TESTING AND COMMISSIONING PROCEDURE

FOR

FIRE SERVICE INSTALLATION

IN

GOVERNMENT BUILDINGS

OF

THE HONG KONG SPECIAL ADMINISTRATIVE REGION

2007 EDITION

ARCHITECTURAL SERVICES DEPARTMENT


THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION
PREFACE

This Testing and Commissioning (T & C) Procedure aims to lay down the minimum
testing and commissioning requirements to be carried out on fire service installation in
Government Buildings of the Hong Kong Special Administrative Region (HKSAR). Such
requirements are applicable to both new installations upon completion and existing ones
after major alteration.

The present edition was developed based on its 2001 edition by the Fire Service,
LPG, Catering and Plumbing Specialist Support Group that was established under the
Building Services Branch Technical Information and Research & Development Committee.
With the benefit of information technology, electronic version of this new edition is to be
viewed on and free for download from the Architectural Services Department (ArchSD)
Internet homepage. As part of the Governments efforts to limit paper consumption, hard
copies of this T & C Procedure will not be put up for sale.

The Architectural Services Department welcomes comments on its contents at


anytime since the updating of this T & C Procedure is a continuous process to tie in with
technological advances.
DISCLAIMER

This T & C Procedure is solely compiled for use on fire service installation carried
out for or on behalf of the ArchSD in Government buildings of the HKSAR.

There are no representations, either expressed or implied, as to the suitability of this


T & C Procedure for purposes other than that stated above. The material contained in this
T & C Procedure may not be pertinent or fully cover the extent of the installation in non-
government buildings. Users who choose to adopt this T & C Procedure for their works are
responsible for making their own assessments and judgement of all information contained
here. The Architectural Services Department does not accept any liability and
responsibility for any special, indirect or consequential loss or damage whatsoever arising
out of or in connection with the use of this T & C Procedure or reliance placed on it.
TABLE OF CONTENTS
Page

1. Introduction 1

2. Objectives of the T & C Works 1

3. Scope of the T & C Works 2-4


3.1 General Requirements
3.2 Testing and Inspection
3.3 Documentation and Deliverables

4. T & C Procedures 5-11


4.1 Water System Tests
4.2 Electrical and Alarm System Tests
4.3 Gaseous Extinguishing System Tests
4.4 Emergency Lighting and Exit Sign Tests
4.5 Emergency Generators Tests
4.6 Hot Smoke Tests
4.7 Tests on Other Fire Services Installations

5. Statutory Inspection/Commissioning and Inspection by the 11


Authority

6. Calibrated Equipment 11

Table of Contents FS_TCP


Page 1 of 3 2007 Edition
Annex A Page

Testing and Commissioning Certificate on Fire Service Installation 1-244

Part 1 : Details of Project

Part 2 : Declaration

Part 3 : Items Inspected and Tested

3.1 Hydrant and Hose Reel System

3.2 Automatic Sprinkler System

3.3 Manual and Automatic Fire Alarm System and Fire Alarm
Control System

3.4 Gaseous Extinguishing System

3.5 Street Hydrant

3.6 Drencher System

3.7 Audio/Visual Advisory System

3.8 Portable Hand-Operated Approved Appliances

3.9 Fire Shutter

3.10 Emergency Generator Installation

3.11 Fireman's Lift

3.12 Emergency Lighting & Exit Signs

3.13 Ventilation and Air-conditioning (VAC) Control System

3.14 Pressurization of Staircases System

3.15 Smoke Extraction System

3.16 Hot Smoke Test

3.17 Comments (if any)

Part 4 : Test Records attached to the Test Certificate

4.1 Record of Tests on Hydrant and Hose Reel System

4.2 Record of Tests on Automatic Sprinkler Installation

Table of Contents FS_TCP


Page 2 of 3 2007 Edition
Page
4.3 Record of Tests on Manual and Automatic Fire Alarm System
and Fire Alarm Control System

4.4 Record of Tests on Gaseous Extinguishing Installation

4.5 Record of Tests on Street Hydrant

4.6 Record of Tests on Drencher System

4.7 Record of Tests on Audio/Visual Advisory System

4.8 Record of Tests on Portable Hand-Operated Approved


Appliances

4.9 Record of Tests on Fire Shutter

4.10 Record of Tests on Emergency Generator Installation

4.11 Record of Tests on Firemans Lift

4.12 Record of Tests on Emergency Lighting & Exit Signs

4.13 Record of Tests on Ventilation and Air-conditioning (VAC)


Control System

4.14 Record of Tests on Pressurization of Staircases System

4.15 Record of Tests on Smoke Extraction System

4.16 Record of Hot Smoke Test

4.17 Record of Inspection and Witness of tests on Works installed by


Others

4.18 Record of Factory/Off-Site Test Certificates

4.19 Test Equipment

4.20 Documents required in Specification

4.21 Equipment Schedule of Approved and Installed Equipment

4.22 Record of Certification on Design by Contractor

Annex B 1-5
Testing and commissioning progress chart fire service installation

Annex C 1-2

Abbreviations
Table of Contents FS_TCP
Page 3 of 3 2007 Edition
B.S.B. Testing and Commissioning Procedure Fire Service Installation
1. Introduction

1.1 This procedure is intended to lay down the minimum testing and
commissioning requirements to be carried out by the Contractor on a new
Fire Service Installation upon completion or on an existing Fire Service
installation after alteration. Additional testing and commissioning (T & C)
requirements and procedures may be proposed by the Contractor as
appropriate and agreed by the Project Building Services Engineer (PBSE),
e.g. for special equipment supplied and/or installed by the Contractor.

1.2 This procedure is also written to facilitate the PBSE and Project Building
Services Inspector (PBSI) in carrying out the following aspects of work
with respect to T & C.

(i) To vet and approve the T & C procedures proposed and submitted
by the Contractor.

(ii) To witness the tests in the T & C procedures as specified.

(iii) To receive the T & C reports, record forms, certificates and other
supporting data.

1.3 This procedure shall be read in conjunction with the General Specification
for Fire Service Installation in Government Buildings of The Hong Kong
Special Administrative Region issued by the Building Services Branch,
Architectural Services Department (Fire Service General Specification or
General Specification), particularly on Part D of Fire Services General
Specification. The PBSE and PBSI in this procedure are Architect's
representatives as advised by the Architect from time to time.

2. Objectives of the T & C Works

The objectives of the T & C works are:

(i) to verify the proper functioning of the equipment/system after installation;

(ii) to verify that the performance of the installed equipment/systems meet


with the specified design intent through a series of tests and adjustments;

(iii) to verify the presence and proper functioning of safety, protection and
alarm devices;

and

(iv) to capture and record performance data of the whole installation as the
baseline for future operation and maintenance.

All the test results shall be recorded by the Contractor in the appropriate test
record forms, the reference of which is shown against each individual test. A
complete set of these forms is included in Part 3 and Part 4 of Annex A.

FS_TCP
Page 1 of 11 2007 Edition
3. Scope of the T & C Works

3.1. General Requirements

3.1.1 The Contractor shall submit the T&C procedures together with the
proposed Testing and Commissioning programme, and Testing and
Commissioning Progress Chart shown in Annex B to the PBSE/PBSI for
approval. This procedure only indicates the minimum T&C requirements.
The Contractor shall add and include additional installations, T&C
procedures, and details not included in this procedure in his submitted
T&C procedures. The submission shall be made within the time limit
stated in the Particular Specification or the Fire Service General
Specification and shall be no later than three months before the
commencement of relevant T&C.

3.1.2 Where tests are required to be witnessed by the PBSE/PBSI, the Contractor
shall give due advance notice (usually not less than four calendar days) and
provide details of date, time and type of tests to be performed. PBSE/PBSI
in this procedure shall deem to include Project E&M Engineer/Project
E&M Inspector (PEME/PEMI) or any other person(s) as required by the
Architect.

3.1.3 Upon completion of such inspections and tests in T & C procedures, the
Contractor shall complete and sign a testing and commissioning certificate
by an authorised person approved by the PBSE as in Annex A, to the effect
that the agreed T & C procedures have been duly carried out and
satisfactorily completed. The requirements are detailed in the Fire Service
General Specification.

3.1.4 Before carrying out any test, the Contractor shall ensure installations
comply with the statutory requirements and regulations, particularly on the
safety and protection requirements.

3.1.5 The Contractor shall carry out his/her own adjustment, testing and
commissioning to ensure installations comply with the requirements prior
to inviting the PBSE/PBSI to witness the testing and commissioning.

3.1.6 The definitions and interpretation of abbreviation and abbreviated terms,


words or expressions shall follow the Fire Service General Specification,
unless otherwise defined in this procedure.

FS_TCP
Page 2 of 11 2007 Edition
3.2 Testing and Inspection

3.2.1 The requirements are in general as specified in the Fire Service General
Specification and this procedure. If there is any discrepancy between this
procedure and the Fire Service General Specification, the Fire Service
General Specification shall take precedence.

3.2.2 The Contractor shall carry out the tests and inspections as shown in Part 3
and record the test results on Part 4 of Annex A and as agreed between the
PBSE/PBSI and the Contractor. Where required in the Particular
Specification or Fire Service General Specification, the Contractor shall
also carry out inspection, witness the testing and/or arrange his own testing
on related fire service installations and related fire service provisions
installed by others in order to check and certify their compliance with the
fire service requirements. All interfacing of the fire service installation
with related fire service installation and related fire service provisions
such as firemans lift, etc. installed by others and the functioning of the
interfacing equipment when a fire signal is initiated shall be checked,
tested and certified by the Contractor.

3.3.3 The Contractor shall provide all the necessary staff, labour, consumable
and non-consumable materials for carrying out testing and commissioning
works at their expenses. Electricity supply, water, diesel, chemicals, LP
gas, town gas, fire extinguishing gases/media, lubricants, and other fuel oil
for engine-driven pumps and generators for carrying out testing and
commissioning works shall be arranged and provided by the Contractor at
no cost to the Employer, as detailed in the General Specification.

FS_TCP
Page 3 of 11 2007 Edition
3.3 Documentation and Deliverables

The Contractor shall submit his proposed T & C procedures together with the
proposed Testing and Commissioning programme, and Testing and
Commissioning Progress Chart shown in Annex B to PBSE for approval.

The Contractor shall record all commissioning information and testing results at
the witness of the PBSE/PBSI or his representatives. All inspection and T & C
results shall be recorded in the data record forms shown in Part 3 and 4 of Annex
A. Data recorded in other formats may also be accepted subject to the approval
by the PBSE given before the test, or the agreement between PBSE/PBSI and the
contractor during the test. Immediately after each test, the Contractor's
Commissioning Engineer in Charge (CEIC) shall sign the test/data record sheet,
and obtain the endorsement of the PBSE or PBSI who has witnessed the test on
site, irrespective of whether the test is successful or not, and submit a copy of the
test/data record sheet to the PBSE.

For testing that is required during the construction period, the Contractor shall
also submit a formal testing and commissioning report endorsed by the CEIC
within fourteen (14) calendar days after the completion of the whole test for any
part of the installation.

Upon completion of all the required T&C procedures, the Contractor shall
complete and sign a testing and commissioning certificate by an authorised
person as shown in Part 1 and 2 of Annex A to the effect that the agreed T & C
works have been duly carried out and satisfactory completed.

The Contractor shall submit full testing and commissioning report to the
Architect within fourteen (14) calendar days after completion of testing and
commissioning of the installation. All testing and commissioning report shall be
properly checked and certified by Contractors CEIC before submission. For
testing that is required during construction period, the Contractor shall submit
testing and commissioning report endorsed by CEIC within 14 calendar days
after the completion of the whole test for any part of the installation.

The full testing and commissioning report shall cover all measured data, data
sheets, and a comprehensive summary describing the operation of the system at
the time of the functional and performance tests. Deviations in performance
from the Particular Specification or Fire Service General Specification or the
design intent shall be recorded, with a description and analysis included.

FS_TCP
Page 4 of 11 2007 Edition
4. T & C Procedures

4.1 WATER SYSTEM TESTS

Water systems and circuits shall be tested hydraulically to a minimum


pressure of 1000 kPa or 1.5 times the working pressure whichever is
higher applied at the highest point of the system and held for a period of
not less than 15 min without leaks appearing.

All pipework shall be thoroughly cleaned and flushed before test. The
Contractor shall ascertain that there is adequate drainage nearby to
discharge by large hose in order to ensure flooding of low level areas
will not occur. Where necessary, the Contractor shall provide chemical
cleaning to the pipes. After flushing out the pipework, a flow test shall
be performed on the hydrant/hose reel system in accordance with the
requirements of the Code of Practice for Minimum Fire Service
Installations and Equipment.

A water supply test with the drain and test valves fully opened shall be
made on the sprinkler system in accordance with the requirements of the
LPC Rules for Sprinkler Installations. An alarm test for at least 30
seconds on the water gong shall also be carried out by opening the test
valve to ensure that it shall sound continuously after water flow in the
system is detected. All controls and air supply system for the pre-action
system, recycling pre-action system and dry pipe system shall be tested.

An actual water discharge test shall be performed on the


drencher/deluge/water spray/water mist system and for other automatic
fixed installations using water to test the water flow and discharge
pattern of the nozzles.

For street hydrant system without pumps, the Contractor shall test the
incoming water supply pressure at a nearby supply point and at such
time as agreed with the PBSE/PBSI before the commencement of the
installation works to establish the adequacy of the water supply
pressure. If the supply pressure is inadequate, the Contractor shall
propose remedial measures for the approval of the PBSE. The
Contractor shall find and select the most appropriate nearby supply point
for the test.

The Contractor shall provide whatever hoses or drainage channels


required to safely remove the test water discharged while carrying out
these tests in order to ensure that no damage to the building and property
will be caused by the test water.

The Contractor shall submit hydraulic test certificates/reports that shall


be signed by the Contractor's CEIC and by the PBSE or the PBSI who
has witnessed the test. The test certificates/reports shall contain the
following particulars: -

FS_TCP
Page 5 of 11 2007 Edition
- Date of test
- Apparatus or section under test
- Makers number (if any)
- Nature, duration and conditions of test
- Result of test
- Name of Contractors representative (in block letter) in charge
of test
- Name of Employers representative at witness the test

4.2 ELECTRICAL AND ALARM SYSTEM TESTS

Electrical wiring systems shall be tested generally as required by the


General Specification for Electrical Installation in Government
Buildings of The Hong Kong Special Administrative Region issued by
the Building Services Branch, Architectural Services Department
(General Electrical Specification), Testing and Commissioning
Procedure for Electrical Installation in Government Buildings, Hong
Kong, issued by the Architectural Services Department, the HKSAR
(EE_TC), and this procedure. Extra low voltage wiring shall be
insulation tested to a D.C. voltage of twice the normal working voltage
of the system. Any tests that are liable to cause damage to the delicate
components such as those incorporating electronic circuits shall be
carried out with the components disconnected.

Smoke detectors shall be checked for correct sensitivity settings by


means of manufacturer's test set and for operation by simulated smoke
tests. The smoke detectors shall be tested and checked for correct
settings after every cleaning and right after the occupation of the
building.

Rate-of-rise heat detectors shall be tested by gentle application of a heat


source such as hair dryer. Fixed temperature heat detectors must not be
tested other than using simulated tests.

Each sensing element of the multi-sensor detectors shall be checked for


correct sensitivity settings by means of manufacturer's test set approved
by the PBSE and for operation by simulated tests.

Soak test of least 1 week shall be carried out for all automatic detectors
at the time after the completion of all works including fitting-out works
and the whole area is cleaned up, normally at the time of occupation by
users or immediately after. Such test shall deemed to be successful only
if during such period no false fire alarm is occurred or necessary action
has been taken to rectify the causes.

Battery capacity shall be tested by discharging through the alarm circuits


and being charged via the incorporated charger unit. The specific
gravity of the electrolyte shall be tested with a clean hydrometer where
applicable. Battery voltage shall be checked.

FS_TCP
Page 6 of 11 2007 Edition
The Contractor shall arrange power failure load tests to prove proper
functioning of the fire service installation and the associated power
supply changeover control during power failure and fire mode.

The input D.C. supply to the alarm supervisory circuitry shall be


checked for correct voltage and stability such as to match the signal and
alarm triggering devices.

For fire alarm direct link to the FSD or FSD's approved centre, the
Contractor shall, unless approved by the PBSE, initiate the fire alarm
direct link applications to the appropriate agencies within 3 months after
commencement of the Contract so that the fire alarm direct link will be
connected and tested before the fire service inspections. The Contractor
shall submit a copy of the application document to the PBSE/PBSI for
record.

The Contractor shall co-ordinate and shall closely monitor the status of
completion of fire alarm direct link and the telephone line before the fire
service inspections by the FSD. The Contractor shall apply for and
provide at the Contractor's own cost the required telephone point for
connection of the fire alarm direct link as required. If the Contractor
cannot complete the fire alarm direct link by the date of fire service
inspection by the FSD, the Contractor shall be responsible to provide all
necessary manpower and telephone equipment, at the Contractor's own
expenses, solely for the purpose for a 24-hour/day full attendant service
to substitute the fire alarm direct link, to the approval of the FSD and the
PBSE, up to the date of the completion of the fire alarm direct link.

The fire alarm direct link shall be tested after connection.

4.3 GASEOUS EXTINGUISHING SYSTEM TESTS

Gaseous extinguishing system and manifolds shall be tested in


accordance with Section B5.13 of the Fire Service General
Specification, and all requirements of FSD including FSD Circular
Letters and Fire Protection Notices of the Fire Services Department, the
HKSAR (hereinafter collectively referred as FSD Requirements and
Circular Letters). Pipework shall be tested for 10 minutes to a minimum
of 1.5 times the operating pressure of the system and 10 bars whichever
is larger. A 'puff' test(s) to the installed pipework is required.

The Contractor shall allow carrying out on-site full discharge test after
completion of the installation when required by the FSD to confirm the
design conditions can be met and to the satisfaction of the FSD and
approval of the PBSE. The Contractor shall follow relevant FSD
Requirements and Circular Letters on the requirements of discharge
tests. The Contractor shall refill the gas cylinders with the design agents
after the tests and reset all the equipment after the discharge test.

FS_TCP
Page 7 of 11 2007 Edition
4.4 EMERGENCY LIGHTING AND EXIT SIGN TESTS

Each self-contained luminaire and internally illuminated exit sign shall


be energized from its battery by simulation of a failure of the normal
supply to the lighting for a period of the rated duration of the battery.
During this period all luminaires and/or signs shall be examined and
tested in accordance with BS 5266-1: 2005 and BS EN 50172: 2004 to
ensure that they are functioning correctly.

Each central battery system shall be energized from its battery by


simulation of a failure of the supply to the normal lighting for a period
of the rated duration of the battery. During this period all luminaires
and/or signs shall be examined and tested in accordance with BS 5266-
1: 2005, BS EN 50172: 2004 and BS EN 1838: 1999 and the
requirements of the FSD to ensure that they are functioning correctly.
All tests required in the Code of Practice for Minimum Fire Service
Installations and Equipment and Inspection, Testing and Maintenance of
Installations and Equipment (FSDCoP) and in this procedure shall be
carried out and recorded.

For those emergency lighting system with battery and backed up by


emergency generators, each emergency generator shall be started up and
allowed to energize the emergency lighting system for a continuous
period of at least 1 hour. During this period all luminaires and/or signs
shall be examined visually to ensure that they are functioning correctly.
The start up time of the generator and the illumination level in terms of
`lux' and `cd/m2' etc. shall be recorded and the Contractor shall ensure
that the start up time matches with FSD's requirements.

For emergency lighting system and exit signs provided with central
monitoring, testing and logging system, the system shall be tested in
accordance with the manufacturer's specification and to meet the
requirements in the FSDCoP, EE_TC and this procedure.

Where indicated that there are emergency lighting installation and/or


exit signs in a building carried out by others and not included in the
Works under Fire Service Installation, the Contractor shall follow the
requirements in Clause B11.1.12 of Fire Service General Specification.
The Contractor shall include the emergency lighting installation and exit
signs as part of the fire service installation in the submission to the FSD
with the necessary information to be provided by the relevant parties.

FS_TCP
Page 8 of 11 2007 Edition
4.5 EMERGENCY GENERATORS TESTS

The Contractor shall carry out full visual inspection, safety check,
functional and performance test for the emergency generator
installation. The tests shall include measurement on noise confirming
compliance with the statutory requirements and/or as required by the
Environmental Protection Department, the HKSAR. Emergency
generators for fire service installation shall be located in separate room
unless otherwise agreed by the FSD and approved by the PBSE.

After full test of the fire service installations in a building or premises


have been carried out, with all systems connected to the mains
electricity supply, the mains electricity supply shall be switched off to
simulate power failure and the emergency generator shall start
automatically.

When the emergency generator has gained its capacity and is ready to
accept the fire service load, each fire service installation shall be
switched on until all installations are in operating conditions. If an
automatic starting programme or device is provided for controlling the
starting sequence of the equipment using emergency power supply, the
programme or device shall be allowed to operate and test. A
'simultaneous running' test shall then take place and shall last for a
continuous period of 1 hour. During this period, the performance of each
fire service installation shall be monitored and recorded.

After 1 hour of testing, the emergency generator set shall be examined


and all instruments, safety devices etc. shall indicate normal running of
the generator.

The fuel tank shall be topped up after the tests.

Where the emergency generator installation is provided under the fire


service installation, in addition to the tests required by the FSD, the
Contractor shall test and commission the emergency generator
installation complying with the requirements in General Electrical
Specification and EE_TC.

Where indicated that there is emergency generator installation in the


same building carried out by others and not included in the Works under
Fire Service Installation, the Contractor shall follow the requirements in
Clause B11.3 of Fire Service General Specification. The Contractor
shall include the emergency generator installation as part of the fire
service installation in the submission to the FSD with the necessary
information to be provided by the relevant parties.

FS_TCP
Page 9 of 11 2007 Edition
4.6 HOT SMOKE TEST

Hot smoke test shall be carried out where specified or required by the
FSD. The Contractor shall arrange, co-ordinate and carry out the hot
smoke test to meet the purpose for simulating the prototype of a real fire
under specific dynamic buoyant flow of smoke and heat intensity in a
controlled manner and for assessing the performance of smoke
management system, smoke control system and smoke extraction
system with the given building geometry. Hot smoke test shall follow
FSD Circular Letter No. 2/2002, Australian Standard AS 4391-1999
"Smoke Management System Hot Smoke Test" or approved
international standards and practices and to the satisfaction of the FSD
and the PBSE. The Contractor shall obtain comments from the FSD and
all relevant parties on the detailed requirements and arrangement for the
hot smoke test at early stage of the Contract.

The Contractor shall provide all materials, equipment, facilities, fuels,


manpower and the like for hot smoke test. The Contractor shall co-
ordinate and arrange with the Building Contractor to provide all
necessary temporary protection to the building finishes, parts, fixtures,
furniture and other building works during the test. The Contractor shall
submit the details of such requirements to the Building Contractor in
good times before the test and to the PBSE for approval. The Contractor
shall supply and install all necessary protections and allow all
appropriate provisions to other parts of the building not covered by the
Building Contractor so as not to cause any damage, and to keep any
disturbance to the possible minimum to any occupants or services during
hot smoke test. The Contractor shall co-ordinate with the Building
Contractor and the FSD and shall propose a suitable location and a
suitable fire size to the approval of the FSD for carrying out the hot
smoke test. The Contractor shall carry out a risk assessment of the hot
smoke test and allow adequate protection and provisions for the risk.
The Contractor shall employ a standby fire fighting team during hot
smoke test for the purpose of fire safety. The Contractor shall deem to
allow all necessary insurance coverage for the hot smoke test when such
or any part of it is not covered under the general insurance policy of the
Building Contractor for the Site.

The Contractor shall arrange and co-ordinate with relevant parties in


carrying out the hot smoke test. The Contractor shall employ a qualified
professional engineer to arrange the details and co-ordinate the hot
smoke test. The engineer employed shall be a Registered Professional
Engineer in Hong Kong under CAP 409 in building services or
mechanical discipline or equivalent approved professional qualification.

Where hot smoke test indicates deficiency in smoke management


system, smoke control system, smoke extraction system and the like
included in the Works, the Contractor shall rectify them to the
satisfaction of the FSD and the PBSE at no additional cost. Where the
smoke management system is not included in the Works, the Contractor
shall report the deficiency to the PBSE and propose improvement
measures. The Contractor shall submit a detailed test report at the end
of the test that shall include all the recommendations and improvement

FS_TCP
Page 10 of 11 2007 Edition
measures.

Details of the hot smoke test requirement shall refer to the Fire Service
General Specification and FSDCoP.

4.7 TESTS ON OTHER FIRE SERVICE INSTALLATIONS

Tests on fire service installations other than those listed hereinabove


shall be in accordance with the FSDCoP and FSD Requirements and
Circular Letters, and the approved detailed testing and commissioning
procedures proposed by the Contractor and approved by the PBSE. The
Contractor shall propose and submit detailed testing and commissioning
procedures for all fire service installations for approval by the PBSE
where such details of testing and commissioning are not available in
EE_TC, FSDCoP and this procedure e.g. pressurization of staircases
system, smoke extraction system etc. The detailed testing and
commissioning procedures submitted shall be comprehensive and
sufficient to demonstrate the functioning and performance of all the
systems and equipment.

5.0 Statutory Inspection/Commissioning and Inspection by the Authority

5.1 After the proper testing and commissioning of the Fire Service
Installation, the Contractor shall notify the appropriate Authority,
through the PBSE, on the completion of the installation and its readiness
for inspection and testing. The Contractor shall arrange all necessary
inspections and tests as required by the Authority.

5.2 Before notifying the appropriate Authority for inspection, the Contractor
shall arrange a mock up inspection and test with the PBSE/PBSI to
demonstrate the readiness of the fire service installation for statutory
inspection. The mock up test shall be a full inspection test same as the
statutory inspection to be conducted for appropriate Authority. The
Contractor shall prepare and make ready all documents required for
statutory inspection that will be examined during the mock up inspection
and statutory inspection.

Further mock-up test(s) shall be required if the installation fails to meet


with the satisfaction of the PBSE/PBSI in the test. The Contractor shall
not arrange inspection with the Authority till the satisfactory acceptance
of the mock-up inspection and test by the PBSE/PBSI.

6. Calibrated Equipment

The Contractor shall supply calibrated equipment as stipulated in the Particular


Specification of the Contract for the inspection, measuring and testing of the
installation. Certified true copy of calibration certificates shall be submitted.

FS_TCP
Page 11 of 11 2007 Edition
Annex A
Testing and Commissioning Certificate
on Fire Service Installation

Part 1 : Details of Project

1.1 Project title (with location) :

1.2 *P.W.P. / Project No. :

1.3 *Contract/sub-contract/Quotation No. :

1.4 *Contractor/Sub-Contractor :

1.5 FSD Ref. :

1.6 PBSE :

1.7 PBSI :

Part 2 : Declaration

2.1 I certify that the Fire Service Installation as specified in the


*Contract/Sub-contract/Quotation at the above location has been
inspected, tested and commissioned in accordance with this procedure
*and/or any other procedures agreed between the PBSE and the
Contractor. The results are satisfactory in the aspects as mentioned in
Part 3 and/or as recorded in Part 4 of this Certificate, except as
indicated in the COMMENTS items.
2.2 I also certify that site tests have been performed in accordance with the
requirements set out in Annex A of this procedure and that the results
are satisfactory. A record of the tests has been prepared and submitted
to the PBSE.

(Name of Contractors Signature - Post :


Representative)
Tel. No. :
( ) Date :
(Designation of Contractors Signature - Post :
Representative)
Tel. No. :
( ) Date :
(Name and Stamp of Signature - Post :
Contractor)
Tel. No. :
( ) Date :
Note : 1. This certificate must be signed by a person authorized by the
Firm/Company.
2. The person(s) authorized by the Firm/Company to sign part 2, 3 and 4
shall possess the relevant qualifications required by the Particular
Specification and Fire Service General Specification.
3. The Contractors Representative signing part 3 and part 4 shall be the
Commissioning Engineer in Charge of the Firm/Company who witness the
test, or the same person in part 2 who witnessed the test.
* Delete if not applicable

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 1 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

Part 3 : Items Inspected and Tested


3.1 Hydrant and Hose Reel System

Type of Building: *Domestic/Industrial/ Godown/


Others

3.1.1 F.S.I. Drawings Against Building Plans

3.1.1.1 Check nos. and locations of:

a) Fire service inlets *Yes/No/N.A. *Yes/No/N.A.

b) Fire hydrants and hose reels *Yes/No/N.A. *Yes/No/N.A.

c) Fixed fire pumps *Yes/No/N.A. *Yes/No/N.A.

d) Intermediate booster pumps *Yes/No/N.A. *Yes/No/N.A.

e) Water tank and capacity *Yes/No/N.A. *Yes/No/N.A.

3.1.2 Plumbing Line Diagram

3.1.2.1 Check:

a) Pipings are suitably connected to the fire pumps, fire *Yes/No/N.A. *Yes/No/N.A.
hydrants, hose reels and fire service inlets.

b) Size of the rising mains are correct. *Yes/No/N.A. *Yes/No/N.A.

c) Size of the inter-connection header pipe(s) for fire service *Yes/No/N.A. *Yes/No/N.A.
inlets is correct.

d) By-pass pipings for intermediate booster pumps. *Yes/No/N.A. *Yes/No/N.A.

e) F.S. appliance to be provided by F.S.D. to test the system. *Yes/No/N.A. *Yes/No/N.A.


(to be confirmed by F.S.D.)

3.1.3 Visual Inspection

3.1.3.1 Water Supply

a) Is an independent town main connection provided for the *Yes/No/N.A. *Yes/No/N.A.


FH/HR installation alone?

b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 2 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

c) Are the effective water capacity correct of the :

(i) Supply tank? *Yes/No/N.A. *Yes/No/N.A.


(ii) Transfer tank? *Yes/No/N.A. *Yes/No/N.A.

d) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.

e) Does the size of the water pump suction water pipe from *Yes/No/N.A. *Yes/No/N.A.
the tank match the size of the pump suction inlet?

f) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


suction pipe from supply tank?

g) Are levels of suction pipes correct? *Yes/No/N.A. *Yes/No/N.A.

h) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?

i) Are water pumps permanently primed? *Yes/No/N.A. *Yes/No/N.A.

j) Is anti-overheating circulating pipe provided? *Yes/No/N.A. *Yes/No/N.A.

k) Is vertex inhibitor provided and clear of debris? *Yes/No/N.A. *Yes/No/N.A.

l) Has the Fire Service Completion Advice issued? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 3 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.3.2 Pipework

a) Are water pipes up to 150 mm dia. to BS 1387 / ISO 65 *Yes/No/N.A. *Yes/No/N.A.


medium grade or other approved type?

b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?

c) Are U/G water pipes to BS EN 545 Class K12 or to BS *Yes/No/N.A. *Yes/No/N.A.


1387 / ISO 65 heavy grade or other approved type?

d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?

e) Are water pipes up to 65 mm dia. Provided with screw *Yes/No/N.A. *Yes/No/N.A.


joints?

f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?

g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?

h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?

i) Are water pipes provided with adequate disconnecting *Yes/No/N.A. *Yes/No/N.A.


flanges, mechanical pipe couplings or screwed unions for
future ease of dismantling?

j) Are pipes suitably connected to the fire pumps, *Yes/No/N.A. *Yes/No/N.A.


hydrants, hose reels and fire service inlets?

k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?

l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?

m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 4 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?

o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?

p) Are adequate clearances provided between pipe and *Yes/No/N.A. *Yes/No/N.A.


sleeve?

q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish

r) Are pipes installed without being embedded in concrete *Yes/No/N.A. *Yes/No/N.A.


structure?

s) Are adequate pipe hangers and supports provided as *Yes/No/N.A. *Yes/No/N.A.


required? (G.S. Clause B1.9)

t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?

u) Are expansion pipe joints provided at location through *Yes/No/N.A. *Yes/No/N.A.


building expansion joint?

v) Are strainers in water pipes cleaned? *Yes/No/N.A. *Yes/No/N.A.

w) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.

x) Are valves closed at clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.

y) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?

z) Are by-pass pipings provided for intermediate booster *Yes/No/N.A. *Yes/No/N.A.


pumps?

aa) Are pressure gauges of correct Specification (G.S. *Yes/No/N.A. *Yes/No/N.A.


Clause B1.15)?

ab) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.

ac) Are sprinkler heads provided at top of refuse chutes? *Yes/No/N.A. *Yes/No/N.A.

ad) Do water pipe sizes tally with drawings? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 5 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

ae) Are equipotential earth bondings provided for all *Yes/No/N.A. *Yes/No/N.A.
sections of the pipeworks?

