE HOSE REEL( *Yes/No/N.A. *Yes/No/N.A.
) with characters of at least 50 mm high?
o) Is the notice clearly marked with the standard wordings *Yes/No/N.A. *Yes/No/N.A.
in English and Chinese characters of at least 5mm high
in red letters on white background or vice versa?
r) Are the control valves sited adjacent to the nozzles? *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
t) Is the nozzle fitted with simple two-way on/off valve and *Yes/No/N.A. *Yes/No/N.A.
closed by clockwise rotation?
u) Are the control valves and nozzles 1350 mm or less *Yes/No/N.A. *Yes/No/N.A.
above finished floor level, and for a recessed type hose
reel not more than 500 mm from the surface of the wall?
v) Are control valves and nozzles sited in a discernible and *Yes/No/N.A. *Yes/No/N.A.
accessible position of not more than 500 mm from the
surface of the doors?
w) Are guide rings provided for fixed type hose reel? *Yes/No/N.A. *Yes/No/N.A.
z) Can the cradle be swung freely into the corridor or *Yes/No/N.A. *Yes/No/N.A.
passage when required?
aa) Are the tubing of the hose reels properly wound round *Yes/No/N.A. *Yes/No/N.A.
the drum without kinking?
ab) Are the outer face of the hose reels flush with the wall *Yes/No/N.A. *Yes/No/N.A.
when the reels are not in use?
ac) Are the jet nozzles unbroken and installed? *Yes/No/N.A. *Yes/No/N.A.
ad) Are the guide bracket unbroken and installed? *Yes/No/N.A. *Yes/No/N.A.
af) Are the manual fire alarm call points not more than *Yes/No/N.A. *Yes/No/N.A.
1200 mm above the finished floor level?
ag) Upon actuation of any manual fire alarm call point in the *Yes/No/N.A. *Yes/No/N.A.
building, shall the fixed fire pump come into operation
regardless of the zoning of the fire alarm call point?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
ii) Do such doors cause no obstruction to the hose being *Yes/No/N.A. *Yes/No/N.A.
run out in either directions.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Are air relief valves provided for rising mains? *Yes/No/N.A. *Yes/No/N.A.
e) Are the rising main supply the correct number of hydrant *Yes/No/N.A. *Yes/No/N.A.
outlets (2 outlets per floor for industrial/godown and 1
outlet per floor for other buildings)?
j) Is/Are the Header pipe(s) provided to connect the fire *Yes/No/N.A. *Yes/No/N.A.
service inlets to the rising mains?
l) Are the number and location of fire service inlets *Yes/No/N.A. *Yes/No/N.A.
conforming to latest approved building plan?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Location
Quantity (No(s).)
Pump
Manufacturer
Motor
Pump
Model No.
Motor
Pump
Serial
Motor
Pressure (kPa)
Starting method
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Is electricity used for driving the pump? If no, please *Yes/No/N.A. *Yes/No/N.A.
specify.
c) Is jockey pump provided for up fed system (water tank at *Yes/No/N.A. *Yes/No/N.A.
low level)?
d) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guards?
f) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power for the rated flow of the
system?
k) Are doors to pump rooms clearly labelled FIXED FIRE *Yes/No/N.A. *Yes/No/N.A.
PUMP ( ) *and/or INTERMEDIATE
BOOSTER PUMP ()?
m) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
n) Are pump rooms laid clear of any exit or normal *Yes/No/N.A. *Yes/No/N.A.
communication routes through the premises?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
t) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control installed near the pump, rather than by any
automatic means?
u) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
v) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
w) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
z) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?
aa) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
ab) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?
ac) Are pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?
ag) Are the pumps enclosures suitably locked to prevent *Yes/No/N.A. *Yes/No/N.A.
unauthorized tampering of the pumps?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
ah) Are the running and static pressure at any hydrant outlet *Yes/No/N.A. *Yes/No/N.A.
not exceeding 850Kpa?
a) Height between the topmost hydrant and the lowest F.S. ____________ _____________
inlet (m):
d) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
h) Are the motors driving the pumps rated to give 20% *Yes/No/N.A. *Yes/No/N.A.
more power in addition to the hydraulic power required
for the rated flow?
k) Are the Start/stop push buttons with pump running *Yes/No/N.A. *Yes/No/N.A.
indication light and buzzer provided adjacent to the fire
service inlet?
l) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panels in
the pump enclosures.
m) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
n) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?
o) Are the pump enclosures suitably locked and laid clear *Yes/No/N.A. *Yes/No/N.A.
of any exit or normal communication routes through the
premises?
p) Are the pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?
q) Is the intermediate booster pump utilized as the fixed fire *Yes/No/N.A. *Yes/No/N.A.
pump?
s) Do the running and static pressure at any hydrant outlet *Yes/No/N.A. *Yes/No/N.A.
not exceeding 850 Kpa?
ab) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Are the fire service inlet couplings between 600 mm and *Yes/No/N.A. *Yes/No/N.A.
1000 mm above finished floor level?
b) Are the fire service inlets suitably enclosed and *Yes/No/N.A. *Yes/No/N.A.
protected?
l
c) Are the fire service inlets readily accessible by Fire *Yes/No/N.A. *Yes/No/N.A.
Services personnel?
c) Are the fire service inlet enclosures clearly and *Yes/No/N.A. *Yes/No/N.A.
permanently labelled F.S. INLET () with
characters at least 50 mm high?
3.1.3.9 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.1.4.1 Pipeworks
f) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?
a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.1 Table 3)
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
e) Do the fixed fire pumps come into operation upon *Yes/No/N.A. *Yes/No/N.A.
actuation of any manual fire alarm call point, regardless
of the zoning of the fire alarm call point?
f) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the water pumps function properly?
g) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
n) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly? (Test records on Part
4.1 Table 4)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Can the hose reel tubing be drawn out freely and easily *Yes/No/N.A. *Yes/No/N.A.
in any direction without obstruction?
b) Are the hose reels capable to cover within 6 m of each *Yes/No/N.A. *Yes/No/N.A.
part of the occupied area? (Test Records on Part 4.1
Table 5)
c) Are the hose reels capable to project a water jet of 6 m or *Yes/No/N.A. *Yes/No/N.A.
greater and min. flow of 24 L/min? (Test Records on
Part 4.1 Table 5)
d) Is the water tightness of the stop valves, nozzles, and *Yes/No/N.A. *Yes/No/N.A.
tubing connections satisfactory when the water pump is
running?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.1.4.6 Hydrant
b) Do the flow capacity and pressure test satisfy Fire Services *Yes/No/N.A. *Yes/No/N.A.
Departments requirements as the following Table? (Test
records on Part 4.1 Tables 6 and 7)
Building Type Running Pressure (kPa) Static Pressure No. of hydrant Minimum
(kPa) outlet operating aggregate Flow
Rate (L/min)
Minimum Maximum
Note : Each hydrant outlet shall have a flow of 450 L/min at a running pressure of not less than 350 kPa.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the sprinkler tank tally with the vertical
plumbing diagram approved by W.S.D.?
d) Is water depth indicator provided for the sprinkler tank *Yes/No/N.A. *Yes/No/N.A.
which is used as a gravity tank?
e) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.
Note: (1) Positive head - water capacity between pump centre line and the lowest effective water
level of tank not exceeding one-third total capacity.
(2) Suction lift - vertical height between pump centre line and the lowest effective water
level of tank not exceeding 3.7 m.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Are the sizes of the water pump suction water pipes *Yes/No/N.A. *Yes/No/N.A.
correct as the following Table?
i) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
k) Are sizes of priming water pipes correct ? (LH - 25 mm, *Yes/No/N.A. *Yes/No/N.A.
OH and HH -50 mm)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
LH OH HH L.P.C. Rules/Remarks
Special area 9 m2 9 m2
Max. distance from open face of 1.5 m 1.5 m 1.5 m Clause 26.3.1.1
building
150/
Max. distance below combustible/ 300/ 300/ 300/ Clause 26.5.1.1,
incombustible ceiling/roof 450 mm 450 mm 450 mm Table 76
Max. distance from column 0.6 m 0.6 m 0.6 m Clause 26.5.2.1 & 26.5.2.2
Max. depth of ceiling void without 0.8 m 0.8 m 0.8 m Clause 26.6 & TB11
sprinkler
Max. extent of canopy from 2.3 m 2.3 m 2.3 m Clause 4.2.2.2 (b)
building without sprinkler
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(xii) Are construction of open ceiling spacing and location *Yes/No/N.A. *Yes/No/N.A.
of sprinkler heads in accordance with L.P.C. Rules as
the following Table and regarding :
Requirements of Open Ceiling (LH and OH Only) (See L.P.C. Rules Clause 26.8.2.2)
Min. dimensions of opening (shall not be smaller than vertical thickness of ceiling) 25 mm
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
h) Are the Nos. of sprinklers installed on the range and *Yes/No/N.A. *Yes/No/N.A.
distribution pipes in accordance with L.P.C. Rules as the
following Tables?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
j) Are sprinkler heads installed in upright position for Type *Yes/No/N.A. *Yes/No/N.A.
2 pre-action system?
k) Are sprinkler heads installed in upright position for dry *Yes/No/N.A. *Yes/No/N.A.
pipe system installations in cold room?
Light Hazard
20# 1
25 3
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.2.1.4 Pipeworks
b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
x) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?
aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?
ab) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.
(min. for LH - 40 mm, OH and HH - 50 mm)
ac) Are the water pipes laid to the following minimum *Yes/No/N.A. *Yes/No/N.A.
slope?
ad) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?
50 mm 20 mm
65 & 80 mm 32 mm
100 mm 50 mm
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
af) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
ah) Are installation control valves in accordance with BSB *Yes/No/N.A. *Yes/No/N.A.
Standard Drawings?
ai) Are main stop valves secured at OPEN position by *Yes/No/N.A. *Yes/No/N.A.
padlock or riveted strap?
aj) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?
ak) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?
al) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?
am) Is the total length of water pipe between alarm valve and *Yes/No/N.A. *Yes/No/N.A.
alarm gong 25 m or less?
an) Is the water pipe between alarm valve and alarm gong of *Yes/No/N.A. *Yes/No/N.A.
correct size ? (6 m length - 15 mm dia, over 6 m length -
20 mm dia)
ao) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Or
b) Does the pre-action system control panel incorporate the *Yes/No/N.A. *Yes/No/N.A.
necessary relays, timers, key types switches, alarm and
trouble lights essential to the operation of the system?
c) Does the control panel employ printed circuit boards for *Yes/No/N.A. *Yes/No/N.A.
the components and is completely factory wired and
ready for connection on site?
d) Are the pre-action control panel relays and circuitry *Yes/No/N.A. *Yes/No/N.A.
operating the pre-action alarm valve solenoid valves or
actuator mechanisms duplicated and wired such that no
single fault or failure shall render the installation
inoperable?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
5) Is the heat probe stainless steel and the top colour *Yes/No/N.A. *Yes/No/N.A.
coded for temperature set point and spacing?
6) Is the conduit box attached with the detector fire *Yes/No/N.A. *Yes/No/N.A.
and explosion proof and made of copper free
aluminium with threaded conduit connections
and adaptors provided for detector cables?
8) Are the detectors spaced for not more than 12 m *Yes/No/N.A. *Yes/No/N.A.
apart and 6 m from walls or as approved?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3) Are the binding tapes used with the cables flame *Yes/No/N.A. *Yes/No/N.A.
retardant?