3.1.3.3 Hydrant

a) Do the layouts of the hydrant tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?

b) Are outlets of male round thread? *Yes/No/N.A. *Yes/No/N.A.

c) Are outlets of female instantaneous? *Yes/No/N.A. *Yes/No/N.A.

d) Are outlets adaptable to F.S.D equipment? *Yes/No/N.A. *Yes/No/N.A.

e) Are adequate clearances provided around the hydrant *Yes/No/N.A. *Yes/No/N.A.


outlet and valve for the free use of the hydrant?

f) Are the hydrant outlets between 800 mm and 1200 mm *Yes/No/N.A. *Yes/No/N.A.
above finished floor level?

g) Is the outlet not obstructing any door opening, or any *Yes/No/N.A. *Yes/No/N.A.
existing route?

h) Are the hydrants at positions without being concealed by *Yes/No/N.A. *Yes/No/N.A.


adjacent opened doors?

i) Are the hydrant valves individually controlled by wheel *Yes/No/N.A. *Yes/No/N.A.


operated screw valve designed to open in counter-
clockwise direction?
j) Is the direction of opening engraved in both English and *Yes/No/N.A. *Yes/No/N.A.
Chinese on the wheel of the valve?

k) Are the hydrant outlet provided with bronze caps *Yes/No/N.A. *Yes/No/N.A.
complete with chains?

l) Is water fed by gravity? *Yes/No/N.A. *Yes/No/N.A.

m) Is water fed by fixed fire pump? *Yes/No/N.A. *Yes/No/N.A.

3.1.3.4 Hose Reel

a) Do the layouts of the hose reels tally with the latest *Yes/No/N.A. *Yes/No/N.A.
approved building plans?

b) Is the length of the tubing not exceeding 30 m? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 6 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

c) Is the internal bore of tubing not less than 19mm in *Yes/No/N.A. *Yes/No/N.A.
diameter?
d) Is the hose reel drum not less than 150mm in diameter? *Yes/No/N.A. *Yes/No/N.A.

e) Is nozzle fitted with simple two-way on/off valve and the *Yes/No/N.A. *Yes/No/N.A.
valve is not spring loaded?

f) Are the control valves of gate type or of simple two-way *Yes/No/N.A. *Yes/No/N.A.
ball type?

g) Are the gates valves are closed by clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.

h) Are the rising mains and associated pipework not less *Yes/No/N.A. *Yes/No/N.A.
than 40mm nominal bore?

i) Are the pipes feeding individual hose reel are not less *Yes/No/N.A. *Yes/No/N.A.
than 25mm nominal bore.

j) Are the doors of the hose reel cabinets or recesses *Yes/No/N.A. *Yes/No/N.A.
provided without any locks?

k) Are manual fire alarm call points sited at a prominent *Yes/No/N.A. *Yes/No/N.A.
position near to the hose reels?

l) Are the doors clearly bear FIRE HOSE REEL( *Yes/No/N.A. *Yes/No/N.A.
) with characters of at least 50 mm high?

m) Are operation instruction notices (BSB Standard *Yes/No/N.A. *Yes/No/N.A.


Drawing) provided for and adjacent to each of the hose
reels?

n) Are the operation instruction notices fixed immediately *Yes/No/N.A. *Yes/No/N.A.


below the words FIRE HOSE REEL on the outer
surface of the doors?

o) Is the notice clearly marked with the standard wordings *Yes/No/N.A. *Yes/No/N.A.
in English and Chinese characters of at least 5mm high
in red letters on white background or vice versa?

p) Can every part of the building be reached by a nozzle? *Yes/No/N.A. *Yes/No/N.A.

q) Is the nozzle capable of projecting a 6-metre jet? *Yes/No/N.A. *Yes/No/N.A.

r) Are the control valves sited adjacent to the nozzles? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 7 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

s) Is the orifice of nozzle 4.5 mm? *Yes/No/N.A. *Yes/No/N.A.

t) Is the nozzle fitted with simple two-way on/off valve and *Yes/No/N.A. *Yes/No/N.A.
closed by clockwise rotation?

u) Are the control valves and nozzles 1350 mm or less *Yes/No/N.A. *Yes/No/N.A.
above finished floor level, and for a recessed type hose
reel not more than 500 mm from the surface of the wall?

v) Are control valves and nozzles sited in a discernible and *Yes/No/N.A. *Yes/No/N.A.
accessible position of not more than 500 mm from the
surface of the doors?

w) Are guide rings provided for fixed type hose reel? *Yes/No/N.A. *Yes/No/N.A.

x) Is suitable guide ring provided to permit easy withdrawal *Yes/No/N.A. *Yes/No/N.A.


of the hose reel tubing?

y)) Are hose reels of swinging cradle type? *Yes/No/N.A. *Yes/No/N.A.

z) Can the cradle be swung freely into the corridor or *Yes/No/N.A. *Yes/No/N.A.
passage when required?

aa) Are the tubing of the hose reels properly wound round *Yes/No/N.A. *Yes/No/N.A.
the drum without kinking?

ab) Are the outer face of the hose reels flush with the wall *Yes/No/N.A. *Yes/No/N.A.
when the reels are not in use?

ac) Are the jet nozzles unbroken and installed? *Yes/No/N.A. *Yes/No/N.A.

ad) Are the guide bracket unbroken and installed? *Yes/No/N.A. *Yes/No/N.A.

ae) Are strikers provided inside the cabinets? *Yes/No/N.A. *Yes/No/N.A.

af) Are the manual fire alarm call points not more than *Yes/No/N.A. *Yes/No/N.A.
1200 mm above the finished floor level?

ag) Upon actuation of any manual fire alarm call point in the *Yes/No/N.A. *Yes/No/N.A.
building, shall the fixed fire pump come into operation
regardless of the zoning of the fire alarm call point?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 8 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

ah) Door fitted to the hose reel cabinet.

i) Do such doors cause no undue obstruction and no *Yes/No/N.A. *Yes/No/N.A.


interference with any exit point when in open position?

ii) Do such doors cause no obstruction to the hose being *Yes/No/N.A. *Yes/No/N.A.
run out in either directions.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 9 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.3.5 Rising Mains

a) Are air relief valves provided for rising mains? *Yes/No/N.A. *Yes/No/N.A.

b) Are draining facilities provided at the lowest points of *Yes/No/N.A. *Yes/No/N.A.


rising mains?

c) Are the rising mains interconnected by header pipes of *Yes/No/N.A. *Yes/No/N.A.


correct sizes? (Industrial/Godown not less than 150
mm, Others not less than 100 mm)

d) Are the rising mains of the correct sizes? *Yes/No/N.A. *Yes/No/N.A.


(Industrial/Godown not less than 100 mm, Others not
less than 80 mm)

e) Are the rising main supply the correct number of hydrant *Yes/No/N.A. *Yes/No/N.A.
outlets (2 outlets per floor for industrial/godown and 1
outlet per floor for other buildings)?

f) Is each rising main provided with an independent F.S. *Yes/No/N.A. *Yes/No/N.A.


inlet?

g) Are rising and down-coming mains permanently *Yes/No/N.A. *Yes/No/N.A.


primed?

h) Is there any provision of by-pass for intermediate booster *Yes/No/N.A. *Yes/No/N.A.


pump?

j) Is/Are the Header pipe(s) provided to connect the fire *Yes/No/N.A. *Yes/No/N.A.
service inlets to the rising mains?

k) For godown/industrial buildings, is the rising main *Yes/No/N.A. *Yes/No/N.A.


provided for each staircase with a fire service inlet?

l) Are the number and location of fire service inlets *Yes/No/N.A. *Yes/No/N.A.
conforming to latest approved building plan?

h) Are suitable air relief valve provided? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 10 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.1.3.6 Fire Pump

a) Pump/Motor Set Data :

Fixed Fire Pump Intermediate Pump Transfer Pump Jockey Pump

Duty Standby Duty Standby Duty Standby

Location

Quantity (No(s).)

Pump
Manufacturer
Motor

Pump
Model No.
Motor

Pump
Serial
Motor

Motor Power (kW)

Pump Power (kW)

Flow rate (L/s)

Pressure (kPa)

Starting method

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 11 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

b) Is electricity used for driving the pump? If no, please *Yes/No/N.A. *Yes/No/N.A.
specify.

c) Is jockey pump provided for up fed system (water tank at *Yes/No/N.A. *Yes/No/N.A.
low level)?

d) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guards?

e) Is the standby pump energized within 15 second upon *Yes/No/N.A. *Yes/No/N.A.


failure of the duty pump?

f) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power for the rated flow of the
system?

g) Are emergency lock-off buttons provided adjacent to *Yes/No/N.A. *Yes/No/N.A.


pump motors with visual and audible indication on the
panel when the pump is locked?

h) Are pump motors protected by HRC fuses? *Yes/No/N.A. *Yes/No/N.A.

i) Is secondary power supply provided for electric pumps? *Yes/No/N.A. *Yes/No/N.A.

j) If no, is r diesel engine driven standby pump provided ? *Yes/No/N.A. *Yes/No/N.A.

k) Are doors to pump rooms clearly labelled FIXED FIRE *Yes/No/N.A. *Yes/No/N.A.
PUMP ( ) *and/or INTERMEDIATE
BOOSTER PUMP ()?

l) Are doors to pump rooms provided with locking *Yes/No/N.A. *Yes/No/N.A.


devices?

m) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?

n) Are pump rooms laid clear of any exit or normal *Yes/No/N.A. *Yes/No/N.A.
communication routes through the premises?

o) Are start/stop buttons, pump running indicating lights *Yes/No/N.A. *Yes/No/N.A.


and audible alarms for the intermediate booster pumps
provided near the F.S. Inlets?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 12 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

p) Are the above switches clearly labelled *Yes/No/N.A. *Yes/No/N.A.


INTERMEDIATE BOOSTER PUMP SWITCH (
)?

q) Are pump rooms clear of debris? *Yes/No/N.A. *Yes/No/N.A.

r) Are alternative means of starting the pump manually, in *Yes/No/N.A. *Yes/No/N.A.


addition to manual fire alarm call points provided, where
the pump is not electrically operated?
s) Are starting instructions for diesel driven pump *Yes/No/N.A. *Yes/No/N.A.
prominently displayed in the pump room?

t) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control installed near the pump, rather than by any
automatic means?

u) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?

v) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.

w) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?

x) Are pumps permanently primed? *Yes/No/N.A. *Yes/No/N.A.

y) Are non-return valve(s) provided to prevent water *Yes/No/N.A. *Yes/No/N.A.


backflow into the water tank?

z) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?

aa) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?

ab) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?

ac) Are pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?

ag) Are the pumps enclosures suitably locked to prevent *Yes/No/N.A. *Yes/No/N.A.
unauthorized tampering of the pumps?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 13 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

ah) Are the running and static pressure at any hydrant outlet *Yes/No/N.A. *Yes/No/N.A.
not exceeding 850Kpa?

3.1.3.7 Intermediate booster pump

a) Height between the topmost hydrant and the lowest F.S. ____________ _____________
inlet (m):

b) No. of rising main: ____________ _____________

c) Required aggregate flow (l/min): ____________ _____________

d) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.

e) Is the standby pump energized within 15 seconds upon *Yes/No/N.A. *Yes/No/N.A.


failure of the duty pump?

f) Is a intermediate booster pump set provided consisting of *Yes/No/N.A. *Yes/No/N.A.


duty and standby to feed all rising mains in the same
system?

g) Are two/three pumps of same capacity provided using *Yes/No/N.A. *Yes/No/N.A.


sequential starting as duty pumps with one standby to
achieve required flow and pressure within 30 seconds?

h) Are the motors driving the pumps rated to give 20% *Yes/No/N.A. *Yes/No/N.A.
more power in addition to the hydraulic power required
for the rated flow?

i) Are all pumps permanently primed and electrically *Yes/No/N.A. *Yes/No/N.A.


driven?

j) Does the pump continue to run irrespective of power *Yes/No/N.A. *Yes/No/N.A.


interruption when start button is activated?

k) Are the Start/stop push buttons with pump running *Yes/No/N.A. *Yes/No/N.A.
indication light and buzzer provided adjacent to the fire
service inlet?

l) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panels in
the pump enclosures.

m) Are such signals repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 14 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

n) Are all fire pumps housed in suitable enclosures and *Yes/No/N.A. *Yes/No/N.A.
designed solely for accommodating pumps for fire
service installations?

o) Are the pump enclosures suitably locked and laid clear *Yes/No/N.A. *Yes/No/N.A.
of any exit or normal communication routes through the
premises?

p) Are the pump enclosures clearly marked in English and *Yes/No/N.A. *Yes/No/N.A.
Chinese characters?

q) Is the intermediate booster pump utilized as the fixed fire *Yes/No/N.A. *Yes/No/N.A.
pump?

r) Is flow rate and pressure tested in accordance with *Yes/No/N.A. *Yes/No/N.A.


t . ................................................... in fire pump
schematic drawing submission to FSD.

aa) Floor level of tested hydrant: ____________ _____________

ii) Flow (l/min): ____________ _____________

iii) Pressure (Kpa): ____________ _____________

s) Do the running and static pressure at any hydrant outlet *Yes/No/N.A. *Yes/No/N.A.
not exceeding 850 Kpa?

z) Are two/three intermediate booster pumps of same *Yes/No/N.A. *Yes/No/N.A.


capacity provided using sequential starting as duty
pumps with one standby to achieve required flow and
pressure within 30 seconds?

aa) Do the immediate booster pumps continue to run *Yes/No/N.A. *Yes/No/N.A.


irrespective of power interruption when start button is
activated?

ab) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 15 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.3.8 Fire Service Inlet

a) Are the fire service inlet couplings between 600 mm and *Yes/No/N.A. *Yes/No/N.A.
1000 mm above finished floor level?

b) Are the fire service inlets suitably enclosed and *Yes/No/N.A. *Yes/No/N.A.
protected?
l
c) Are the fire service inlets readily accessible by Fire *Yes/No/N.A. *Yes/No/N.A.
Services personnel?

b) Is a non-return valve provided for each inlet? *Yes/No/N.A. *Yes/No/N.A.

c) Are the fire service inlet enclosures clearly and *Yes/No/N.A. *Yes/No/N.A.
permanently labelled F.S. INLET () with
characters at least 50 mm high?

d) Is each inlet affixed with a metal identification plate *Yes/No/N.A. *Yes/No/N.A.


raised on engraved with English and Chinese characters?

3.1.3.9 Miscellaneous

a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?

b) Are proper identification provided for pipeworks, *Yes/No/N.A. *Yes/No/N.A.


wirings and equipment?

c) Are water tanks clear of debris? *Yes/No/N.A. *Yes/No/N.A.

d) Is permanent water supply connected? *Yes/No/N.A. *Yes/No/N.A.

e) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

f) Is emergency electricity supply available? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 16 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.4 Testing and Commissioning

3.1.4.1 Pipeworks

a) Are hydraulic tests performed satisfactorily for water *Yes/No/N.A. *Yes/No/N.A.


tightness of all sections of the pipeworks? (At 1.5 times
highest working pressure or above for 15 minutes, and
for hydrant mains minimum 1700 kPa for 15 minutes)
(Test records on Part 4.1 Table 1)

b) Is flushing out of all water pipes performed? *Yes/No/N.A. *Yes/No/N.A.

c) Is flushing out of all hose reel tubing performed? *Yes/No/N.A. *Yes/No/N.A.

d) Do the automatic air release valves function properly? *Yes/No/N.A. *Yes/No/N.A.

e) Do the pressure reducing valve sets function properly? *Yes/No/N.A. *Yes/No/N.A.


(Test records on Part 4.1 Table 2)

f) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?

3.1.4.2 Electrical Wiring

a) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T&C procedure No. 2 for Electrical
Installation and to Electricity Ordinance requirements?

b) Does the battery charger function properly? *Yes/No/N.A. *Yes/No/N.A.

c) Is the telephone link connected and functioning? *Yes/No/N.A. *Yes/No/N.A.

3.1.4.3 Water Pump

a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.1 Table 3)

b) Do the water pumps run at an acceptable noise and *Yes/No/N.A. *Yes/No/N.A.


vibration levels?

c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?

d) Do the water pump protective devices function properly? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 17 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

e) Do the fixed fire pumps come into operation upon *Yes/No/N.A. *Yes/No/N.A.
actuation of any manual fire alarm call point, regardless
of the zoning of the fire alarm call point?

f) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the water pumps function properly?

g) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?

h) Are the temperatures of the water pump bearings *Yes/No/N.A. *Yes/No/N.A.


satisfactorily at running condition?

i) Are the temperatures of the pump motors satisfactorily at *Yes/No/N.A. *Yes/No/N.A.


running condition?

j) Do the pressure gauges function properly? *Yes/No/N.A. *Yes/No/N.A.

k) Is water leakage from the pump shafts at an acceptable *Yes/No/N.A. *Yes/No/N.A.


level?

l) Do the non-return valves function properly? *Yes/No/N.A. *Yes/No/N.A.

m) Does the pressure relief valve of the anti-overheating *Yes/No/N.A. *Yes/No/N.A.


circulating pipe function properly? (Operate at _______
bars)

n) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly? (Test records on Part
4.1 Table 4)

o) Does the change-over from duty to standby pump *Yes/No/N.A. *Yes/No/N.A.


complete within 15 seconds? (charge-over in _________
sec.)

3.1.4.4 Fire Service Inlet

a) Do the non-return valves of the F.S. inlets function *Yes/No/N.A. *Yes/No/N.A.


properly?

b) Do the stop/start buttons, indicating lights and audible *Yes/No/N.A. *Yes/No/N.A.


alarms for the intermediate booster pumps function
properly?

c) Do the drain valves function properly? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 18 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.4.5 Hose reel

a) Can the hose reel tubing be drawn out freely and easily *Yes/No/N.A. *Yes/No/N.A.
in any direction without obstruction?

b) Are the hose reels capable to cover within 6 m of each *Yes/No/N.A. *Yes/No/N.A.
part of the occupied area? (Test Records on Part 4.1
Table 5)

c) Are the hose reels capable to project a water jet of 6 m or *Yes/No/N.A. *Yes/No/N.A.
greater and min. flow of 24 L/min? (Test Records on
Part 4.1 Table 5)

d) Is the water tightness of the stop valves, nozzles, and *Yes/No/N.A. *Yes/No/N.A.
tubing connections satisfactory when the water pump is
running?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 19 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.1.4.6 Hydrant

a) Is the water tightness of the hydrant outlet satisfactory *Yes/No/N.A. *Yes/No/N.A.


when the water pump is running?

b) Do the flow capacity and pressure test satisfy Fire Services *Yes/No/N.A. *Yes/No/N.A.
Departments requirements as the following Table? (Test
records on Part 4.1 Tables 6 and 7)

Building Type Running Pressure (kPa) Static Pressure No. of hydrant Minimum
(kPa) outlet operating aggregate Flow
Rate (L/min)
Minimum Maximum

Industrial 350 850 3 1350

All other types 350 850 2 900

Note : Each hydrant outlet shall have a flow of 450 L/min at a running pressure of not less than 350 kPa.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 20 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.2 Automatic Sprinkler System

3.2.1 Visual Inspection

3.2.1.1 Water Supplies

a) Is an independent town main connection provided for the *Yes/No/N.A. *Yes/No/N.A.


sprinkler system installation alone?

b) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the sprinkler tank tally with the vertical
plumbing diagram approved by W.S.D.?

c) Is the effective water capacity correct of the :

(i) Sprinkler tank? *Yes/No/N.A. *Yes/No/N.A.


(ii) Transfer tank? *Yes/No/N.A. *Yes/No/N.A.
(iii) Priming tank? *Yes/No/N.A. *Yes/No/N.A.

d) Is water depth indicator provided for the sprinkler tank *Yes/No/N.A. *Yes/No/N.A.
which is used as a gravity tank?

e) Are the ball valves of the water tank readily accessible? *Yes/No/N.A. *Yes/No/N.A.

Size of Pump Suction

Pump Suction Pipe Size (dia. mm)

LH OH(I) OH(II) OH(III) OH(III S)

Positive Head (1) 65 150 150 200 200

Suction Lift (2) 80 150 150 200 200

Note: (1) Positive head - water capacity between pump centre line and the lowest effective water
level of tank not exceeding one-third total capacity.

(2) Suction lift - vertical height between pump centre line and the lowest effective water
level of tank not exceeding 3.7 m.

(3) Automatic priming arrangement is required for suction lift condition.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 21 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

f) Are the sizes of the water pump suction water pipes *Yes/No/N.A. *Yes/No/N.A.
correct as the following Table?

g) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


suction pipe?

h) Are levels of suction pipes correct? *Yes/No/N.A. *Yes/No/N.A.

i) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?

j) Are automatic priming arrangements provided for *Yes/No/N.A. *Yes/No/N.A.


suction lift condition?

k) Are sizes of priming water pipes correct ? (LH - 25 mm, *Yes/No/N.A. *Yes/No/N.A.
OH and HH -50 mm)

l) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


priming tank?

m) Is anti-overheating circulating pipe provided? *Yes/No/N.A. *Yes/No/N.A.

n) Is vertex inhibitor provided and clear of debris? *Yes/No/N.A. *Yes/No/N.A.

o) Are strainers in water tank cleaned? *Yes/No/N.A. *Yes/No/N.A.

p) Is the tank clear of debris? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 22 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.2.1.2 Spacing and Location of Sprinklers

LH OH HH L.P.C. Rules/Remarks

Max. area Sidewall 17 m2 9 m2 Clause 26.1


Coverage per Table 70 & 71,
Sprinkler Others 21 m2 12 m2 9 m2 Fig. 38

Special area 9 m2 9 m2

Max. distance Sidewall 4.6 m 3.7/3.4 m Table 71, Fig. 39


Between
Sprinkler Others 4.6 m 4m 3.7 m Table 70, 72 & 73,
Fig. 40 to 46
Special area 3.7/3.0 m 3m

Staggered 4.6/4 m Table 70 , Fig. 38

Min. distance between sprinklers 2m 2m 2m Clause 26.2

Max. distance from wall/partition 2.3 m 2m 2m Clause 26.3,


(standard) Table 74 & 75, Fig. 38

Max. distance from open face of 1.5 m 1.5 m 1.5 m Clause 26.3.1.1
building
150/
Max. distance below combustible/ 300/ 300/ 300/ Clause 26.5.1.1,
incombustible ceiling/roof 450 mm 450 mm 450 mm Table 76

Min. distance to & max. distance Clause 26.5.1.2 &


above beams 26.5.1.3,
Table 77 & 78, Fig. 47

Max. distance from column 0.6 m 0.6 m 0.6 m Clause 26.5.2.1 & 26.5.2.2

Clear min. space below 0.5/0.8 m 0.5/0.8 m 0.3/1.0 m Clause 26.4

Max. depth of ceiling void without 0.8 m 0.8 m 0.8 m Clause 26.6 & TB11
sprinkler

Max. width of Rectangular 0.8/#1m 0.8/#1m 0.8/#1m Clause 26.8.3


Obstruction #with at least 150 mm
Below sprinkler clearance from adjacent
Circular 1/#1.2 m 1/#1.2 m 1/#1.2 m wall

Max. extent of canopy from 2.3 m 2.3 m 2.3 m Clause 4.2.2.2 (b)
building without sprinkler

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 23 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

a) Are spacing and location of sprinkler heads in


accordance with L.P.C. Rules regarding :

(i) Area of coverage? *Yes/No/N.A. *Yes/No/N.A.

(ii) Maximum distance between sprinklers? *Yes/No/N.A. *Yes/No/N.A.

(iii) Minimum distance between sprinklers? *Yes/No/N.A. *Yes/No/N.A.

(iv) Distance from wall/partition? *Yes/No/N.A. *Yes/No/N.A.

(v) Distance from open face of building? *Yes/No/N.A. *Yes/No/N.A.

(vi) Distance from beam? *Yes/No/N.A. *Yes/No/N.A.

(vii) Distance from column? *Yes/No/N.A. *Yes/No/N.A.

(viii) Clear space below sprinklers? *Yes/No/N.A. *Yes/No/N.A.

(ix) Depth of ceiling void? *Yes/No/N.A. *Yes/No/N.A.

(x) Obstruction below sprinklers? *Yes/No/N.A. *Yes/No/N.A.

(xi) Canopy? *Yes/No/N.A. *Yes/No/N.A.

(xii) Are construction of open ceiling spacing and location *Yes/No/N.A. *Yes/No/N.A.
of sprinkler heads in accordance with L.P.C. Rules as
the following Table and regarding :

Requirements of Open Ceiling (LH and OH Only) (See L.P.C. Rules Clause 26.8.2.2)

Min. open area 70%

Min. open area with suspended fittings & services 60%

Min. dimensions of opening (shall not be smaller than vertical thickness of ceiling) 25 mm

Max. distance between sprinklers 3m

Max. area of coverage per sprinkler 9 m2

Min. vertical separation between sprinklers and suspended ceiling 800 mm

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 24 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

1) Open area of ceiling? *Yes/No/N.A. *Yes/No/N.A.

2) Dimensions of opening? *Yes/No/N.A. *Yes/No/N.A.

3) Distance of sprinklers? *Yes/No/N.A. *Yes/No/N.A.

4) Area of coverage? *Yes/No/N.A. *Yes/No/N.A.

5) Vertical separation between sprinklers and *Yes/No/N.A. *Yes/No/N.A.


ceiling?

3.2.1.3 Sprinkler Heads

a) Are sprinklers clean from contamination by paint, etc.? *Yes/No/N.A. *Yes/No/N.A.

b) Are sprinklers of correct orifice sizes? (LH - 10 mm, OH *Yes/No/N.A. *Yes/No/N.A.


- 15 mm and HH - 15 or 20 mm)

c) Are sprinklers of correct temperature ratings? (68oC red *Yes/No/N.A. *Yes/No/N.A.


bulb for normal use, 93oC for heated rooms)

d) Are replacement sprinklers provided and completed with *Yes/No/N.A. *Yes/No/N.A.


cabinets? (LH - 6 Nos., OH - 24 Nos. & HH - 36 Nos.
For more than 2 installations, added 50% to the figures.)

e) Is sprinkler spanner provided and kept in sprinkler *Yes/No/N.A. *Yes/No/N.A.


cabinet?

f) Are sprinkler guards provided at locations where the *Yes/No/N.A. *Yes/No/N.A.


sprinklers are liable to damage?

g) For LH and HH cases only, are sprinklers inside *Yes/No/N.A. *Yes/No/N.A.


concealed false ceiling space fed by separate branch
pipework from that feeding sprinklers for room space
below the ceiling?

h) Are the Nos. of sprinklers installed on the range and *Yes/No/N.A. *Yes/No/N.A.
distribution pipes in accordance with L.P.C. Rules as the
following Tables?

i) Are sprinkler heads installed in upright or pendant *Yes/No/N.A. *Yes/No/N.A.


position for Type 1 pre-action system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 25 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

j) Are sprinkler heads installed in upright position for Type *Yes/No/N.A. *Yes/No/N.A.
2 pre-action system?

k) Are sprinkler heads installed in upright position for dry *Yes/No/N.A. *Yes/No/N.A.
pipe system installations in cold room?

Maximum Number of Sprinklers allowed on Range and Distribution Pipes

Light Hazard

Pipe Size (dia. mm) Max. No. on Range Pipe only

20# 1

25 3

# - The maximum length of 20 mm pipe allowed is 8m including allowance for elbow.

Ordinary Hazard - Range Pipes

Pipe Size Max. No. of


Range Pipes (nominal dia. mm) Sprinklers
allowed on Range
Pipes

(a) Ranges at remote end of each distribution


pipe spur

(i) 2 end-side layouts 25 1


Last two ranges 32 2

(ii) 3 end-side layouts 25 2


Last three ranges 32 3

(iii) All other layouts 25 2


Last range 32 3
40 4
50 9

(b) All other ranges 25 3


32 4
40 6
50 9

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 26 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Ordinary Hazard - Distribution Pipes

Distribution Pipes Pipe Size Max. No. of Sprinklers to be


(nominal dia. mm) fed by Distribution Pipe

Pipes at extremities of system

(i) 2 end-side layouts 32 2


40 4
50 8
65 16

(ii) All other layouts 32 3


40 6
50 9
65 18

Maximum Number of Sprinkler Heads for Preaction System

(i) Light-hazard installation 500 per installation


(ii) Ordinary-hazard installation 1000 per installation
(iii) High-hazard installation 1000 per installation

Maximum Number of Sprinkler Heads for Recycling System

FFor all installation 1000 per installation

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.2.1.4 Pipeworks

a) Are water pipes up to 150 mm dia. to BS 1387 / ISO 65 *Yes/No/N.A. *Yes/No/N.A.


medium grade or other approved type?

b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?

c) Are U/G water pipes to BS EN 545 Class K12 or to BS *Yes/No/N.A. *Yes/No/N.A.


1387 / ISO 65 heavy grade or other approved type?

d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?

e) Are water pipes up to 65 mm dia. provided with screw *Yes/No/N.A. *Yes/No/N.A.


joints?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 27 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?

g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?

h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?

i) Are water pipes provided with adequate disconnecting *Yes/No/N.A. *Yes/No/N.A.


flanges, mechanical pipe couplings or screwed unions for
future ease of dismantling?

j) Are pipes suitably connected to the sprinkler pumps, *Yes/No/N.A. *Yes/No/N.A.


sprinkler control valves and sprinkler inlets?

k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?

l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?

m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?

n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?

o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?

p) Are adequate clearances provided between pipe and *Yes/No/N.A. *Yes/No/N.A.


sleeve?

q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish

r) Are pipes installed without being embedded in concrete *Yes/No/N.A. *Yes/No/N.A.


structure?

s) Are adequate pipe hangers and supports provided as *Yes/No/N.A. *Yes/No/N.A.


required? (G.S. Clause B1.9)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 28 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?

u) Are expansion pipe joints provided at location through *Yes/No/N.A. *Yes/No/N.A.


building expansion joint?

v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.

w) Are valves closed at clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.

x) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?

y) Do water pipe sizes tally with drawings ? *Yes/No/N.A. *Yes/No/N.A.

z) Can all sections of water pipes be drained? *Yes/No/N.A. *Yes/No/N.A.

aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?
ab) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.
(min. for LH - 40 mm, OH and HH - 50 mm)

ac) Are the water pipes laid to the following minimum *Yes/No/N.A. *Yes/No/N.A.
slope?

(i) Wet pipe system : 2 mm to 1 m

(ii) All others system : for pipes of 40 mm and above


- 4 mm to 1 m

for pipes less than 40 mm


- 12 mm to 1 m

ad) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?

Pipework Size of Drain Pipe & Valve (minimum)

50 mm 20 mm
65 & 80 mm 32 mm
100 mm 50 mm

ae) Are pressure gauges of correct Specification ? (G.S. *Yes/No/N.A. *Yes/No/N.A.


Clause B1.15)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 29 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

af) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.

ag) Are strainers in water pipes cleaned? *Yes/No/N.A. *Yes/No/N.A.

ah) Are installation control valves in accordance with BSB *Yes/No/N.A. *Yes/No/N.A.
Standard Drawings?

ai) Are main stop valves secured at OPEN position by *Yes/No/N.A. *Yes/No/N.A.
padlock or riveted strap?

aj) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?

ak) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?

al) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?

am) Is the total length of water pipe between alarm valve and *Yes/No/N.A. *Yes/No/N.A.
alarm gong 25 m or less?

an) Is the water pipe between alarm valve and alarm gong of *Yes/No/N.A. *Yes/No/N.A.
correct size ? (6 m length - 15 mm dia, over 6 m length -
20 mm dia)

ao) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?

3.2.1.5 Dry Pipe Installation

a) Is the installation pressurized with air within the *Yes/No/N.A. *Yes/No/N.A.


pressure range recommended by the alarm valve
manufacturer and shall not exceed 400 kPa?

b) Is each installation served by an independent air supply *Yes/No/N.A. *Yes/No/N.A.


system?

c) For cold room application, do automatic means provided *Yes/No/N.A. *Yes/No/N.A.


to automatically shut down the air circulation fans when
the sprinkler system operates?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 30 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

d) Is air-supply pipework fitted with pressure relief valve, *Yes/No/N.A. *Yes/No/N.A.


non-return valve, stop valve (normally open), suitably
sized restrictor, and by-pass with stop valve (normally
strapped and padlocked closed)?

e) Is the air-supply pipework connected to the installation *Yes/No/N.A. *Yes/No/N.A.


above the normal priming water level of the dry alarm
valve?

f) Are air compressors equipped with automatic off-loading *Yes/No/N.A. *Yes/No/N.A.


devices to depressurize the compressor prior to start up?

g) Are air-supplies to sprinkler installations possessing a *Yes/No/N.A. *Yes/No/N.A.


cold store dried by passing through a suitable air dryer or
freezer?

h) Is the restrictor in the air-supply pipework correctly sized *Yes/No/N.A. *Yes/No/N.A.


to limit the mass flow of air from the air supply to the
installation, so as to avoid delay of water discharge from
the open sprinklers?

i) Is filter provided at the upstream of the non-return valve *Yes/No/N.A. *Yes/No/N.A.


and restrictor?

j) Are restrictors made from non-corrosive materials such *Yes/No/N.A. *Yes/No/N.A.


as austenitic stainless steel or copper alloy having
orifices with rounded edges?
k) Are distribution and range pipes of terminal range *Yes/No/N.A. *Yes/No/N.A.
configuration. (Gridded and looped configurations of
pipework are not allowed)?

l) Is a test facility provided at the end of the hydraulically *Yes/No/N.A. *Yes/No/N.A.


most remote range pipe on the installation, consisting of
a 32 mm nominal diameter pipe and quick-acting test
valve, with an outlet nozzle equivalent in size to the
smallest sprinkler in the installation?

m) Is the quick-acting test valve located in an easily *Yes/No/N.A. *Yes/No/N.A.


accessible position and secured in the closed position
with a suitable strap or chain?

n) Is the end of the test line capped or plugged? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 31 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

o) Does the sprinkler installation in the dry-pipe mode *Yes/No/N.A. *Yes/No/N.A.


comply with the following?:

(i) have an internal volume of air-filled pipe not


exceeding :

Light hazard 1.0 m3

Ordinary hazard 2.5 m3

High hazard 2.5 m3

Or

(ii) discharge water from the test facility within 60


seconds of opening the quick-acting test valve
when the installation is in the normal stand-by
condition.

3.2.1.6 Pre-action System

a) Is the sprinkler installation pipework charged with air *Yes/No/N.A. *Yes/No/N.A.


under pressure and monitored to give a warning
indication on reduction of the air pressure?

b) Does the pre-action system control panel incorporate the *Yes/No/N.A. *Yes/No/N.A.
necessary relays, timers, key types switches, alarm and
trouble lights essential to the operation of the system?
c) Does the control panel employ printed circuit boards for *Yes/No/N.A. *Yes/No/N.A.
the components and is completely factory wired and
ready for connection on site?

d) Are the pre-action control panel relays and circuitry *Yes/No/N.A. *Yes/No/N.A.
operating the pre-action alarm valve solenoid valves or
actuator mechanisms duplicated and wired such that no
single fault or failure shall render the installation
inoperable?

e) Is the fire detection system used to activate a pre-action *Yes/No/N.A. *Yes/No/N.A.


sprinkler system comply with FOC Rules for AFA
Installations where appropriate and the following?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 32 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(i) Each room or compartment protected by *Yes/No/N.A. *Yes/No/N.A.


sprinklers shall have sufficient fire detectors to
initiate release of the pre-action installation
without the operation of any detectors external to
the room or compartment or located within
equipment.

(ii) Fire detection systems employing coincidence *Yes/No/N.A. *Yes/No/N.A.


connection (requiring a response from two
detectors to initiate operation of the pre-action
alarm valve) may be used with Type 1 and Type
2 pre-action installations. (Consideration shall be
given to actuating the pre-action alarm valve on
operation of a single fire detector where fast-
developing fires may occur).

(iii) Any two detectors of a group of detectors which *Yes/No/N.A. *Yes/No/N.A.


may initiate the operation of the pre-action alarm
valve shall be separately connected to
independent wiring circuits.

3.2.1.7 Recycling System

a) Is the complete installation, including all equipment, *Yes/No/N.A. *Yes/No/N.A.


components and wiring, approved by LPCB and
accepted by the Fire Services Department (FSD)?

b) Is it supplied from a proprietary manufacturer *Yes/No/N.A. *Yes/No/N.A.


specialized in the manufacture of the system?

c) Are the major components of each recycling installation


consist of, but not limited to, the following :

(i) Recycling heat detector *Yes/No/N.A. *Yes/No/N.A.

(ii) Fire resisting detector cable *Yes/No/N.A. *Yes/No/N.A.

(iii) Control panel *Yes/No/N.A. *Yes/No/N.A.

(iv) Valve trim box *Yes/No/N.A. *Yes/No/N.A.

(v) Batteries and charger *Yes/No/N.A. *Yes/No/N.A.

(vi) Electric alarm bell *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 33 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

(vii) Pipework and fittings *Yes/No/N.A. *Yes/No/N.A.

(viii) Sprinkler head *Yes/No/N.A. *Yes/No/N.A.

(ix) Flow control and other auxiliary valves *Yes/No/N.A. *Yes/No/N.A.

(x) Air supply system including air compressor, *Yes/No/N.A. *Yes/No/N.A.


piping and fittings

d) Are all the components LPCB approved as an integral *Yes/No/N.A. *Yes/No/N.A.


part of the recycling installation?

(i) Heat Detector

1) Is the heat detector a heat sensitive, normally *Yes/No/N.A. *Yes/No/N.A.


closed, electrical detector which shall operate at a
fixed temperature?

2) Is it rate compensating and feature automatic *Yes/No/N.A. *Yes/No/N.A.


recycling?

3) Is each detector complete with a tell-tale of zinc *Yes/No/N.A. *Yes/No/N.A.


alloy?

4) Is the detector units connected with low smoke *Yes/No/N.A. *Yes/No/N.A.


fire resisting cable to the control panel?

5) Is the heat probe stainless steel and the top colour *Yes/No/N.A. *Yes/No/N.A.
coded for temperature set point and spacing?

6) Is the conduit box attached with the detector fire *Yes/No/N.A. *Yes/No/N.A.
and explosion proof and made of copper free
aluminium with threaded conduit connections
and adaptors provided for detector cables?

7) Do the detectors have a 60oC detection rating *Yes/No/N.A. *Yes/No/N.A.


which can monitor up to a maximum of 149 m2
of area under optimum conditions of a smooth
ceiling?

8) Are the detectors spaced for not more than 12 m *Yes/No/N.A. *Yes/No/N.A.
apart and 6 m from walls or as approved?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 34 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

(ii) Fire Resisting Cable

1) Is the whole re-cycling preaction system wired *Yes/No/N.A. *Yes/No/N.A.


with low smoke fire resisting cables?

2) Is the low smoke fire resisting cable consist of *Yes/No/N.A. *Yes/No/N.A.


copper conductors and withstand 815oC
temperature for at least 30 minutes?

3) Are the binding tapes used with the cables flame *Yes/No/N.A. *Yes/No/N.A.
retardant?

4) Are the cables installed in cable trays or other *Yes/No/N.A. *Yes/No/N.A.


approved supports, and be fastened by approved
fasteners or clamps specially designed and
constructed for the purpose?

(iii) Control Panel

1) Does the control panel incorporate the necessary *Yes/No/N.A. *Yes/No/N.A.


relays, timers, key type switches, alarm and
trouble lights essential to the operation of the
system?

2) Does the panel employ printed circuit boards for *Yes/No/N.A. *Yes/No/N.A.
the components and completely factory wired and
ready for connection on site?

3) Does a key operated control located on the side *Yes/No/N.A. *Yes/No/N.A.


of the control panel allow the re-cycling
preaction system to be operated as a cycling pre-
action system with the electrical detection circuit
in service or as a dry system without the
electrical detection circuit in service?

4) Does an ON/OFF light incorporated to monitor *Yes/No/N.A. *Yes/No/N.A.


the selection of the recycling ON/OFF switch?

5) Is the control panel incorporate a system tripped *Yes/No/N.A. *Yes/No/N.A.


light and a low air pressure light?

6) Is a key operated thermal test button provided on *Yes/No/N.A. *Yes/No/N.A.


the panel which act to open the detector circuit
momentarily to cycle the system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 35 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

7) Does a reset button on the panel reset the timer *Yes/No/N.A. *Yes/No/N.A.
and alarm circuits after system operation?

(iv) Valve Trim Box

1) Is a valve trim box provided to house electrical *Yes/No/N.A. *Yes/No/N.A.


terminal blocks, 24 Volt D.C. solenoid valves,
and pressure switches necessary for the operation
of the recycling installation?

2) Is it prewired and plumbed by the manufacturer *Yes/No/N.A. *Yes/No/N.A.


for connections?

3) Does it have a full opening door of 180o *Yes/No/N.A. *Yes/No/N.A.


minimum for easy access to all components?

(v) Flow Control Valve

1) Is the flow control valve a quick opening, *Yes/No/N.A. *Yes/No/N.A.


differential diaphragm valve with a spring loaded
floating clapper?

2) Does the flow control valve facilitate manual or *Yes/No/N.A. *Yes/No/N.A.


automatic on/off control?

3) Is it used to control water pressure or water flow *Yes/No/N.A. *Yes/No/N.A.


rates?

4) Is the flow control valve used as pressure *Yes/No/N.A. *Yes/No/N.A.


reducing valve to limit or conserve water flow?

(vi) Air Supply

1) Is each recycling installation provided with an *Yes/No/N.A. *Yes/No/N.A.


independent air supply system?

2) Does each air supply system of the recycling *Yes/No/N.A. *Yes/No/N.A.


installation consist of an compressor, pneumatic
actuators, air maintenance devices, pressure
monitoring valves, controls, wiring, copper
pipework and fittings, and all other necessary
accessories for the operation of the system?

3) Is the compressor of the compressed air system *Yes/No/N.A. *Yes/No/N.A.


an oil-free, permanently lubricated type?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 36 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

4) Is the compressor direct driven type with no belts *Yes/No/N.A. *Yes/No/N.A.


or gears, and compatible with air maintenance
devices and other system components for
effective operation, with no special source of air
required?

5) Is the compressor complete with thermal *Yes/No/N.A. *Yes/No/N.A.


protection, air filters, safety relief valve and other
protective provisions?

6) Is the air maintenance device an automatic, field- *Yes/No/N.A. *Yes/No/N.A.


adjustable air maintenance provision for the
compressed air system?

7) Is the air maintenance device equipped with *Yes/No/N.A. *Yes/No/N.A.


pressure switch, restrictor check valve, strainer,
bypass valve, etc. for the optimum operation of
the system, and enable the compressor to be
started under load?

8) Does the device provide a balancing means to *Yes/No/N.A. *Yes/No/N.A.


minimize on-off cycling of the compressor and
the need to rapidly relieve the system pressure to
the actuation point?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 37 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.2.1.8 Fire Pump

Pump/Motor Set Data :

Sprinkler Pump Jockey Pump Transfer Pump

Duty Standby Duty Standby Duty Standby

Location

Quantity (No(s).)

Manufacturer Pump

Motor

Model Pump

Motor

Serial No. Pump

Motor

Motor power (kW)

Pump power (kW)

Flow rate (L/s)

Pressure (kPa)

Starting method

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?

b) Is pump motor power rated at 10% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?

c) Are emergency lock-off buttons provided adjacent to *Yes/No/N.A. *Yes/No/N.A.


pump motors with visual and audible indication on the
panel when the pump is locked?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 38 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

d) Are pump motors protected by HRC fuse? *Yes/No/N.A. *Yes/No/N.A.

e) Is secondary power supply provided for electric pumps? *Yes/No/N.A. *Yes/No/N.A.

f) Is standby pump provided for diesel engine driven *Yes/No/N.A. *Yes/No/N.A.


pumps?

g) Are doors to pump rooms clearly labelled "SPRINKLER *Yes/No/N.A. *Yes/No/N.A.


PUMP" (?

h) Are doors to pump rooms provided with locking *Yes/No/N.A. *Yes/No/N.A.


devices?

i) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?

j) Are pump rooms clear of debris? *Yes/No/N.A. *Yes/No/N.A.

k) Are alternative means of starting the pump manually, in *Yes/No/N.A. *Yes/No/N.A.


addition to manual fire alarm call points provided, where
the pump is not electrically operated?

l) Are starting instructions for diesel driven pump *Yes/No/N.A. *Yes/No/N.A.


prominently displayed in the pump room?

m) Can the pump just be stopped by switching off at the *Yes/No/N.A. *Yes/No/N.A.
pump control not installed near the pump, rather than by
any automatic means?

n) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?

o) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.

p) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?

q) Are pumps permanently primed? *Yes/No/N.A. *Yes/No/N.A.

r) Are non-return valve(s) provided to prevent water *Yes/No/N.A. *Yes/No/N.A.


backflow into the water tank?

s) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 39 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

t) Are such signal repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?

u) Are two/three (one as standby) intermediate booster *Yes/No/N.A. *Yes/No/N.A.


pumps of the same capacity provided to achieve required
flow and pressure within 30 seconds?

v) Do the intermediate booster pumps continue to run *Yes/No/N.A. *Yes/No/N.A.


irrespective of power interruption when start button is
activated?

w) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?

3.2.1.9 Miscellaneous

a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?

b) Are proper identification provided for pipeworks, *Yes/No/N.A. *Yes/No/N.A.


wirings and equipment?

c) Are water tanks clear of debris? *Yes/No/N.A. *Yes/No/N.A.

d) Is permanent water supply connected? *Yes/No/N.A. *Yes/No/N.A.

e) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

f) Is emergency electricity supply available? *Yes/No/N.A. *Yes/No/N.A.

3.2.2 Testing and Commissioning

3.2.2.1 Pipeworks

a) Are hydraulic tests performed satisfactorily for water *Yes/No/N.A. *Yes/No/N.A.


tightness of all sections of the pipeworks ? (At 1500 kPa
or 1.5 times the working pressure whichever higher for
15 min.)(Test records on Part 4.2 Table 1)

b) Is flushing out of all water pipes performed? *Yes/No/N.A. *Yes/No/N.A.

c) Do the automatic air release valves function properly? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 40 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.2.2.2 Dry Pipe Installations

a) Is the air-supply pressure-relief valve set to relieve at a *Yes/No/N.A. *Yes/No/N.A.


pressure of not more than 500 kPa in excess of the air
pressure requirement of the installation dry alarm valve?

b) With the installation valve primed in the ready position, *Yes/No/N.A. *Yes/No/N.A.
is it possible to fully pressurize the installation in one
hour, at any time ?

3.2.2.3 Pre-action System

a) Does the fire detection system automatically give an *Yes/No/N.A. *Yes/No/N.A.


alarm at the fire alarm control and indicating panel, pre-
action system control panel and any repeater panels and
operate two independent LPCB certified solenoid valves
or actuator mechanisms either of which shall release
(Type 1 or Type 2) pre-action alarm valves?

b) Do the solenoid valves or actuator mechanisms energised *Yes/No/N.A. *Yes/No/N.A.


or de-energised to operate a pneumatic pre-action valve
control system?

c) Does the control panel work as follow? *Yes/No/N.A. *Yes/No/N.A.

(i) The duration of the battery stand-by power supply


shall be at least 72 hours. After the 72 hour
stand-by period the stand-by power supply shall
be capable of operating the pre-action control
panel and solenoid valve or actuator to release the
pre-action alarm valve.

(ii) The pre-action control panel shall initiate


operation of the pre-action alarm valve
immediately in the event of a fire alarm system
fault (including a failure of the primary and
stand-by power supplies) which result in failure
to execute the appropriate actions in the event of
fire.

d) Are the monitoring devices provided to give the *Yes/No/N.A. *Yes/No/N.A.


following?

(i) Indication that any stop valves down-stream of


the installation control valve set are fully open;

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 41 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(ii) Audible and visual warnings at the pre-action


control panel that any monitored stop valve is not
fully open;

(iii) Audible and visual warnings at the pre-action


control panel that the cover to a condition
indicator switch has been removed;

(iv) Audible and visual warnings at the pre-action


control panel of short circuit or disconnection of
the leads of any solenoid valve or actuator which
is energised to open;

(v) Audible and visual warnings at the pre-action


control panel of short circuit or disconnection of
the primary power supply, the secondary power
supply or any battery charger associated with the
operation of the pre-action system.

3.2.2.4 Recycling System

a) Heat Detector

(i) When a detector is heated to the temperature set *Yes/No/N.A. *Yes/No/N.A.


point, does a mechanical switch open and break
the series circuit interrupting the flow of current?

(ii) When the temperature drops below the set point, *Yes/No/N.A. *Yes/No/N.A.
is the circuit re-established? At 426oC sustained
ambient temperature, does the tell-tale tab drop
away, indicating possible detector damage?

b) Mode of Operation

(i) Does the system work as follow? *Yes/No/N.A. *Yes/No/N.A.

(ii) Water discharge cycling to be controlled by heat *Yes/No/N.A *Yes/No/N.A


detectors installed at the roof or ceiling which
operate as an electrical interlock causing the
water flow control valve to open and close. A
timer to be provided to delay closure of the flow
control valve for a predetermined period of at
least 5 minutes in each cycle after lowering of the
temperature of the heat detectors.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 42 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(iii) The fire alarm bell to continue to sound until the *Yes/No/N.A *Yes/No/N.A
reset button is pushed. Should the temperature
build to the trip point of any detector during any
phase of the cycle, the system will continue to
flow or immediately start the flow of water to the
fire.

c) Control Panel

(i) Does system operation or low air pressure *Yes/No/N.A. *Yes/No/N.A.


activate the corresponding light and the audible
trouble alarm and other alarms required which
can be silenced by ON/OFF switches?

(ii) Is the whole recycling installation designed and *Yes/No/N.A. *Yes/No/N.A.


constructed as a fail safe installation?

(iii) If the detector circuit and/or pressurized air are *Yes/No/N.A. *Yes/No/N.A.
unavailable for service, will the system turn into
an ordinary automatic dry pipe or wet pipe
system?

(iv) Do all alarms except the low air pressure alarm *Yes/No/N.A. *Yes/No/N.A.
operate constantly unless shut off and cycling
features are negated?

d) Air Supply

(i) Is the compressor operated by means of air *Yes/No/N.A. *Yes/No/N.A.


pressure switches installed on the main pipe?

(ii) On detecting air leakage reduced to a *Yes/No/N.A. *Yes/No/N.A.


predetermined value, does the compressor
automatically cut-in, and cut-out after the air
pressure has been built-up adequately?

(iii) Does the compressed air system allow the *Yes/No/N.A. *Yes/No/N.A.
recharging of the recycling installation manually
after the sprinkler system has been operated and
the actuated sprinkler heads are replaced?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 43 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.2.2.5 Electrical Wiring

a) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C procedure No. 2 for
Electrical Installation and to Electricity Ordinance
requirements?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 44 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

b) Does the battery charger function properly? *Yes/No/N.A. *Yes/No/N.A.

c) Is the telephone link connected and functioning? *Yes/No/N.A. *Yes/No/N.A.

3.2.2.6 Water Pump

a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.2 Table 2)

b) Do the water pumps run at an acceptable noise and *Yes/No/N.A. *Yes/No/N.A.


vibration levels?

c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?

d) Do the water pump protective devices function properly? *Yes/No/N.A. *Yes/No/N.A.

e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?

f) Are the temperatures of the water pump bearings normal *Yes/No/N.A. *Yes/No/N.A.
at running condition?

g) Are the temperatures of the pump motors normal at *Yes/No/N.A. *Yes/No/N.A.


running condition?

h) Do the pressure gauges function properly? *Yes/No/N.A. *Yes/No/N.A.

i) Is water leakage from the pump shafts at an acceptable *Yes/No/N.A. *Yes/No/N.A.


level?

j) Do the non-return valves function properly? *Yes/No/N.A. *Yes/No/N.A.

k) Does the pressure relief valve of the anti-overheating *Yes/No/N.A. *Yes/No/N.A.


circulating pipe function properly? (Operate at
bar)

l) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly? (Test records on Part
4.2 Table 3)

m) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting ?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 45 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

n) Does the change-over from duty to standby pump *Yes/No/N.A. *Yes/No/N.A.


complete within 30 sec.? (Change-over in ___ sec.)

3.2.2.7 Sprinkler Inlet

a) Do the non-return valves of the sprinkler inlets function *Yes/No/N.A. *Yes/No/N.A.


properly?

b) Do the drain valves function properly? *Yes/No/N.A. *Yes/No/N.A.

3.2.2.8 Alarm Switch

a) Do the flow switches for zone operating indication and *Yes/No/N.A. *Yes/No/N.A.
alarm function properly? (Test records on Part 4.2 Table
4)

b) Does the water alarm for each installation valve operate *Yes/No/N.A. *Yes/No/N.A.
when the test valve is opened?

c) Do the high and low water level alarms and indication *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?

3.2.2.9 Proving of Water Supplies

a) Do the installation pressure and flow rate at each *Yes/No/N.A. *Yes/No/N.A.


installation valve complying with the L.P.C. Rules
requirements as the following Table? (Test records on
Part 4.2 Tables 5 and 6)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 46 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Pressure and Flow Requirement (L.P.C. Rules Table 15)

Hazard Class (i) Actual Pressure (ii) Plus Calculated Pressure


Minimum required Based on Height between
Running Pressure # Highest Sprinkler and
(bar) Valves when Rate of Flow
is: (L/min)

Light hazard 2.2 225

Ordinary : Group I 1.0 375


0.7 540

Ordinary : Group II 1.4 725


1.0 1000

Ordinary : Group III 1.7 1110


1.4 1350

Ordinary : Group III(S) 2.0 1800


1.5 2100

# Measured on the installation pressure gauge.

Pressure and Flow Requirement for High Rise Sprinkler Installation (L.P.C. Rules Table TB13.T1)

Hazard Class (i) Actual Pressure (ii) Plus Calculated Pressure


Minimum Required Base on Height between
Running Pressure++ Highest Sprinkler and the
(bar) Installation Zone Subsidiary
Stop Valve (L/min)

Ordinary : 1.4 725


Group II 1.0 1000

Ordinary : 1.7 1100


Group III 1.4 1350

++ Measured on the installation zone subsidiary stop valve.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 47 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.3 Manual and Automatic Fire Alarm System and Fire Alarm Control System

3.3.1 Type of Equipment

3.3.1.1 Alarm annunciation panel

a) Manufacturer/Model No. of Alarm annunciation panel :


i. Main panel : ____________________________________________
ii. Sub-panel/repeater panel, if any : _______________________________________

b) FSD approved type *Yes/No

c) Conventional (electronic) type *Yes/No


Addressable type *Yes/No

3.3.1.2 Power Supplies

Mains supply : Supply Voltage/Phase/Hz

Emergency : Rating of generator (KVA)


generator
: Fuel oil supply capacity
(Litres of oil)

Standby battery : Type of batteries

: Capacity of batteries (Ahr)

: Backup period for fire service (hr)

3.3.1.3 Detectors

a) Heater detector:
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Fixed temperature *Yes/No
Rate-of rise temperature *Yes/No
Combination *Yes/No
Linear cable *Yes/No
Others : ____________

b) Smoke detector :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Ionization *Yes/No
Optical *Yes/No
Point *Yes/No
Aspirating *Yes/No
Others :
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 48 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

c) Multi-sensor detector :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type of sensors :
Heat sensing element : ____________
Smoke sensing element : ____________
Radiation sensing element : ____________
Other sensing element : ____________

d) Flame detector:
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type :
Infra-red Yes/No
Ultra-violet Yes/No
Others:

e) Others :
Manufacturer/model No. : ____________
FSD approved type : *Yes/No
Type : ____________

3.3.1.4 Manual Call Points

Manufacturer/model no. : ......

F.S.D. approved type : Yes/No

Type : Breakglass type [ ]


Others [ ]
(please
specify ......)

3.3.1.5 Alarm Sounders

Manufacturer/model no. : ..
.
...
F.S.D. approved type : Yes/No

3.3.1.6 Visual Fire Alarm Lamps

Manufacturer/model no. : ..
.
...

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 49 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

F.S.D. approved type ( only


for those lamps integrated : Yes/No
with alarm sounders )

3.3.1.7 Fire Resistant Cables

Manufacturer/model no. : ..
.
...
Type : BS 6387 Cat. AWX, AWY or AWZ [ ]
BS 6387 Cat. BWX, BWY or BWZ [ ]
BS 6387 Cat. CWX, CWY or CWZ [ ]
BS 6387 Cat. SWX, SWY or SWZ [ ]
MICS cable to BS 6207 [ ]
Others with F.S.D.s acceptance letter [ ]
(please specify .)

3.3.2 Zoning

3.3.2.1 Detectors

Zone No. Location Total no. of Detector type * Remark


detectors

Total no. of Total no. of


detectors detector zones ..

* S-smoke, H-heat, F-flame, O-others (please specify)

3.3.2.2 Alarm Sounders

Zone No. Location Total no. of sounders Remark

Total no. of Total no. of


sounders . sounder zones .

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 50 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.3.2.3 Manual Call Points

Zone No. Location Total no. of call Remark


points

Total no. of Total no. of


manual call points .. call point zones .

3.3.2.4 Visual Fire Alarm Signal Lamps

Zone No. Location Total no. of VFA Remark


signal lamps

Total no. of Total no. of


VFA signal lamps .. VFA zones .

(use separate sheets or computer printouts in full accordance with the above format if the space is not sufficient for
inserting all the zones)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 51 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3 Visual Inspection

3.3.3.1 General

3.3.3.1.1 All fire detection and equipment are conformed to *Yes/No/N.A. *Yes/No/N.A.
F.S.D.s requirements.

3.3.3.1.2 All individual components of a fire alarm system are *Yes/No/N.A. *Yes/No/N.A.
mutually compatible.

3.3.3.1.3 Operating instructions showing the fault indication or *Yes/No/N.A. *Yes/No/N.A.


correct action that should be taken in the event of a fire
are provided adjacent to the alarm annunciation panel.

3.3.3.1.4 Diagrammatic representation of the building, showing at *Yes/No/N.A. *Yes/No/N.A.


least the building entrances, the circulation areas, the
escape routes and the division of zones is provided on or
adjacent to the alarm annunciation panel.

3.3.3.1.5 As-fitted zoning schedule is provided adjacent to the *Yes/No/N.A. *Yes/No/N.A.


alarm annunciation panel.

3.3.3.1.6 Log book is provided adjacent to the alarm annunciation *Yes/No/N.A. *Yes/No/N.A.
panel.

3.3.3.2 Detectors

3.3.3.2.1 Appropriate types of detectors are provided in areas as *Yes/No/N.A. *Yes/No/N.A.


indicated on the approved building plans.

3.3.3.2.2 Detectors are provided in areas as indicated on the *Yes/No/N.A. *Yes/No/N.A.


endorsed FSI plans.

3.3.3.2.3 Detection zonings are properly labelled at the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel.

3.3.3.2.4 In the floor where sleeping risk exists (e.g. hotel, *Yes/No/N.A. *Yes/No/N.A.
hospital, etc.) :

(a) heat detector should be used in kitchen.


(b) smoke detector should be used in other areas
except sprinkler protected toilets, bathrooms and
staircases.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 52 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.2.5 Detectors are provided to entire basement (except car *Yes/No/N.A. *Yes/No/N.A.
parking area, strong room & safe deposit vault).

3.3.3.2.6 Intrinsically safe detector is used in the environment *Yes/No/N.A. *Yes/No/N.A.


which may have the presence of explosive or flammable
gas.

3.3.3.2.7 The aggregate floor area covered by any single detection *Yes/No/N.A. *Yes/No/N.A.
loop circuit is 10,000 m2 calculated on those portions
of the premises installed with fire detectors.

3.3.3.2.8 The aggregate floor area covered by a single detection *Yes/No/N.A. *Yes/No/N.A.
zone is 2,000 m2 calculated on those portions of the
premises installed with fire detectors.

3.3.3.2.8 Remote indicator lamps are provided to show visually *Yes/No/N.A. *Yes/No/N.A.
the position of the fire detection signal for search
distance > 30 m.

3.3.3.2.8 Remote indicator lamps outside doors (near door exit) *Yes/No/N.A. *Yes/No/N.A.
are provided for detectors installed inside rooms if doors
are likely to be locked.

3.3.3.2.9 If the building consists of more than one storey, a single *Yes/No/N.A. *Yes/No/N.A.
zone design is adopted for the total floor area is 300
m2.

3.3.3.2.10 As the total floor area of the building is > 300 m2, all *Yes/No/N.A. *Yes/No/N.A.
zones are restricted to a single storey, except that :

(a) if the total floor area of a fire compartment is


300 m2, and any communication with other
fire compartments is only at the lowest level of
the building, then that fire compartment is
considered as a single zone even though there
may be more than one storey within it; and

(b) if detectors or call points are fitted in stairwells,


lightwells, liftwells and other flue-like structures
extending beyond one floor but within one fire
compartment, then the volume of the well or shaft
should be considered as one or more separate zones.

3.3.3.3 Alarm Sounders

3.3.3.3.1 An alarm sounder (weatherproof type) is installed at the *Yes/No/N.A. *Yes/No/N.A.


external/outside of the building (near the main entrance).

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 53 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.3.2 An alarm sounder is provided near the control and *Yes/No/N.A. *Yes/No/N.A.
indicating equipment.

3.3.3.3.3 One alarm sounder is provided at each hose reel point. *Yes/No/N.A. *Yes/No/N.A.

3.3.3.3.4 All alarm sounder cases are painted in red colour and *Yes/No/N.A. *Yes/No/N.A.
clearly marked FIRE ALARM in white color.
The height of all the English and Chinese wordings shall
not be less than 10 mm and 15 mm respectively.

3.3.3.3.5 A clearly labelled facility is available at or near the alarm *Yes/No/N.A. *Yes/No/N.A.
annunciation panel for starting or restarting the fire alarm
sounders. Operation of this facility is not dependent on
the state of any silencing device.

3.3.3.3.6 For sounders used for simple ring circuits, the *Yes/No/N.A. *Yes/No/N.A.
distribution wiring to each sounder circuit should be
protected against overload due to short circuit by a fuse
or similar device.

3.3.3.4 Manual Call Points *Yes/No/N.A. *Yes/No/N.A.

3.3.3.4.1 Zoning of manual call points is at least one zone per *Yes/No/N.A. *Yes/No/N.A.
floor or storey.

3.3.3.4.2 One manual call point is located at each of the following *Yes/No/N.A. *Yes/No/N.A.
equipment/location.

(a) hose reel point;


(b) adjacent to all storey exits;
(c) adjacent to all exits to open air.

3.3.3.4.3 The travel distance for finding a manual call point is *Yes/No/N.A. *Yes/No/N.A.
30 m.

3.3.3.4.4 Manual call points are fixed at a height of about 1.2m *Yes/No/N.A. *Yes/No/N.A.
above the finished floor level.

3.3.3.5 Visual Fire Alarm Signals

3.3.3.5.1 VFA signal lamps are labelled FIRE ALARM . *Yes/No/N.A. *Yes/No/N.A.
The height of English and Chinese characters is not less
than 10 mm and 15 mm, respectively.

3.3.3.5.2 Visual alarm signal is in the form of red flashing light. *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 54 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.5.3 Each compartment is provided with at least one VFA *Yes/No/N.A. *Yes/No/N.A.
signal lamp.

3.3.3.5.4 Areas to be covered by VFA are in full compliance with *Yes/No/N.A. *Yes/No/N.A.
the approved building plans.

3.3.3.5.5 The design of the VFA system conforms to : *Yes/No/N.A. *Yes/No/N.A.

(a) Section 4 4, NFPA 72 : 1999, or


(b) Clause 9.7, BS 5839 : Part 1 : 1988.

3.3.3.6 Time Related Systems and Transmission Delay Units

3.3.3.6.1 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
provided.

3.3.3.6.2 Time related system and/or transmission delay unit are/is *Yes/No/N.A. *Yes/No/N.A.
approved by F.S.D..

3.3.3.6.3 An indicator light is provided on or adjacent to the *Yes/No/N.A. *Yes/No/N.A.


control and indicating equipment showing the working
or silent hours state of the system.

3.3.3.6.4 A manual override switch is provided on or adjacent to t *Yes/No/N.A. *Yes/No/N.A.


he control equipment for de-activating the time related sy
stem when the building is unoccupied.

3.3.3.7 Control and Indicating Equipment

3.3.3.7.1 The alarm annunciation panel is located in an area on the *Yes/No/N.A. *Yes/No/N.A.
ground floor and in the immediate vicinity of the
building entrance easily to be accessed by the F.S.D. or
in the buildings Fire Control Centre/Room.

3.3.3.7.2 Repeater panels are provided at different entrances or *Yes/No/N.A. *Yes/No/N.A.


other points of entry to be used by the F.S.D. in
accordance with the approved building plans.

3.3.3.7.3 Where the control and indicating equipment is installed *Yes/No/N.A. *Yes/No/N.A.
in a severe weather environment, a weatherproof
protective enclosure with adequate ventilation is
provided to protect it from being damaged by high
humidity and water.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 55 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.7.4 All the alarm indications are displayed in both Chinese *Yes/No/N.A. *Yes/No/N.A.
and English so that the origin of the alarm position in
relation to this building can be easily, quickly and
unambiguously identified.

3.3.3.7.5 The method of indication of the origin of alarms is by *Yes/No/N.A. *Yes/No/N.A.


means of :

(a) a display of letters and/or numbers.


(b) a permanent mimic diagram.
(c) a display of a mimic diagram on a visual display
unit (VDU) and (a) or (b) above or a second VDU or
a printer.
(d) by other suitable means.
(please specify )

3.3.3.7.6 The operation of all manual controls and isolating *Yes/No/N.A. *Yes/No/N.A.
devices should be limited to authorized personnel. It
may be provided by restricting access to the equipment
by means of the following : -

(a) the use of a lock.


(b) a key-operated switch.
(c) in a disciplined environment, by the use of a list of
authorized personnel.
(d) other acceptable means.
(please specify )

3.3.3.7.7 No silencing switch device is installed as a single *Yes/No/N.A. *Yes/No/N.A.


component. This device is incorporated in either the
main fire service control panel or a repeater panel.

3.3.3.8 Power Supplies *Yes/No/N.A. *Yes/No/N.A.

3.3.3.8.1 Permanent electricity supply is connected. *Yes/No/N.A. *Yes/No/N.A.

3.3.3.8.2 Battery powered standby supply is connected. *Yes/No/N.A. *Yes/No/N.A.

3.3.3.8.3 Battery power supply is provided. *Yes/No/N.A. *Yes/No/N.A.


(Voltage:.. DC volts:.. Ahr:.....)