2) Does the panel employ printed circuit boards for *Yes/No/N.A. *Yes/No/N.A.
the components and completely factory wired and
ready for connection on site?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
7) Does a reset button on the panel reset the timer *Yes/No/N.A. *Yes/No/N.A.
and alarm circuits after system operation?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Location
Quantity (No(s).)
Manufacturer Pump
Motor
Model Pump
Motor
Motor
Pressure (kPa)
Starting method
a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?
b) Is pump motor power rated at 10% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
i) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
m) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control not installed near the pump, rather than by
any automatic means?
n) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
o) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
p) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
s) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
t) Are such signal repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
w) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?
3.2.1.9 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
3.2.2.1 Pipeworks
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) With the installation valve primed in the ready position, *Yes/No/N.A. *Yes/No/N.A.
is it possible to fully pressurize the installation in one
hour, at any time ?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Heat Detector
(ii) When the temperature drops below the set point, *Yes/No/N.A. *Yes/No/N.A.
is the circuit re-established? At 426oC sustained
ambient temperature, does the tell-tale tab drop
away, indicating possible detector damage?
b) Mode of Operation
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(iii) The fire alarm bell to continue to sound until the *Yes/No/N.A *Yes/No/N.A
reset button is pushed. Should the temperature
build to the trip point of any detector during any
phase of the cycle, the system will continue to
flow or immediately start the flow of water to the
fire.
c) Control Panel
(iii) If the detector circuit and/or pressurized air are *Yes/No/N.A. *Yes/No/N.A.
unavailable for service, will the system turn into
an ordinary automatic dry pipe or wet pipe
system?
(iv) Do all alarms except the low air pressure alarm *Yes/No/N.A. *Yes/No/N.A.
operate constantly unless shut off and cycling
features are negated?
d) Air Supply
(iii) Does the compressed air system allow the *Yes/No/N.A. *Yes/No/N.A.
recharging of the recycling installation manually
after the sprinkler system has been operated and
the actuated sprinkler heads are replaced?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.2 Table 2)
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?
f) Are the temperatures of the water pump bearings normal *Yes/No/N.A. *Yes/No/N.A.
at running condition?
l) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly? (Test records on Part
4.2 Table 3)
m) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting ?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Do the flow switches for zone operating indication and *Yes/No/N.A. *Yes/No/N.A.
alarm function properly? (Test records on Part 4.2 Table
4)
b) Does the water alarm for each installation valve operate *Yes/No/N.A. *Yes/No/N.A.
when the test valve is opened?
c) Do the high and low water level alarms and indication *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Pressure and Flow Requirement for High Rise Sprinkler Installation (L.P.C. Rules Table TB13.T1)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3 Manual and Automatic Fire Alarm System and Fire Alarm Control System
3.3.1.3 Detectors
a) Heater detector:
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Fixed temperature *Yes/No
Rate-of rise temperature *Yes/No
Combination *Yes/No
Linear cable *Yes/No
Others : ____________
b) Smoke detector :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Ionization *Yes/No
Optical *Yes/No
Point *Yes/No
Aspirating *Yes/No
Others :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Multi-sensor detector :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type of sensors :
Heat sensing element : ____________
Smoke sensing element : ____________
Radiation sensing element : ____________
Other sensing element : ____________
d) Flame detector:
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Infra-red Yes/No
Ultra-violet Yes/No
Others:
e) Others :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type : ____________
Manufacturer/model no. : ..
.
...
F.S.D. approved type : Yes/No
Manufacturer/model no. : ..
.
...
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Manufacturer/model no. : ..
.
...
Type : BS 6387 Cat. AWX, AWY or AWZ [ ]
BS 6387 Cat. BWX, BWY or BWZ [ ]
BS 6387 Cat. CWX, CWY or CWZ [ ]
BS 6387 Cat. SWX, SWY or SWZ [ ]
MICS cable to BS 6207 [ ]
Others with F.S.D.s acceptance letter [ ]
(please specify .)
3.3.2 Zoning
3.3.2.1 Detectors
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(use separate sheets or computer printouts in full accordance with the above format if the space is not sufficient for
inserting all the zones)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.1 General
3.3.3.1.1 All fire detection and equipment are conformed to *Yes/No/N.A. *Yes/No/N.A.
F.S.D.s requirements.
3.3.3.1.2 All individual components of a fire alarm system are *Yes/No/N.A. *Yes/No/N.A.
mutually compatible.
3.3.3.1.6 Log book is provided adjacent to the alarm annunciation *Yes/No/N.A. *Yes/No/N.A.
panel.
3.3.3.2 Detectors
3.3.3.2.3 Detection zonings are properly labelled at the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel.
3.3.3.2.4 In the floor where sleeping risk exists (e.g. hotel, *Yes/No/N.A. *Yes/No/N.A.
hospital, etc.) :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.2.5 Detectors are provided to entire basement (except car *Yes/No/N.A. *Yes/No/N.A.
parking area, strong room & safe deposit vault).
3.3.3.2.7 The aggregate floor area covered by any single detection *Yes/No/N.A. *Yes/No/N.A.
loop circuit is 10,000 m2 calculated on those portions
of the premises installed with fire detectors.
3.3.3.2.8 The aggregate floor area covered by a single detection *Yes/No/N.A. *Yes/No/N.A.
zone is 2,000 m2 calculated on those portions of the
premises installed with fire detectors.
3.3.3.2.8 Remote indicator lamps are provided to show visually *Yes/No/N.A. *Yes/No/N.A.
the position of the fire detection signal for search
distance > 30 m.
3.3.3.2.8 Remote indicator lamps outside doors (near door exit) *Yes/No/N.A. *Yes/No/N.A.
are provided for detectors installed inside rooms if doors
are likely to be locked.
3.3.3.2.9 If the building consists of more than one storey, a single *Yes/No/N.A. *Yes/No/N.A.
zone design is adopted for the total floor area is 300
m2.
3.3.3.2.10 As the total floor area of the building is > 300 m2, all *Yes/No/N.A. *Yes/No/N.A.
zones are restricted to a single storey, except that :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.3.2 An alarm sounder is provided near the control and *Yes/No/N.A. *Yes/No/N.A.
indicating equipment.
3.3.3.3.3 One alarm sounder is provided at each hose reel point. *Yes/No/N.A. *Yes/No/N.A.
3.3.3.3.4 All alarm sounder cases are painted in red colour and *Yes/No/N.A. *Yes/No/N.A.
clearly marked FIRE ALARM in white color.
The height of all the English and Chinese wordings shall
not be less than 10 mm and 15 mm respectively.
3.3.3.3.5 A clearly labelled facility is available at or near the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel for starting or restarting the fire alarm
sounders. Operation of this facility is not dependent on
the state of any silencing device.
3.3.3.3.6 For sounders used for simple ring circuits, the *Yes/No/N.A. *Yes/No/N.A.
distribution wiring to each sounder circuit should be
protected against overload due to short circuit by a fuse
or similar device.
3.3.3.4.1 Zoning of manual call points is at least one zone per *Yes/No/N.A. *Yes/No/N.A.
floor or storey.
3.3.3.4.2 One manual call point is located at each of the following *Yes/No/N.A. *Yes/No/N.A.
equipment/location.
3.3.3.4.3 The travel distance for finding a manual call point is *Yes/No/N.A. *Yes/No/N.A.
30 m.
3.3.3.4.4 Manual call points are fixed at a height of about 1.2m *Yes/No/N.A. *Yes/No/N.A.
above the finished floor level.
3.3.3.5.1 VFA signal lamps are labelled FIRE ALARM . *Yes/No/N.A. *Yes/No/N.A.
The height of English and Chinese characters is not less
than 10 mm and 15 mm, respectively.
3.3.3.5.2 Visual alarm signal is in the form of red flashing light. *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.5.3 Each compartment is provided with at least one VFA *Yes/No/N.A. *Yes/No/N.A.
signal lamp.
3.3.3.5.4 Areas to be covered by VFA are in full compliance with *Yes/No/N.A. *Yes/No/N.A.
the approved building plans.
3.3.3.6.1 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
provided.
3.3.3.6.2 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
approved by F.S.D..
3.3.3.7.1 The alarm annunciation panel is located in an area on the *Yes/No/N.A. *Yes/No/N.A.
ground floor and in the immediate vicinity of the
building entrance easily to be accessed by the F.S.D. or
in the buildings Fire Control Centre/Room.
3.3.3.7.3 Where the control and indicating equipment is installed *Yes/No/N.A. *Yes/No/N.A.
in a severe weather environment, a weatherproof
protective enclosure with adequate ventilation is
provided to protect it from being damaged by high
humidity and water.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.7.4 All the alarm indications are displayed in both Chinese *Yes/No/N.A. *Yes/No/N.A.
and English so that the origin of the alarm position in
relation to this building can be easily, quickly and
unambiguously identified.
3.3.3.7.6 The operation of all manual controls and isolating *Yes/No/N.A. *Yes/No/N.A.
devices should be limited to authorized personnel. It
may be provided by restricting access to the equipment
by means of the following : -
3.3.3.8.4 The battery charger is capable of recharging the batteries *Yes/No/N.A. *Yes/No/N.A.
from fully discharged to fully charged within 24 hours.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.8.6 Every isolator, switch and protective device that can *Yes/No/N.A. *Yes/No/N.A.
supply for the fire alarm system is properly labelled as
appropriate :
3.3.3.8.7 Normal and standby battery supplies can each be capable *Yes/No/N.A. *Yes/No/N.A.
of supplying the maximum alarm load irrespective of the
condition of the other supply.
3.3.3.9.1 Cables used for the interconnections between VFA *Yes/No/N.A. *Yes/No/N.A.
signalling devices, sounders, control and indicating
equipment and power supplies are suitable for prolonged
operation during a fire or can resist fire for at least 30
minutes.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.9.3 Cables other than MICS cable complying with BS 6207 *Yes/No/N.A. *Yes/No/N.A.
or sheathed steel-wire-armoured cable complying with
BS 6346 or BS 5467 should be mechanically protected
if :
3.3.3.9.5 Conductors carrying fire alarm power or signals are *Yes/No/N.A. *Yes/No/N.A.
separated from conductors used for other systems by one
or more of the followings :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.3.9.6 For cable which should be segregated from cables of *Yes/No/N.A. *Yes/No/N.A.
other services but is not enclosed in ducting, trunking or
a channel reserved for fire alarm circuits, it is suitably
marked or labelled at intervals not exceeding 2 m to
indicate its function and the need for segregation.
3.3.3.9.8 Cabling and wiring installation is in accordance with the *Yes/No/N.A. *Yes/No/N.A.
latest edition of the EE Code.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4 Testing
3.3.4.1 Detectors
3.3.4.1.1 Upon actuation of any detector in the building, the *Yes/No/N.A. *Yes/No/N.A.
correct audio/ visual warning device for the fire
alarm and detection system is initiated.
3.3.4.2.1 Upon the actuation of the detector, alarm should be given *Yes/No/N.A. *Yes/No/N.A.
by alarm sounder installed at the building external near
the entrance.
3.3.4.2.2 Background noise (N) likely to persist for a period *Yes/No/N.A. *Yes/No/N.A.
longer than 30 seconds.
3.3.4.2.3 For domestic building, the minimum sound level of *Yes/No/N.A. *Yes/No/N.A.
alarm sounders is measured at 3 m from the inside of the
main entrance door with all doors shut off at all flats and
the result is,
dB(A) which is :
3.3.4.2.4 For building other than domestic building, the minimum *Yes/No/N.A. *Yes/No/N.A.
sound level of alarm sounders is measured at 3 m from
the inside of the main entrance door with all doors shut
off at all rooms/ premises and the result is,
dB(A) which is :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.2.5 The primary sounders should meet the required sound *Yes/No/N.A. *Yes/No/N.A.
level when the machine noise ceases and the secondary
sounders are out of service.