3.3.3.8.4 The battery charger is capable of recharging the batteries *Yes/No/N.A. *Yes/No/N.A.
from fully discharged to fully charged within 24 hours.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 56 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.8.5 Connections to the mains supply is via an isolating *Yes/No/N.A. *Yes/No/N.A.


protective device (e.g. an isolating switch-fuse) reserved
solely for all the fire service installations.

3.3.3.8.6 Every isolator, switch and protective device that can *Yes/No/N.A. *Yes/No/N.A.
supply for the fire alarm system is properly labelled as
appropriate :

(a) FIRE ALARM ;


(b) FIRE ALARM DO NOT SWITCH OFF
; or
(c) WARNING: THIS SWITCH ALSO CONTROLS
THE SUPPLY TO THE FIRE ALARM SYSTEM
: .

All warning labels are engraved in white letter/


character with red colour background. The height of
all the English and Chinese wordings is not less
than 10 mm and 15 mm respectively.

3.3.3.8.7 Normal and standby battery supplies can each be capable *Yes/No/N.A. *Yes/No/N.A.
of supplying the maximum alarm load irrespective of the
condition of the other supply.

3.3.3.8.8 Power supply equipment for multiple occupancy *Yes/No/N.A. *Yes/No/N.A.


buildings is sited in an area of common access.

3.3.3.9 Cables, Wiring and Other Interconnections

3.3.3.9.1 Cables used for the interconnections between VFA *Yes/No/N.A. *Yes/No/N.A.
signalling devices, sounders, control and indicating
equipment and power supplies are suitable for prolonged
operation during a fire or can resist fire for at least 30
minutes.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 57 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.9.2 Cables requiring prolonged operation during a fire *Yes/No/N.A. *Yes/No/N.A.


should be:

(a) MICS cable complying with BS6207; or


(b) complying with BS6387, meeting with the
requirements for Cat. AWX or SWX; or
(c) embedded in the structure of the building and
protected by the equivalent of at least 12 mm of
plaster; or
(d) separated from any significant fire risk by a wall,
partition or floor having at least 30 minutes fire
resistance; or
(e) by other acceptable means as stipulated in relevant
F.S.D. Circular Letters.

3.3.3.9.3 Cables other than MICS cable complying with BS 6207 *Yes/No/N.A. *Yes/No/N.A.
or sheathed steel-wire-armoured cable complying with
BS 6346 or BS 5467 should be mechanically protected
if :

(a) they are not monitored; or


(b) they are less than 2.25 m above the floor; or
(c) physical damage or rodent attack is likely.

3.3.3.9.4 Mechanical protection is provided to the cables by one of *Yes/No/N.A. *Yes/No/N.A.


the following methods :

(a) installation in conduit, ducting or trunking;


(b) by laying the cable in a channel;
(c) using MICS cable complying with BS 6207 or
sheathed steel-wire-armoured cable complying with
BS 6346 or BS 5467.

3.3.3.9.5 Conductors carrying fire alarm power or signals are *Yes/No/N.A. *Yes/No/N.A.
separated from conductors used for other systems by one
or more of the followings :

(a) installation in conduit, ducting, trunking or a


channel reserved for fire alarm conductors;
(b) a mechanically strong, rigid and continuous partition
of non-combustible material;
(c) mounting at a distance of at least 300 mm from
conductors of other systems;
(d) wiring in cables complying with BS 7629;
(e) wiring in MICS cable with an insulating sheath or
barrier. The exposed-to-touch rating of the IEE
Wiring Regulations should not be exceeded.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 58 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.3.9.6 For cable which should be segregated from cables of *Yes/No/N.A. *Yes/No/N.A.
other services but is not enclosed in ducting, trunking or
a channel reserved for fire alarm circuits, it is suitably
marked or labelled at intervals not exceeding 2 m to
indicate its function and the need for segregation.

3.3.3.9.7 DTL is mechanically protected in accordance with the *Yes/No/N.A. *Yes/No/N.A.


methods mentioned in item 3.3.3.9.4 above.

3.3.3.9.8 Cabling and wiring installation is in accordance with the *Yes/No/N.A. *Yes/No/N.A.
latest edition of the EE Code.

3.3.3.9.9 Any joint in a cable is enclosed in a suitable and *Yes/No/N.A. *Yes/No/N.A.


accessible junction box labelled FIRE ALARM
engraved in white letter/character with red colour
background. The height of all the English and Chinese
wordings is not less than 10 mm and 15 mm
respectively to avoid confusion with other services.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 59 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4 Testing

3.3.4.1 Detectors

3.3.4.1.1 Upon actuation of any detector in the building, the *Yes/No/N.A. *Yes/No/N.A.
correct audio/ visual warning device for the fire
alarm and detection system is initiated.

3.3.4.1.2 The sensitivity of all heat/smoke/flame detectors is *Yes/No/N.A. *Yes/No/N.A.


correctly adjusted/ set and checked in full accordance
with the manufacturers recommendations.

3.3.4.1.3 The zoning of detectors is correct. *Yes/No/N.A. *Yes/No/N.A.

3.3.4.2 Alarm Sounders

3.3.4.2.1 Upon the actuation of the detector, alarm should be given *Yes/No/N.A. *Yes/No/N.A.
by alarm sounder installed at the building external near
the entrance.

3.3.4.2.2 Background noise (N) likely to persist for a period *Yes/No/N.A. *Yes/No/N.A.
longer than 30 seconds.

3.3.4.2.3 For domestic building, the minimum sound level of *Yes/No/N.A. *Yes/No/N.A.
alarm sounders is measured at 3 m from the inside of the
main entrance door with all doors shut off at all flats and
the result is,
dB(A) which is :

(a) 60 dB(A); and


(b) [5 dB(A) + . (background
noise, N at item 3.3.4.2.2)]
= .. dB(A)

3.3.4.2.4 For building other than domestic building, the minimum *Yes/No/N.A. *Yes/No/N.A.
sound level of alarm sounders is measured at 3 m from
the inside of the main entrance door with all doors shut
off at all rooms/ premises and the result is,
dB(A) which is :

(a) 65 dB(A); and


(b) [5 dB(A) + . (background
noise, N at item 3.3.4.2.2)]
= .. dB(A)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 60 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.2.5 The primary sounders should meet the required sound *Yes/No/N.A. *Yes/No/N.A.
level when the machine noise ceases and the secondary
sounders are out of service.

3.3.4.2.6 Where secondary sounders are installed, the primary *Yes/No/N.A. *Yes/No/N.A.
sounders in those parts of the premises without noisy
machines are distinctly audible at all times when
operated.

3.3.4.2.7 Failure of the power supply to the secondary sounders is *Yes/No/N.A. *Yes/No/N.A.
either :

(a) resulted in silencing of the noisy machines; or


(b) in the giving of an audible and visible fault warning
at the control and indicating equipment.

3.3.4.2.8 Sounding sequence of alarm sounder operation complies *Yes/No/N.A. *Yes/No/N.A.


with requirements stipulated in F.S.D. Circular Letter
No. 4/96, Part VIII. Item 4.

3.3.4.3 Manual Call Points

3.3.4.3.1 The zoning of manual call points is correct. *Yes/No/N.A. *Yes/No/N.A.

3.3.4.3.2 Upon actuation of any manual call point in the *Yes/No/N.A. *Yes/No/N.A.
building, the fixed fire pump comes into operation
regardless of the zoning of the manual call point.

3.3.4.3.3 Upon actuation of any manual call point in the *Yes/No/N.A. *Yes/No/N.A.
building, the correct audio/ visual warning device
for the fire alarm and detection system is initiated.

3.3.4.3.4 The delay between operation of a call point and the *Yes/No/N.A. *Yes/No/N.A.
giving of the general alarm is 3 seconds.

3.3.4.4 Visual Fire Alarm Signals

3.3.4.4.1 The power supply of the VFA system is from : *Yes/No/N.A. *Yes/No/N.A.

(a) DC supply source with back-up supply by battery;


or
(b) AC supply source with secondary supply from
emergency generator; or
(c) AC supply source with secondary AC supply from
the main electricity supply obtained from before the
consumer side main power supply switch.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 61 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.4.2 All VFA flashing light is visible to normal eyesight in *Yes/No/N.A. *Yes/No/N.A.
the required protected areas when the fire alarm system
is actuated.

3.3.4.4.3 VFA signal is clearly distinguishable from any other *Yes/No/N.A. *Yes/No/N.A.
non-fire service visual signals used in the premises.

3.3.4.5 Time Related Systems and Transmission Delay Units

3.3.4.5.1 Repeated switch operations to delay the automatic *Yes/No/N.A. *Yes/No/N.A.


changeover to more sensitive state should not extend > 6
minutes after the last operation of the switch.

3.3.4.5.2 The alarm is automatically transmitted to FSCC after a *Yes/No/N.A. *Yes/No/N.A.


fixed delay period 1 minute, unless a manual override
operation has been carried out.

3.3.4.5.3 Automatic transmission of alarm to FSCC/Chubb Centre *Yes/No/N.A. *Yes/No/N.A.


or remote manned center is delayed for an initial period
1 minute.

3.3.4.5.4 Transmission of alarm is further delayed for a period *Yes/No/N.A. *Yes/No/N.A.


5 minutes after the manual operation is performed at the
control equipment.

3.3.4.5.5 During any delay period, a manual operation at the contr *Yes/No/N.A. *Yes/No/N.A.
ol panel or the operation of a manual call point causes th
e immediate sounding of the fire alarm and transmission
of the alarm.

3.3.4.5.6 The sounding of the fire alarm and transmission of the al *Yes/No/N.A. *Yes/No/N.A.
arm is not delayed or prevented by the operation of a ma
nual call point or the actuation of a sprinkler flow switch
at any time.

3.3.4.5.7 The manual override switch is only capable of de-activati *Yes/No/N.A. *Yes/No/N.A.
ng the system from the time related system but cannot re-
activate the system again.

3.3.4.5.8 The system is not capable of permitting the action of the *Yes/No/N.A. *Yes/No/N.A.
manual override switch to be temporarily or permanently
cancelled by any automatic function

3.3.4.6 Control and Indicating Equipment

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 62 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.6.1 Audio, visual alarms for the fire detection and alarm *Yes/No/N.A. *Yes/No/N.A.
system, signals for system/ detector/ manual call point/
sounder fault and signals to all the ancillary equipment
are given correctly at the control and indicating
equipment.

3.3.4.6.2 DTL to the FSCC/Chubb Centre is functioning properly. *Yes/No/N.A. *Yes/No/N.A.


(please state DTL no.: .)

3.3.4.6.3 The following panel functions and switches are working *Yes/No/N.A. *Yes/No/N.A.
properly :

(a) alarm silence and reset switches.


(b) normal supply and standby battery supply.
(c) Power on/failure indicator.
(d) DTL failure indicator.
(e) zone alarm/fault indicator.

3.3.4.6.4 Two simultaneous faults should not remove fire *Yes/No/N.A. *Yes/No/N.A.
alarm protection from an aggregate area greater
than 10,000 m2 calculated on those portions of the
premises installed with fire detectors.

3.3.4.6.5 Removal of a detector is causing a fault signal to *Yes/No/N.A. *Yes/No/N.A.


be generated at the control equipment.

3.3.4.6.6 A facility/provision is provided so that individual *Yes/No/N.A. *Yes/No/N.A.


detector can be tested without either sounding an
alarm or requiring the complete system to be
disabled to prevent such an alarm.

3.3.4.6.7 The operation of a silencing device : *Yes/No/N.A. *Yes/No/N.A.

(a) requires a manual operation;


(b) causes an audible signal to be given in the control
and indicating equipment with a distinctive sound
different from any alarm and control sounder;
(c) should not cancel any visual signal of the alarm at
the control equipment;
(d) should not prevent the proper receipts of alarm from
any zones(s) not already providing an alarm;
(e) should not prevent the correct operation of any
control for starting or restarting the alarm sounders;
(f) should not prevent the transmission of an alarm to a
remote manned centre.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 63 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.6.8 A fault warning signal is generated at the control *Yes/No/N.A. *Yes/No/N.A.


and indicating equipment when any sounder is disc
onnected.

3.3.4.6.9 A fault warning is given in the event of failure on m *Yes/No/N.A. *Yes/No/N.A.


icroprocessors for program controlled system.

3.3.4.6.10 The operation of microprocessors for program *Yes/No/N.A. *Yes/No/N.A.


controlled system is automatically reset after the
system has been restarted.

3.3.4.6.11 Following reinitialization, repair of any fault, or *Yes/No/N.A. *Yes/No/N.A.


restoration of any power supply failure, all program
controlled systems should be capable of :

(a) sounding a general alarm within 30 seconds; and


(b) within a further period of 10 minutes of attaining
normal operating conditions without further manual
intervention.
(Remark: The silencing of any fault warning is not
regarded as manual intervention)

3.3.4.6.12 The audible indications of the control and indicating *Yes/No/N.A. *Yes/No/N.A.
equipment are easily heard in its vicinity.

3.3.4.7 Power Supplies

3.3.4.7.1 Both the normal supply and the standby supply is *Yes/No/N.A. *Yes/No/N.A.
capable of continually supplying the largest load
under normal, fire and fault conditions.

3.3.4.7.2 A green lamp when lit indicates normal condition of *Yes/No/N.A. *Yes/No/N.A.
power supply.

3.3.4.7.3 For systems supervised at intervals of 2 hours, or *Yes/No/N.A. *Yes/No/N.A.


that having a link over which a warning of failure of the
normal supply can be given to a remote manned centre,
the battery supply is capable of maintaining the system
in operation for at 1east 24 hours, after which sufficient
capacity should remain to provide an evacuation alarm in
all zones for at least 30 minutes.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 64 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.7.4 For systems not supervised, the battery supply is capable *Yes/No/N.A. *Yes/No/N.A.
of automatically maintaining the system in normal
operation for a period of not less than 24 hours after the
detection of a fault in the normal supply and the
initiation of remedial action.

3.3.4.7.5 For unoccupied building with systems not supervised for *Yes/No/N.A. *Yes/No/N.A.
periods > 24 hours, facilities are provided to give
protection for a period of at least 24 hours after
reoccupation, with sufficient capacity at the end of that
time to sound an evacuation alarm in all zones for at
least 30 minutes.

3.3.4.7.6 For systems backed up by standby generators, the battery *Yes/No/N.A. *Yes/No/N.A.
supply is capable of maintaining operation for a period
of not less than 6 hours, after which sufficient capacity
should remain to provide an evacuation alarm in all
zones for at least 30 minutes.

3.3.4.8 Cables, Wiring and Other Interconnections

3.3.4.8.1 Insulation test of all installed cables and wiring is made *Yes/No/N.A. *Yes/No/N.A.
at 500 V DC and all insulation resistance are 0.5 M
.

3.3.4.8.2 The completed circuit is tested at a voltage *Yes/No/N.A. *Yes/No/N.A.


recommended by the equipment manufacturer.

3.3.2.8.3 Earth continuity and earth-loop impedance is tested and *Yes/No/N.A. *Yes/No/N.A.
the results are in compliance with the EE Code.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 65 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.9 Documentation

3.3.4.9.1 The following equipment list and catalogues are *Yes/No/N.A. *Yes/No/N.A.
provided.

(a) alarm annunciation panel;


(b) repeater panels;
(c) detectors;
(d) manual call points;
(e) alarm sounders;
(f) visual fire alarm signal lamps;
(g) fire resistant cables.

3.3.4.9.2 F.S.D. approval/acceptance letters for the following *Yes/No/N.A. *Yes/No/N.A.


equipment are provided.

(a) alarm annunciation panel;


(b) repeater panels;
(c) detectors;
(d) manual call points;
(e) alarm sounders;
(f) visual fire alarm signal lamps integrated with alarm
sounders.

3.3.4.9.3 Test certificates on fire properties or F.S.D.s prior *Yes/No/N.A. *Yes/No/N.A.


acceptance letters for all the fire resistant cables used are
provided.

3.3.4.9.4 Noise measurement (including background noise) *Yes/No/N.A. *Yes/No/N.A.


records for alarm sounders are provided.

3.3.4.9.5 Calculation showing the required battery capacity is *Yes/No/N.A. *Yes/No/N.A.


provided.

3.3.4.9.6 Letter certifying the completion of the DTL to the *Yes/No/N.A. *Yes/No/N.A.
FSCC/Chubb Centre is provided.

3.3.4.9.7 Confirmation or certification on the compatibility is give *Yes/No/N.A. *Yes/No/N.A.


n by the manufacturers of the fire alarm system for all in
dividual components of a fire alarm system such as fire d
etectors, alarm devices, manual call points, power suppli
es, interfacing equipment, remote indication and control
panels.

3.3.4.9.8 F.S.D. approval letter on Time Related *Yes/No/N.A. *Yes/No/N.A.


System/Transmission Delay Unit is provided.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 66 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.3.4.9.9 A method of test recommended by the supplier to predict *Yes/No/N.A. *Yes/No/N.A.


the failure of the battery during the intervals between
routine tests is provided.

3.3.4.9.10 As-fitted fire service installation drawings including the *Yes/No/N.A. *Yes/No/N.A.
followings are provided :

(a) schematic power supply and distribution diagrams


and layout plans showing the types, size and routing
of all power supply cables, fire resistant cables and
wiring for the fire alarm and detection system;
(b) wiring diagrams and layout plans of all junction
boxes and distribution boards;
(c) floor layout plans showing the location of each fire
detection zone, detectors and detector types, manual
call points, VFA signal lamps, alarm sounders,
alarm annunciation panel and repeater panels.

3.3.4.10 Measuring and Testing Instrument / Equipment


Calibration(Optional for record use)
3.3.4.10.1 Calibration certificates showing that the following
(please specify) testing and measuring instruments or
equipment have been calibrated in the past 12 months are
provided
Type Model No. Serial No.
a)_____________ _____________ _____________
b)_____________ _____________ _____________
c)_____________ _____________ _____________
e)_____________ _____________ _____________
f)_____________ _____________ _____________
g)_____________ _____________ _____________

(Note: Detailed T&C procedure for fire alarm control system and fire alarm control panels (G.S. Section
B8) shall be submitted by the Contractor and approved by the Architect prior to testing and
commissioning)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 67 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.4 Gaseous Extinguishing System

Location/Room :

Type of Gas : *CO2 / FM200 / NAFS III and other approved agents ___________

Type of System :

Total Flooding ( ) Local Application ( )

Modular ( ) Cylinder ( )

Pre-engineered ( ) Engineered ( )

High Pressure ( ) Low Pressure ( )

Single Hazard ( ) Multiple Hazard ( )

Primary Bank Only ( ) With Reserve Bank ( )

Working/Design Drawing Ref. : ________________________________________________

Approved Computer Programme Ref. : __________________________________________

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.4.1 Visual Inspection

3.4.1.1 General

a) Is approved computer programme enclosed? *Yes/No/N.A. *Yes/No/N.A.

b) Is catalogue enclosed? *Yes/No/N.A. *Yes/No/N.A.

c) Is certification for pneumatic test to pipings enclosed? *Yes/No/N.A. *Yes/No/N.A.

d) Does occupancy tally with approved building plans? *Yes/No/N.A. *Yes/No/N.A.

e) Does compartmentation of protected premises tally with *Yes/No/N.A. *Yes/No/N.A.


approved building plans?

f) Does general layout tally with F.S.I. drawings? *Yes/No/N.A. *Yes/No/N.A.

g) Are openings to adjacent compartment or external *Yes/No/N.A. *Yes/No/N.A.


properly sealed or closable automatically during/before
agent discharge?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 68 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

h) Are permanent openings provided with automatic *Yes/No/N.A. *Yes/No/N.A.


shutters?

i) Are warning/instruction notices provided at entrance to *Yes/No/N.A. *Yes/No/N.A.


the protected area?

j) Are warning/instruction notices provided inside the *Yes/No/N.A. *Yes/No/N.A.


protected area which is normally occupied?

3.4.1.2 System Components

a) Do the locations of the following components tally with


the approved drawings regarding :

(i) Audio alarm bell, buzzer, etc.? *Yes/No/N.A. *Yes/No/N.A.

(ii) Visual alarm light, strobe, etc.? *Yes/No/N.A. *Yes/No/N.A.

(iii) Detector? *Yes/No/N.A. *Yes/No/N.A.

(iv) Manual release? *Yes/No/N.A. *Yes/No/N.A.

(v) Piping? *Yes/No/N.A. *Yes/No/N.A.

(vi) Nozzles? *Yes/No/N.A. *Yes/No/N.A.

(vii) Gas cylinder / Agent container? *Yes/No/N.A. *Yes/No/N.A.

(viii) Control/indication panel? *Yes/No/N.A. *Yes/No/N.A.

(ix) Ignition/fuel source shut down device? *Yes/No/N.A. *Yes/No/N.A.

(x) Other mechanical/ electrical/ pneumatic operating *Yes/No/N.A. *Yes/No/N.A.


device?

b) Are the following components approved/listed :

(i) Actuating solenoid? *Yes/No/N.A. *Yes/No/N.A.

(ii) Cylinder valve assembly? *Yes/No/N.A. *Yes/No/N.A.

(iii) Gas Cylinder/agent container? *Yes/No/N.A. *Yes/No/N.A.

(iv) Flexible hose? *Yes/No/N.A. *Yes/No/N.A.

(v) Distributor/selector valve? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 69 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(vi) Pilot cylinder? *Yes/No/N.A. *Yes/No/N.A.

(vii) Alarm bell (for normal application)? *Yes/No/N.A. *Yes/No/N.A.

(viii) Siren/yodalarm? *Yes/No/N.A. *Yes/No/N.A.

(ix) Control/indication panel? *Yes/No/N.A. *Yes/No/N.A.

(x) Remote manual release unit? *Yes/No/N.A. *Yes/No/N.A.

(xi) Detector? *Yes/No/N.A. *Yes/No/N.A.

(xii) Discharge nozzle? *Yes/No/N.A. *Yes/No/N.A.

(xiii) Safety Barrier? *Yes/No/N.A. *Yes/No/N.A.

c) Is permanent nameplate with adequate information *Yes/No/N.A. *Yes/No/N.A.


provided to gas cylinder? (CO2 / FM200 / NAFS III)

d) Is reliable means of indication provided for the *Yes/No/N.A. *Yes/No/N.A.


determination of pressure in gas cylinder?

e) Does the above mentioned indication means account for *Yes/No/N.A. *Yes/No/N.A.
variation of cylinder pressure with temperature?

f) Is sufficient quantity of agent provided? *Yes/No/N.A. *Yes/No/N.A.

g) Is cylinder properly mounted/secured? *Yes/No/N.A. *Yes/No/N.A.

h) Are nozzles provided with markings showing make, type *Yes/No/N.A. *Yes/No/N.A.
and orifice size?

3.4.1.3 Pipings

a) Are pipings properly installed and secured in accordance *Yes/No/N.A. *Yes/No/N.A.


with approved guide?

b) Are all sections of the piping provided with equipotential *Yes/No/N.A. *Yes/No/N.A.
earth bonding?

c) Are pipings suitably protected against mechanical, *Yes/No/N.A. *Yes/No/N.A.


chemical, vibration or other damage?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 70 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

d) Are pipings of the approved type? (Type - __________ *Yes/No/N.A. *Yes/No/N.A.


)

For 25 bar or 42 bar For 25 bar only

BS 3601 Seamless Schedule 80 BS 1387 Heavy Grade Butt Welded


(upto and including 50 mm nominal
pipe size)

ASTM A53 BS 3601 Seamless Schedule 40 (up


to and including 100 mm nominal
pipe sizing)

ASTM A106

JIS 3454

or as approved or as approved

e) Are pipe joints of approved type provided? (Type - *Yes/No/N.A. *Yes/No/N.A.


*screwed/welded/flanged, G.S. Clause B5.13)

3.4.1.4 Detection, Actuation & Control System

a) Is correct type of detector provided? (Type - *Yes/No/N.A. *Yes/No/N.A.


*heat/smoke/______________ )

b) Is operating alarm / indicator provided? (Type *Yes/No/N.A. *Yes/No/N.A.


*Alarm/Indication / Both / Audio / Visual / Olfactory)

c) Do electrical primary A.C. supply and secondary battery *Yes/No/N.A. *Yes/No/N.A.


D.C. supply provide adequate capacity for both the
detection and operating devices?

d) Are the following electrical apparatus intrinsically safe *Yes/No/N.A. *Yes/No/N.A.


or of flame-proof type? (For explosive atmosphere only
e.g. fuel oil tank room)

(i) Detector *Yes/No/N.A. *Yes/No/N.A.

(ii) Fire alarm bell *Yes/No/N.A. *Yes/No/N.A.

(iii) Sparkless type opening/closing device *Yes/No/N.A. *Yes/No/N.A.

(iv) Fan motor *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 71 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(v) Sparkless type ventilating duct damper closing *Yes/No/N.A. *Yes/No/N.A.


device

e) Is manual control suitably protected against mechanical, *Yes/No/N.A. *Yes/No/N.A.


weather or environmental damage?

f) Is manual control easily accessible at all times? *Yes/No/N.A. *Yes/No/N.A.

3.4.1.5 Miscellaneous

a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?

b) Are the gas cylinder rooms clear of debris? *Yes/No/N.A. *Yes/No/N.A.

c) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

d) Is emergency electricity supply available? *Yes/No/N.A. *Yes/No/N.A.

e) Are bar code labels provided to the gas cylinder? *Yes/No/N.A. *Yes/No/N.A.

3.4.1.6 After Discharge Test

a) Is replacement cylinder of correct type with sufficient *Yes/No/N.A. *Yes/No/N.A.


gas pressure and content provided?

b) Is cylinder properly mounted? *Yes/No/N.A. *Yes/No/N.A.

c) Is cylinder properly connected? *Yes/No/N.A. *Yes/No/N.A.

d) Is control/indication panel properly reset? *Yes/No/N.A. *Yes/No/N.A.

e) Is electro-thermal link properly replaced/ reinstated? *Yes/No/N.A. *Yes/No/N.A.

f) Is actuating solenoid properly linked/connected? *Yes/No/N.A. *Yes/No/N.A.

3.4.2 Testing and Commissioning

3.4.2.1 General

a) Is the computer programme for the design of the system *Yes/No/N.A. *Yes/No/N.A.
approved by FSD?

b) Are working/design drawings approved by FSD? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 72 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

c) Is approval letter(s) from FSD enclosed? *Yes/No/N.A. *Yes/No/N.A.

3.4.2.2 Pneumatical Test of Piping

a) Is the pneumatical test of the piping according to the *Yes/No/N.A. *Yes/No/N.A.


following requirements satisfactory?

b) For 25-Bar System only

(i) Test in a closed circuit

(ii) Test for a period of 10 min. at 10 bar

(iii) At the end of test, pressure drop not more than 1


bar

(iv) Pressurizing the piping at 3.5 bar incremental


steps

3.4.2.3 Functional Test of System (System in MANUAL mode)

a) Does AUTO/MANUAL selector key switch function *Yes/No/N.A. *Yes/No/N.A.


properly?

b) Do detectors operate satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

c) If cross-zoning is employed, is the zoning of detectors *Yes/No/N.A. *Yes/No/N.A.


satisfactorily arranged?

d) Does operating alarm/indication function properly? *Yes/No/N.A. *Yes/No/N.A.

e) Does actuating solenoid operate satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

f) Does selector/distributor valve operate properly? *Yes/No/N.A. *Yes/No/N.A.

g) Does the manual control require a force of 18 kg or less *Yes/No/N.A. *Yes/No/N.A.


(or 178 N) to secure operation?

h) Does the manual control require a movement of 356 mm *Yes/No/N.A. *Yes/No/N.A.


or less to secure operation?

i) Is the shut-down of ventilating system satisfactorily *Yes/No/N.A. *Yes/No/N.A.


accomplished?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 73 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

j) Do fire damper opening/closing devices operate *Yes/No/N.A. *Yes/No/N.A.


satisfactorily?

k) If time delay of not more than 30 sec is incorporated, *Yes/No/N.A. *Yes/No/N.A.


does it function properly?

l) Does the battery charger function properly? *Yes/No/N.A. *Yes/No/N.A.

m) Is the telephone link connected and functioning *Yes/No/N.A. *Yes/No/N.A.


properly?

n) Does the system pass the puff test? *Yes/No/N.A. *Yes/No/N.A.

3.4.2.4 Practical Discharge Test of System


(Should be avoided wherever possible)

a) By Designed Agent? *Yes/No/N.A. *Yes/No/N.A.


b) By Approved Substitute? *Yes/No/N.A. *Yes/No/N.A.
c) Discharge agent used? *Yes/No/N.A. *Yes/No/N.A.
- *CO2/FM200/__________________

d) Does agent fully discharge within the time limit *Yes/No/N.A. *Yes/No/N.A.
specified by FSD?

e) Are pipings securely installed to prevent pipe *Yes/No/N.A. *Yes/No/N.A.


displacement or hazardous movement during discharge?

f) Do piping and associated equipment remain *Yes/No/N.A. *Yes/No/N.A.


mechanically and structurally sound after test?

3.4.2.5 Reinstatement of system after discharge (static check)


a) Is replacement cylinder/container of the correct type *Yes/No/N.A. *Yes/No/N.A.
with sufficient pressure and content
provided?

b) Is cylinder/container properly mounted? *Yes/No/N.A. *Yes/No/N.A.

c) Is cylinder/container properly connected? *Yes/No/N.A. *Yes/No/N.A.

d) Is control/indication panel properly reset? *Yes/No/N.A. *Yes/No/N.A.

e) Is ETL properly replaced/reinstated? *Yes/No/N.A. *Yes/No/N.A.

f) Is actuating solenoid properly linked / connected? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 74 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.5 Street Hydrant

3.5.1 Visual Inspection

3.5.1.1 Pipework

a) Is an independent town main connection provided for the *Yes/No/N.A. *Yes/No/N.A.


street hydrant installation alone?

b) Are U/G water pipes to BS EN 545 Class K12 or to BS *Yes/No/N.A. *Yes/No/N.A.


1387 / ISO 65 heavy grade or other approved type?

c) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?

d) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?

e) Are water pipes provided with adequate disconnecting *Yes/No/N.A. *Yes/No/N.A.


flanges, mechanical pipe couplings or screwed unions for
future ease of dismantling?

f) Are bends of long radius type? *Yes/No/N.A. *Yes/No/N.A.

g) Are water pipes installed without being embedded in *Yes/No/N.A. *Yes/No/N.A.


concrete structure?

h) Are valves closed at clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.

i) Are adequately sized manholes provided for valves? *Yes/No/N.A. *Yes/No/N.A.

j) Do water pipes sizes tally with drawings? *Yes/No/N.A. *Yes/No/N.A.

k) Does layout of hydrant tally with approved building *Yes/No/N.A. *Yes/No/N.A.


plans?

l) Are adequate clearances provided around the hydrant for *Yes/No/N.A. *Yes/No/N.A.
its free use?

m) Are hydrants sited 6 metres or greater from the building? *Yes/No/N.A. *Yes/No/N.A.

n) Is water supply pressure adequate? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 75 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.5.1.2 Water Pump


(For installation with pump and sump tank only)

a) Pump/Motor Set Data :

Fire Pump
Duty Standby

Location

Quantity (No(s).)

Manufacturer Pump

Motor

Model No. Pump

Motor

Serial No. Pump

Motor

Motor power (kW)

Pump power (kW)

Flow rate (L/s)

Pressure (kPa)

Starting method

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 76 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

b) Are pump motors rated at 20% higher than the required *Yes/No/N.A. *Yes/No/N.A.
hydraulic power?

c) Are emergency lock-off buttons provided adjacent to *Yes/No/N.A. *Yes/No/N.A.


pump motor with visual and audible indication on the
panel when the pump is locked?

d) Are pump motors protected by HRC fuses? *Yes/No/N.A. *Yes/No/N.A

e) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the supply tank tally with the vertical
plumbing diagram approved by W.S.D.?

f) Are the effective water capacity of the water tanks *Yes/No/N.A. *Yes/No/N.A.
correct?

g) Are the ball valves of the water tanks readily accessible? *Yes/No/N.A. *Yes/No/N.A.

h) Do the sizes of the water pump suction water pipe from *Yes/No/N.A. *Yes/No/N.A.
the tank match the size of the pump suction inlet?

i) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


suction pipe from supply tank?

j) Are levels of suction pipes correct? *Yes/No/N.A. *Yes/No/N.A.

k) Are puddle flanges of the same sizes as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?

l) Are water pumps permanently primed? *Yes/No/N.A. *Yes/No/N.A.

m) Are non-return valve(s) provided to prevent water *Yes/No/N.A. *Yes/No/N.A.


backflow into the water tank?

n) Is anti-overheating circulating pipe provided? *Yes/No/N.A. *Yes/No/N.A.

o) Are pressure gauges of correct Specification? (G.S. *Yes/No/N.A. *Yes/No/N.A.


Clause B1.15).

p) Are isolating cocks/valves provided for pressure *Yes/No/N.A. *Yes/No/N.A.


gauges ?

q) Are equipotential earth bondings provided for all *Yes/No/N.A. *Yes/No/N.A.


sections of pipeworks?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 77 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

r) Are doors to pump rooms clearly labelled "FIRE PUMP" *Yes/No/N.A. *Yes/No/N.A.
()?

s) Are doors to pump rooms provided with locking *Yes/No/N.A. *Yes/No/N.A.


devices?

t) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?

u) Are pump rooms laid clear of any exit or normal *Yes/No/N.A. *Yes/No/N.A.
communication routes through the premises?

v) Are pump rooms clear of debris? *Yes/No/N.A. *Yes/No/N.A.