3.3.4.2.6 Where secondary sounders are installed, the primary *Yes/No/N.A. *Yes/No/N.A.
sounders in those parts of the premises without noisy
machines are distinctly audible at all times when
operated.
3.3.4.2.7 Failure of the power supply to the secondary sounders is *Yes/No/N.A. *Yes/No/N.A.
either :
3.3.4.3.2 Upon actuation of any manual call point in the *Yes/No/N.A. *Yes/No/N.A.
building, the fixed fire pump comes into operation
regardless of the zoning of the manual call point.
3.3.4.3.3 Upon actuation of any manual call point in the *Yes/No/N.A. *Yes/No/N.A.
building, the correct audio/ visual warning device
for the fire alarm and detection system is initiated.
3.3.4.3.4 The delay between operation of a call point and the *Yes/No/N.A. *Yes/No/N.A.
giving of the general alarm is 3 seconds.
3.3.4.4.1 The power supply of the VFA system is from : *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.4.2 All VFA flashing light is visible to normal eyesight in *Yes/No/N.A. *Yes/No/N.A.
the required protected areas when the fire alarm system
is actuated.
3.3.4.4.3 VFA signal is clearly distinguishable from any other *Yes/No/N.A. *Yes/No/N.A.
non-fire service visual signals used in the premises.
3.3.4.5.5 During any delay period, a manual operation at the contr *Yes/No/N.A. *Yes/No/N.A.
ol panel or the operation of a manual call point causes th
e immediate sounding of the fire alarm and transmission
of the alarm.
3.3.4.5.6 The sounding of the fire alarm and transmission of the al *Yes/No/N.A. *Yes/No/N.A.
arm is not delayed or prevented by the operation of a ma
nual call point or the actuation of a sprinkler flow switch
at any time.
3.3.4.5.7 The manual override switch is only capable of de-activati *Yes/No/N.A. *Yes/No/N.A.
ng the system from the time related system but cannot re-
activate the system again.
3.3.4.5.8 The system is not capable of permitting the action of the *Yes/No/N.A. *Yes/No/N.A.
manual override switch to be temporarily or permanently
cancelled by any automatic function
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.6.1 Audio, visual alarms for the fire detection and alarm *Yes/No/N.A. *Yes/No/N.A.
system, signals for system/ detector/ manual call point/
sounder fault and signals to all the ancillary equipment
are given correctly at the control and indicating
equipment.
3.3.4.6.3 The following panel functions and switches are working *Yes/No/N.A. *Yes/No/N.A.
properly :
3.3.4.6.4 Two simultaneous faults should not remove fire *Yes/No/N.A. *Yes/No/N.A.
alarm protection from an aggregate area greater
than 10,000 m2 calculated on those portions of the
premises installed with fire detectors.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.6.12 The audible indications of the control and indicating *Yes/No/N.A. *Yes/No/N.A.
equipment are easily heard in its vicinity.
3.3.4.7.1 Both the normal supply and the standby supply is *Yes/No/N.A. *Yes/No/N.A.
capable of continually supplying the largest load
under normal, fire and fault conditions.
3.3.4.7.2 A green lamp when lit indicates normal condition of *Yes/No/N.A. *Yes/No/N.A.
power supply.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.7.4 For systems not supervised, the battery supply is capable *Yes/No/N.A. *Yes/No/N.A.
of automatically maintaining the system in normal
operation for a period of not less than 24 hours after the
detection of a fault in the normal supply and the
initiation of remedial action.
3.3.4.7.5 For unoccupied building with systems not supervised for *Yes/No/N.A. *Yes/No/N.A.
periods > 24 hours, facilities are provided to give
protection for a period of at least 24 hours after
reoccupation, with sufficient capacity at the end of that
time to sound an evacuation alarm in all zones for at
least 30 minutes.
3.3.4.7.6 For systems backed up by standby generators, the battery *Yes/No/N.A. *Yes/No/N.A.
supply is capable of maintaining operation for a period
of not less than 6 hours, after which sufficient capacity
should remain to provide an evacuation alarm in all
zones for at least 30 minutes.
3.3.4.8.1 Insulation test of all installed cables and wiring is made *Yes/No/N.A. *Yes/No/N.A.
at 500 V DC and all insulation resistance are 0.5 M
.
3.3.2.8.3 Earth continuity and earth-loop impedance is tested and *Yes/No/N.A. *Yes/No/N.A.
the results are in compliance with the EE Code.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.9 Documentation
3.3.4.9.1 The following equipment list and catalogues are *Yes/No/N.A. *Yes/No/N.A.
provided.
3.3.4.9.6 Letter certifying the completion of the DTL to the *Yes/No/N.A. *Yes/No/N.A.
FSCC/Chubb Centre is provided.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.3.4.9.10 As-fitted fire service installation drawings including the *Yes/No/N.A. *Yes/No/N.A.
followings are provided :
(Note: Detailed T&C procedure for fire alarm control system and fire alarm control panels (G.S. Section
B8) shall be submitted by the Contractor and approved by the Architect prior to testing and
commissioning)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Location/Room :
Type of Gas : *CO2 / FM200 / NAFS III and other approved agents ___________
Type of System :
Modular ( ) Cylinder ( )
Pre-engineered ( ) Engineered ( )
3.4.1.1 General
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
e) Does the above mentioned indication means account for *Yes/No/N.A. *Yes/No/N.A.
variation of cylinder pressure with temperature?
h) Are nozzles provided with markings showing make, type *Yes/No/N.A. *Yes/No/N.A.
and orifice size?
3.4.1.3 Pipings
b) Are all sections of the piping provided with equipotential *Yes/No/N.A. *Yes/No/N.A.
earth bonding?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
ASTM A106
JIS 3454
or as approved or as approved
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.4.1.5 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
e) Are bar code labels provided to the gas cylinder? *Yes/No/N.A. *Yes/No/N.A.
3.4.2.1 General
a) Is the computer programme for the design of the system *Yes/No/N.A. *Yes/No/N.A.
approved by FSD?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Does agent fully discharge within the time limit *Yes/No/N.A. *Yes/No/N.A.
specified by FSD?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.5.1.1 Pipework
c) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
d) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
l) Are adequate clearances provided around the hydrant for *Yes/No/N.A. *Yes/No/N.A.
its free use?
m) Are hydrants sited 6 metres or greater from the building? *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Fire Pump
Duty Standby
Location
Quantity (No(s).)
Manufacturer Pump
Motor
Motor
Motor
Pressure (kPa)
Starting method
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are pump motors rated at 20% higher than the required *Yes/No/N.A. *Yes/No/N.A.
hydraulic power?
e) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.?
f) Are the effective water capacity of the water tanks *Yes/No/N.A. *Yes/No/N.A.
correct?
g) Are the ball valves of the water tanks readily accessible? *Yes/No/N.A. *Yes/No/N.A.
h) Do the sizes of the water pump suction water pipe from *Yes/No/N.A. *Yes/No/N.A.
the tank match the size of the pump suction inlet?
k) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
r) Are doors to pump rooms clearly labelled "FIRE PUMP" *Yes/No/N.A. *Yes/No/N.A.
()?
t) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
u) Are pump rooms laid clear of any exit or normal *Yes/No/N.A. *Yes/No/N.A.
communication routes through the premises?
3.5.1.3 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
3.5.2.1 Pipeworks
c) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.5 Table 2)
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
e) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the water pumps function properly?
f) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
n) Does the actuation of a bursting fire alarm start the water *Yes/No/N.A. *Yes/No/N.A.
pumps?
b) Do the flow capacity and pressure tests satisfy FSD's *Yes/No/N.A. *Yes/No/N.A.
requirements as the following Table? (Test Records on
Part 4.5 Table 3)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Does the water tank have capacity for operation of the *Yes/No/N.A. *Yes/No/N.A.
drencher system for 30 minutes minimum?
d) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the drencher tank tally with the vertical
plumbing diagram approved by W.S.D.?
f) Are the ball valves of the water tank readily *Yes/No/N.A. *Yes/No/N.A.
accessible?
j) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Does each deluge valve control have less than 72 *Yes/No/N.A. *Yes/No/N.A.
drenches?
3.6.1.4 Pipeworks
b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?
d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?
g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?
h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?
k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?
l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?
m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?
n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?
o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?
q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.
x) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?
aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?
ab) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.
ac) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?
ae) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.
ag) Are main stop valves secured at OPEN position by *Yes/No/N.A. *Yes/No/N.A.
padlock or riveted strap?
ah) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
ai) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?
aj) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?
ak) Is the total length of water pipe between alarm valve and *Yes/No/N.A. *Yes/No/N.A.
alarm gong 25 m or less?
al) Is the water pipe between alarm valve and alarm gong of *Yes/No/N.A. *Yes/No/N.A.
correct size?
am) Is a deluge valve installed closed to the inlet for the *Yes/No/N.A. *Yes/No/N.A.
drencher system?
an) Are manually operating devices complete with operating *Yes/No/N.A. *Yes/No/N.A.
instruction displayed nearby and provided on refuge
floor?
ap) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?
a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?
b) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
i) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?
m) Can the pump just be started by switching off at the *Yes/No/N.A. *Yes/No/N.A
pump control not installed near the pump, rather than by
any automatic means?
n) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?
o) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.
p) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?
s) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?
t) Are such signal repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
w) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?
3.6.1.6 Miscellaneous
a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?
3.6.2.1 Pipeworks
d) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current?
c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?
e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
k) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly?
l) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting ?
a) Do the installation pressure and flow rate comply with *Yes/No/N.A. *Yes/No/N.A.
the FSD requirements?
b) Is the water flow from each nozzle the same and with a *Yes/No/N.A. *Yes/No/N.A.
similarly uniform flow pattern?
c) Is the water flow rate maintained at not less than 10 *Yes/No/N.A. *Yes/No/N.A.
L/min per m2 of external wall opening and allowing for
wastage and uneven flow (15% additional capacity)?
d) Is the hydraulic pressure at either end along any water *Yes/No/N.A. *Yes/No/N.A.
pipes identical?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.7.1.1 General
a) Does the layout of flashing light points and loudspeakers *Yes/No/N.A. *Yes/No/N.A.
tally with the latest approved building plans?
b) Are the flashing lights and loudspeakers provided for all *Yes/No/N.A. *Yes/No/N.A.
areas that required the system?
e) Are the low level directional signs of self luminous types *Yes/No/N.A. *Yes/No/N.A.
and conform to BS5499 Part 2, or of photoluminous type
to DIN 67510 Part 4 or equivalent?
f) Are the colour of the lens/lamps of the flashing lights *Yes/No/N.A. *Yes/No/N.A.
meet FSD requirements?
g) Does the visual system comply with the Code of Practice *Yes/No/N.A. *Yes/No/N.A.
for Minimum Fire Service Installations and Equipment
and Inspection, Testing and Maintenance of Installations
and Equipment (FSDCOP), BS 5499 and BS 4533?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
i) Are the lamp elements positioned to produce the best *Yes/No/N.A. *Yes/No/N.A.
illumination effect for the sign?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
j) Is a flashing light control gear integrated with each sign? *Yes/No/N.A. *Yes/No/N.A.
a) Desktop Microphone
b) Amplifier/Preamplifier
(iv) Are the amplifiers provided with at least 10% *Yes/No/N.A. *Yes/No/N.A.
spare capacity/power to drive all the speakers
within the broadcasting zone ?
(vi) Does the amplifier have an audio response level *Yes/No/N.A. *Yes/No/N.A.
within +2 dB from 50 Hz to 14 kHz at full output,
and the total harmonic distortion not exceed 1%
at full load?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(ix) Does amplifier have a low hum level and low *Yes/No/N.A. *Yes/No/N.A.
over-shoot or ringing when a square wave
generator is connected to the input level within
the working range and variable tone control
providing attenuation of the high frequencies, i.e.
0 20 dB at 8 kHz?
(xii) Are the signal incoming leads terminate at the *Yes/No/N.A. *Yes/No/N.A.
rear of the amplifier through suitable screened
type plug mountings?
(xiv) Are input sockets and output terminals well *Yes/No/N.A. *Yes/No/N.A.
separated and in separate cut-outs in order to
prevent coupling between the amplifier input and
output?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(xvii) Is the power amplifier completed with mixer, for *Yes/No/N.A. *Yes/No/N.A.
single broadcasting zone?
(xix) Does each power amplifier have built in with *Yes/No/N.A. *Yes/No/N.A.
On/Off switch, headphone outlet, volume control
for each channel and matching transformers with
tapping to enable loudspeakers to be driven at
100V, 70V or 50V up to 8?
(xxi) Is the power output adequate for the connected *Yes/No/N.A. *Yes/No/N.A.
loudspeakers in the broadcasting zone?
(xxv) Is the power output adequate for the number of *Yes/No/N.A. *Yes/No/N.A.
connected loudspeakers within the zone?
c) Loudspeaker
(ii) Are they constructed of sheet steel or high impact *Yes/No/N.A. *Yes/No/N.A.
ABS plastic in white colour or as specified
matching the false ceiling or wall finishes?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(v) Is the attenuator integral with the speaker unit *Yes/No/N.A. *Yes/No/N.A.
and comprise carbon type volume controls with
adjustment?
d) Cassette Deck
(i) Does cassette deck have two individual cassette *Yes/No/N.A. *Yes/No/N.A.
players with standard interlocking set of play,
stop, pause, fast forward and fast reverse buttons
and auto-reverse playback feature?
(ii) Does it have a playing tape speed of 4.75 cm/s *Yes/No/N.A. *Yes/No/N.A.
and an nominal output signal of 1 V, and a signal
to noise ratio better than 40 dB?
(iii) Has the recorded message been submitted to the *Yes/No/N.A. *Yes/No/N.A.
Architect for approval?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Are all cables running continuously from the originating *Yes/No/N.A. *Yes/No/N.A.
point to termination, with no joint or connector?
g) Are components include the following items and any *Yes/No/N.A. *Yes/No/N.A.
other items necessary for the proper control and
operation of the system to the satisfaction of the Fire
Services Department?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
h) Does the microphone control panel contain dual pre- *Yes/No/N.A. *Yes/No/N.A.
amplifiers continuously supervised?
i) Can the microphone control panel transfer to the standby *Yes/No/N.A. *Yes/No/N.A.
pre-amplifier upon failure of the duty unit?
l) Does the speaker zone selector switchbank control the *Yes/No/N.A. *Yes/No/N.A.
audio dispersion throughout the protected premises?
m) Does each switch permit the transfer of its zone of *Yes/No/N.A. *Yes/No/N.A.
speakers into either all call, page and fire operation
modes?
q) Will the system cause any interference with all electrical *Yes/No/N.A. *Yes/No/N.A.
or electronic system, the telephone system, radio paging
system, audible paging and other communication system
and vice versa, whether they are in operation or not?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
w) Are the metal enclosures secured and have sufficient *Yes/No/N.A. *Yes/No/N.A.
space for cable routing and bending?
aa) Is the battery charger provided with voltmeter and *Yes/No/N.A. *Yes/No/N.A.
charging ammeter?
3.7.1.6 Miscellaneous
b) When the fire alarm is activated, will the following *Yes/No/N.A. *Yes/No/N.A.
operations be performed automatically?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(ii) The alarm bells and flashing light units within the
alarm zone shall operate. After 10 seconds, the
alarm bells shall stop while the flashing light units
shall continue to flash. Then the pre-recorded
audio alarm messages shall announce within the
alarm zone to alert the occupants and direct them
to evacuate immediately following the directional
and exit signs. The alarm bells and the audio
alarm messages shall repeat in sequence
continuously until the fire alarm has been reset at
the fire alarm panel.
e) Is the message audible in all areas within the specified *Yes/No/N.A. *Yes/No/N.A.
zone of the building including toilets, stores, staircases,
etc.?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Is the signal to noise ratio less than 40 dB when the *Yes/No/N.A. *Yes/No/N.A.
loudspeaker output level in the area concerned is not less
than 20 dB above the background noise level normally
expected in the respective area during fire conditions?
g) Is the variation in sound power level between the outlet *Yes/No/N.A. *Yes/No/N.A.
nearest to and farthest from the amplifier not exceeding 3
dB ?
c) Is the wiring so arranged that any damage to the wiring *Yes/No/N.A. *Yes/No/N.A.
for any one loudspeaker or directional sign will not
affect the proper operation of other loudspeakers or
directional signs?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are all mounting fixtures provided and fixed in place? *Yes/No/N.A. *Yes/No/N.A.
g) Are all fire extinguishers and fixed sprayer unit provided *Yes/No/N.A. *Yes/No/N.A.
with certificates signed by a registered class 3 fire
contractor? (Certificates should be enclosed)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
(i) The total weight should be checked against that recorded when the extinguisher was put
into service. If a loss of weight of more than 10 per cent is detected, the extinguisher
should be discharged and returned to the suppliers for examination, test and recharging.
(ii) The body of the extinguisher should be examined and, if there are signs of damage or
extensive external corrosion, the extinguisher should be discharged and returned to
suppliers for examination, test and recharging.
(iii) The discharge horn and hose should be checked to see that it moves freely and should be
replaced if damaged is detected.
(iv) Hydraulic pressure test should be carried out every five years on the cylinder in accordance
with the manufacturers' instructions. Extreme care should be exercised when preparing and
conducting the test.
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.
(ii) Remove the headcap to check the liquid level. The liquid should be topped up as necessary.
(iii) The nozzle, strainer and internal discharge tube should be checked for cleanliness and free from
obstruction. Defective items shall be replaced.
(iv) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(v) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.
(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.
(vi) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(viii) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.
(ix) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.
(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher.
(STORED-PRESSURE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.
(iii) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.
(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all extinguishers
should be overhauled and recharged.
(v) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.
(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers instructions. Extreme care should be exercised when preparing and conducting
the test.
(vi) Unserviceable extinguisher should be discharged prior to disposal.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.
(ii) The extinguisher should be weighed to check that it contains the correct weight of powder. The
weight when fully charged should be recorded at the time of charging. If the weight is found to
have dropped by more than 10 per cent, the dry powder should be replaced by a fresh charge. Care
should be taken not to mix different types of dry powder because they could react with one
another.
(iv) Remove the headcap to check the condition of powder. The chemical should be renewed if it is not
in good condition.
(v) The nozzle and discharge control (if fitted) should be checked for cleanliness and free from
obstruction. Defective items shall be replaced.
(vi) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.
(vi) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.
(viii) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.
(ix) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(x) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.
(xi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(xii) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
the dry powder should be collected for subsequent re-cycling/disposal. Never empty the contents
by discharging the extinguisher.
(xiii) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and the dry powder should be collected for subsequent re-cycling/disposal. Never empty
the contents by discharging the extinguisher.
(STORED-PRESSURE TYPE)
(i) The extinguisher should be weighed to check it contains the correct weight of powder. If the
weight is found to have dropped by more than 10 per cent, the dry powder should be replaced by a
fresh charge. Care should be taken not to mix different types of dry powder because they could
react with one another.
(ii) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.
(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.
(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.
(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. The dry powder should be discharged to an enclosure for
collection and subsequent re-cycling/disposal. Should any extinguisher fail in the test, all
extinguishers should be overhauled and recharged.
(vi) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.
(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
(viii) Unserviceable extinguisher should be discharged prior to disposal. The dry powder should be
discharged to an enclosure for collection and subsequent re-cycling/disposal.
NOTE:
(a) Dry powder extinguishers must be thoroughly dry internally before they are recharged.
(b) Advice should be obtained from the Fire Services Department as to the possible reaction between the
powder or expellent and the material to protected.
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(PORTABLE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The extinguisher should be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher should be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.
(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.
(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.
(v) If there are signs of damage or external corrosion, the extinguisher should be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.
(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
(vii) Unserviceable extinguisher should be discharged to a closed recycling system prior to disposal.
(ii) The extinguisher should be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher should be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.
(iii) The deflector and the sensing element should be checked and cleaned.
(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.
(v) If there are signs of damage or external corrosion, the extinguisher should be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.
(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
(vi) Unserviceable extinguisher should be discharged to a closed recycling system prior to disposal.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
(i) The nozzle and the vent holes in the cap should be checked for cleanliness and free from
obstruction.
(ii) Remove the headcap to check the liquid levels in the body and in the inner container. Any slight
loss may be made up with water; otherwise a new charge should be used.
(iii) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.
(iv) Before the headcap is replaced, the plunger, the headcap lever for the sealing device or other
operating device should be checked to see that it operates freely. The washer should be replaced if
necessary and the cap should then be tightly screwed to the container to form a gas-tight joint.
(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all should be tested by
discharge. Extreme care should be exercised during preparing and conducting discharge test. Prior
to discharging, the container should be ensured in good condition such as no corrosion, damage or
rust should be visible externally or internally on any part of the container; otherwise hydraulic
pressure test should then be carried out to confirm the container structurally sound. Should there
be doubt in the condition of the container, hydraulic pressure test shall be conducted instead.
(vi) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.
(vi) Hydraulic pressure test should be carried out every five years on the outer container in accordance
with the manufacturers' instructions; the inner container should be examined to ensure it is in good
condition and not leaking. Extreme care should be exercised when preparing and conducting the
test.
(viii) Before carrying out hydraulic pressure test, remove the headcap and clear the contents. Never
empty the contents by discharging the extinguisher.
(ix) Also, before disposal of unserviceable extinguisher, remove the headcap and clear the contents.
Never empty the contents by discharging the extinguisher.
NOTE:
Inverted type chemical foam extinguishers have ceased production and not permitted for sale. However,
products already sold may continued to be used.
Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-
(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.
(ii) Remove the headcap to check the liquid level. If the liquid level was found to have dropped by
more than 10 per cent, the foam concentrate or foam solution as appropriate should be replaced by
a fresh charge.
(iii) The branchpipe, strainer and internal discharge tube should be checked for cleanliness and free
from obstruction. Defective items shall be replaced.
(iv) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.
(v) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.
(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.
(vi) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.
(viii) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.
(ix) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.
(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher
(STORED-PRESSURE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.
(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(iii) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.
(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher failed in the test, all extinguishers
should be overhauled and recharged.
(v) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.
(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.
Use: On fires involving flammable liquids, such as small fires in the kitchen and laboratory.
Method For Drape the blanket over the flames to seal off air. Switch off heat and leave in position until
Use: cool.
Maintenance: This blanket should be examined every 12 months or after use in fire. The following
maintenance should be carried out :-
(iii) If manufacturers instructions are not available, fire blanket can be washed (soak overnight in
detergent, gently hand rinse in warm water). Do not machine wash or dry clean.