3.5.1.3 Miscellaneous

a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?

b) Are proper identification provided for pipeworks, *Yes/No/N.A. *Yes/No/N.A.


wirings and equipment?

c) Are water tanks clear of debris? *Yes/No/N.A. *Yes/No/N.A.

Is permanent water supply connected? *Yes/No/N.A. *Yes/No/N.A.


d)
e) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

f) Is emergency electricity supply available ? *Yes/No/N.A. *Yes/No/N.A.

3.5.2 Testing and Commissioning

3.5.2.1 Pipeworks

a) Are hydraulic tests performed satisfactorily for water *Yes/No/N.A. *Yes/No/N.A.


tightness of all sections of the pipeworks ? (At 1.5 times
the highest working pressure for 15 minutes) (Test
records on Part 4.5 Table 1)

b) Is flushing out of all water pipes performed? *Yes/No/N.A. *Yes/No/N.A.

c) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 78 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.5.2.2 Electrical Wiring

a) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C procedure No. 2 for
Electrical Installation and to Electricity Ordinance
requirements?

3.5.2.3 Water Pump

a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current? (Test records on Part 4.5 Table 2)

b) Do the water pumps run at an acceptable noise and *Yes/No/N.A. *Yes/No/N.A.


vibration levels?

c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?

d) Do the water pump protective devices function properly? *Yes/No/N.A. *Yes/No/N.A.

e) Do the float switches in the water tanks for controlling *Yes/No/N.A. *Yes/No/N.A.
the water pumps function properly?

f) Do the high and low water level alarms and indications *Yes/No/N.A. *Yes/No/N.A.
for the water tanks function properly?

g) Are the temperatures of the water pump bearings *Yes/No/N.A. *Yes/No/N.A.


satisfactorily at running condition?

Are the temperatures of the pump motors satisfactorily at *Yes/No/N.A. *Yes/No/N.A.


h) running condition?

i) Do the pressure gauges function properly? *Yes/No/N.A. *Yes/No/N.A.

j) Is water leakage from the pump shafts at an acceptable *Yes/No/N.A. *Yes/No/N.A.


level?

k) Do the non-return valves function properly? *Yes/No/N.A. *Yes/No/N.A.

l) Does the pressure relief valve of the anti-overheating *Yes/No/N.A. *Yes/No/N.A.


circulating pipe function properly? (Operate at
bars)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 79 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

m) Does the change-over from duty to standby pump *Yes/No/N.A. *Yes/No/N.A.


complete within 15 sec.? (Change-over within
sec.)

n) Does the actuation of a bursting fire alarm start the water *Yes/No/N.A. *Yes/No/N.A.
pumps?

3.5.2.4 Street Hydrant

a) Is the water tightness of the hydrant outlets satisfactorily *Yes/No/N.A. *Yes/No/N.A.


when the water pumps are running?

b) Do the flow capacity and pressure tests satisfy FSD's *Yes/No/N.A. *Yes/No/N.A.
requirements as the following Table? (Test Records on
Part 4.5 Table 3)

Pressure and Flow Requirement for Street Hydrant

Min. Flow Rate Min. Running Pressure


(L/s) (kPa)

Each 65 mm outlet 33.3 170


Independently
Two farthest 65 mm outlet 66.7 (total) 170
Discharging simultaneously

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 80 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.6 Drencher System

3.6.1 Visual Inspection

3.6.1.1 Water Supplies

a) Is an independent town main connection provided *Yes/No/N.A. *Yes/No/N.A.


for the drencher system installation alone?

b) Is an independent water tank provided for the drencher *Yes/No/N.A. *Yes/No/N.A.


system?

c) Does the water tank have capacity for operation of the *Yes/No/N.A. *Yes/No/N.A.
drencher system for 30 minutes minimum?

d) Does the size of the incoming water pipe from the town *Yes/No/N.A. *Yes/No/N.A.
mains up to the drencher tank tally with the vertical
plumbing diagram approved by W.S.D.?

e) Is the effective water capacity correct of the *Yes/No/N.A. *Yes/No/N.A.


drencher tank?

f) Are the ball valves of the water tank readily *Yes/No/N.A. *Yes/No/N.A.
accessible?

g) Is the calculation of the water tank size available *Yes/No/N.A. *Yes/No/N.A.


from the Contractor ?

h) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


suction pipe?

i) Are levels of suction pipes correct? *Yes/No/N.A. *Yes/No/N.A.

j) Are puddle flanges of the same size as the water pump *Yes/No/N.A. *Yes/No/N.A.
suction pipes?

k) Are automatic priming arrangements provided for *Yes/No/N.A. *Yes/No/N.A.


suction lift condition?

l) Are sizes of priming water pipes correct? *Yes/No/N.A. *Yes/No/N.A.

m) Is each water pump provided with an independent *Yes/No/N.A. *Yes/No/N.A.


priming tank?

n) Is anti-overheating circulating pipe provided? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 81 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

o) Is vortex inhibitor provided and clear of debris? *Yes/No/N.A. *Yes/No/N.A.

p) Are strainers in water tank cleaned? *Yes/No/N.A. *Yes/No/N.A.

q) Is the tank clear of debris? *Yes/No/N.A. *Yes/No/N.A.

3.6.1.2 Deluge Valve

a) Is the deluge valve of automatic type operated by *Yes/No/N.A. *Yes/No/N.A.


detection system installed in the same area as the
drencher system?

b) Is it operated by a remote manual means? *Yes/No/N.A. *Yes/No/N.A.

c) Does each deluge valve control have less than 72 *Yes/No/N.A. *Yes/No/N.A.
drenches?

3.6.1.3 Spacing and Quantity of Drencher Heads/Water Spray Nozzles

Maximum distance between drencher heads/water spray 2.5m *Yes/No/N.A


nozzles

Maximum distance of drencher from opening/surface 1.25m *Yes/No/N.A

Maximum No. of drencher heads/water spray nozzles on 12 *Yes/No/N.A


any horizontal pipe

Maximum No. of drencher heads/water spray nozzles on 6 *Yes/No/N.A


any vertical pipe

3.6.1.4 Pipeworks

a) Are water pipes up to 150 mm dia. to BS 1387 / ISO 65 *Yes/No/N.A. *Yes/No/N.A.


medium grade or other approved type?

b) Are water pipes larger than 150 mm dia. to BS EN 545 *Yes/No/N.A. *Yes/No/N.A.
Class K12 or other approved type?

c) Are U/G water pipes to BS EN 545 Class K12 or to BS *Yes/No/N.A. *Yes/No/N.A.


1387 / ISO 65 heavy grade or other approved type?

d) Are U/G water pipes protected with two coats of *Yes/No/N.A. *Yes/No/N.A.
bituminous paint and wrapped with self-amalgamating
tapes and mastics having 55% overlapping?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 82 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

e) Are water pipes up to 65 mm dia. provided with screw *Yes/No/N.A. *Yes/No/N.A.


joints?

f) Are water pipes of dia. larger than 65 mm and up to 150 *Yes/No/N.A. *Yes/No/N.A.
mm provided with mechanical pipe couplings?

g) Are water pipes of dia. larger than 150 mm provided *Yes/No/N.A. *Yes/No/N.A.
with flanged joints and flanged fittings?

h) Are U/G water pipes provided with mechanical pipe *Yes/No/N.A. *Yes/No/N.A.
couplings or other approved couplings?

i) Are water pipes provided with adequate disconnecting *Yes/No/N.A. *Yes/No/N.A.


flanges, mechanical pipe couplings or screwed unions for
future ease of dismantling?

j) Are pipes suitably connected to the fire pumps, *Yes/No/N.A. *Yes/No/N.A.


hydrants, hose reels and fire service inlets?

k) Are bends of water pipes larger than 65 mm dia. and *Yes/No/N.A. *Yes/No/N.A.
bends of water pipes installed outside false
ceiling/concealed void of long radius type, or as
approved?

l) Are galvanised mild steel sleeves provided for pipes *Yes/No/N.A. *Yes/No/N.A.
through wall or slab?

m) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
wall or slab filled with approved fire proof material and
sealant?

n) Are fire rated pipe sleeves provided for pipes through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab?

o) Are spaces between water pipes and pipe sleeves through *Yes/No/N.A. *Yes/No/N.A.
fire rated wall or slab filled with approved fire proof
material and sealant?

p) Are adequate clearances provided between pipe and *Yes/No/N.A. *Yes/No/N.A.


sleeve?

q) Are sleeves projected at least 100 mm above finish floor *Yes/No/N.A. *Yes/No/N.A.
level and at least 150 mm above roof finish

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 83 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

r) Are pipes installed without being embedded in concrete *Yes/No/N.A. *Yes/No/N.A.


structure?

s) Are adequate pipe hangers or supports provided as *Yes/No/N.A. *Yes/No/N.A.


required?

t) Are pipe hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?

u) Are expansion pipe joints provided at location through *Yes/No/N.A. *Yes/No/N.A.


building expansion joint?

v) Are adequate air vents and drain cocks provided? *Yes/No/N.A. *Yes/No/N.A.

w) Are valves closed at clockwise rotation? *Yes/No/N.A. *Yes/No/N.A.

x) Are valves locked at OPEN position with leather strip *Yes/No/N.A. *Yes/No/N.A.
and padlock?

y) Do water pipe sizes tally with drawings? *Yes/No/N.A. *Yes/No/N.A.

z) Can all sections of water pipes be drained? *Yes/No/N.A. *Yes/No/N.A.

aa) Are the water pipes suitably sloped and drained to the *Yes/No/N.A. *Yes/No/N.A.
installation drain valve as far as practical?

ab) Are installation drain pipes and valves of correct sizes? *Yes/No/N.A. *Yes/No/N.A.

ac) Are correct sizes of drain pipes and valves provided as *Yes/No/N.A. *Yes/No/N.A.
following for pipeworks to be drained?

ad) Are pressure gauges of correct Specification? (G.S. *Yes/No/N.A. *Yes/No/N.A.


Clause B1.15)

ae) Are isolating cocks/valves provided for pressure gauges? *Yes/No/N.A. *Yes/No/N.A.

af) Are strainers in water pipes cleaned? *Yes/No/N.A. *Yes/No/N.A.

ag) Are main stop valves secured at OPEN position by *Yes/No/N.A. *Yes/No/N.A.
padlock or riveted strap?

ah) Are main stop valves placed at proximity to an entrance *Yes/No/N.A. *Yes/No/N.A.
to the premises?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 84 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

ai) Are location plates for main stop valves provided with *Yes/No/N.A. *Yes/No/N.A.
correct wording and character sizes?

aj) Are each set of alarm valve and alarm gong provided *Yes/No/N.A. *Yes/No/N.A.
with identification label and number?

ak) Is the total length of water pipe between alarm valve and *Yes/No/N.A. *Yes/No/N.A.
alarm gong 25 m or less?

al) Is the water pipe between alarm valve and alarm gong of *Yes/No/N.A. *Yes/No/N.A.
correct size?

am) Is a deluge valve installed closed to the inlet for the *Yes/No/N.A. *Yes/No/N.A.
drencher system?

an) Are manually operating devices complete with operating *Yes/No/N.A. *Yes/No/N.A.
instruction displayed nearby and provided on refuge
floor?

ao) Is a hydraulic calculation of the drencher system *Yes/No/N.A. *Yes/No/N.A


provided by the Contractor?

ap) Are equipotential earth bondings provided for the *Yes/No/N.A. *Yes/No/N.A.
pipeworks?

3.6.1.5 Drencher Pump

a) Are the motor/pump set rotating parts protected by safety *Yes/No/N.A. *Yes/No/N.A.
guard?

b) Is pump motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?

c) Are emergency lock-off buttons provided adjacent to *Yes/No/N.A. *Yes/No/N.A.


pump motors with visual and audible indication on the
panel when the pump is locked?

d) Are pump motors protected by HRC fuse? *Yes/No/N.A. *Yes/No/N.A.

e) Is secondary power supply provided for electric pumps? *Yes/No/N.A. *Yes/No/N.A.

f) Is standby pump provided for diesel engine driven *Yes/No/N.A. *Yes/No/N.A.


pumps?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 85 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

g) Are doors to pump rooms clearly labelled "DRENCHER *Yes/No/N.A. *Yes/No/N.A.


PUMP" ()?

h) Are doors to pump rooms provided with locking *Yes/No/N.A. *Yes/No/N.A.


devices?

i) Are doors to pump rooms provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closers?

j) Are pump rooms clear of debris? *Yes/No/N.A. *Yes/No/N.A.

k) Are alternative means of starting the pump manually, in *Yes/No/N.A. *Yes/No/N.A.


addition to manual fire alarm call points provided, where
the pump is not electrically operated?

l) Are starting instructions for diesel driven pump *Yes/No/N.A. *Yes/No/N.A.


prominently displayed in the pump room?

m) Can the pump just be started by switching off at the *Yes/No/N.A. *Yes/No/N.A
pump control not installed near the pump, rather than by
any automatic means?

n) Are manual fire alarm call points wired for starting the *Yes/No/N.A. *Yes/No/N.A.
pump?

o) Are the pumps duplicated for duty and standby use? *Yes/No/N.A. *Yes/No/N.A.

p) Are the fire pump starters wired through a selector *Yes/No/N.A. *Yes/No/N.A.
switch for duty and standby pump selection?

q) Are pumps permanently primed? *Yes/No/N.A. *Yes/No/N.A

r) Are non-return valve(s) provided to prevent water *Yes/No/N.A. *Yes/No/N.A


backflow into the water tank?

s) Are the status of each fire pump comprising Power *Yes/No/N.A. *Yes/No/N.A.
Supply On, Pump Running and Pump Failed
monitored and displayed at the pump control panel in the
pump room?

t) Are such signal repeated to fire control room or a status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 86 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

u) Are two/three one as standby intermediate booster *Yes/No/N.A. *Yes/No/N.A.


pumps of the same capacity provided to achieve required
flow and pressure within 30 seconds?

v) Do the intermediate booster pumps continue to run *Yes/No/N.A. *Yes/No/N.A.


irrespective of power interruption when start button is
activated?

w) Are start/stop push buttons with pump running indication *Yes/No/N.A. *Yes/No/N.A.
light and buzzer provided adjacent to the fire service
inlet?

3.6.1.6 Miscellaneous

a) Are all pipeworks and metal works properly painted *Yes/No/N.A. *Yes/No/N.A.
(G.S. Clause B13.3)?

b) Are proper identification provided for pipeworks, *Yes/No/N.A. *Yes/No/N.A.


wirings and equipment?

c) Are water tanks clear of debris? *Yes/No/N.A. *Yes/No/N.A.

d) Is permanent water supply connected? *Yes/No/N.A. *Yes/No/N.A.

e) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

f) Is emergency electricity supply available ? *Yes/No/N.A. *Yes/No/N.A.

3.6.2 Testing and Commissioning

3.6.2.1 Pipeworks

a) Are hydraulic tests performed satisfactorily for water *Yes/No/N.A. *Yes/No/N.A.


tightness of all sections of the pipeworks ? (At 1.5 times
the highest working pressure for 15 minutes) (Test
records on Part 4.6 Table 1)

b) Is flushing out of all water pipes performed? *Yes/No/N.A. *Yes/No/N.A.

c) Do the automatic air release valves function properly? *Yes/No/N.A. *Yes/No/N.A.

d) Do the gate valves, stop valves and globe valves function *Yes/No/N.A. *Yes/No/N.A.
properly?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 87 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.6.2.2 Electrical Wiring

a) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C procedure No. 2 for
Electrical Installation?

b) Does the battery charger function properly? *Yes/No/N.A. *Yes/No/N.A.

c) Is the telephone link connected and functioning? *Yes/No/N.A. *Yes/No/N.A.

3.6.2.3 Means of Actuation

a) Is the drencher system operated on actuation the *Yes/No/N.A. *Yes/No/N.A.


corresponding detector system, for automatic system?

b) Is the drencher system operated on actuation of manual *Yes/No/N.A. *Yes/No/N.A.


release?

3.6.2.4 Water Pump

a) Do the water pumps and motors run at the designed *Yes/No/N.A. *Yes/No/N.A.
discharge water pressure and operating electrical
current?

b) Do the water pumps run at an acceptable noise and *Yes/No/N.A. *Yes/No/N.A.


vibration levels?

c) Do the water pump control switches and indicating lights *Yes/No/N.A. *Yes/No/N.A.
function properly?

d) Do the water pump protective devices function properly? *Yes/No/N.A. *Yes/No/N.A.

e) Do the float switches in the water tanks controlling the *Yes/No/N.A. *Yes/No/N.A.
water pumps function properly?

f) Are the temperatures of the water pump bearings *Yes/No/N.A. *Yes/No/N.A.


satisfactorily at running condition?

g) Do the pressure gauges function properly? *Yes/No/N.A. *Yes/No/N.A.

h) Is water leakage from the pump shafts at an acceptable *Yes/No/N.A. *Yes/No/N.A.


level?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 88 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

i) Do the non-return valves function properly? *Yes/No/N.A. *Yes/No/N.A.

j) Does the pressure relief valve of the anti-overheating *Yes/No/N.A. *Yes/No/N.A


circulating pipe function properly? (Operate at
bar)

k) Do the pressure switches controlling the jockey, duty and *Yes/No/N.A. *Yes/No/N.A.
standby pumps operate properly?

l) Are the pumps fully operational within 30 sec. after *Yes/No/N.A. *Yes/No/N.A.
starting ?

3.6.2.5 Proving of Water Supplies

a) Do the installation pressure and flow rate comply with *Yes/No/N.A. *Yes/No/N.A.
the FSD requirements?

b) Is the water flow from each nozzle the same and with a *Yes/No/N.A. *Yes/No/N.A.
similarly uniform flow pattern?

c) Is the water flow rate maintained at not less than 10 *Yes/No/N.A. *Yes/No/N.A.
L/min per m2 of external wall opening and allowing for
wastage and uneven flow (15% additional capacity)?

d) Is the hydraulic pressure at either end along any water *Yes/No/N.A. *Yes/No/N.A.
pipes identical?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 89 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.7 Audio/Visual Advisory System

3.7.1 Visual Inspection

3.7.1.1 General

a) Does the layout of flashing light points and loudspeakers *Yes/No/N.A. *Yes/No/N.A.
tally with the latest approved building plans?

b) Are the flashing lights and loudspeakers provided for all *Yes/No/N.A. *Yes/No/N.A.
areas that required the system?

3.7.1.2 Visual System

a) Is a system of coloured and flashing light installed? *Yes/No/N.A. *Yes/No/N.A.

b) Is the above supplemented by low-level directional signs *Yes/No/N.A. *Yes/No/N.A.


to indicate :

(ii) the floor(s) to be evacuated by operating the


lights on that floor/those floors in flashing mode?

(ii) the evacuation routes by following the low-level


directional signs ?

c) Do the flashing lights remain intact? *Yes/No/N.A. *Yes/No/N.A.

d) Do the low level directional signs remain intact? *Yes/No/N.A. *Yes/No/N.A.

e) Are the low level directional signs of self luminous types *Yes/No/N.A. *Yes/No/N.A.
and conform to BS5499 Part 2, or of photoluminous type
to DIN 67510 Part 4 or equivalent?

f) Are the colour of the lens/lamps of the flashing lights *Yes/No/N.A. *Yes/No/N.A.
meet FSD requirements?

g) Does the visual system comply with the Code of Practice *Yes/No/N.A. *Yes/No/N.A.
for Minimum Fire Service Installations and Equipment
and Inspection, Testing and Maintenance of Installations
and Equipment (FSDCOP), BS 5499 and BS 4533?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 90 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

h) Do the directional signs internally illuminated and in *Yes/No/N.A. *Yes/No/N.A.


compliance with BS 5499 Part 1 Table 10?

i) Are the lamp elements positioned to produce the best *Yes/No/N.A. *Yes/No/N.A.
illumination effect for the sign?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 91 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

j) Is a flashing light control gear integrated with each sign? *Yes/No/N.A. *Yes/No/N.A.

k) Is an independent circuit including a separate set of *Yes/No/N.A. *Yes/No/N.A.


lamp-holder, wiring and protective gear provided for
each lamp element?

l) Are the lamp elements in the ON condition in normal *Yes/No/N.A. *Yes/No/N.A.


situation?

3.7.1.3 Audio System

a) Desktop Microphone

(i) Is desktop microphone single zone type complete *Yes/No/N.A. *Yes/No/N.A.


with condenser microphone on gooseneck for use
with the amplifier?

(ii) Is it complete with a minimum of 1m length *Yes/No/N.A. *Yes/No/N.A.


cable and a plug?

b) Amplifier/Preamplifier

(i) Is the audio system provided with pre-amplifier *Yes/No/N.A. *Yes/No/N.A.


and amplifier of sufficient power to drive all the
loudspeakers and other equipment in the system?

(ii) Does each amplifier and amplifier respectively *Yes/No/N.A. *Yes/No/N.A.


have a 100% standby unit, so arranged that if any
one unit failed, the corresponding standby unit
shall take up the duty for the respective operation
automatically within 15 seconds?

(iii) Are amplifiers fully transistorized solid state *Yes/No/N.A. *Yes/No/N.A.


device?

(iv) Are the amplifiers provided with at least 10% *Yes/No/N.A. *Yes/No/N.A.
spare capacity/power to drive all the speakers
within the broadcasting zone ?

(v) Does each amplifier have a regulation of rated *Yes/No/N.A. *Yes/No/N.A.


power output from no load to full load of 2 dB?

(vi) Does the amplifier have an audio response level *Yes/No/N.A. *Yes/No/N.A.
within +2 dB from 50 Hz to 14 kHz at full output,
and the total harmonic distortion not exceed 1%
at full load?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 92 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(vii) Is the noise level of each amplifier at least 40 dB *Yes/No/N.A. *Yes/No/N.A.


below maximum output with all inputs and
outputs correctly terminated, and sensitivity to be
such that full output can be obtained from a 2 mV
microphone or equivalent input?

(viii) Is amplifier maintaining a damping factor of not *Yes/No/N.A. *Yes/No/N.A.


less than three over the frequency range of 100 to
5,000 Hz?

(ix) Does amplifier have a low hum level and low *Yes/No/N.A. *Yes/No/N.A.
over-shoot or ringing when a square wave
generator is connected to the input level within
the working range and variable tone control
providing attenuation of the high frequencies, i.e.
0 20 dB at 8 kHz?

(x) Is the amplifier of constant voltage output type *Yes/No/N.A. *Yes/No/N.A.


not requiring dummy load to maintain matching
of the amplifier output?

(xi) Is the output provided with an overload *Yes/No/N.A. *Yes/No/N.A.


protection device to prevent damage to the output
stage from overload or a short circuit on the
speaker lines?

(xii) Are the signal incoming leads terminate at the *Yes/No/N.A. *Yes/No/N.A.
rear of the amplifier through suitable screened
type plug mountings?

(xiii) Is a screw driver adjustment provided at the rear *Yes/No/N.A. *Yes/No/N.A.


for each additional input for preset balancing of
the inputs, when more than one input is required?

(xiv) Are input sockets and output terminals well *Yes/No/N.A. *Yes/No/N.A.
separated and in separate cut-outs in order to
prevent coupling between the amplifier input and
output?

(xv) Is preamplifier provided with connection to *Yes/No/N.A. *Yes/No/N.A.


power amplifier, microphone, CD deck and
cassette deck?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 93 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(xvi) Does preamplifier have built in On/Off switch, *Yes/No/N.A. *Yes/No/N.A.


headphone outlet and volume control for each
channel, and with a LED VU meter provided to
indicate the output level?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 94 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

(xvii) Is the power amplifier completed with mixer, for *Yes/No/N.A. *Yes/No/N.A.
single broadcasting zone?

(xviii) Is the power amplifier capable of connecting with *Yes/No/N.A. *Yes/No/N.A.


microphone, CD deck and cassette deck?

(xix) Does each power amplifier have built in with *Yes/No/N.A. *Yes/No/N.A.
On/Off switch, headphone outlet, volume control
for each channel and matching transformers with
tapping to enable loudspeakers to be driven at
100V, 70V or 50V up to 8?

(xx) Is an LED VU meter provided to indicate the *Yes/No/N.A. *Yes/No/N.A.


output level?

(xxi) Is the power output adequate for the connected *Yes/No/N.A. *Yes/No/N.A.
loudspeakers in the broadcasting zone?

(xxii) For multiple broadcasting zones, is each zone *Yes/No/N.A. *Yes/No/N.A.


provided with a power amplifier?

(xxiii) Does power amplifier provided with input *Yes/No/N.A. *Yes/No/N.A.


transformers for audio inputs from the
preamplifier and built-in loudspeaker matching
transformer?

(xxiv) Does power amplifier have built in On/Off *Yes/No/N.A. *Yes/No/N.A.


switch, headphone outlet and an LED VU meter
showing the output level?

(xxv) Is the power output adequate for the number of *Yes/No/N.A. *Yes/No/N.A.
connected loudspeakers within the zone?

c) Loudspeaker

(i) Are loudspeakers provide a crisp, clear audio *Yes/No/N.A. *Yes/No/N.A.


reproduction for voice and alarm tone signalling,
designed for fast and easy surface/flush
installation on ceiling or wall?

(ii) Are they constructed of sheet steel or high impact *Yes/No/N.A. *Yes/No/N.A.
ABS plastic in white colour or as specified
matching the false ceiling or wall finishes?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 95 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(iii) Does the back of each loudspeaker have an *Yes/No/N.A. *Yes/No/N.A.


enclosure to prevent ingress of dirt to the speaker
zone?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 96 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(iv) Is loudspeaker equipped with tapped transformer *Yes/No/N.A. *Yes/No/N.A.


suitable for the system operating voltage and
having individual attenuator?

(v) Is the attenuator integral with the speaker unit *Yes/No/N.A. *Yes/No/N.A.
and comprise carbon type volume controls with
adjustment?

(vi) Does loudspeaker have a maximum output rating *Yes/No/N.A. *Yes/No/N.A.


of at least 1 watt and a frequency response of
within +3 and 7 dB from 100 to 10,000 Hz with
respect to 1 kHz?

d) Cassette Deck

(i) Does cassette deck have two individual cassette *Yes/No/N.A. *Yes/No/N.A.
players with standard interlocking set of play,
stop, pause, fast forward and fast reverse buttons
and auto-reverse playback feature?

(ii) Does it have a playing tape speed of 4.75 cm/s *Yes/No/N.A. *Yes/No/N.A.
and an nominal output signal of 1 V, and a signal
to noise ratio better than 40 dB?

(iii) Has the recorded message been submitted to the *Yes/No/N.A. *Yes/No/N.A.
Architect for approval?

3.7.1.4 Control Panel/Console

a) Is the control panel/console located near the main *Yes/No/N.A. *Yes/No/N.A.


entrance or in Fire Control Room?

b) Is the control panel/console properly labelled and *Yes/No/N.A. *Yes/No/N.A.


identified in both English and Chinese characters?

c) Is the control panel/console approved by FSD and *Yes/No/N.A. *Yes/No/N.A.


compatible with the loudspeaker and flashing light
system?

d) Is the control panel/console of robust construction with *Yes/No/N.A. *Yes/No/N.A.


hinged door, gasket and cylinder type lock?

e) Is the whole system fail-safe? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 97 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.7.1.5 Power Supply/Wiring

a) Is the permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

b) Is the battery an approved type? *Yes/No/N.A. *Yes/No/N.A.

c) Are the wiring in concealed conduits? *Yes/No/N.A. *Yes/No/N.A.

d) Are all cables running continuously from the originating *Yes/No/N.A. *Yes/No/N.A.
point to termination, with no joint or connector?

e) Are the wirings from amplifier output circuits to *Yes/No/N.A. *Yes/No/N.A.


loudspeakers in twin 16/0/20 figure-of-eight insulated
conductors?

f) Is each loudspeaker correctly phased? *Yes/No/N.A. *Yes/No/N.A.

g) Are components include the following items and any *Yes/No/N.A. *Yes/No/N.A.
other items necessary for the proper control and
operation of the system to the satisfaction of the Fire
Services Department?

(i) Microphone control panel.

(ii) Speaker zone switchbank and annunciator


module.

(iii) Tape transfer, power supervisor and remote


transmission module.

(iv) Automatic timer sequencer which shall be a multi-


function assembly to provide pre-recorded
messages, timing sequences, transfer function
plus supervisory signal to amplifiers.

(v) Alarm failure transfer units which shall transfer


audio output from main duty amplifiers to
standby amplifiers upon detecting the absence of
a supervisory signal.

(vi) General alarm and all call module.

(vii) Alarm input transfer module for controlling the


amplifiers.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 98 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

h) Does the microphone control panel contain dual pre- *Yes/No/N.A. *Yes/No/N.A.
amplifiers continuously supervised?

i) Can the microphone control panel transfer to the standby *Yes/No/N.A. *Yes/No/N.A.
pre-amplifier upon failure of the duty unit?

j) Is it provided with a noise cancelling and microphone *Yes/No/N.A. *Yes/No/N.A.


having a UL listed and supervised coil cord?

k) Does it include provision for automatic alarm zone *Yes/No/N.A. *Yes/No/N.A.


override of speaker switching to ensure proper alarm
zoning should selector switches be left in an incorrect
mode?

l) Does the speaker zone selector switchbank control the *Yes/No/N.A. *Yes/No/N.A.
audio dispersion throughout the protected premises?

m) Does each switch permit the transfer of its zone of *Yes/No/N.A. *Yes/No/N.A.
speakers into either all call, page and fire operation
modes?

n) Will the failure of any zone be indicated by the *Yes/No/N.A. *Yes/No/N.A.


corresponding amber LED?

o) Are indicators for alarm and switchbank trouble *Yes/No/N.A. *Yes/No/N.A.


provided?

p) Do tape transfer, power supervisor and remote *Yes/No/N.A. *Yes/No/N.A.


transmission module supervise the remote rack
equipment, provide output and supervision of the remote
transmitting function, and control the sequencing of
evacuation tape messages and the selection of tape track?

q) Will the system cause any interference with all electrical *Yes/No/N.A. *Yes/No/N.A.
or electronic system, the telephone system, radio paging
system, audible paging and other communication system
and vice versa, whether they are in operation or not?

r) Is the operation of all controls automatic and as simple as *Yes/No/N.A. *Yes/No/N.A.


possible?

s) Have the operating procedures been provided to give *Yes/No/N.A. *Yes/No/N.A.


concise and clear indications?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 99 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

t) Are these indications accompanied by the connection *Yes/No/N.A. *Yes/No/N.A.


diagram which show the various operation alternatives
available to each equipment?

u) Do all equipment mounted in well ventilated but water *Yes/No/N.A. *Yes/No/N.A.


protected metal enclosure and equipment rack?

v) Where permanently fixed in position, do the top and *Yes/No/N.A. *Yes/No/N.A.


undersides of the equipment readily accessible by means
of removable panels?

w) Are the metal enclosures secured and have sufficient *Yes/No/N.A. *Yes/No/N.A.
space for cable routing and bending?

x) Do all operating controls and equipment adequately *Yes/No/N.A. *Yes/No/N.A.


labelled to assist ease of operation and maintenance of
the system?

y) Is the battery charger of automatic trickle charge type? *Yes/No/N.A. *Yes/No/N.A.

z) Is the battery charger provided with a manual booster *Yes/No/N.A. *Yes/No/N.A.


charging facility?

aa) Is the battery charger provided with voltmeter and *Yes/No/N.A. *Yes/No/N.A.
charging ammeter?

3.7.1.6 Miscellaneous

a) Are proper identification provided for wirings and *Yes/No/N.A. *Yes/No/N.A.


equipment?

3.7.2 Testing and Commissioning

3.7.2.1 Operation of the System

a) Is the audio/visual advisory system interconnected with *Yes/No/N.A. *Yes/No/N.A.


the fire alarm system of the building?

b) When the fire alarm is activated, will the following *Yes/No/N.A. *Yes/No/N.A.
operations be performed automatically?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 100 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(i) The flashing light control gear of all the


illuminated directional signs and exit signs which
are incorporated with flashing lights within the
fire alarm zone shall operate. The lamp elements
shall be switched on and off continuously at a
duration of 1 to 2 seconds. The flashing rate shall
be continuously adjustable between 30 60 times
per minute. All the lamp elements in the
directional sign shall be lighted up and turned off
simultaneously to produce the maximum visual
effect. The process shall continue until the fire
alarm is reset. Then the lamp elements shall the
switched back to the normal ON condition
automatically and shall be switched to the
flashing mode again on receiving any further fire
alarm signal.

(ii) The alarm bells and flashing light units within the
alarm zone shall operate. After 10 seconds, the
alarm bells shall stop while the flashing light units
shall continue to flash. Then the pre-recorded
audio alarm messages shall announce within the
alarm zone to alert the occupants and direct them
to evacuate immediately following the directional
and exit signs. The alarm bells and the audio
alarm messages shall repeat in sequence
continuously until the fire alarm has been reset at
the fire alarm panel.

c) Does audio alarm message in Cantonese and English *Yes/No/N.A. *Yes/No/N.A.


announced repeatedly with the audio alarm bell signal in
sequence?

d) Is the message in English as follow or as required by the *Yes/No/N.A. *Yes/No/N.A.


Fire Services Department?

This is an emergency situation. Please keep calm.


Follow the flashing lights to the nearest exit. Do not use
the lift.

e) Is the message audible in all areas within the specified *Yes/No/N.A. *Yes/No/N.A.
zone of the building including toilets, stores, staircases,
etc.?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 101 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

f) Is the signal to noise ratio less than 40 dB when the *Yes/No/N.A. *Yes/No/N.A.
loudspeaker output level in the area concerned is not less
than 20 dB above the background noise level normally
expected in the respective area during fire conditions?

g) Is the variation in sound power level between the outlet *Yes/No/N.A. *Yes/No/N.A.
nearest to and farthest from the amplifier not exceeding 3
dB ?

3.7.2.2 Power Supply

a) Is the battery capable of operating the system at *Yes/No/N.A. *Yes/No/N.A.


maximum alarm condition for at least 30 min.?

b) Is the battery capable of operating the system at normal *Yes/No/N.A. *Yes/No/N.A.


condition for at least 24 hours or 18 hours with
emergency generator back-up ?

c) Is the battery charger capable of recharging the batteries *Yes/No/N.A. *Yes/No/N.A.


from fully discharged to fully charged within 24 hours?

3.7.2.3 Testing of Wiring

a) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C procedure No. 2 for
Electrical Installation and the Electricity Ordinance
requirements?

b) Is the signal wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the General Requirement for Electronic
Contracts?

c) Is the wiring so arranged that any damage to the wiring *Yes/No/N.A. *Yes/No/N.A.
for any one loudspeaker or directional sign will not
affect the proper operation of other loudspeakers or
directional signs?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 102 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.8 Portable Hand Operated Approved Appliances

3.8.1 Visual Inspection

a) Are the appliances in the list of FSD approved? *Yes/No/N.A. *Yes/No/N.A.

b) Are all mounting fixtures provided and fixed in place? *Yes/No/N.A. *Yes/No/N.A.

c) Is sand bucket of 10 litres of more? *Yes/No/N.A. *Yes/No/N.A.

d) Is fire extinguisher rechargeable hand-operated type? *Yes/No/N.A. *Yes/No/N.A.

e) Is fixed sprayer unit of self-contained automatically *Yes/No/N.A. *Yes/No/N.A.


operated inert gas or dry powder type fixed with a
sprinkler head of 68oC?

f) Is there any observable damage on the appliance? *Yes/No/N.A. *Yes/No/N.A.

g) Are all fire extinguishers and fixed sprayer unit provided *Yes/No/N.A. *Yes/No/N.A.
with certificates signed by a registered class 3 fire
contractor? (Certificates should be enclosed)

h) Are bar code labels provided? *Yes/No/N.A. *Yes/No/N.A.

i) Is batch approval certificate for fire extinguishers *Yes/No/N.A. *Yes/No/N.A.


available?

j) Are fire extinguishers in public areas or at outdoors *Yes/No/N.A. *Yes/No/N.A.


installed as approved?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 103 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Notes on Fire Extinguishers and Fire Blankets (Suitability and Maintenance)

I. CARBON DIOXIDE TYPE EXTINGUISHERS


Use: On electrical fires, flammable liquids, delicate equipment, important documents, or fires in
confined spaces.

Note: Vapours will asphyxiate. Withdraw to open air after use.

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

(i) The total weight should be checked against that recorded when the extinguisher was put
into service. If a loss of weight of more than 10 per cent is detected, the extinguisher
should be discharged and returned to the suppliers for examination, test and recharging.

(ii) The body of the extinguisher should be examined and, if there are signs of damage or
extensive external corrosion, the extinguisher should be discharged and returned to
suppliers for examination, test and recharging.

(iii) The discharge horn and hose should be checked to see that it moves freely and should be
replaced if damaged is detected.

(iv) Hydraulic pressure test should be carried out every five years on the cylinder in accordance
with the manufacturers' instructions. Extreme care should be exercised when preparing and
conducting the test.

(v) Unserviceable extinguisher should be discharged prior to disposal.


]

II. WATER TYPE EXTINGUISHERS

Use: On fires involving woods, textiles and paper.

Never: On fires involving electrical or flammable liquids or metals.

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.

(ii) Remove the headcap to check the liquid level. The liquid should be topped up as necessary.

(iii) The nozzle, strainer and internal discharge tube should be checked for cleanliness and free from
obstruction. Defective items shall be replaced.

(iv) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 104 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

(v) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.

(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.

(vi) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.

(viii) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.

(ix) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.

(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher.

(STORED-PRESSURE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.

(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.

(iii) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.

(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all extinguishers
should be overhauled and recharged.

(v) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.

(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers instructions. Extreme care should be exercised when preparing and conducting
the test.
(vi) Unserviceable extinguisher should be discharged prior to disposal.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 105 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

III. DRY POWDER TYPE EXTINGUISHERS

Use: On most fires, flammable liquids, metal fires or electrical fires.

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.

(ii) The extinguisher should be weighed to check that it contains the correct weight of powder. The
weight when fully charged should be recorded at the time of charging. If the weight is found to
have dropped by more than 10 per cent, the dry powder should be replaced by a fresh charge. Care
should be taken not to mix different types of dry powder because they could react with one
another.

(iii) The powder should be agitated to ensure it is free from caking.

(iv) Remove the headcap to check the condition of powder. The chemical should be renewed if it is not
in good condition.

(v) The nozzle and discharge control (if fitted) should be checked for cleanliness and free from
obstruction. Defective items shall be replaced.

(vi) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.

(vi) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.

(viii) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.

(ix) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.

(x) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.

(xi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 106 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

(xii) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
the dry powder should be collected for subsequent re-cycling/disposal. Never empty the contents
by discharging the extinguisher.

(xiii) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and the dry powder should be collected for subsequent re-cycling/disposal. Never empty
the contents by discharging the extinguisher.

(STORED-PRESSURE TYPE)
(i) The extinguisher should be weighed to check it contains the correct weight of powder. If the
weight is found to have dropped by more than 10 per cent, the dry powder should be replaced by a
fresh charge. Care should be taken not to mix different types of dry powder because they could
react with one another.

(ii) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.

(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.

(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.

(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. The dry powder should be discharged to an enclosure for
collection and subsequent re-cycling/disposal. Should any extinguisher fail in the test, all
extinguishers should be overhauled and recharged.

(vi) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.

(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(viii) Unserviceable extinguisher should be discharged prior to disposal. The dry powder should be
discharged to an enclosure for collection and subsequent re-cycling/disposal.

NOTE:
(a) Dry powder extinguishers must be thoroughly dry internally before they are recharged.
(b) Advice should be obtained from the Fire Services Department as to the possible reaction between the
powder or expellent and the material to protected.

IV. CLEAN AGENT FIRE EXTINGUISHERS

Use: On electrical fires, flammable liquids, delicate equipment, important documents.

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 107 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

(PORTABLE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.

(ii) The extinguisher should be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher should be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.

(iii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.

(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.

(v) If there are signs of damage or external corrosion, the extinguisher should be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.

(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(vii) Unserviceable extinguisher should be discharged to a closed recycling system prior to disposal.

(FIXED SPRAYER UNIT)


(i) The pressure indicating device (if fitted) should be checked to see the correct pressure is being
maintained within the extinguisher body.

(ii) The extinguisher should be weighed to check against the total weight record when it is put into
service. If a loss of weight of more than 10 per cent is detected, the extinguisher should be
discharged to a closed recycling system and returned to the supplier for examination, test and
recharging.

(iii) The deflector and the sensing element should be checked and cleaned.

(iv) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.

(v) If there are signs of damage or external corrosion, the extinguisher should be discharged to a closed
recycling system and returned to the suppliers for examination, test and recharging.

(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(vi) Unserviceable extinguisher should be discharged to a closed recycling system prior to disposal.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 108 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

V. FOAM (CHEMICAL) TYPE EXTINGUISHERS

Use: On fires involving flammable liquids.

Never: On electrical fires.

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

(i) The nozzle and the vent holes in the cap should be checked for cleanliness and free from
obstruction.

(ii) Remove the headcap to check the liquid levels in the body and in the inner container. Any slight
loss may be made up with water; otherwise a new charge should be used.

(iii) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.

(iv) Before the headcap is replaced, the plunger, the headcap lever for the sealing device or other
operating device should be checked to see that it operates freely. The washer should be replaced if
necessary and the cap should then be tightly screwed to the container to form a gas-tight joint.

(v) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all should be tested by
discharge. Extreme care should be exercised during preparing and conducting discharge test. Prior
to discharging, the container should be ensured in good condition such as no corrosion, damage or
rust should be visible externally or internally on any part of the container; otherwise hydraulic
pressure test should then be carried out to confirm the container structurally sound. Should there
be doubt in the condition of the container, hydraulic pressure test shall be conducted instead.

(vi) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.

(vi) Hydraulic pressure test should be carried out every five years on the outer container in accordance
with the manufacturers' instructions; the inner container should be examined to ensure it is in good
condition and not leaking. Extreme care should be exercised when preparing and conducting the
test.

(viii) Before carrying out hydraulic pressure test, remove the headcap and clear the contents. Never
empty the contents by discharging the extinguisher.

(ix) Also, before disposal of unserviceable extinguisher, remove the headcap and clear the contents.
Never empty the contents by discharging the extinguisher.

NOTE:
Inverted type chemical foam extinguishers have ceased production and not permitted for sale. However,
products already sold may continued to be used.

VI. FOAM (MECHANICAL) TYPE EXTINGUISHERS

Use: On fires involving flammable liquids.

Never: On electrical fires.


Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 109 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Maintenance: This type of extinguisher should be examined every 12 months and the following
maintenance carried out :-

(GAS-CARTRIDGE TYPE)
(i) The vent holes in the cap should be checked for cleanliness and free from obstruction.

(ii) Remove the headcap to check the liquid level. If the liquid level was found to have dropped by
more than 10 per cent, the foam concentrate or foam solution as appropriate should be replaced by
a fresh charge.

(iii) The branchpipe, strainer and internal discharge tube should be checked for cleanliness and free
from obstruction. Defective items shall be replaced.

(iv) The gas cartridge should be weighed and the weight checked against that marked on the cartridge.
The cartridge should be renewed if a loss of more than 10 per cent of the contents is recorded.

(v) No corrosion, damage or rust should be visible either externally or internally. Special attention
should be paid to the concealed parts of the container.

(vi) Before the headcap is replaced and while the gas cartridge is unscrewed therefrom, the plunger or
other operating device should be checked to see that it operates freely. The washer should be
examined and replaced if necessary. The cap should then be tightly screwed to the container to
form a gas-tight joint.

(vi) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher fail in the test, all cartridges in the
remainder should be replaced. Extreme care should be exercised during preparing and conducting
discharge test. Prior to discharging, the container should be ensured in good condition such as no
corrosion, damage or rust should be visible externally or internally on any part of the container;
otherwise hydraulic pressure test should then be carried out to confirm the container structurally
sound. Should there be doubt about the condition of the container, hydraulic pressure test shall be
conducted instead.

(viii) Corroded parts should be cleaned up and refinished after the hydraulic pressure test.

(ix) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(x) Before carrying out hydraulic pressure test, remove the headcap, disconnect the gas cartridge and
clear the contents. Never empty the contents by discharging the extinguisher.

(xi) Also, before disposal of unserviceable fire extinguisher, remove the headcap, disconnect the gas
cartridge and clear the contents. Never empty the contents by discharging the extinguisher

(STORED-PRESSURE TYPE)
(i) The pressure indicating device should be checked to see the correct pressure is being maintained
within the extinguisher body.

(ii) The nozzle or branch-pipe (if fitted) and the pressure releasing valve in the cap should be checked
for cleanliness and free from obstruction. Defective items shall be replaced.
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 110 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

(iii) No corrosion, damage or rust should be visible externally on any part of the container. Special
attention should be paid to the concealed parts of the container.

(iv) Test 50 per cent of extinguishers by discharge every year in rotation so that all extinguishers are
tested by discharge every two years. Should any extinguisher failed in the test, all extinguishers
should be overhauled and recharged.

(v) Prior to recharging, the container should be ensured in good condition such as no corrosion,
damage or rust was noted; otherwise hydraulic pressure test should be conducted to confirm the
container structurally sound.

(vi) Hydraulic pressure test should be carried out every five years on the container in accordance with
the manufacturers' instructions. Extreme care should be exercised when preparing and conducting
the test.

(vii) Unserviceable extinguisher should be discharged prior to disposal.

VII. FIRE BLANKETS

Use: On fires involving flammable liquids, such as small fires in the kitchen and laboratory.

Method For Drape the blanket over the flames to seal off air. Switch off heat and leave in position until
Use: cool.

Maintenance: This blanket should be examined every 12 months or after use in fire. The following
maintenance should be carried out :-

(i) Check for any deterioration.

(ii) Cleaning in accordance with the manufacturer's instructions as when necessary.

(iii) If manufacturers instructions are not available, fire blanket can be washed (soak overnight in
detergent, gently hand rinse in warm water). Do not machine wash or dry clean.

REMARKS:
(i) Fire blankets are classified into two categories, namely:-
"Heavy Duty" fire blankets (BS 7944:1999); and
"Light Duty" fire blankets (BS EN 1869:1997)
(ii) Only "Heavy Duty" and "reusable" fire blankets will be approved as a Fire Service
Standard Requirement.
(iii) "Light Duty" fire blankets may be accepted for use on a private basis and should be
disposed of after use.

Checked/Certified by : ____________________________________ Certificate No.:__________________


(Name of person holding FSI class 3 registration)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 111 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.9 Fire Shutters

3.9.1 Type Sizes (mm)


Single Steel Rolling Shutter *Yes/No/N.A.
Double Steel Rolling Shutter *Yes/No/N.A.
Push-up Type with Lifting Handle *Yes/No/N.A.
With Mechanical Gearing *Yes/No/N.A.

3.9.1.1 Wall Opening

a) Does location tally with approved building plans? *Yes/No/N.A. *Yes/No/N.A.

b) Is the doorway not exceeding 15.6 sq. m. in area? *Yes/No/N.A. *Yes/No/N.A.

c) Is the doorway not exceeding 4.27 m in width? *Yes/No/N.A. *Yes/No/N.A.

d) Is the doorway not exceeding 3.66 m in height? *Yes/No/N.A. *Yes/No/N.A.

e) Are sill and jambs constructed of approved materials? *Yes/No/N.A. *Yes/No/N.A.

f) Is the head constructed of reinforced concrete of at least *Yes/No/N.A. *Yes/No/N.A.


125 mm in depth?

g) Where steel lintel is provided, is it protected by *Yes/No/N.A. *Yes/No/N.A.


brickwork/concrete not less than 50 mm thick?

h) Is a minimum bearing of 100 mm at each end provided *Yes/No/N.A. *Yes/No/N.A.


on the jambs to support the barrel enclosure?

i) Is adequate expansion clearance provided to barrel *Yes/No/N.A. *Yes/No/N.A.


enclosure and enclosing jambs?

j) Are chases with nominal dimension of 115 mm x 115 *Yes/No/N.A. *Yes/No/N.A.


mm provided to house the channel guides?

k) Are chases set back at least 100 mm from the front of the *Yes/No/N.A. *Yes/No/N.A.
jambs?

l) Is the barrel enclosure housed completely within the wall *Yes/No/N.A. *Yes/No/N.A.
opening?

m) Is the clearance between the sill and shutter, when *Yes/No/N.A. *Yes/No/N.A.
closed, not exceeding 6 mm?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 112 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

n) Is there a minimum gap of 225 mm between the inner *Yes/No/N.A. *Yes/No/N.A.


faces of double rolling shutters when they are in a closed
position?

o) Are barrels of double shutters installed at the same level? *Yes/No/N.A. *Yes/No/N.A.

p) Are projecting jambs of a width not less than 225 mm *Yes/No/N.A. *Yes/No/N.A.
provided?

q) Are projecting jambs of at least 100 mm in width *Yes/No/N.A. *Yes/No/N.A.


provided to enclose the ends of the barrel enclosure?

r) Is the projecting head constructed of reinforced concrete *Yes/No/N.A. *Yes/No/N.A.


of not less than 125 mm thick?

s) Does the projecting head rest on projecting jambs? *Yes/No/N.A. *Yes/No/N.A.

t) Does the projecting head extend the full width and *Yes/No/N.A. *Yes/No/N.A.
projections of the projecting jambs?

u) Where wall opening is to be used for the passage of *Yes/No/N.A. *Yes/No/N.A.


powered vehicles, is adequate protection provided to
prevent mechanical damage to the shutter assembly,
frame and wall opening?

3.9.1.2 Construction of Curtain

a) Is the curtain formed from rolled steel lath of 1.2 mm *Yes/No/N.A. *Yes/No/N.A.
thick?

b) Is steel of the appropriate class used for the laths? *Yes/No/N.A. *Yes/No/N.A.

c) Do laths have sheared parallel edges? *Yes/No/N.A. *Yes/No/N.A.

d) Do laths curl on both edges to form quirks of not more *Yes/No/N.A. *Yes/No/N.A.
than 10 mm outside diameter?

e) Does each quirk form a continuous, full-interlocking *Yes/No/N.A. *Yes/No/N.A.


hinge with that on the adjacent lath?

f) Is a minimum engagement of 2 mm provided between 2 *Yes/No/N.A. *Yes/No/N.A.


adjacent laths?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 113 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

g) Are centres of interlocks not less than 45 mm apart? *Yes/No/N.A. *Yes/No/N.A.

h) Are centres of interlocks not more than 75 mm apart? *Yes/No/N.A. *Yes/No/N.A.

i) Does the curtain have sufficient width to extend at least *Yes/No/N.A. *Yes/No/N.A.
64 mm (75 mm when the wall opening exceeds 2.44 min
width) into channel guides?

j) Does the curtain have sufficient length to extend from *Yes/No/N.A. *Yes/No/N.A.
the sill to the top of the barrel and thence round at least a
quarter of the barrel circumference before fixing?

k) Are steel or malleable cast iron end locks fitted to the *Yes/No/N.A. *Yes/No/N.A.
ends of each lath ?

l) Do end locks have a minimum thickness of 3 mm? *Yes/No/N.A. *Yes/No/N.A.

m) Are end locks riveted to the lath by 2 mild steel rivets of *Yes/No/N.A. *Yes/No/N.A.
not less than 3 mm diameter?

n) Do end locks fit the contour of the curtain laths and fill *Yes/No/N.A. *Yes/No/N.A.
the channel guides closely?

o) Is the bottom lath fitted with a bottom rail of one of the *Yes/No/N.A. *Yes/No/N.A.
following methods of construction?

(i) a steel Tee section of at least 75 x 5 x 3# mm *Yes/No/N.A. *Yes/No/N.A.


section with a backing strip of at least 64 x 6 mm.

(ii) 2 steel flats of at least 38 x 6 mm. *Yes/No/N.A. *Yes/No/N.A.

(iii) 2 steel angles of at least 38 x 38 x 3# mm section. *Yes/No/N.A. *Yes/No/N.A.

# 5 mm for shutters in opening in excess of 2.44 m


in width.

p) Does the curtain extend at least 32 mm between the Tee *Yes/No/N.A. *Yes/No/N.A.
section, flats or angles ?

q) Are Tee section, flats or angles welded, bolted or riveted *Yes/No/N.A. *Yes/No/N.A.
to the laths by at least 8 mm diameter steel bolts or steel
rivets?

r) Do the above fixings space not more than 300 mm *Yes/No/N.A. *Yes/No/N.A.
apart ?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 114 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

s) Is the bottom rail extend the full width of the curtain *Yes/No/N.A. *Yes/No/N.A.
except for the portion housed within the channel guides ?

t) Do expansion clearances of at least 12.5 mm per metre *Yes/No/N.A. *Yes/No/N.A.


run provided for the bottom rail relative to the channel
guides?

u) Does bottom rail make flush contact with the sill when *Yes/No/N.A. *Yes/No/N.A.
the shutter is closed?

v) Are steel lifting handles bolted, riveted or welded to the *Yes/No/N.A. *Yes/No/N.A.
bottom rail on each side of the curtain?

w) Do the lifting handles space not more than 750 mm *Yes/No/N.A. *Yes/No/N.A.
apart?

x) Do the handles interfere with the correct opening or *Yes/No/N.A. *Yes/No/N.A.


closing of the shutter?

y) Is the curtain secured to the barrel by steel screws or *Yes/No/N.A. *Yes/No/N.A.


steel bolts at least 6 mm in diameter?

z) Are screws/bolts passing through laterally elongated *Yes/No/N.A. *Yes/No/N.A.


horizontal holes (nominally 50 mm in length) in the top
lath into drilled and tapped holes in the barrel?

aa) Do screws/bolt space not more than 250 mm apart? *Yes/No/N.A. *Yes/No/N.A.

ab) Does a screw/bolt provided to within 125 mm from each *Yes/No/N.A. *Yes/No/N.A.
end of the top lath?

ac) Are screws/bolts located at centres of elongated holes? *Yes/No/N.A. *Yes/No/N.A.

ad) Are fusible metal and steel washers fitted to each *Yes/No/N.A. *Yes/No/N.A.
screw/bolt?

3.9.1.3 Channel Guides

a) Do channel guides extend continuously from within the *Yes/No/N.A. *Yes/No/N.A.


barrel enclosure to the sill?

b) Does the top of the channel guide locate such as to *Yes/No/N.A. *Yes/No/N.A.
permit upward expansion?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 115 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

c) Are guides fabricated from steel sections of at least 3 mm *Yes/No/N.A. *Yes/No/N.A.


thick (5 mm when the doorway exceeds 3 m in width or
3 m in height)?

d) Are steel rivets or steel bolts not less than 6 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 3 mm fillet welds used in fabrication of the
guides?

e) Do centres of rivets/bolts space not more than 150 mm *Yes/No/N.A. *Yes/No/N.A.


apart?

f) Is the length of the fillet welds not less than 50 mm and *Yes/No/N.A. *Yes/No/N.A.
spaced not more than 150 mm apart?

g) Do guides form a channel of sufficient depth to *Yes/No/N.A. *Yes/No/N.A.


accommodate at least 64 mm (75 mm when the wall
opening exceeds 2.44 m in width) of the curtain together
with sufficient clearance to permit unrestricted expansion
of the curtain?

h) Are guides set back as far as possible within the chases *Yes/No/N.A. *Yes/No/N.A.
provided in the jambs?

i) Are they fitted as close as possible to the front side of the *Yes/No/N.A. *Yes/No/N.A.
chases?

j) Are they wholly contained within the chases so as not to *Yes/No/N.A. *Yes/No/N.A.
project beyond the faces of the jambs?

k) Are guides fixed to jambs by steel expanding anchor *Yes/No/N.A. *Yes/No/N.A.


bolts of at least 6 mm diameter?

l) Are centres of fixing not more than 600 mm apart? *Yes/No/N.A. *Yes/No/N.A.

m) Is there a fixing bolt within 150 mm of the barrel *Yes/No/N.A. *Yes/No/N.A.


enclosure and one within 150 mm of the sill?

n) With the exception of the lowest one, are fixings *Yes/No/N.A. *Yes/No/N.A.
provided with vertically elongated bolt holes (nominally
50 mm in length)?

o) Are bolts fitted with fusible metal washers? *Yes/No/N.A. *Yes/No/N.A.

p) Are bolts fitted with steel washers? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 116 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

q) Are bolts fixed at the highest positions of the slots to *Yes/No/N.A. *Yes/No/N.A.
allow expansion of the guides in an upward direction?

3.9.1.4 Barrel

a) Is the barrel formed from mild steel tube of not less than *Yes/No/N.A. *Yes/No/N.A.
114 mm outside diameter?

b) Is the mild steel tube not less than 5.4 mm thick? *Yes/No/N.A. *Yes/No/N.A.

c) Is the barrel mounted on mild steel axle of not less than *Yes/No/N.A. *Yes/No/N.A.
25 mm diameter?

d) Does the axle extend the full length of the barrel? *Yes/No/N.A. *Yes/No/N.A.

e) Is a minimum bearing of 25 mm provided in each axle *Yes/No/N.A. *Yes/No/N.A.


support bracket?

f) Does the axle project not more than 100 mm beyond *Yes/No/N.A. *Yes/No/N.A.
each end of the barrel?

g) Is expansion clearance provided between the axle and the *Yes/No/N.A. *Yes/No/N.A.
ends of the barrel enclosure?

h) Does barrel enclose helical steel spring for counter *Yes/No/N.A. *Yes/No/N.A.
balancing the curtain?

i) Is the barrel mounted on rigid or self-aligning bearings? *Yes/No/N.A. *Yes/No/N.A.

j) Is it fitted with mild steel spring charging device to *Yes/No/N.A. *Yes/No/N.A.


enable the spring to be adjusted after the curtain is in
position?

k) Are axle support brackets made of steel or malleable cast *Yes/No/N.A. *Yes/No/N.A.
iron?

l) Do they support and enclose the axle at each end? *Yes/No/N.A. *Yes/No/N.A.

m) Are they fixed to the ends of the barrel enclosure by at *Yes/No/N.A. *Yes/No/N.A.
least 2 steel rivets or steel bolts at least 8 mm in diameter
or 6 mm fillet welds?

n) Are they of sufficient size to accommodate the axle and *Yes/No/N.A. *Yes/No/N.A.
fusible metal packing?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 117 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.9.1.5 Barrel Enclosure

a) Are barrel and axle enclosed completely by an enclosure *Yes/No/N.A. *Yes/No/N.A.


pressed or fabricated from steel at least 6 mm thick?

b) Are steel rivets, steel bolts not less than 8 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 6 mm fillet welds not less than 50 mm in
length being used for the fixings?

c) Are centres of fixings not more than 150 mm apart? *Yes/No/N.A. *Yes/No/N.A.

d) Does the fabrication extend completely along each edge *Yes/No/N.A. *Yes/No/N.A.
of the enclosure?

e) Does the front edge of the bottom enclosure form a 40 *Yes/No/N.A. *Yes/No/N.A.
mm wide flange?

f) Is the distance between the flange and the face of the *Yes/No/N.A. *Yes/No/N.A.
curtain not more than 15 mm?

g) Where a drop bar is used, is the distance between the *Yes/No/N.A. *Yes/No/N.A.
flange and the face of the curtain not more than 50 mm?

h) Is the barrel enclosure bolted to each enclosing jamb by *Yes/No/N.A. *Yes/No/N.A.


2 steel expanding anchor bolts of not less than 10 mm
diameter?

i) If fixed vertically, are elongated fixing holes provided? *Yes/No/N.A. *Yes/No/N.A.

j) Are fusible metal washers provided to the fixing bolts? *Yes/No/N.A. *Yes/No/N.A.

k) Are steel washers provided to the fixing bolts? *Yes/No/N.A. *Yes/No/N.A.

l) Where double shutters are fitted and barrels are *Yes/No/N.A. *Yes/No/N.A.
accommodated in the same enclosure, is dividing plate
made of steel at least 6 mm thick provided to separate
the barrels?

m) Is a fascia plate of 6 mm steel provided to form the front *Yes/No/N.A. *Yes/No/N.A.


of the barrel enclosure?

n) Does the fascia plate overlap the opening by at least 100 *Yes/No/N.A. *Yes/No/N.A.
mm at the top and at each end?

o) Is the fascia plate made of steel of at least 6 mm thick? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 118 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

p) Does the bottom edge of the fascia plate form a channel *Yes/No/N.A. *Yes/No/N.A.
of a depth not less than 100 mm?

q) Does the channel extend to within 15 mm of the face of *Yes/No/N.A. *Yes/No/N.A.


the curtain?

r) Does the channel have a flange not less than 40 mm wide *Yes/No/N.A. *Yes/No/N.A.
next to the face of the curtain?

s) Is the fascia plate fixed independently of the barrel *Yes/No/N.A. *Yes/No/N.A.


enclosure by bolting to the head and jambs?

t) Are steel expanding bolts of not less than 10 mm *Yes/No/N.A. *Yes/No/N.A.


diameter used for the fixings?

u) Are fixing bolts located as follows :

(i) 25 mm from top edge spaced at not more than 600 *Yes/No/N.A. *Yes/No/N.A.
mm centres?

(ii) 50 mm from ends? *Yes/No/N.A. *Yes/No/N.A.

(iii) 50 mm from bottom edge? *Yes/No/N.A. *Yes/No/N.A.

(iv) at mid-height of the fascia? *Yes/No/N.A. *Yes/No/N.A.

v) Are elongated bolt holes provided to the fascia plate? *Yes/No/N.A. *Yes/No/N.A.

w) Are bolts located in the centre of the elongated? *Yes/No/N.A. *Yes/No/N.A.

x) Are bolts fitted with fusible metal washers? *Yes/No/N.A. *Yes/No/N.A.

y) Are bolts fitted with steel washers? *Yes/No/N.A. *Yes/No/N.A.

z) Where an opening is provided for the adjustment of the *Yes/No/N.A. *Yes/No/N.A.


barrel springs, does the opening not exceed 250 mm x
150 mm?

aa) Is it covered by a 6 mm steel plate at least 50 mm longer *Yes/No/N.A. *Yes/No/N.A.


and wider than the opening?

ab) Is the cover plate fixed by not less than six steel *Yes/No/N.A. *Yes/No/N.A.
screws/bolts not less than 8 mm diameter?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 119 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.9.1.6 Mechanical Gearing

a) Is mechanical gearing provided to doorway exceeding *Yes/No/N.A. *Yes/No/N.A.


5.2 sq.m. in area?

b) Is mechanical gearing provided when the height of the *Yes/No/N.A. *Yes/No/N.A.


bottom of the barrel enclosure above floor level exceeds
2.2 m?

c) Is the gearing system so arranged that the shutter could *Yes/No/N.A. *Yes/No/N.A.
be manually opened and closed from either side of the
wall opening?

d) Where double shutters were provided, do they operate *Yes/No/N.A. *Yes/No/N.A.


simultaneously?

e) Is the gearing system made of steel mounted on self- *Yes/No/N.A. *Yes/No/N.A.


lubricating bushes and/or rigid self-aligning ball or roller
bearings?

f) Area gears machine cut from a suitable grade of steel? *Yes/No/N.A. *Yes/No/N.A.

g) Are gears connected by shafts not less than 19 mm in *Yes/No/N.A. *Yes/No/N.A.


diameter?

h) Where gearing mechanism is housed in a chase, does the *Yes/No/N.A. *Yes/No/N.A.


chase have a minimum dimension of 114 x 114 mm with
side walls each at least 114 mm thick and the rear wall
not less than 150 mm thick?

i) Is the chase covered by steel plate at least 6 mm thick? *Yes/No/N.A. *Yes/No/N.A.

j) Is the cover plate fixed by steel expanding bolts of not *Yes/No/N.A. *Yes/No/N.A.
less than 6 mm diameter?

k) Are centres of fixings not exceeding 600 mm? *Yes/No/N.A. *Yes/No/N.A.

l) Are anchor bolts fitted with steel washers? *Yes/No/N.A. *Yes/No/N.A.

m) Where chases are enclosed by brickwork/blockwork, *Yes/No/N.A. *Yes/No/N.A.


does the latter have a minimum thickness of 100 mm?

n) Is brickwork/blockwork keyed into the wall? *Yes/No/N.A. *Yes/No/N.A.

o) Are steel maintenance covers provided and installed *Yes/No/N.A. *Yes/No/N.A.


adjacent to the gearing?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 120 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

p) Where gearing mechanism is enclosed in a casing, is the *Yes/No/N.A. *Yes/No/N.A.


casing fabricated from steel at least 6 mm thick?

q) Are steel rivets or steel bolts not less than 8 mm in *Yes/No/N.A. *Yes/No/N.A.
diameter or 6 mm fillet welds at least 50 mm in length
used for the fabrication of the casing?

r) Do centres of rivets/bolts/welds not more than 150 mm? *Yes/No/N.A. *Yes/No/N.A.

s) Is the casing fixed to the face of the wall by expanding *Yes/No/N.A. *Yes/No/N.A.
anchor bolts?

t) Is the diameter of the anchor bolts not less than 8 mm? *Yes/No/N.A. *Yes/No/N.A.

u) Are steel washers fitted to the anchor bolts? *Yes/No/N.A. *Yes/No/N.A.

v) Do centres of anchor bolts within 600 mm? *Yes/No/N.A. *Yes/No/N.A.

w) Is access opening for maintenance incorporated in the *Yes/No/N.A. *Yes/No/N.A.


casing?

x) Is it covered by at least 6 mm thick steel plate at least 50 *Yes/No/N.A. *Yes/No/N.A.


mm longer and wider than the opening?

y) Is cover plate attached to casing by steel screws/bolts at *Yes/No/N.A. *Yes/No/N.A.


least 8 mm in diameter?

z) Are screws/bolts spaced at not more than 150 mm *Yes/No/N.A. *Yes/No/N.A.


centres?

aa) Where the barrel enclosure, fascia plate or dividing plate *Yes/No/N.A. *Yes/No/N.A.
are perforated to permit passage of gearing system, are
size and number of perforations kept to a minimum
consistent with the satisfactory operation of the gearing?

ab) Are perforations so arranged that there is not exposed *Yes/No/N.A. *Yes/No/N.A.
opening into the barrel enclosure?

ac) Are they so arranged that lateral expansion of barrel *Yes/No/N.A. *Yes/No/N.A.
enclosure and fascia plate is not restricted?

ad) Are operating wheels spokeless? *Yes/No/N.A. *Yes/No/N.A.

ae) Are operating wheels non-detachable? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 121 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

af) Are they located adjacent to the wall opening? *Yes/No/N.A. *Yes/No/N.A.

ag) Are they located not less than 750 n m, nor more than *Yes/No/N.A. *Yes/No/N.A.
1200 mm above the floor?

ah) Where handles on the operating wheels are provided, are *Yes/No/N.A. *Yes/No/N.A.
they so arranged as to close within the wheel when not in
use?