REMARKS:
(i) Fire blankets are classified into two categories, namely:-
"Heavy Duty" fire blankets (BS 7944:1999); and
"Light Duty" fire blankets (BS EN 1869:1997)
(ii) Only "Heavy Duty" and "reusable" fire blankets will be approved as a Fire Service
Standard Requirement.
(iii) "Light Duty" fire blankets may be accepted for use on a private basis and should be
disposed of after use.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
k) Are chases set back at least 100 mm from the front of the *Yes/No/N.A. *Yes/No/N.A.
jambs?
l) Is the barrel enclosure housed completely within the wall *Yes/No/N.A. *Yes/No/N.A.
opening?
m) Is the clearance between the sill and shutter, when *Yes/No/N.A. *Yes/No/N.A.
closed, not exceeding 6 mm?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
o) Are barrels of double shutters installed at the same level? *Yes/No/N.A. *Yes/No/N.A.
p) Are projecting jambs of a width not less than 225 mm *Yes/No/N.A. *Yes/No/N.A.
provided?
t) Does the projecting head extend the full width and *Yes/No/N.A. *Yes/No/N.A.
projections of the projecting jambs?
a) Is the curtain formed from rolled steel lath of 1.2 mm *Yes/No/N.A. *Yes/No/N.A.
thick?
b) Is steel of the appropriate class used for the laths? *Yes/No/N.A. *Yes/No/N.A.
d) Do laths curl on both edges to form quirks of not more *Yes/No/N.A. *Yes/No/N.A.
than 10 mm outside diameter?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
i) Does the curtain have sufficient width to extend at least *Yes/No/N.A. *Yes/No/N.A.
64 mm (75 mm when the wall opening exceeds 2.44 min
width) into channel guides?
j) Does the curtain have sufficient length to extend from *Yes/No/N.A. *Yes/No/N.A.
the sill to the top of the barrel and thence round at least a
quarter of the barrel circumference before fixing?
k) Are steel or malleable cast iron end locks fitted to the *Yes/No/N.A. *Yes/No/N.A.
ends of each lath ?
m) Are end locks riveted to the lath by 2 mild steel rivets of *Yes/No/N.A. *Yes/No/N.A.
not less than 3 mm diameter?
n) Do end locks fit the contour of the curtain laths and fill *Yes/No/N.A. *Yes/No/N.A.
the channel guides closely?
o) Is the bottom lath fitted with a bottom rail of one of the *Yes/No/N.A. *Yes/No/N.A.
following methods of construction?
p) Does the curtain extend at least 32 mm between the Tee *Yes/No/N.A. *Yes/No/N.A.
section, flats or angles ?
q) Are Tee section, flats or angles welded, bolted or riveted *Yes/No/N.A. *Yes/No/N.A.
to the laths by at least 8 mm diameter steel bolts or steel
rivets?
r) Do the above fixings space not more than 300 mm *Yes/No/N.A. *Yes/No/N.A.
apart ?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
s) Is the bottom rail extend the full width of the curtain *Yes/No/N.A. *Yes/No/N.A.
except for the portion housed within the channel guides ?
u) Does bottom rail make flush contact with the sill when *Yes/No/N.A. *Yes/No/N.A.
the shutter is closed?
v) Are steel lifting handles bolted, riveted or welded to the *Yes/No/N.A. *Yes/No/N.A.
bottom rail on each side of the curtain?
w) Do the lifting handles space not more than 750 mm *Yes/No/N.A. *Yes/No/N.A.
apart?
aa) Do screws/bolt space not more than 250 mm apart? *Yes/No/N.A. *Yes/No/N.A.
ab) Does a screw/bolt provided to within 125 mm from each *Yes/No/N.A. *Yes/No/N.A.
end of the top lath?
ad) Are fusible metal and steel washers fitted to each *Yes/No/N.A. *Yes/No/N.A.
screw/bolt?
b) Does the top of the channel guide locate such as to *Yes/No/N.A. *Yes/No/N.A.
permit upward expansion?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Are steel rivets or steel bolts not less than 6 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 3 mm fillet welds used in fabrication of the
guides?
f) Is the length of the fillet welds not less than 50 mm and *Yes/No/N.A. *Yes/No/N.A.
spaced not more than 150 mm apart?
h) Are guides set back as far as possible within the chases *Yes/No/N.A. *Yes/No/N.A.
provided in the jambs?
i) Are they fitted as close as possible to the front side of the *Yes/No/N.A. *Yes/No/N.A.
chases?
j) Are they wholly contained within the chases so as not to *Yes/No/N.A. *Yes/No/N.A.
project beyond the faces of the jambs?
l) Are centres of fixing not more than 600 mm apart? *Yes/No/N.A. *Yes/No/N.A.
n) With the exception of the lowest one, are fixings *Yes/No/N.A. *Yes/No/N.A.
provided with vertically elongated bolt holes (nominally
50 mm in length)?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
q) Are bolts fixed at the highest positions of the slots to *Yes/No/N.A. *Yes/No/N.A.
allow expansion of the guides in an upward direction?
3.9.1.4 Barrel
a) Is the barrel formed from mild steel tube of not less than *Yes/No/N.A. *Yes/No/N.A.
114 mm outside diameter?
b) Is the mild steel tube not less than 5.4 mm thick? *Yes/No/N.A. *Yes/No/N.A.
c) Is the barrel mounted on mild steel axle of not less than *Yes/No/N.A. *Yes/No/N.A.
25 mm diameter?
d) Does the axle extend the full length of the barrel? *Yes/No/N.A. *Yes/No/N.A.
f) Does the axle project not more than 100 mm beyond *Yes/No/N.A. *Yes/No/N.A.
each end of the barrel?
g) Is expansion clearance provided between the axle and the *Yes/No/N.A. *Yes/No/N.A.
ends of the barrel enclosure?
h) Does barrel enclose helical steel spring for counter *Yes/No/N.A. *Yes/No/N.A.
balancing the curtain?
k) Are axle support brackets made of steel or malleable cast *Yes/No/N.A. *Yes/No/N.A.
iron?
l) Do they support and enclose the axle at each end? *Yes/No/N.A. *Yes/No/N.A.
m) Are they fixed to the ends of the barrel enclosure by at *Yes/No/N.A. *Yes/No/N.A.
least 2 steel rivets or steel bolts at least 8 mm in diameter
or 6 mm fillet welds?
n) Are they of sufficient size to accommodate the axle and *Yes/No/N.A. *Yes/No/N.A.
fusible metal packing?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are steel rivets, steel bolts not less than 8 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 6 mm fillet welds not less than 50 mm in
length being used for the fixings?
c) Are centres of fixings not more than 150 mm apart? *Yes/No/N.A. *Yes/No/N.A.
d) Does the fabrication extend completely along each edge *Yes/No/N.A. *Yes/No/N.A.
of the enclosure?
e) Does the front edge of the bottom enclosure form a 40 *Yes/No/N.A. *Yes/No/N.A.
mm wide flange?
f) Is the distance between the flange and the face of the *Yes/No/N.A. *Yes/No/N.A.
curtain not more than 15 mm?
g) Where a drop bar is used, is the distance between the *Yes/No/N.A. *Yes/No/N.A.
flange and the face of the curtain not more than 50 mm?
j) Are fusible metal washers provided to the fixing bolts? *Yes/No/N.A. *Yes/No/N.A.
l) Where double shutters are fitted and barrels are *Yes/No/N.A. *Yes/No/N.A.
accommodated in the same enclosure, is dividing plate
made of steel at least 6 mm thick provided to separate
the barrels?
n) Does the fascia plate overlap the opening by at least 100 *Yes/No/N.A. *Yes/No/N.A.
mm at the top and at each end?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
p) Does the bottom edge of the fascia plate form a channel *Yes/No/N.A. *Yes/No/N.A.
of a depth not less than 100 mm?
r) Does the channel have a flange not less than 40 mm wide *Yes/No/N.A. *Yes/No/N.A.
next to the face of the curtain?
(i) 25 mm from top edge spaced at not more than 600 *Yes/No/N.A. *Yes/No/N.A.
mm centres?
v) Are elongated bolt holes provided to the fascia plate? *Yes/No/N.A. *Yes/No/N.A.
ab) Is the cover plate fixed by not less than six steel *Yes/No/N.A. *Yes/No/N.A.
screws/bolts not less than 8 mm diameter?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Is the gearing system so arranged that the shutter could *Yes/No/N.A. *Yes/No/N.A.
be manually opened and closed from either side of the
wall opening?
f) Area gears machine cut from a suitable grade of steel? *Yes/No/N.A. *Yes/No/N.A.
j) Is the cover plate fixed by steel expanding bolts of not *Yes/No/N.A. *Yes/No/N.A.
less than 6 mm diameter?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
q) Are steel rivets or steel bolts not less than 8 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 6 mm fillet welds at least 50 mm in length
used for the fabrication of the casing?
s) Is the casing fixed to the face of the wall by expanding *Yes/No/N.A. *Yes/No/N.A.
anchor bolts?
t) Is the diameter of the anchor bolts not less than 8 mm? *Yes/No/N.A. *Yes/No/N.A.
aa) Where the barrel enclosure, fascia plate or dividing plate *Yes/No/N.A. *Yes/No/N.A.
are perforated to permit passage of gearing system, are
size and number of perforations kept to a minimum
consistent with the satisfactory operation of the gearing?
ab) Are perforations so arranged that there is not exposed *Yes/No/N.A. *Yes/No/N.A.
opening into the barrel enclosure?
ac) Are they so arranged that lateral expansion of barrel *Yes/No/N.A. *Yes/No/N.A.
enclosure and fascia plate is not restricted?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
af) Are they located adjacent to the wall opening? *Yes/No/N.A. *Yes/No/N.A.
ag) Are they located not less than 750 n m, nor more than *Yes/No/N.A. *Yes/No/N.A.
1200 mm above the floor?
ah) Where handles on the operating wheels are provided, are *Yes/No/N.A. *Yes/No/N.A.
they so arranged as to close within the wheel when not in
use?
3.9.1.7 Installation
b) Where smoke detectors are provided for the actuation of *Yes/No/N.A. *Yes/No/N.A.
the shutter, are they fitted to both sides of the wall
opening?
e) Are manual controls provided to both sides of the wall *Yes/No/N.A. *Yes/No/N.A.
opening?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.10.2 Fuel
c. Time allowed for max. fuel consumption at full load : _____ hours
d. Fuel storage is sufficient for 6 hrs. generator running
to support fire service installation : *Yes/No
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.10.2.1 Has fuel tank room been inspected and approved by FSD *Yes/No/N.A. *Yes/No/N.A.
Regional Office?
(N.B. : Supporting document to be attached)
3.10.2.2 Has surveyor report for fuel tank been obtained as *Yes/No/N.A. *Yes/No/N.A.
required by FSD Dangerous Goods Divison?
3.10.2.3 Has DG licence for fuel tank room holding more than *Yes/No/N.A. *Yes/No/N.A.
2,500 litres diesel (or as approved) been obtained?
(N.B. : Supporting document to be attached)
a) Is adequate space (not less than 600 mm) provided all *Yes/No/N.A. *Yes/No/N.A.
round emergency generator for maintenance/cleaning?
b) Are air supply and discharge ductworks (if any) provided *Yes/No/N.A. *Yes/No/N.A.
free from obstruction?
e) Is generator built-in fuel tank not greater than 500 litres? *Yes/No/N.A. *Yes/No/N.A.
i) Is a shut off valve provided on the supply pipe from fuel *Yes/No/N.A. *Yes/No/N.A.
tank to the service tank of generator?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
k) Are the batteries kept in fully charged condition and is *Yes/No/N.A. *Yes/No/N.A.
the trickle charge operating?
e) Are audible and visual alarms given locally, and at fire *Yes/No/N.A. *Yes/No/N.A.
control main panel when the generator starting sequence
is locked out due to starting failure?
f) After one hour of running test, do all instruments, safety *Yes/No/N.A. *Yes/No/N.A.
devices, etc. indicate normal condition?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
g) Will the generator set continue to run after a pre- *Yes/No/N.A. *Yes/No/N.A.
determined time recommended by manufacturer unless it
is stopped manually if the normal power supply has
resumed?
h) Are all testing carried out with generator room doors *Yes/No/N.A. *Yes/No/N.A.
kept closed?
i) Is warning signal given locally and at fire control main *Yes/No/N.A. *Yes/No/N.A.
panel when manual/auto selector switch turn to manual
position?
(N.B. such provision is strongly recommended)
j) Is remote control valve on supply pipe to the service tank *Yes/No/N.A. *Yes/No/N.A.
in good working order?
k) Are all moving parts effectively and rigidly guarded for *Yes/No/N.A. *Yes/No/N.A.
safety?
m) Is any exhaust leak detected inside generator room while *Yes/No/N.A. *Yes/No/N.A.
the generator is running?
p) Does emergency generator pass the running test at full *Yes/No/N.A. *Yes/No/N.A.
load?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Does the firemans lift serve the floors of the building *Yes/No/N.A. *Yes/No/N.A.
without having to traverse more than two floors by the
fire service personnel?
c) Is separate lift shaft provided for the fireman's lift? *Yes/No/N.A. *Yes/No/N.A.
d) Is the internal size of the lift car 1.35 m or greater? *Yes/No/N.A. *Yes/No/N.A.
e) Is the rated load of the lift car 680 kg or greater? *Yes/No/N.A. *Yes/No/N.A.
g) Is the opening of the lift car/landing door 800 mm wide *Yes/No/N.A. *Yes/No/N.A.
and 2000 mm high or greater?
h) Are the car and landing door fitted with power operated *Yes/No/N.A. *Yes/No/N.A.
automatic self-closing device?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
l) Are notices provided outside and inside the building in *Yes/No/N.A. *Yes/No/N.A.
conformity with the Code of Practice for Means of
Access for Firefighting and Rescue?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Does the opening of the safety hatch door inside the lift *Yes/No/N.A. *Yes/No/N.A.
car automatically cut off the electric fan?
b) Does the fireman's switch when operated over-ride all *Yes/No/N.A. *Yes/No/N.A.
registered instructions and return to the designated floor
of entry?
c) Is the fireman's lift capable to travel from the designated *Yes/No/N.A. *Yes/No/N.A.
floor of entry to the topmost floor within 1 minute
calculating from the lift door completely closed to the lift
door started to open? (Actual sec.)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Are there not less than two emergency luminaires in each *Yes/No/N.A. *Yes/No/N.A.
space?
g) Are self-contained exit signs and centrally supplied exit *Yes/No/N.A. *Yes/No/N.A.
signs provided in accordance with approved drawings?
m) Are bar code labels provided to the battery lighting and *Yes/No/N.A. *Yes/No/N.A.
central battery system?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
p) Does the exit sign comply with FSD requirements (letter *Yes/No/N.A. *Yes/No/N.A.
sizes and colour)?
q) Are the emergency lighting and exit sign connected to *Yes/No/N.A. *Yes/No/N.A.
emergency generator power supply?
a) Acceptance Testing
Does the installations comply with BS5266: Part 1 and *Yes/No/N.A. *Yes/No/N.A.
BS EN 1838?
b) Discharge Test
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Functional Test
d) Performance Test
(iv) Does the central monitoring, testing and logging *Yes/No/N.A *Yes/No/N.A
system perform as specified (G.S. Clause
B11.1.6)?
(Remark: Detailed testing and commissioning
procedures to be submitted by the contractor for
approval.)
a) Acceptance Testing
Does the installation comply with BS 5499 and BS 5266: *Yes/No/N.A. *Yes/No/N.A.
Part 1 and FSDCOP?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Discharge Test
(1) Connections between the battery and the source *Yes/No/N.A *Yes/No/N.A
of charging current to be such that in no
circumstances should the battery discharge other
than to the secondary lighting circuits.
c) Functional Test
d) Performance Test
(i) Is the illumination level adequate when all signs *Yes/No/N.A *Yes/No/N.A
are on using battery supply?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.13.1.1 Method of overriding control (Refer to para. 5.25 in C.O.P for Minimum F.S.I. & Equipment):
Method A/B/C/combination of
3.13.1.3 On/Off status monitoring of MVAC systems at: FS Control Room/B.M. Office/MVAC
Control Console
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Do the sizes of the MVAC systems and associated air *Yes/No/N.A. *Yes/No/N.A.
ducts tally with the FSD endorsed MVAC layouts?
c) Are all the MVAC systems required to be included in the *Yes/No/N.A. *Yes/No/N.A.
VAC control system highlighted on the air-side
schematic diagram?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are the probes length (>2/3 duct width in most products) *Yes/No/N.A. *Yes/No/N.A.
and model appropriate?
d) Are the filters at the end of the smoke collecting/ *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
e) Is the smoke collecting probe installed in such a way that *Yes/No/N.A. *Yes/No/N.A.
the smoke collecting holes are facing the air stream
being detected?
a) Can all the MVAC systems involved in the VAC control *Yes/No/N.A. *Yes/No/N.A.
system be shut off when this switch is activated?
b) Does any breakage in circuit wiring of this switch cause *Yes/No/N.A. *Yes/No/N.A.
the above MVAC systems to shut down?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the detector head is removed
from its mounting base?
b) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the power supply to the
detector is lost?
a) Each MVAC system shall operate steadily to its rated *Yes/No/N.A. *Yes/No/N.A.
speed and capacity first. Smoke is generated and
conveyed to the lower pressure side of the MVAC
system or air duct where it can be collected and detected.
After a reasonably short period of time, the MVAC
system must be able to shut down and a signal will be
relayed to the F.S. Panel in the F.S. Control Room. All
other MVAC systems installed within and serving the
same compartment must also be shut down through
interlocking arrangement. No MVAC system can
resume normal function unless the fire signal registered
has been cleared. (Test records on Part 4, 4.13 Table 1)
a) The central fresh air supply and/or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
be shut down
b) The central fresh air supply and/or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
not require to be shut down but the fresh air and/or
exhaust to the affected compartment/unit shall be closed
off from the central system by actuation of a local
motorised smoke damper.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Minimum airflow velocity between specified areas with the exit door of any three ___________m/s
consecutive floors and G/F main entrance door at fully open state:
Specific pressure relief system for over pressure control : (*i / ii / iii / iv )
Refer to FSDCOP
Para. 5.21 Cl. B.9
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.14.2.1 General
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Does system layout tally with approved building plans *Yes/No/N.A. *Yes/No/N.A.
and F.S.I. drawings?
Fan / Motor Set Data : Single Supply Fan Multiple Supply Fan
Duty Duplicated No. 1 No. 1 No. 2 No. 2
Motor Motor Duty Fan Standby Fan Duty Fan Standby Fan
Location
Fan
Manufacturer
Motor
Fan
Model
Motor
Fan
Serial No.
Motor
Starting method
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Is pressurization fan & motor supplied from one single *Yes/No/N.A. *Yes/No/N.A.
proprietary manufacturer specialized in the manufacture
of the pressurization of staircases system?
c) Is nominal fan motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?
f) Are pressurization fan motors protected with HRC fuses? *Yes/No/N.A. *Yes/No/N.A.
i) Are the fans installed in a separate fire resistant plant *Yes/No/N.A. *Yes/No/N.A.
room or enclosed by fire resistant enclosure with a FRP
not less than that of the staircase served?
k) Are doors to fan room provided with key locking *Yes/No/N.A. *Yes/No/N.A.
devices?
l) Are door(s) to fan room provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closer(s)?
n) Shall the plant room housing the staircase pressurization *Yes/No/N.A. *Yes/No/N.A.
fans contain no other services.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.14.2.4 Ductworks
a) Does air intake distant from any potential fire hazards *Yes/No/N.A. *Yes/No/N.A.
and avoid contamination by the corresponding source of
smoke?
b) Does the size of the outdoor air intake duct tally with the *Yes/No/N.A. *Yes/No/N.A.
vertical air flow diagram approved by FSD?
h) Are gaps / spaces between ductwork and wall openings *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
k) Are duct hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
o) Does system equipped with fire / smoke dampers or any *Yes/No/N.A. *Yes/No/N.A.
other restrictions along the passage of supply & exhaust
air in accordance with the approved drawings?
q) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are the pressure sensors and its associated equipment of *Yes/No/N.A. *Yes/No/N.A.
industrial process grade conforming to BS EN 60654-1
or equivalent?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Is the pressure sensing unit(s) connected with fire rated *Yes/No/N.A. *Yes/No/N.A.
cables of high temperature grade to BS 6724 suitable for
operating at 250 oC?
d) Is the high temperature grade fire rated type cable *Yes/No/N.A. *Yes/No/N.A.
enclosed in galvanized steel conduit and run within the
pressurized space in the fire resistance duct?
d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?
c) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and fastened by approved fasteners or clamps
specially designed and constructed for the purpose?
d) Are the cables installed outside the pressurized staircase *Yes/No/N.A. *Yes/No/N.A.
enclosed by fire resistant enclosure with FRP not less
than that of the compartment served or 2 hrs FRP,
whichever is the higher?
c) Is the cubicle type motor control panel constructed from *Yes/No/N.A. *Yes/No/N.A.
2 mm thick (min) panel steel and conform to BS EN
60439-1 or as approved?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
e) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarm and trouble lights
essential to the operation of the system?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Does the controls, starters, relays, etc., be suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250 oC for not less than one
hour?
g) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the pressurization
system?
j) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?
k) A further label shall be provided with letters not less than *Yes/No/N.A. *Yes/No/N.A.
6 mm high stating that the controls shall be operated by
authorized personnel.
3.14.2.9 Miscellaneous
a) Are all ductworks and metal works properly painted for *Yes/No/N.A. *Yes/No/N.A.
identification?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) Are door sets (i.e. doors, frames and ironmongery *Yes/No/N.A. *Yes/No/N.A.
hardware) complied with Building Authoritys
requirement and suitable for use continuously at 35 oC
and 100% RH, and with certificates enclosed as
required?
g) If, however, except for sleeping risk premises, the total *Yes/No/N.A. *Yes/No/N.A.
air requirement for each pressurized staircase is made up
from two or more separate supplies acting together (e.g.
top and bottom plants), then no further duplication of
equipment is necessary.
h) All doors sets (i.e. doors, frames and hardware) *Yes/No/N.A. *Yes/No/N.A.
providing access to or from any pressurized staircase
shall be to the satisfaction of the Building Authority.
j) Self closers shall be provided for all doors to ensure *Yes/No/N.A. *Yes/No/N.A.
integrity of the enclosure. The closers shall have been
part of a door, door frame and ironmongery test
assembly which has successfully passed the test in
accordance with British Standard 476: Part 22. The
closers shall be of such a design that they cannot be
defeated i.e. no removable pins or bolts, etc.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
g) If, however, except for sleeping risk premises, the total *Yes/No/N.A. *Yes/No/N.A.
air requirement for each pressurized
staircase is made up from two or more separate supplies
acting together (e.g. top and bottom
plants), then no further duplication of equipment is
necessary.
b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.20 in FSDCOP)
c) Are manual reset and monitoring provision with audio / *Yes/No/N.A. *Yes/No/N.A.
visual indications provided? (Refer to Para. 5.20 in
FSDCOP)
h) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?
i) Are the fan motors duplicated for duty and standby used *Yes/No/N.A. *Yes/No/N.A.
for buildings with more than one pressurized staircase?
j) Are sleeping risk premises and where designated by the *Yes/No/N.A. *Yes/No/N.A.