3.9.1.7 Installation

a) Where automatic self-closing devices are fitted, do they *Yes/No/N.A. *Yes/No/N.A.


cause no interference to the manual opening and closing
of the shutter?

b) Where smoke detectors are provided for the actuation of *Yes/No/N.A. *Yes/No/N.A.
the shutter, are they fitted to both sides of the wall
opening?

c) Are smoke detectors installed as far as practicable to the *Yes/No/N.A. *Yes/No/N.A.


provisions of the L.P.C. rules for A.F.A.?

d) Is permanent nameplate with adequate information *Yes/No/N.A. *Yes/No/N.A.


provides?

e) Are manual controls provided to both sides of the wall *Yes/No/N.A. *Yes/No/N.A.
opening?

3.9.1.8 Shutter Operation

a) Does the automatic actuation device function *Yes/No/N.A. *Yes/No/N.A.


satisfactorily?

b) Is secondary source of electricity supply provided? *Yes/No/N.A. *Yes/No/N.A.

c) Is the descending speed # of the shutter acceptable ? *Yes/No/N.A. *Yes/No/N.A.

# Descending time shall within 15-60 seconds for


shutters in openings in excess of 2.5 m in height;
not faster than 8 seconds for other shutters in
openings of height within 2.5 m and that the
bottom rail of the shutter shall reach the mid-height
in not less than half the total descending time of the
shutter

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 122 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.10 Emergency Generator Installation

Peak Starting Rated Input Starting


Current (IL) Power Method

(A) Fire service installation

i) Fixed fire pump No. x A No. x kW


ii) Intermediate booster pump No. x A No. x kW
iii) Transfer pump No. x A No. x kW
iv) Sprinkler pump No. x A No. x kW
v) Firemans lift No. x A No. x kW
vi) Fire detection system No. x A No. x kW
vii) Smoke extraction system No. x A No. x kW
viii) Staircase pressurization No. x A No. x kW
ix) Exit sign/emergency lighting No. x A No. x kW
x) Others : No.x A No. x kW

(B) Other equipment (please specify)


A kW
A kW
A kW
A kW

Estimated maximum simultaneous Remark :


starting and running load kW/ kVA DOL/Star-delta/
Auto-
transformer/
others

3.10.1 Emergency Generator Set Details

Alternator Prime Mover

Make _____________ _____________


Model _____________ _____________
Serial No. _____________ _____________
Rated Capacity Power____________kVA Voltage: *380/220V
Power____________kW Speed_________rpm
Current___________A Power factor______
Frequency________Hz

3.10.2 Fuel

Type: [ ] Diesel [ ] other (please specify)


Type of tank: [ ] Built-in [ ] Separate
Separate fuel tank room is provided : *Yes/No
Capacity of service tank : ________ L
Capacity of main fuel tank : _____ L
a. Fuel consumption ______ L/hr at full load
b. Fuel consumption curve of generator is attached : *Yes/No
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 123 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

c. Time allowed for max. fuel consumption at full load : _____ hours
d. Fuel storage is sufficient for 6 hrs. generator running
to support fire service installation : *Yes/No

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 124 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.10.2.1 Has fuel tank room been inspected and approved by FSD *Yes/No/N.A. *Yes/No/N.A.
Regional Office?
(N.B. : Supporting document to be attached)

3.10.2.2 Has surveyor report for fuel tank been obtained as *Yes/No/N.A. *Yes/No/N.A.
required by FSD Dangerous Goods Divison?

3.10.2.3 Has DG licence for fuel tank room holding more than *Yes/No/N.A. *Yes/No/N.A.
2,500 litres diesel (or as approved) been obtained?
(N.B. : Supporting document to be attached)

3.10.3 Visual Inspection

a) Is adequate space (not less than 600 mm) provided all *Yes/No/N.A. *Yes/No/N.A.
round emergency generator for maintenance/cleaning?

b) Are air supply and discharge ductworks (if any) provided *Yes/No/N.A. *Yes/No/N.A.
free from obstruction?

c) Are air supply and discharge ductworks running in *Yes/No/N.A. *Yes/No/N.A.


compartment other than emergency generator room
enclosed with proper fire resisting material?

d) Is services fuel tank in generator room made of 3 mm *Yes/No/N.A. *Yes/No/N.A.


steel construction and of capacity less than 500 litres?

e) Is generator built-in fuel tank not greater than 500 litres? *Yes/No/N.A. *Yes/No/N.A.

f) Is fuel tank electrically earthed? *Yes/No/N.A. *Yes/No/N.A.

g) Is a baffle wall of brick-work construction or of 9 mm *Yes/No/N.A. *Yes/No/N.A.


metal sheet provided between the side of service tank (if
installed) and generator, serving as a screen wall
between the two?

h) Is fuel refilling pump connected to essential power *Yes/No/N.A. *Yes/No/N.A.


supply?

i) Is a shut off valve provided on the supply pipe from fuel *Yes/No/N.A. *Yes/No/N.A.
tank to the service tank of generator?

j) Is capacity of battery capable of starting the generator 4 *Yes/No/N.A. *Yes/No/N.A.


times consecutively and calculation sheet enclosed?
(capacity : ________________Ah)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 125 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

k) Are the batteries kept in fully charged condition and is *Yes/No/N.A. *Yes/No/N.A.
the trickle charge operating?

Inside emergency generator room :

l) Is door sill of sufficient height provided to contain the *Yes/No/N.A. *Yes/No/N.A.


total fuel contents of the service tank (if installed), fuel
tank and sump of the generator?

m) Are detailed operation instructions displayed? *Yes/No/N.A. *Yes/No/N.A.

n) Is a log book provided? *Yes/No/N.A. *Yes/No/N.A.

o) Is integrity of the FRP construction of generator room *Yes/No/N.A. *Yes/No/N.A.


and the door intact?

p) Are the notices Emergency Generator and No *Yes/No/N.A. *Yes/No/N.A.


smoking in 120 mm English and Chinese characters
provided at the entrance to the emergency generator
room?

3.10.4 Functional Testing

a) Can the manual starting facilities of the emergency *Yes/No/N.A. *Yes/No/N.A.


generator operate satisfactorily?

Upon failure of normal electricity supply, will


emergency generator:

b) Automatically starts when the duration of power failure *Yes/No/N.A. *Yes/No/N.A.


exceeds 1 second?

c) Transfers to FS loads within 15 seconds? *Yes/No/N.A. *Yes/No/N.A.

d) Is emergency generator capable of re-starting upon *Yes/No/N.A. *Yes/No/N.A.


failure of first attempt in starting?

e) Are audible and visual alarms given locally, and at fire *Yes/No/N.A. *Yes/No/N.A.
control main panel when the generator starting sequence
is locked out due to starting failure?

f) After one hour of running test, do all instruments, safety *Yes/No/N.A. *Yes/No/N.A.
devices, etc. indicate normal condition?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 126 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

g) Will the generator set continue to run after a pre- *Yes/No/N.A. *Yes/No/N.A.
determined time recommended by manufacturer unless it
is stopped manually if the normal power supply has
resumed?

h) Are all testing carried out with generator room doors *Yes/No/N.A. *Yes/No/N.A.
kept closed?

i) Is warning signal given locally and at fire control main *Yes/No/N.A. *Yes/No/N.A.
panel when manual/auto selector switch turn to manual
position?
(N.B. such provision is strongly recommended)

j) Is remote control valve on supply pipe to the service tank *Yes/No/N.A. *Yes/No/N.A.
in good working order?

k) Are all moving parts effectively and rigidly guarded for *Yes/No/N.A. *Yes/No/N.A.
safety?

l) Are all hot parts properly insulated? *Yes/No/N.A. *Yes/No/N.A.

m) Is any exhaust leak detected inside generator room while *Yes/No/N.A. *Yes/No/N.A.
the generator is running?

n) Is actual loading or dummy load provided to carry out a *Yes/No/N.A. *Yes/No/N.A.


simulated full load test?

o) Does emergency generator start at full load? *Yes/No/N.A. *Yes/No/N.A.

p) Does emergency generator pass the running test at full *Yes/No/N.A. *Yes/No/N.A.
load?

Checked/Certified by : ___________________________ Certificate No.:_____________


(Name of electrical worker) Class :____________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 127 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.11 Fireman's Lift

3.11.1 Visual Inspection

a) Does the firemans lift serve the floors of the building *Yes/No/N.A. *Yes/No/N.A.
without having to traverse more than two floors by the
fire service personnel?

b) Is label provided on G/F or designated floor of entry for *Yes/No/N.A. *Yes/No/N.A.


each fireman's lift indicating the floors served?

c) Is separate lift shaft provided for the fireman's lift? *Yes/No/N.A. *Yes/No/N.A.

d) Is the internal size of the lift car 1.35 m or greater? *Yes/No/N.A. *Yes/No/N.A.

e) Is the rated load of the lift car 680 kg or greater? *Yes/No/N.A. *Yes/No/N.A.

f) Is the fireman's lift discharged to a protected lobby with *Yes/No/N.A. *Yes/No/N.A.


a separation not less than 1 hr. F.R.P.?

g) Is the opening of the lift car/landing door 800 mm wide *Yes/No/N.A. *Yes/No/N.A.
and 2000 mm high or greater?

h) Are the car and landing door fitted with power operated *Yes/No/N.A. *Yes/No/N.A.
automatic self-closing device?

i) Is fireman's switch provided with the fireman's lift? *Yes/No/N.A. *Yes/No/N.A.

j) Is the fireman's switch clearly labelled "FIREMAN'S *Yes/No/N.A. *Yes/No/N.A.


SWITCH" ()?

k) Is the label of the fireman's switch in conformity with *Yes/No/N.A. *Yes/No/N.A.


FSD standard and Code of Practice on the Design and
Construction of Lifts and Escalators?

l) Is the electricity supply to the fireman's lift connected *Yes/No/N.A. *Yes/No/N.A.


from an independent sub-main switch?

m) Is permanent electricity supply connected? *Yes/No/N.A. *Yes/No/N.A.

n) Is the electricity supply to the fireman's lift backed up by *Yes/No/N.A. *Yes/No/N.A.


an emergency generator?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 128 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

l) Are notices provided outside and inside the building in *Yes/No/N.A. *Yes/No/N.A.
conformity with the Code of Practice for Means of
Access for Firefighting and Rescue?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 129 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.11.2 Testing and Commissioning

a) Does the opening of the safety hatch door inside the lift *Yes/No/N.A. *Yes/No/N.A.
car automatically cut off the electric fan?

b) Does the fireman's switch when operated over-ride all *Yes/No/N.A. *Yes/No/N.A.
registered instructions and return to the designated floor
of entry?

c) Is the fireman's lift capable to travel from the designated *Yes/No/N.A. *Yes/No/N.A.
floor of entry to the topmost floor within 1 minute
calculating from the lift door completely closed to the lift
door started to open? (Actual sec.)

d) Is the operation of the fireman's lift in conformity with *Yes/No/N.A. *Yes/No/N.A.


the Flow Chart? (T&C Certificate Part 3, 11.4 & Test
Records Part 4, 4.11)

e) In case of power interruption or changeover from the *Yes/No/N.A. *Yes/No/N.A.


normal power supply to the emergency power source,
after the Firemans Switch is operated, does the
firemans lift continue to be in the Fireman control
mode as soon as the power supply to the firemans lift is
made available?

f) Do the following conditions complied with as soon as *Yes/No/N.A. *Yes/No/N.A.


the power supply is made available?

(i) The firemans lift shall immediately continue to


return automatically to the landing of designated
point of entry without stopping for car or landing
call, if the firemans lift was returning to the
landing of designated point of entry upon
operation of the Firemans Switch before the
power interruption.

(ii) If the fireman has gained control of the firemans


lift and the firemans lift stopped at a certain
floor with the doors not firmly closed before the
power interruption, the doors shall automatically
open.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 130 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

The opening and closing of the doors shall be by


pressing continuously the respective control
buttons as under firemans lift operating mode
and the lift shall operate according to (c) below
when the lift doors are fully closed.

g) If the firemans lift was travelling, or the lift doors were


closed before the power interruption, the firemans lift
shall start to travel to the desired floor when that floor
button is pressed, or as an alternative, return to the
landing of designated point of entry or the nearest
landing below and resume the firemans control mode.

h) Is lift certificate (Form 6 or equivalent) provided? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 131 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A
3.11.2 Firem an 's Lift O peration Flow C hart

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 132 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.12 Emergency Lighting & Exit System

3.12.1 Visual Inspection

a) Are emergency luminaires provided in accordance with *Yes/No/N.A. *Yes/No/N.A.


approved drawings?

b) Are exit and directional signs provided in accordance *Yes/No/N.A. *Yes/No/N.A.


with approved drawings and in each escape routes?

c) Are there not less than two emergency luminaires in each *Yes/No/N.A. *Yes/No/N.A.
space?

d) Are centrally supplied emergency luminaires and self- *Yes/No/N.A. *Yes/No/N.A.


contained emergency luminaires provided in accordance
with approved drawings?

e) Are emergency luminaires of approved type provided? *Yes/No/N.A. *Yes/No/N.A.

f) Are exit and directional signs of approved type *Yes/No/N.A. *Yes/No/N.A.


provided?

g) Are self-contained exit signs and centrally supplied exit *Yes/No/N.A. *Yes/No/N.A.
signs provided in accordance with approved drawings?

h) Are the batteries for self-contained emergency *Yes/No/N.A. *Yes/No/N.A.


luminaires and exit signs sealed nickel metal hydride
type or an approved type?

i) Are the batteries for centrally supplied emergency *Yes/No/N.A. *Yes/No/N.A.


luminaires an approved type?

j) Is separate control or separate system provided for *Yes/No/N.A. *Yes/No/N.A.


maintenance type emergency luminaires and non-
maintenance type emergency luminaires for centrally
supplied system?

k) Is calculation for the battery and charger capacity *Yes/No/N.A. *Yes/No/N.A.


submitted for centrally supplied emergency luminaires
system?

l) Is testing facilities provided for emergency luminaires *Yes/No/N.A. *Yes/No/N.A.


and exit signs for weekly, monthly and annual tests?

m) Are bar code labels provided to the battery lighting and *Yes/No/N.A. *Yes/No/N.A.
central battery system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 133 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

n) Is centrally monitoring, testing and logging system *Yes/No/N.A. *Yes/No/N.A.


provided as specified?
(Type : ______________________________________)

o) Are the wirings in concealed conduits or of fire *Yes/No/N.A. *Yes/No/N.A.


resistance type in accordance with the G.S.?

p) Does the exit sign comply with FSD requirements (letter *Yes/No/N.A. *Yes/No/N.A.
sizes and colour)?

q) Are the emergency lighting and exit sign connected to *Yes/No/N.A. *Yes/No/N.A.
emergency generator power supply?

r) Is the premise a place of public entertainment and the *Yes/No/N.A. *Yes/No/N.A.


specific requirements followed?

s) A self-luminous sign illuminated by tritium or other *Yes/No/N.A. *Yes/No/N.A.


radioactive source shall be indelibly marked at its
lower corner to indicate the radiation hazard and the
expiration date (Month/Year) of the sign for easy
identification purposes and shall have a label at its back
giving instruction or warning to users on the proper
method of disposal as required by the Radiation Board.

t) Exit and directional signs shall be positioned between 2 *Yes/No/N.A. *Yes/No/N.A.


m and 2.5 m above floor level measured to the base
of the sign.

3.12.2 Testing and Commissioning

3.12.2.1 Emergency Lighting

a) Acceptance Testing

Does the installations comply with BS5266: Part 1 and *Yes/No/N.A. *Yes/No/N.A.
BS EN 1838?

b) Discharge Test

(i) A discharge test, for 1 minute at the 10-hour *Yes/No/N.A *Yes/No/N.A


discharge rate to be carried out on the battery of
the emergency lighting, and the results to be
entered in a register.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 134 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(ii) For emergency lighting supplied by central


battery systems with control and safety devices
installed, the systems to be checked for the
following :

1) Connections between the battery and the source of *Yes/No/N.A *Yes/No/N.A


charging current to be such that in no
circumstances should the battery discharge other
than to the secondary lighting circuits.

2) A rectifier for battery charging to be for that *Yes/No/N.A *Yes/No/N.A


purpose only and to be so regulated that the
battery cannot discharge appreciably under
normal conditions.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 135 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3) Voltage and hydrometer tests to be carried out and *Yes/No/N.A *Yes/No/N.A


recorded in a register.

c) Functional Test

(i) Do the emergency luminaires light up *Yes/No/N.A *Yes/No/N.A


automatically within the time specified when
normal supply is interrupted (G.S. Clause
B11.1.2 and B11.1.4)?

(ii) Do the lamp test button/other automatic *Yes/No/N.A *Yes/No/N.A


emergency lighting testing facilities function as
designed?

(iii) Do the maintenance type and non-maintenance *Yes/No/N.A. *Yes/No/N.A.


emergency luminaires function as designed?

d) Performance Test

(i) Is the illumination level adequate when all *Yes/No/N.A *Yes/No/N.A


emergency lightings are on using battery supply
(at 5 s after power failure and at 60 s after power
failure)?

(ii) Is the illumination level adequate throughout and *Yes/No/N.A. *Yes/No/N.A.


at the end of discharge test for the rated duration
(G.S. Clause B11.1.3 and B11.1.4)?

(iii) Can the battery be recharged to full load *Yes/No/N.A *Yes/No/N.A


condition within specified period after the
discharge test (24 hours in general, 12 hours for
cinemas, theatres, etc.)?

(iv) Does the central monitoring, testing and logging *Yes/No/N.A *Yes/No/N.A
system perform as specified (G.S. Clause
B11.1.6)?
(Remark: Detailed testing and commissioning
procedures to be submitted by the contractor for
approval.)

3.12.2.2 Exit and Directional Signs

a) Acceptance Testing

Does the installation comply with BS 5499 and BS 5266: *Yes/No/N.A. *Yes/No/N.A.
Part 1 and FSDCOP?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 136 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

b) Discharge Test

(i) A discharge test, for 1 minute at the 10-hour *Yes/No/N.A *Yes/No/N.A


discharge rate to be carried out on the battery, and
the results to be entered in a register.

(ii) For installation supplied by central battery


systems with control and safety devices installed,
the systems to be checked for the following :

(1) Connections between the battery and the source *Yes/No/N.A *Yes/No/N.A
of charging current to be such that in no
circumstances should the battery discharge other
than to the secondary lighting circuits.

(2) A rectifier for battery charging to be for that *Yes/No/N.A *Yes/No/N.A


purpose only and to be so regulated that the
battery cannot discharge appreciably under
normal conditions.

(3) Voltage and hydrometer tests to be carried out *Yes/No/N.A *Yes/No/N.A


and recorded in a register.

c) Functional Test

(i) Is the illumination continuous during normal *Yes/No/N.A *Yes/No/N.A


power supply?

(ii) Is the illumination maintained automatically *Yes/No/N.A *Yes/No/N.A


when normal supply is interrupted (within the
time as specified)?

(iii) Does the lighting testing facilities function as *Yes/No/N.A *Yes/No/N.A


designed?

d) Performance Test

(i) Is the illumination level adequate when all signs *Yes/No/N.A *Yes/No/N.A
are on using battery supply?

(ii) Is the illumination level adequate throughout and *Yes/No/N.A *Yes/No/N.A


at the end of the discharge test for the rated
duration?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 137 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

(iii) Can the battery be recharged to full load *Yes/No/N.A *Yes/No/N.A


condition within specified period after the
discharge test for the rated duration?

(iv) Is the illumination of acceptable level in theatres, *Yes/No/N.A *Yes/No/N.A


cinemas, etc.?

Checked/Certified by : ___________________________ Certificate No.:_____________


(Name of electrical worker) Class :____________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 138 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.13 Ventilation and Air-conditioning (VAC) Control System

3.13.1 System Data

3.13.1.1 Method of overriding control (Refer to para. 5.25 in C.O.P for Minimum F.S.I. & Equipment):

Method A/B/C/combination of

3.13.1.2 Shut down of the MVAC systems utilizing: Conventional AFA/Addressable


AFA/BMS/CCMS

3.13.1.3 On/Off status monitoring of MVAC systems at: FS Control Room/B.M. Office/MVAC
Control Console

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 139 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.13.2 Visual Inspection

3.13.2.1 MVAC layouts

a) For override control method A (Methods refer to *Yes/No/N.A. *Yes/No/N.A.


FSDCOP), are the compartments for the purpose of fire
protection clearly identified?

b) Do the sizes of the MVAC systems and associated air *Yes/No/N.A. *Yes/No/N.A.
ducts tally with the FSD endorsed MVAC layouts?

c) Are all the MVAC systems required to be included in the *Yes/No/N.A. *Yes/No/N.A.
VAC control system highlighted on the air-side
schematic diagram?

d) Are all the interlocking MVAC systems highlighted? *Yes/No/N.A. *Yes/No/N.A.

e) Are the supply/return/intake/exhaust points installed at *Yes/No/N.A. *Yes/No/N.A.


the correct level?

f) Is the flow rate of each MVAC system correct? *Yes/No/N.A. *Yes/No/N.A.

g) Is the Smoke Extraction/Pressurization of Staircases/ *Yes/No/N.A. *Yes/No/N.A.


Toxic Air Extraction/Kitchen Ventilation/Fume
Cupboard Ventilation excluded from the VAC control
system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 140 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.13.2.2 Probe-type Smoke Detector

a) Are the probes installed at appropriate positions that *Yes/No/N.A. *Yes/No/N.A.


smoke can be effectively collected and released (i.e. not
at bends of air duct)?

b) Are the probes length (>2/3 duct width in most products) *Yes/No/N.A. *Yes/No/N.A.
and model appropriate?

c) Is the pair of smoke collecting and releasing probes *Yes/No/N.A. *Yes/No/N.A.


installed correctly in relative positions as recommended
by the manufacturers and that adequate pressure
difference can be achieved for effective smoke
collecting?

d) Are the filters at the end of the smoke collecting/ *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?

e) Is the smoke collecting probe installed in such a way that *Yes/No/N.A. *Yes/No/N.A.
the smoke collecting holes are facing the air stream
being detected?

3.13.2.3 Manual Override Switch

a) Is it provided adjacent to but without damaging to the *Yes/No/N.A. *Yes/No/N.A.


Fire Alarm Control Panel of the building and easy to
operate?

b) Is durable label with proper wordings in Chinese and *Yes/No/N.A. *Yes/No/N.A.


English provided for identification?

3.13.3 Testing and Commissioning

3.13.3.1 Manual Override Switch

a) Can all the MVAC systems involved in the VAC control *Yes/No/N.A. *Yes/No/N.A.
system be shut off when this switch is activated?

b) Does any breakage in circuit wiring of this switch cause *Yes/No/N.A. *Yes/No/N.A.
the above MVAC systems to shut down?

c) Are the above MVAC systems unable to resume *Yes/No/N.A. *Yes/No/N.A.


operation while fire signal still exists?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 141 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.13.3.2 Probe-type Smoke Detector

a) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the detector head is removed
from its mounting base?

b) Does the MVAC system shut down or fault signal *Yes/No/N.A. *Yes/No/N.A.
indicated on the panel when the power supply to the
detector is lost?

3.13.3.3 MVAC System

a) Each MVAC system shall operate steadily to its rated *Yes/No/N.A. *Yes/No/N.A.
speed and capacity first. Smoke is generated and
conveyed to the lower pressure side of the MVAC
system or air duct where it can be collected and detected.
After a reasonably short period of time, the MVAC
system must be able to shut down and a signal will be
relayed to the F.S. Panel in the F.S. Control Room. All
other MVAC systems installed within and serving the
same compartment must also be shut down through
interlocking arrangement. No MVAC system can
resume normal function unless the fire signal registered
has been cleared. (Test records on Part 4, 4.13 Table 1)

3.13.3.4 Central mechanical fresh air supply and/or exhaust


systems

a) The central fresh air supply and/or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
be shut down

b) The central fresh air supply and/or exhaust system shall *Yes/No/N.A. *Yes/No/N.A.
not require to be shut down but the fresh air and/or
exhaust to the affected compartment/unit shall be closed
off from the central system by actuation of a local
motorised smoke damper.

c) Shut down of the mechanical ventilating systems *Yes/No/N.A. *Yes/No/N.A.


utilizing a multiplex automatic fire alarm or Building
Automation System shall be permitted so long as the
multiplex system is on the Fire Services Department list
for this type of equipment/system.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 142 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.14 Pressurization of Staircases System

Working / Design Drawing Ref. :

System Design Calculation Ref. :

System Operating Principles & Sequence Ref. :

3.14.1 Requirements of Pressurization of Staircases System

Staircase No. : _________________

System Classification : ________________ Application : ______________

Operating Classification : (*single / multiple) Building : _____________m


injection Height

Supply Fan Classification : (*single / multiple)

Minimum pressure differentials between specified areas : ____________Pa

Minimum airflow velocity between specified areas with the exit door of any three ___________m/s
consecutive floors and G/F main entrance door at fully open state:

Specific pressure relief system for over pressure control : (*i / ii / iii / iv )
Refer to FSDCOP
Para. 5.21 Cl. B.9

Specific method for measuring the opening force at door : ______________

Maximum force to open the exit door : ____________N

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 143 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.14.2 Visual Inspection

3.14.2.1 General

a) Is FSD approved working/design drawing available? *Yes/No/N.A. *Yes/No/N.A.

b) Is FSD approved system design calculation available? *Yes/No/N.A. *Yes/No/N.A.

c) Is the system operating principles / sequence available? *Yes/No/N.A. *Yes/No/N.A.

d) Is approved procedures for testing & commissioning *Yes/No/N.A. *Yes/No/N.A.


enclosed?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 144 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

e) Are technical catalogues enclosed? *Yes/No/N.A. *Yes/No/N.A.

f) Does system layout tally with approved building plans *Yes/No/N.A. *Yes/No/N.A.
and F.S.I. drawings?

g) Simplified schematic diagram for all staircase *Yes/No/N.A. *Yes/No/N.A.


pressurization systems shall be provided adjacent to the
staircase pressurization control panel.

h) Is the complete installation, including all equipment, *Yes/No/N.A. *Yes/No/N.A.


components and wiring, approved by Architect and
accepted by the Fire Services Department?

i) Are all submissions to FSD certified and signed by *Yes/No/N.A. *Yes/No/N.A.


Registered Professional Engineer under CAP 409?

3.14.2.2 Staircase Pressurization Fan

Fan / Motor Set Data : Single Supply Fan Multiple Supply Fan
Duty Duplicated No. 1 No. 1 No. 2 No. 2
Motor Motor Duty Fan Standby Fan Duty Fan Standby Fan
Location
Fan
Manufacturer
Motor
Fan
Model
Motor
Fan
Serial No.
Motor

Motor power (kW)

Nominal fan power(kW)

Design Flow rate (L/s)

Design Pressure (kPa)

Starting method

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 145 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

a) Is pressurization fan & motor supplied from one single *Yes/No/N.A. *Yes/No/N.A.
proprietary manufacturer specialized in the manufacture
of the pressurization of staircases system?

b) Are the rotating parts of fan/motor set protected by *Yes/No/N.A. *Yes/No/N.A.


safety guard?

c) Is nominal fan motor power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required hydraulic power?

d) Is the insulation of motor windings capable of operating *Yes/No/N.A. *Yes/No/N.A.


at design conditions for a period of one hour in an
ambient temperature of 250 oC?

e) Are emergency lock-off buttons provided adjacent to fan *Yes/No/N.A. *Yes/No/N.A.


motors and easily accessible for operation and with
visual and audible indication on the panel when the fan is
locked?

f) Are pressurization fan motors protected with HRC fuses? *Yes/No/N.A. *Yes/No/N.A.

g) Are staircase pressurization fans connected with power *Yes/No/N.A. *Yes/No/N.A.


supply from essential source?

h) Are starting instructions for pressurization of staircases *Yes/No/N.A. *Yes/No/N.A.


system prominently displayed in the fan room with a
glass front frame?

i) Are the fans installed in a separate fire resistant plant *Yes/No/N.A. *Yes/No/N.A.
room or enclosed by fire resistant enclosure with a FRP
not less than that of the staircase served?

j) Are doors to fan rooms clearly labelled "STAIRCASE *Yes/No/N.A. *Yes/No/N.A.


PRESSURIZATION FAN ROOM"?

k) Are doors to fan room provided with key locking *Yes/No/N.A. *Yes/No/N.A.
devices?

l) Are door(s) to fan room provided with automatic door *Yes/No/N.A. *Yes/No/N.A.
closer(s)?

m) Are fan room(s) clear of debris? *Yes/No/N.A. *Yes/No/N.A.

n) Shall the plant room housing the staircase pressurization *Yes/No/N.A. *Yes/No/N.A.
fans contain no other services.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 146 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

3.14.2.3 Discharge / Pressure Relief Outlet

a) Are the outlets clear of debris? *Yes/No/N.A. *Yes/No/N.A.

b) Is the system provided with over pressure prevention? *Yes/No/N.A. *Yes/No/N.A.

c) Are the pressure relief outlets of automatic mechanical *Yes/No/N.A. *Yes/No/N.A.


type and free to swing?

d) Is the framework of pressure relief damper of 3.2 mm *Yes/No/N.A. *Yes/No/N.A.


stainless steel rigid channel section or of approved
design?

e) Is the functioning of discharge / pressure relief system *Yes/No/N.A. *Yes/No/N.A.


tested satisfactorily in accordance with the T & C
Procedure No. 1 for Air-conditioning, Refrigeration,
Ventilation and Central Monitoring & Control System
Installation?

3.14.2.4 Ductworks

a) Does air intake distant from any potential fire hazards *Yes/No/N.A. *Yes/No/N.A.
and avoid contamination by the corresponding source of
smoke?

b) Does the size of the outdoor air intake duct tally with the *Yes/No/N.A. *Yes/No/N.A.
vertical air flow diagram approved by FSD?

c) Is the ductwork clear of debris? *Yes/No/N.A. *Yes/No/N.A.

d) Is ductwork constructed with fire rated resistant *Yes/No/N.A. *Yes/No/N.A.


enclosure equivalent to that of the compartment served?

e) Are pressurization ductwork and associated fittings *Yes/No/N.A. *Yes/No/N.A.


constructed to DW143 & DW144 as approved?

f) Are pressurization ductworks and associated fittings *Yes/No/N.A. *Yes/No/N.A.


constructed with flange joints for future ease of
dismantling?

g) Are pressurization ductwork and associated fittings *Yes/No/N.A. *Yes/No/N.A.


fabricated from galvanized sheet steel but not aluminum
sheets?

h) Are gaps / spaces between ductwork and wall openings *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 147 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

i) Is any section of ductwork embedded in concrete *Yes/No/N.A. *Yes/No/N.A.


structure?

j) Are adequate hot-dipped galvanized duct hangers or *Yes/No/N.A. *Yes/No/N.A.


supports provided as required?

k) Are duct hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?

l) Is ductwork installed outside the pressurized staircase *Yes/No/N.A. *Yes/No/N.A.


enclosed by fire resistant enclosure with FRP not less
than that of the compartment served or 2 hrs FRP,
whichever is the higher?

m) Are expansion duct joints provided at locations through *Yes/No/N.A. *Yes/No/N.A.


building expansion joints?

n) Is equipotential bonding provided for the ductwork? *Yes/No/N.A. *Yes/No/N.A.

o) Does system equipped with fire / smoke dampers or any *Yes/No/N.A. *Yes/No/N.A.
other restrictions along the passage of supply & exhaust
air in accordance with the approved drawings?

p) Is certified leakage test report of ductwork (DW143 and *Yes/No/N.A. *Yes/No/N.A.