Director of Fire Services, provided with a single
pressurized staircase, duplicate fans and motors?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(l) Is alarm signal repeated to fire control room or status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
p) Is variable flow control for fan(s) adopting for normal *Yes/No/N.A. *Yes/No/N.A.
operating mode?
3.14.3.2 Others
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Operating Air Flow Pattern : *Scouring Pattern / Cross Flow Effect with low level supply
and high level extraction
Design Volume : _____________m3 Total Air Change per Hour : ___________
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.15.2.1 General
e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?
f) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?
j) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning available?
l) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
m) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineers signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?
o) Are all systems with fail safe design to ensure a free *Yes/No/N.A. *Yes/No/N.A.
passage of smoke?
p) Are the fire shutters tested to the relevant requirements *Yes/No/N.A. *Yes/No/N.A.
of the T & C Procedure for Fire Service Installation?
q) Has exemption been granted for one extraction / supply *Yes/No/N.A. *Yes/No/N.A.
system used to serve several compartments?
r) Where the motorized fire and smoke dampers are *Yes/No/N.A. *Yes/No/N.A.
required, has the entire assembly of the fire and smoke
damper been tested to maintain efficient operation at
250oC for not less than one hour?
s) Has the Director of Fire Services approved the adoption *Yes/No/N.A. *Yes/No/N.A.
of performance based fire engineering approach?
t) Where the smoke extraction rate is designed with fire *Yes/No/N.A. *Yes/No/N.A.
engineering approach, is the maximum area of the smoke
reservoir restricted to 2000 m2?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
y) Shafts used for smoke extraction purposes shall contain *Yes/No/N.A. *Yes/No/N.A.
no other services.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Fan
Manufacturer
Motor
Fan
Model
Motor
Fan
Serial No.
Motor
Starting Method
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
c) If the fans are installed within the service compartment, *Yes/No/N.A. *Yes/No/N.A.
is the fan system (including fans, motors, drives,
electrical works, ductworks, boundary of compartment)
protected by a fire resisting material of rating not less
than one hour?
d) Is the supply / makeup air rate at least 80% of the overall *Yes/No/N.A. *Yes/No/N.A.
extraction rate?
g) Is fan motor(s) power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required nominal fan power?
i) Is the fan itself coated with finishing material capable of *Yes/No/N.A. *Yes/No/N.A.
withstanding exposure to an ambient temperature of 250
o
C for a period of not less than one hour without
producing smoke or any toxic fumes, and certified by
the fan manufacturer?
l) Are smoke extraction fans connected with power supply *Yes/No/N.A. *Yes/No/N.A.
from essential source?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
o) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
locking devices?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
p) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
automatic door closer(s)?
3.15.2.3 Ductworks
a) Is air intake distant from any potential fire hazards and is *Yes/No/N.A. *Yes/No/N.A.
prevented from contamination by the same source of
smoke?
d) Does the size of the outside air intake duct tally with *Yes/No/N.A. *Yes/No/N.A.
vertical air flow diagram approved by FSD?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
i) Are gaps / spaces between ductwork and wall opening *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?
l) Are duct hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?
o) Does system clear from any fire / smoke dampers or any *Yes/No/N.A. *Yes/No/N.A.
other restrictions of air passage as approved?
r) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?
t) Are motorized fire / smoke dampers provided only for *Yes/No/N.A. *Yes/No/N.A.
system where one extraction or supply system is used to
serve several compartments as approved?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
x) Are fire and smoke dampers provided at the main *Yes/No/N.A. *Yes/No/N.A.
exhaust outlet louvre and / or main supply intake louvre?
y) Do fire and smoke dampers comply with UL 555s class I *Yes/No/N.A. *Yes/No/N.A.
or other international standards?
iv) Hard body impact test to BS 5669 : Part 1 & 2 *Yes/No/N.A. *Yes/No/N.A.
with exterior surface free from accidental
mechanical damage?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?
b) Is the whole smoke extraction system wired with fire *Yes/No/N.A. *Yes/No/N.A.
resisting cables?
d) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?
e) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and are fastened by approved fasteners or
clamps specially designed and constructed for the
purpose?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Are the cable routes provided with proper protective *Yes/No/N.A. *Yes/No/N.A.
enclosure to reduce the likelihood of failure due to
external effects mechanical, electrical or physical?
c) Is the control panel for each smoke extraction system *Yes/No/N.A. *Yes/No/N.A.
normally manned or installed in public area?
g) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarms and trouble lights
essential to the operation of the system?
h) Are the controls, starters, relays, etc., suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250 oC for not less than one
hour?
i) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the smoke
extraction system?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
l) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?
o) A further label shall be provided with letters not less than *Yes/No/N.A. *Yes/No/N.A.
6 mm high stating that the controls shall be operated by
authorised personnel.
p) All labels shall be permanent, legible and firmly secured *Yes/No/N.A. *Yes/No/N.A.
(adhesive is not satisfactory) and shall be lettered in both
English and Chinese by engraving or similar.
e) Does the fault silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving visual light ON?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
f) Does the alarm silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving the red alarm indicating light ON until the
system is reset?
h) Does test switch for simulating alarm condition and *Yes/No/N.A. *Yes/No/N.A.
operate properly?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.15.2.8 Miscellaneous
c) Are all ductworks and metal works properly painted? *Yes/No/N.A. *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
b) Has full and complete records been taken of all tests and
the results submitted with not less than the following in
the report :
c) Has mechanical check for motorized smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?
d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
e) Are switches for all smoke extraction / removal systems *Yes/No/N.A. *Yes/No/N.A.
grouped in one area of the panel together with those for
staircase pressurization systems or the like?
f) Are all switches have the same method / direction of *Yes/No/N.A. *Yes/No/N.A.
operation?
h) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
show operating positions and systems served and stating
that the controls shall be operated only by authorized
personnel?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Are the electrically driven fans equipped with audio and *Yes/No/N.A. *Yes/No/N.A.
visual warnings to indicate the fault signals?
iii) The correct balancing and direction of air flow? *Yes/No/N.A. *Yes/No/N.A.
d) Are egress / escape routes kept free from smoke (i.e. *Yes/No/N.A. *Yes/No/N.A.
smoke flow shall be away from the escape route)?
e) Are air / smoke flow paths under scouring or cross- *Yes/No/N.A. *Yes/No/N.A.
flow effect in all areas within the fire compartment as
approved?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
j) Does makeup air supply follow an air path as direct and *Yes/No/N.A. *Yes/No/N.A.
short as possible, and enter at low level in order to avoid
premature mixing with the hot gases?
b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.22 in FSDCOP)
c) Are manually reset and monitor by audio & visual *Yes/No/N.A. *Yes/No/N.A.
indication function provided? (Refer to Para. 5.22 in
FSDCOP)
g) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Operating air flow pattern : *Scouring pattern / Cross flow effect with low level supply
and high level extraction
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
1) *Smoke Generator(s)
2) *Tracer Smoke
3) *Fire Chamber
4) *Combustion Fuel
5) *Thermal Couples
6) *Temperature Sensor(s)
7) *Anemometer
8) *Clamp-on Ammeter
9) *Voltmeter
10) *Tachometer
13) *U gauges
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
3.16.3.1 General
e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?
f) Are all wet fire service installations completed with full *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning?
g) Are all automatic fire alarm installations completed with *Yes/No/N.A. *Yes/No/N.A.
full testing & commissioning?
h) Are all static & dynamic smoke extracting installations *Yes/No/N.A. *Yes/No/N.A.
completed with full testing & commissioning?
i) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?
n) Are all finishes of building envelop completed with full *Yes/No/N.A. *Yes/No/N.A.
inspection?
o) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
Testing & Commissioning available?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
p) Is mock-up test with set up details for Testing & *Yes/No/N.A. *Yes/No/N.A.
Commissioning available and approved by Architect?
v) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?
w) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineers signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?
y) Are all fire fighting squads available throughout the *Yes/No/N.A. *Yes/No/N.A.
testing process?
z) Is the safety arrangement and precautions for the test *Yes/No/N.A. *Yes/No/N.A.
approved by Architect and accepted by the FSD?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?
f) Is the smoke management supply fan tripped off upon *Yes/No/N.A. *Yes/No/N.A.
the sensing of smoke at the air intake passage by the
designated smoke detector?
g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?
3.16.3.3 Miscellaneous
d) Is static photo recording carried out to record the smoke *Yes/No/N.A. *Yes/No/N.A.
movement upon the hot smoke test?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Are the ductwork and all relevant parts of the systems for *Yes/No/N.A. *Yes/No/N.A.
the hot smoke test tested satisfactorily in accordance
with the T & C Procedure No. 1 for Air-conditioning,
Refrigeration, Ventilation and Central Monitoring
Control System Installation?
b) Are preliminary and visual test on the sealing of all *Yes/No/N.A. *Yes/No/N.A.
openings in the ductwork using chemical white smoke
generators be carried out?
c) Has mechanical check for motorized smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?
d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a) Is the fire size identified with total heat output estimated *Yes/No/N.A. *Yes/No/N.A.
to ensure the test to be carried out without damage to the
building?
d) Are the plume temperature reading data logged with *Yes/No/N.A. *Yes/No/N.A.
computer programme and linked to trigger the alarm
signal for executing fire suppression, if required?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.1.2 Records
(This form can also be used for hydraulic test carried out during the construction period)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Pressure (bars)
Pressure Reducing Riser/Stair No. Floor Level
Set No. Upstream Downstream
Standby
Pump Standby
Standby
Duty Pump
Standby Pump
Location of Hose reel Floor Level Riser/Stair No. Range (m) Flow rate
(L/min)
Branch
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Location of Hydrant Floor Level Riser/Stair No. Pressure (bars) Flow rate (L/min)
Topmost outlet
Bottom outlet
Intermediate outlet
Table 7 Test Records on Static Pressure without Pump at the Topmost Hydrant Outlet
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Type of town mains: *single end feed/ double end feed/ direct feed/ unrestricted
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
6
Use separate sheet for large installation.
4.2.2 Records
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Jockey Pump
Sprinkler Duty
Pump
Standby
Transfer Duty
Pump
Standby
Jockey Pump
Duty Pump
Standby Pump
Note : Duty pump cut-in pressure shall be not less than 80% of the design/maintained pressure in
the trunk main.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Table 5 Test Record of Proving of Water Supplies with Measuring Orifice Fitted
#- Actual minimum running pressure = Installation pressure - Static pressure of highest sprinkler
Table 6 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.3 Record of Tests on Manual and Automatic Fire Alarm System and Fire Alarm Control
System
Alarm Bell
Heat
Fire Smoke
Detector
Probe Unit
Sprinkler Flow
Switch
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.3.1.1.2 Detectors
a) Heat detector:
Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.3.2 Records
Table 1 Test Record of Manual Call Points, Alarm Bells and Control Panel
Control Panel
Location of Manual Floor on which
Call Point Alarm Bell Sound Zone No. and Buzzer Fire Pump
Indication Cut-in
(No./NO/OFF) (ON/OFF) (ON/OFF)
Control Panel
Location/ LED Indicator Floor on which
Identification Local/Remote Alarm Bell Zone No. and Buzzer
of Detector (ON/0FF) Sounds Indication
(Heat/Smoke) (No./ON/OFF) (ON/OFF)
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Location/Room :
Type of Gas : *CO2 / FM200 / ________________
Type of System :
Modular ( ) Cylinder ( )
Pre-engineered ( ) Engineered ( )
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.4.2 Records
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.5.2 Records
Table 1 Record of Hydraulic Test of Pipeworks
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Jockey Pump
Others
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Type of town mains : *single end feed/ double end feed/ direct feed/ unrestricted
Water tank capacity : m at Location :
Total Nos. of drencher head/water spray nozzle : Nos.
Total Nos. of deluge valve set : Nos.
Nos. of drencher head/water spray nozzle connected to each deluge valve set :
9
Use separate sheet for large installation.
4.6.2 Records
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Duty
Standby
Duty
Standby
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Table 4 Test Record of Proving of Water Supplies with Measuring Orifice Fitted
Note : # - Actual minimum running pressure = Installation pressure - Static pressure of highest nozzle
Table 5 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted
Remark:
4.7 Record of Tests on Audio/Visual Advisory System
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Control Panel
Location of Floor on which
Loudspeakers Loudspeakers Zone No. and Loudspeaker
Operated Indication
(No./NO/OFF) (ON/OFF)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Control Panel
Location/ Flashing Lights
Identification (ON/OFF) Zone No. and Flashing
of Flashing Lights Indication Light
(No./ON/OFF) (ON/OFF)
Note: Flashing lights in the same area shall operate in synchronous mode.
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(a) Water
kg
kg
Automatic Fixed
Sprayer Unit
(Type: )
(*)
Others (please specify)
Note: *Capacity and type of fire extinguishers and their locations shall be stated.
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Operation
Location of Fire
Shutters Zone No. and Buzzer Fire Shutters Fire Shutters
Indication (Close by fire signal (Re-open after fire
(No./NO/OFF) (ON/OFF) automatically signal cleared
Yes/No) Yes/No)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Control Panel
Location/ LED Indicator Floor on which
Identification Local/Remote Alarm Bell Sound Zone No. and Buzzer
of Detector (ON/OFF) Indication
(Heat/Smoke) (No./ON/OFF) (ON/OFF)
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Project title :
*P.W.P./Project No. :
*Contract/Sub-contract/Quotation No. :
Date of test :
Test instruments used :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.10.1.3 Alternator
a) Make :
b) Model :
c) Serial No. :
d) Rated kVA :
e) Voltage (V) / Full load current (A) :
f) Phase / Rated p.f. :
g) Insulation class :
a) Manufacturer :
b) Make/Model No. :
c) No(s). of battery / Voltage (V) :
d) Ampere hour :
e) Starting time (sec) :
a) Manufacturer :
b) Make / Model No. :
c) Safe working load (kg) :
d) Lifting height (m) :
e) Test Certificate : *Yes/No
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
a. Starting Manual
Simulate Test 1 ^
Mains Failure
Test 2 **
Delay Start Timer
Delay Repeat Start
b. Stopping Manual
Resumption of Mains ***
Delay Stop Timer ****
c. Engine Overload Trip (MCCB)
Protection
Engine HL
Overspeed
LL
Low Lub-oil HL
Pressure (kPa) LL
High Water HL
Temp.
(oC) LL
Under Voltage Trip
Overvoltage Trip
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Note : ^ Refer to function test on capability to start and transfer load to generator automatically.
** Refer to function test on capability to start but without load transfer if mains resumes
during engine starting.
*** Refer to function test on capability to automatic transfer load back to mains automatically
after a preset time delay and immediately back to generator if mains fails within the above
time delay period.
**** Refer to function test on capability to cool engine for a preset period after load is
transferred to mains.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Lift No.
Manufacturer
Speed (m/s)
Floor served to to to
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.11.2 Records
Items tested/checked
e) Alarm? *Yes/No/N.A.
f) Intercom? *Yes/No/N.A.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Items tested/checked
4.11.2.5 When lift NOT at main floor and stopping at other floor with
door OPEN :
4.11.2.6 When lift NOT at main floor and stopping at other floor with
door CLOSE :
e) Door is totally closed with car call button or door close button *Yes/No/N.A.
pressed continuously otherwise door opened ?
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Items tested/checked
g) Lift stops at nearest car call and all other car calls cancelled ? *Yes/No/N.A.
c) Door remains fully opened and car call can be registered again ? *Yes/No/N.A.
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Exit Sign
Directional Sign
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Floor 2
Floor 3
Floor 4
Floor 5
Floor 6
Floor 7
Floor 8
Floor 9
Floor 10
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Floor 2
Floor 3
Floor 4
Floor 5
Floor 6
Floor 7
Floor 8
Floor 9
Floor 10
Remark:
Checked/Certified by : Certificate No.:
(Name of electrical worker) Class
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Ref. No. Method of Shut down Fire signal MVAC Operate Other
and type of Tripping by smoke registered in system Manual MVAC
MVAC off detector FS Panel unable to override system
system and type restart while switch to shut interlocked
fire signal off the MVAC
exists system and
test on FAIL
SAFE
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.14.2 Records
Table 1 Record of Air Velocity Across Smoke Lobby to Corridor / Plant Room
Open Door Air Velocity from Staircase to Lobby (Remarks (ii) referred)
Location
Velocity 1 Velocity 2 Velocity 3 Velocity 4 Average Door Velocity Remarks
Remarks (i)
(m/s) (m/s) (m/s) (m/s) (Criteria : ___ m/s)
referred
Remarks :
(i) Single leaf doors on the lift lobbies of any three consecutive floors and one leaf of double-leaf
door at G/F main entrance open
(ii) Airflow across lift lobby door and corridor at the middle of the three consecutive floors are
measured by using calibrated air flow meter.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Table 2 Record of Door Opening Force and Pressure Differential Measurement Across Smoke Lobby
to Corridor
Remarks :
(i) Measure the differential pressure across each lift lobby and corridor by using calibrated airflow
meter with pressure measurement function.
(ii) Measure the differential pressure across staircase and lift lobby by using calibrated airflow meter
with pressure measurement function.
(iii) Inside stairwell with all doors closed and all pressure relief systems operating.
(iv) Measure the force required for opening the door from the lift lobby entrance to corridor by using
calibrated push pull gauge.
(v) Measure the force required for opening the lift lobby door entrance to staircase by using
calibrated push pull gauge.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.15.2 Records
(Intake) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )
(Discharge) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )
Remarks :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(Intake) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )
(Discharge) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )
Remarks :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Date of calibration :
Compartment volume : m3
Headroom height : m
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Yes No Remark
Yes No Remark
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.16.4 Records
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
The following fire service installations by others, related fire service installations and related fire service
provisions are inspected and the final tests are witnessed (G.S. Clause A3.4, B12.7 and C1.12) :
Note: The inspection and witness of final tests on works by others should only be made on items and
aspects related to and required in FSDCOP and for fire service inspection by Fire Services
Department.
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
This is to certify that the following fire service installation *has/have been tested in factory/off-site with
the following test certificates and factory test certificates (G.S. Clause C1.1.1, B4.3, B5.8, A2.10, etc.) :
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
4.20.1 Recommended spare parts and special tools lists with prices. *Yes/No/N.A.
(3 sets) (G.S. Clause A5.7 and B13.4)
4.20.7 Key data summary sheet (3 sets). (G.S. Clause A5.7) *Yes/No/N.A.
4.20.8 *Form 501 /Fire certificate or FSD acceptance memo /Form *Yes/No/N.A.
WR1-a or equivalent by electrical workers /Certificates on
heavy load support and pressurized equipment /Certificates on
gas cylinder /Submissions for Form 314, Form 251, D.G.
store, PPE licence, restaurant licence, etc. /Batch approval
certificate for fire extinguishers /Performance based fire
engineering reports and certificates of designer and
independent checker /Certification by Ventilation Contractor
/Other certificates and licences to be included as record.
(G.S. Clause A5.7)
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
(*The equipment schedule should include all equipment items of the installation. Catalogues and approval
certificate/factory certificate shall be provided and attached)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Remark:
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
*Contract/sub-contract/Quotation No. :
*Contractor/Sub-Contractor :
FSD Ref. :
Drawing No. :
I certify that the following Fire Service Installations as specified in the Contract/Sub-
*contract/Quotation have been designed in accordance with relevant standards, guidelines,
codes of practice, statutory regulations, and good trade practice to meet with the functional,
performance, operation and maintenance requirements and in accordance with the
Specifications and the contract requirements. I certify that the Fire Service Installations
have been checked and tested satisfactorily to comply with the design:
1. _________________________________________________
2. _________________________________________________
3. _________________________________________________
4. _________________________________________________
5. _________________________________________________
Signature - Post :
Tested / Checked by :
(Name of Contractors Representative) Tel. No. :
( ) Date :
Signature - Post :
Witnessed by :
(Name(s) of BSB Staff) Tel. No. :
( ) Date :
Signature - Post :
Name in full :
(Designers firm) Tel. No. :
( ) Date :
Company Chop :
Note : 1. This certificate must be signed by the person responsible for the design and authorized by the
Firm/Company.
2. The person authorized by the Firm/Company shall possess the relevant qualifications
required by the Particular Specification and Fire Service General Specification.
Contract Title:
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark
Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
1. Hydrant and Hose Part 3.1
Reel System
Visual Inspection
G/F
1/F
2/F
3/F
4/F
Functional and
performance test
Submission of
Record of Test
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Contract Title:
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark
Activities Reference to S A S A S A S A S A S A S A S A
Approved
T&C
Procedure
3. Manual and Part 3.3
Automatic Fire
Alarm System and
Fire Alarm Control
System
Visual Inspection
G/F
1/F
2/F
3/F
Functional and
performance test
Submission of
Record of Test
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Contract Title:
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark
Activities Reference to S A S A S A S A S A S A S A S A
Approved
T&C
Procedure
5. Street Hydrant Part 3.5
Visual inspection
Functional and
performance test
Submission of
Record of Test
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Contract Title:
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark
Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
Submission of
Record of Test
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :
Contract Title:
Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark
Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
14. Pressurization of Part 3.14
Staircases System
Visual inspection
Functional test
Performance test
Submission of
Record of Test
Abbreviations
The following abbreviations are applicable to Annex A and Annex B:
AC - Alternating Current
Ahr - Ampere-hour
BS - BS 5839 : Part 1 : 1988 Fire Detection and Alarm Systems for Buildings, Part 1. Code of
Practice for System Design, Installation and Servicing
Cat - Category
cd - Candela
DC - Direct Current
EE Code - Code of Practice for the Electricity (Wiring) Regulations issued by Electrical and
Mechanical Services Department
Code - Codes of Practice for Minimum Fire Service Installations and Equipment and Inspection,
Testing and Maintenance of Installations and Equipment issued by Hong Kong Fire
Services Department
ft - Foot(Feet)
Hz - Hertz
in - Inch(es)
KVA - Kilo-Volt-Ampere
LPC - Loss Prevention Council Rules for Automatic Fire Detection and Alarm Installations for
the Protection of Property (Schedule for the use of BS 5839:Part 1:1988)
m - Metre(s)
M - Megaohm(s)
- Less than/equal to