DW144 as approved) enclosed?

q) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?

r) Is testing point/facility provided in the installation? *Yes/No/N.A. *Yes/No/N.A.

s) In each staircase pressurization fan intake duct, is a *Yes/No/N.A. *Yes/No/N.A.


suitably designed smoke sensor installed which, when
sensing the passage of smoke, shall override all other
controlling devices, and shut down the staircase
pressurization system, being served by that fan?

t) Is the ductwork tested satisfactorily in accordance with *Yes/No/N.A. *Yes/No/N.A.


the T & C Procedure No. 1 for Air-conditioning,
Refrigeration, Ventilation and Central Monitoring &
Control System Installation?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 148 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.14.2.5 Pressure Sensor

a) Is the pressure sensor operated at normal ambient *Yes/No/N.A. *Yes/No/N.A.


conditions (37 oC & 100 % R.H.)?

b) Are the pressure sensors and its associated equipment of *Yes/No/N.A. *Yes/No/N.A.
industrial process grade conforming to BS EN 60654-1
or equivalent?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 149 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

c) Is the pressure sensing unit(s) connected with fire rated *Yes/No/N.A. *Yes/No/N.A.
cables of high temperature grade to BS 6724 suitable for
operating at 250 oC?

d) Is the high temperature grade fire rated type cable *Yes/No/N.A. *Yes/No/N.A.
enclosed in galvanized steel conduit and run within the
pressurized space in the fire resistance duct?

e) Is the pressure sensor tested satisfactorily in accordance *Yes/No/N.A. *Yes/No/N.A.


with the T & C Procedure No. 1 for Air-conditioning,
Refrigeration, Ventilation and Central Monitroing &
Control System Installation?

3.14.2.6 Smoke Detector

a) Is the smoke-collecting probe installed? *Yes/No/N.A. *Yes/No/N.A.

b) Is correct type of smoke detector provided? *Yes/No/N.A. *Yes/No/N.A.

c) Is the pair of smoke collecting and releasing probes *Yes/No/N.A. *Yes/No/N.A.


installed correctly in relative positions as recommended
by the manufacturers and that adequate pressure
difference can be achieved for effective smoke
collection?

d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?

e) Is (are) designated smoke detector(s) provided at the air *Yes/No/N.A. *Yes/No/N.A.


intake for pressurization of staircases system?

f) Is the system designed to override all other controlling *Yes/No/N.A. *Yes/No/N.A.


devices and shut down the pressurization of staircases
system being served by the respective fan upon the
sensing of smoke at the air intake by the designated
smoke detector?

g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?

h) Is the functioning of smoke detector tested satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 150 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

3.14.2.7 Electrical Wiring / Fire Resisting Cable

a) Is the whole pressurization of staircases system wired *Yes/No/N.A. *Yes/No/N.A.


with fire resisting cables of copper conductors and
withstand 815 oC temperature for at least 30 minutes?

b) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?

c) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and fastened by approved fasteners or clamps
specially designed and constructed for the purpose?

d) Are the cables installed outside the pressurized staircase *Yes/No/N.A. *Yes/No/N.A.
enclosed by fire resistant enclosure with FRP not less
than that of the compartment served or 2 hrs FRP,
whichever is the higher?

e) Are the cables enclosed with protective enclosures to *Yes/No/N.A. *Yes/No/N.A.


reduce the likelihood of failure due to external effects
mechanical, electrical or physical?

f) All equipment serving staircase pressurization systems *Yes/No/N.A. *Yes/No/N.A.


shall be provided with an electrical
supply from essential source.

g) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C Procedure No. 2 for
Electrical Installation and to Electricity Ordinance?

3.14.2.8 Control Panel

a) Is the control panel provided for each pressurization of *Yes/No/N.A. *Yes/No/N.A.


staircases system and located adjacent to the fire control
panel?

b) Is the control panel for each pressurization of staircases *Yes/No/N.A. *Yes/No/N.A.


system normally manned or installed in public area?

c) Is the cubicle type motor control panel constructed from *Yes/No/N.A. *Yes/No/N.A.
2 mm thick (min) panel steel and conform to BS EN
60439-1 or as approved?

d) Does the control panel incorporate the necessary *Yes/No/N.A. *Yes/No/N.A.


switches with same method/direction of operation?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 151 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

e) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarm and trouble lights
essential to the operation of the system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 152 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

f) Does the controls, starters, relays, etc., be suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250 oC for not less than one
hour?

g) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the pressurization
system?

h) Does the control panel incorporate manual override *Yes/No/N.A. *Yes/No/N.A.


facility with manual reset & are audio / visual indications
provided?

i) Is the pressurization of staircases system operated via the *Yes/No/N.A. *Yes/No/N.A.


actuation of manual override facility?

j) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?

k) A further label shall be provided with letters not less than *Yes/No/N.A. *Yes/No/N.A.
6 mm high stating that the controls shall be operated by
authorized personnel.

l) Switches for all staircase pressurization systems shall be *Yes/No/N.A. *Yes/No/N.A.


grouped in one area of the panel together with those for
smoke extraction systems or the like. On/Off switches
for each fan shall be provided.

m) All switches shall have the same method/direction of *Yes/No/N.A. *Yes/No/N.A.


operation.

n) Is the cubicle type motor control panel tested *Yes/No/N.A. *Yes/No/N.A.


satisfactorily in accordance with the T & C Procedure
No. 2 for Electrical Installation and to Electricity
Ordinance?

3.14.2.9 Miscellaneous

a) Are all ductworks and metal works properly painted for *Yes/No/N.A. *Yes/No/N.A.
identification?

b) Is proper identification provided for ductworks, wirings *Yes/No/N.A. *Yes/No/N.A.


and equipment?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 153 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

c) Are door sets (i.e. doors, frames and ironmongery *Yes/No/N.A. *Yes/No/N.A.
hardware) complied with Building Authoritys
requirement and suitable for use continuously at 35 oC
and 100% RH, and with certificates enclosed as
required?

d) Are all components, materials and workmanship *Yes/No/N.A. *Yes/No/N.A.


complying fully with the requirements of FSDCOP?

e) Does compartmentation of pressurization plant room *Yes/No/N.A. *Yes/No/N.A.


tally with that of the staircase served?

f) Are warning / instruction notices provided at entrance & *Yes/No/N.A. *Yes/No/N.A.


inside the protected areas that are normally occupied?

g) If, however, except for sleeping risk premises, the total *Yes/No/N.A. *Yes/No/N.A.
air requirement for each pressurized staircase is made up
from two or more separate supplies acting together (e.g.
top and bottom plants), then no further duplication of
equipment is necessary.

h) All doors sets (i.e. doors, frames and hardware) *Yes/No/N.A. *Yes/No/N.A.
providing access to or from any pressurized staircase
shall be to the satisfaction of the Building Authority.

i) The provision of supplementary gaskets to assist in *Yes/No/N.A. *Yes/No/N.A.


preventing smoke leakage will not be permitted.

j) Self closers shall be provided for all doors to ensure *Yes/No/N.A. *Yes/No/N.A.
integrity of the enclosure. The closers shall have been
part of a door, door frame and ironmongery test
assembly which has successfully passed the test in
accordance with British Standard 476: Part 22. The
closers shall be of such a design that they cannot be
defeated i.e. no removable pins or bolts, etc.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 154 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

g) If, however, except for sleeping risk premises, the total *Yes/No/N.A. *Yes/No/N.A.
air requirement for each pressurized
staircase is made up from two or more separate supplies
acting together (e.g. top and bottom
plants), then no further duplication of equipment is
necessary.

3.14.3 Testing and Commissioning

3.14.3.1 Mode of Operation

a) Is pressurization of staircases system automatically *Yes/No/N.A. *Yes/No/N.A.


activated whenever any fire fighting system activated?

b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.20 in FSDCOP)

c) Are manual reset and monitoring provision with audio / *Yes/No/N.A. *Yes/No/N.A.
visual indications provided? (Refer to Para. 5.20 in
FSDCOP)

d) Are designated smoke detection system / detector(s) *Yes/No/N.A. *Yes/No/N.A.


provided for pressurization of staircases system?

e) Is pressurization of staircases system stop automatically *Yes/No/N.A. *Yes/No/N.A.


if smoke is detected?

f) Is pressurization of staircases system monitored by *Yes/No/N.A. *Yes/No/N.A.


BMS/BAS/CCMS under normal mode?

g) Can control of pressurization of staircases system be *Yes/No/N.A. *Yes/No/N.A.


isolated from BMS/BAS/CCMS under fire mode?

h) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?

i) Are the fan motors duplicated for duty and standby used *Yes/No/N.A. *Yes/No/N.A.
for buildings with more than one pressurized staircase?

j) Are sleeping risk premises and where designated by the *Yes/No/N.A. *Yes/No/N.A.
Director of Fire Services, provided with a single
pressurized staircase, duplicate fans and motors?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 155 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked By
by Contractor PBSE/PBSI

k) Are non-return damper(s) provided to prevent backflow *Yes/No/N.A. *Yes/No/N.A.


between parallel connected multiple pressurized fans?

(l) Is alarm signal repeated to fire control room or status *Yes/No/N.A. *Yes/No/N.A.
panel at the main entrance of the building?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 156 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


checked by
by Contractor PBSE/PBSI

m) No transmission of actuating signals for the staircase *Yes/No/N.A. *Yes/No/N.A.


pressurization system shall be effected by multiplex or
similar devices unless such devices have the approval or
certification of one of the Testing Authorities recognised
by the Fire Services Department.

n) All systems shall be automatically actuated and remain *Yes/No/N.A. *Yes/No/N.A.


in operation. It shall be able for
manually reset and monitored by audio and visual
indication. Actuation of all systems shall be
direct from the local automatic fire alarm panel
whenever that panel transmits a Fire signal to
the Fire Service Communication Centre.

o) Where any building or that portion of a building *Yes/No/N.A. *Yes/No/N.A.


immediately adjacent to a designated
pressurized staircase is not provided with a smoke
detection system, smoke detectors shall be
installed at a distance not exceeding 1 m from and
outside the access doors to the staircase or
its approach lobbies to activate the system.

p) Is variable flow control for fan(s) adopting for normal *Yes/No/N.A. *Yes/No/N.A.
operating mode?

q) Is (Are) frequency controller(s) provided for *Yes/No/N.A. *Yes/No/N.A.


pressurization fan(s) in order to achieve the variable flow
volume?

r) Is (Are) modulating control bypass damper(s) provided *Yes/No/N.A. *Yes/No/N.A.


for pressurization fan in order to achieve the variable
flow volume?

3.14.3.2 Others

a) Are all relevant parts of the pressurization of staircases *Yes/No/N.A. *Yes/No/N.A.


system tested satisfactorily in accordance with the T & C
Procedure No. 1 for Air-conditioning, Refrigeration,
Ventilation and Central Monitoring & Control System
Installation?

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 157 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.15 Smoke Extraction System

Working / Design Drawing Ref. :

System Design Calculation Ref. :

System Operating Principles & Sequence Ref. :

3.15.1 Requirements of Smoke Extraction System

Zone / Location : _______________

Application / Usage : _______________

Volume of Compartment : _____________m3 *Atrium / Basement

Type of Extraction System : *Static / Dynamic

Operating Air Flow Pattern : *Scouring Pattern / Cross Flow Effect with low level supply
and high level extraction
Design Volume : _____________m3 Total Air Change per Hour : ___________

Minimum Smoke Removal Rate : _________________ m3/s

Minimum Supply or Make-up Air Rate : _________________ m3/s

Maximum airflow velocity based on free area of grille : Specified Measured


(a) make-up air inlets not mechanically propelled : 3 m/s ________ m/s

(b) make-up air inlets mechanically propelled : 6 m/s ________ m/s

(c) extract grilles or outlets : 6 m/s ________ m/s

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 158 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

3.15.2 Visual Inspection

3.15.2.1 General

a) Are FSD approved working / design Drawings available? *Yes/No/N.A. *Yes/No/N.A.

b) Does general layout tally with F.S.I. drawings? *Yes/No/N.A. *Yes/No/N.A.

c) Does occupancy tally with that mentioned in approved *Yes/No/N.A. *Yes/No/N.A.


building plans?

d) Does compartmentation of protected premises tally with *Yes/No/N.A. *Yes/No/N.A.


that marked in approved building plans?

e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?

f) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?

g) Is approved system design calculation enclosed? *Yes/No/N.A. *Yes/No/N.A.

h) Are the system operating principles / sequence enclosed? *Yes/No/N.A. *Yes/No/N.A.

i) Are technical catalogues enclosed? *Yes/No/N.A. *Yes/No/N.A.

j) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning available?

k) Is the design of the complete installation, including all *Yes/No/N.A. *Yes/No/N.A.


equipment, components and wiring, approved by
Architect and accepted by the Fire Services Department
available?

l) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 159 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

m) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineers signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?

n) Have the format / methods of the required operational *Yes/No/N.A. *Yes/No/N.A.


and functional test been agreed with FSD before the
work commences?

o) Are all systems with fail safe design to ensure a free *Yes/No/N.A. *Yes/No/N.A.
passage of smoke?

p) Are the fire shutters tested to the relevant requirements *Yes/No/N.A. *Yes/No/N.A.
of the T & C Procedure for Fire Service Installation?

q) Has exemption been granted for one extraction / supply *Yes/No/N.A. *Yes/No/N.A.
system used to serve several compartments?

r) Where the motorized fire and smoke dampers are *Yes/No/N.A. *Yes/No/N.A.
required, has the entire assembly of the fire and smoke
damper been tested to maintain efficient operation at
250oC for not less than one hour?

s) Has the Director of Fire Services approved the adoption *Yes/No/N.A. *Yes/No/N.A.
of performance based fire engineering approach?

t) Where the smoke extraction rate is designed with fire *Yes/No/N.A. *Yes/No/N.A.
engineering approach, is the maximum area of the smoke
reservoir restricted to 2000 m2?

u) Is a separate system provided for each Atrium or *Yes/No/N.A. *Yes/No/N.A.


Basement compartment?

v) Is static smoke extraction system and associated facilities *Yes/No/N.A. *Yes/No/N.A.


provided as specified and employed as part of the
designed system (e.g. in atrium or basement)?

w) Is the static smoke extraction system installed as *Yes/No/N.A. *Yes/No/N.A.


approved (e.g. smoke vent size and separation, provision
of smoke curtain, actuation, etc.)?

x) All systems shall be provided with remote *Yes/No/N.A. *Yes/No/N.A.


on/off/override control at the fire control panel.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 160 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

y) Shafts used for smoke extraction purposes shall contain *Yes/No/N.A. *Yes/No/N.A.
no other services.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 161 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.15.2.2 Dynamic Smoke Extraction Fan(s)

Supply Fan Extraction Fan


Fan / Motor Set Data :
Duty Duplicated Duty Duplicated
Motor Motor Motor Motor
Location

Fan
Manufacturer
Motor

Fan
Model
Motor

Fan
Serial No.
Motor

Motor Power (kW)

Nominal Fan Power (kW)

Design Flow Rate (L/s)

Design Pressure (kPa)

Starting Current (A)

Starting Method

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 162 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

a) Is smoke extraction fan (supply and extraction) supplied *Yes/No/N.A. *Yes/No/N.A.


from a proprietary manufacturer specialized in the
manufacture of the system?

b) Are the fans connected directly to outside by non- *Yes/No/N.A. *Yes/No/N.A.


combustible ductwork including flexible connection?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 163 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

c) If the fans are installed within the service compartment, *Yes/No/N.A. *Yes/No/N.A.
is the fan system (including fans, motors, drives,
electrical works, ductworks, boundary of compartment)
protected by a fire resisting material of rating not less
than one hour?

d) Is the supply / makeup air rate at least 80% of the overall *Yes/No/N.A. *Yes/No/N.A.
extraction rate?

e) Is the supply or makeup air supplied from an *Yes/No/N.A. *Yes/No/N.A.


independent supply air system?

f) Are the rotating parts of fan/motor set protected by *Yes/No/N.A. *Yes/No/N.A.


safety guard?

g) Is fan motor(s) power rated at 20% higher than the *Yes/No/N.A. *Yes/No/N.A.
required nominal fan power?

h) Is the insulation of motor windings capable of operating *Yes/No/N.A. *Yes/No/N.A.


at design conditions for a period of one hour in an
ambient temperature of 250 oC?

i) Is the fan itself coated with finishing material capable of *Yes/No/N.A. *Yes/No/N.A.
withstanding exposure to an ambient temperature of 250
o
C for a period of not less than one hour without
producing smoke or any toxic fumes, and certified by
the fan manufacturer?

j) Are emergency lock-off buttons provided adjacent to fan *Yes/No/N.A. *Yes/No/N.A.


motors and easily accessible for operation and with
visual and audible indication on the panel when the fan
is locked?

k) Are fan motors protected with HRC fuses? *Yes/No/N.A. *Yes/No/N.A.

l) Are smoke extraction fans connected with power supply *Yes/No/N.A. *Yes/No/N.A.
from essential source?

m) Are starting instructions for dynamic smoke extraction *Yes/No/N.A. *Yes/No/N.A.


system prominently displayed in the fan room with a
glass front frame?

n) Are doors to smoke extraction plant rooms clearly *Yes/No/N.A. *Yes/No/N.A.


labelled "SMOKE EXTRACTION FAN ROOM"?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 164 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

o) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
locking devices?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 165 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

p) Are doors to smoke extraction plant room provided with *Yes/No/N.A. *Yes/No/N.A.
automatic door closer(s)?

q) Are smoke extraction plant room(s) clear of debris? *Yes/No/N.A. *Yes/No/N.A.

3.15.2.3 Ductworks

a) Is air intake distant from any potential fire hazards and is *Yes/No/N.A. *Yes/No/N.A.
prevented from contamination by the same source of
smoke?

b) Are locations of smoke discharge outlets governed by the


following criteria :

i) At least 5 metres in any direction away from any *Yes/No/N.A. *Yes/No/N.A.


make-up air intake or any other openings into the
building?

ii) Air is prohibited to discharge into any means of *Yes/No/N.A. *Yes/No/N.A.


escape or free air path of the firemans staircase?

iii) Discharge shall be at least 3 metres above the *Yes/No/N.A. *Yes/No/N.A.


surrounding horizontal surface from the bottom of
the outlets?

iv) Air shall not be discharged downward if the *Yes/No/N.A. *Yes/No/N.A.


discharge point is less than 6 metres in height?

v) Air Discharge shall not be under any canopy or *Yes/No/N.A. *Yes/No/N.A.


overhang?

c) Are ductwork and associated fittings fabricated from *Yes/No/N.A. *Yes/No/N.A.


galvanized sheet steel but not aluminum?

d) Does the size of the outside air intake duct tally with *Yes/No/N.A. *Yes/No/N.A.
vertical air flow diagram approved by FSD?

e) Is the ductwork clear of debris? *Yes/No/N.A. *Yes/No/N.A.

f) Is ductwork constructed with enclosure of fire rated *Yes/No/N.A. *Yes/No/N.A.


resistant equivalent to that of the compartment served,
and suitable for continuous operation at 250 oC for not
less than 1 hour?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 166 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

g) Are ductworks and associated fittings constructed to *Yes/No/N.A. *Yes/No/N.A.


DW143 and DW144 and subsequent amendments as
approved?

h) Is ductwork and associated fittings constructed with *Yes/No/N.A. *Yes/No/N.A.


flange joints for future ease of dismantling?

i) Are gaps / spaces between ductwork and wall opening *Yes/No/N.A. *Yes/No/N.A.
filled with approved sealant?

j) Is any section of ductwork embedded in concrete *Yes/No/N.A. *Yes/No/N.A.


structure?

k) Are adequate duct hangers or supports provided as *Yes/No/N.A. *Yes/No/N.A.


required?

l) Are duct hangers and supports rigidly fixed and *Yes/No/N.A. *Yes/No/N.A.
unbroken?

m) Are expansion duct joints provided at location through *Yes/No/N.A. *Yes/No/N.A.


building expansion joint?

n) Are equipotential bondings provided for the ductworks? *Yes/No/N.A. *Yes/No/N.A.

o) Does system clear from any fire / smoke dampers or any *Yes/No/N.A. *Yes/No/N.A.
other restrictions of air passage as approved?

p) Does system ductwork contain other service facilities? *Yes/No/N.A. *Yes/No/N.A.

q) Is certified Leakage Test Report of Ductwork (DW143 & *Yes/No/N.A. *Yes/No/N.A.


DW144 as approved) enclosed?

r) Do sizes of air duct, discharge outlet and pressure relief *Yes/No/N.A. *Yes/No/N.A.
damper sizes tally with drawings?

s) Is testing point / facility provided in the installation? *Yes/No/N.A. *Yes/No/N.A.

t) Are motorized fire / smoke dampers provided only for *Yes/No/N.A. *Yes/No/N.A.
system where one extraction or supply system is used to
serve several compartments as approved?

u) Is damper complete with electric motor actuator enclosed *Yes/No/N.A. *Yes/No/N.A.


with fire rated enclosure and capable of withstanding
ambient temperature of at least 250 oC for at least one
hour?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 167 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

v) Is damper module installation fully sealed by gaskets *Yes/No/N.A. *Yes/No/N.A.


between the module frame and the mounting frame?

w) Is the gasket material capable of withstanding exposure *Yes/No/N.A. *Yes/No/N.A.


than ambient temperature of at least 250 oC for at least
one hour without producing smoke or any toxic fumes
and certified by the damper manufacturer?

x) Are fire and smoke dampers provided at the main *Yes/No/N.A. *Yes/No/N.A.
exhaust outlet louvre and / or main supply intake louvre?

y) Do fire and smoke dampers comply with UL 555s class I *Yes/No/N.A. *Yes/No/N.A.
or other international standards?

z) If smoke extraction system ductwork passes through *Yes/No/N.A. *Yes/No/N.A.


compartment, does the part of ductwork outside the
serviced compartment comply with the following :

i) Insulation with fire rated period of 30 minutes in *Yes/No/N.A. *Yes/No/N.A.


compliance with the Code of Practice for Fire
Resisting Construction issued by the Buildings
Department?

ii) Fire resisting construction to BS 476 : Part 24? *Yes/No/N.A. *Yes/No/N.A.

iii) Totally enclosed by fire resisting construction to *Yes/No/N.A. *Yes/No/N.A.


BS 476 : Part 20, to the same fire resisting period
as the serviced compartment or the containing
compartment, whichever is the higher?

iv) Hard body impact test to BS 5669 : Part 1 & 2 *Yes/No/N.A. *Yes/No/N.A.
with exterior surface free from accidental
mechanical damage?

aa) Is the ductwork tested satisfactorily in accordance with *Yes/No/N.A. *Yes/No/N.A.


the T & C Procedure No. 1 for Air-conditioning,
Refrigeration, Ventilation and Central Monitroing &
Control System Installation?

3.15.2.4 Smoke Detector

a) Is the smoke-collecting probe installed properly? *Yes/No/N.A. *Yes/No/N.A.

b) Is appropriate type (early detection type / early response *Yes/No/N.A. *Yes/No/N.A.


type) of smoke detector provided within smoke
extraction system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 168 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

c) Is the pair of smoke collecting and releasing probes *Yes/No/N.A. *Yes/No/N.A.


installed correctly in relative positions as recommended
by the manufacturers and that adequate pressure
difference can be achieved for effective smoke
collection?

d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?

e) Is(are) designated smoke detector(s) provided at the air *Yes/No/N.A. *Yes/No/N.A.


intake for smoke extraction system?

f) Is the smoke detector designed to override all other *Yes/No/N.A. *Yes/No/N.A.


controlling devices and shut down the smoke extraction
system being served by the respective fan upon the
sensing of smoke at the air intake by the designated
smoke detector?

g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?

h) Is the functioning of smoke detector tested satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

3.15.2.5 Electrical Wiring / Fire Resisting Cable

a) Is proper identification provided for wiring and *Yes/No/N.A. *Yes/No/N.A.


equipment?

b) Is the whole smoke extraction system wired with fire *Yes/No/N.A. *Yes/No/N.A.
resisting cables?

c) Is the fire resisting cable consist of copper conductors *Yes/No/N.A. *Yes/No/N.A.


and withstand 815oC temperature for at least 30 minutes?

d) Are the binding tapes used for the cables of flame *Yes/No/N.A. *Yes/No/N.A.
retardant?

e) Are the cables installed in cable trays or other approved *Yes/No/N.A. *Yes/No/N.A.
supports, and are fastened by approved fasteners or
clamps specially designed and constructed for the
purpose?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 169 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

f) Are the cable routes provided with proper protective *Yes/No/N.A. *Yes/No/N.A.
enclosure to reduce the likelihood of failure due to
external effects mechanical, electrical or physical?

g) Is the electrical wiring system tested satisfactorily in *Yes/No/N.A. *Yes/No/N.A.


accordance with the T & C Procedure No. 2 for
Electrical Installation and to Electricity Ordinance?

3.15.2.6 Control Panel

a) Is control / indication panel properly reset? *Yes/No/N.A. *Yes/No/N.A.

b) Is control panel provided for each smoke extraction *Yes/No/N.A. *Yes/No/N.A.


system and located adjacent to the fire control panel?

c) Is the control panel for each smoke extraction system *Yes/No/N.A. *Yes/No/N.A.
normally manned or installed in public area?

d) Is the cubicle type control panel constructed from 2 mm *Yes/No/N.A. *Yes/No/N.A.


thick (min) panel steel and conform to BS EN 60439-1?

e) Does the control panel installed in a room or enclosure *Yes/No/N.A. *Yes/No/N.A.


with FRP of 2 hrs or more containing no other
equipment?

f) Does the control panel incorporate the necessary *Yes/No/N.A. *Yes/No/N.A.


switches with the same method / direction of operation?

g) Does the control panel incorporate the necessary relays, *Yes/No/N.A. *Yes/No/N.A.
timers, key type switches, alarms and trouble lights
essential to the operation of the system?

h) Are the controls, starters, relays, etc., suitable for *Yes/No/N.A. *Yes/No/N.A.
continuous operation at 250 oC for not less than one
hour?

i) Is the indicator light actuated by devices that sense the *Yes/No/N.A. *Yes/No/N.A.
effective operation of the relevant components (i.e.
airflow switch / air pressure switch) of the smoke
extraction system?

j) Does the control panel incorporate manual override *Yes/No/N.A. *Yes/No/N.A.


facility with manual reset and are audio & visual
indications provided?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 170 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

k) Is the smoke extraction system individually operated via *Yes/No/N.A. *Yes/No/N.A.


the actuation of manual override facility?

l) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
indicate the operating positions and systems served?

m) Is the cubicle type motor control panel tested *Yes/No/N.A. *Yes/No/N.A.


satisfactorily in accordance with the T & C Procedure
No. 2 for Electrical Installation and to Electricity
Ordinance?

n) Switches for all smoke extraction systems shall be *Yes/No/N.A. *Yes/No/N.A.


grouped in one area of the panel together with those for
staircase pressurization systems or the like. Where the
smoke extraction system is served by both supply and
extract fans, on/off switches for each fan shall be
provided.

o) A further label shall be provided with letters not less than *Yes/No/N.A. *Yes/No/N.A.
6 mm high stating that the controls shall be operated by
authorised personnel.

p) All labels shall be permanent, legible and firmly secured *Yes/No/N.A. *Yes/No/N.A.
(adhesive is not satisfactory) and shall be lettered in both
English and Chinese by engraving or similar.

q) Simplified schematic diagram for all smoke extraction *Yes/No/N.A. *Yes/No/N.A.


systems shall be provided adjacent to the smoke
extraction control panel.

3.15.2.7 Indication and Control

a) Is the power light ON (green light)? *Yes/No/N.A. *Yes/No/N.A.

b) Does the panel indicate normal working condition? *Yes/No/N.A. *Yes/No/N.A.

c) Are all the indicating lamps functional? *Yes/No/N.A. *Yes/No/N.A.

d) Do the main power failure and system fault activate :

(i) Visual signal? *Yes/No/N.A. *Yes/No/N.A.

(ii) Audible signal? *Yes/No/N.A. *Yes/No/N.A.

e) Does the fault silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving visual light ON?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 171 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

f) Does the alarm silence switch silence the audible alarm *Yes/No/N.A. *Yes/No/N.A.
while leaving the red alarm indicating light ON until the
system is reset?

g) Do alarm and fault reset switches operate properly? *Yes/No/N.A. *Yes/No/N.A.

h) Does test switch for simulating alarm condition and *Yes/No/N.A. *Yes/No/N.A.
operate properly?

i) Does lamp test switch operate properly? *Yes/No/N.A. *Yes/No/N.A.

j) Does the disconnect switch for transmitter, release *Yes/No/N.A. *Yes/No/N.A.


devices, etc. operate properly with both visual and
audible alarms activated?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 172 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

k) Do the following panel functions work properly?

(i) Can alarm silence/reset. *Yes/No/N.A. *Yes/No/N.A.

(ii) Normal supply / battery supply *Yes/No/N.A. *Yes/No/N.A.

(iii) Power on / failure indicator. *Yes/No/N.A. *Yes/No/N.A.

3.15.2.8 Miscellaneous

a) Are warning / instruction notices provided at areas of *Yes/No/N.A. *Yes/No/N.A.


testing?

b) Are warning / instruction notices provided inside the *Yes/No/N.A. *Yes/No/N.A.


testing area(s) which are normally occupied?

c) Are all ductworks and metal works properly painted? *Yes/No/N.A. *Yes/No/N.A.

d) Is proper identification provided for ductworks, wiring *Yes/No/N.A. *Yes/No/N.A.


and equipment?

e) Do door sets (i.e. doors, frames and ironmongery *Yes/No/N.A. *Yes/No/N.A.


hardware) comply with Building Authoritys requirement
and suitable for use continuously under 35 oC and 100%
RH with certificates enclosed as required?

f) Do architectural details with all components, materials *Yes/No/N.A. *Yes/No/N.A.


and workmanship comply with the requirements of the
FSDCOP?

g) Are warning / instruction notices provided at entrance & *Yes/No/N.A. *Yes/No/N.A.


inside the protected areas which are normally occupied?

h) Do smoke curtain systems used for separating different *Yes/No/N.A. *Yes/No/N.A.


smoke compartments comply with BS 7346 Part 3 and
with material comply with BS 476 Part 20?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 173 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

3.15.3 Testing and Commissioning

3.15.3.1 Mechanical Test

a) Are all relevant parts of dynamic smoke extraction *Yes/No/N.A. *Yes/No/N.A.


system tested satisfactorily in accordance with the T &
C Procedure for the Air-conditioning, Refrigeration,
Ventilation and Central Monitoring & Control System
Installation?

b) Has full and complete records been taken of all tests and
the results submitted with not less than the following in
the report :

(i) Record of pressure testing during construction? *Yes/No/N.A. *Yes/No/N.A.

(ii) Resulting airflow rate, current, belt tensions, *Yes/No/N.A. *Yes/No/N.A.


shaft speeds, etc. included in the report?

c) Has mechanical check for motorized smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?

d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?

e) Is electro-thermal link properly installed & reinstated *Yes/No/N.A. *Yes/No/N.A.


and accepted by Registered Professional Engineer under
CAP 409?

3.15.3.2 Functional Test of System (System in MANUAL mode)

a) Does AUTO / MANUAL selector key switch function *Yes/No/N.A. *Yes/No/N.A.


properly and switched to manual mode upon the test?

b) Do smoke detectors operate satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

c) Does operating alarm / indication function properly? *Yes/No/N.A. *Yes/No/N.A.

d) Is the shutdown of Mechanical Ventilation and Air- *Yes/No/N.A. *Yes/No/N.A.


conditioning system satisfactorily accomplished?

e) Do fire damper opening / closing devices operate *Yes/No/N.A. *Yes/No/N.A.


satisfactorily?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 174 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

f) Is the start-up / operation of Smoke Extraction system *Yes/No/N.A. *Yes/No/N.A.


satisfactorily accomplished and remained in operation
until manually reset?

3.15.3.3 Control and Actuation Check

a) Are all systems for smoke extraction automatically *Yes/No/N.A. *Yes/No/N.A.


actuated and remained in operation until manually reset?

b) When in fire mode, is that no system connected thereto *Yes/No/N.A. *Yes/No/N.A.


being controlled by or under the influence of any other
system?

c) Is any transmission of actuating signals from the AFA *Yes/No/N.A. *Yes/No/N.A.


panel for the operation of the smoke extraction systems
affected by multiplexer or addressable or similar devices
unless such devices have the approval or certification of
one of the testing authorities recognized by FSD?

d) Is individual smoke extraction component provided with *Yes/No/N.A. *Yes/No/N.A.


a manual key operated ON / OFF switch with indicator
light provided on the fire control panel?

e) Are switches for all smoke extraction / removal systems *Yes/No/N.A. *Yes/No/N.A.
grouped in one area of the panel together with those for
staircase pressurization systems or the like?

f) Are all switches have the same method / direction of *Yes/No/N.A. *Yes/No/N.A.
operation?

g) Are indicator lights actuated by a device that senses *Yes/No/N.A. *Yes/No/N.A.


effective operation, such as a centrifugal switch or an air
pressure switch, of the relevant smoke / air handling
system?

h) Are all switches and indicators clearly labelled (red *Yes/No/N.A. *Yes/No/N.A.
letters on white background, not less than 3 mm high) to
show operating positions and systems served and stating
that the controls shall be operated only by authorized
personnel?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 175 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

3.15.3.4 Initial start

a) Are the electrically driven fans equipped with audio and *Yes/No/N.A. *Yes/No/N.A.
visual warnings to indicate the fault signals?

b) Are the following functional tests in control circuitry


conducted :

i) The proper function of interlocking devices *Yes/No/N.A. *Yes/No/N.A.


between fans and dampers?

ii) The proper function of remote on / off operation? *Yes/No/N.A. *Yes/No/N.A.

iii) The correct balancing and direction of air flow? *Yes/No/N.A. *Yes/No/N.A.

3.15.3.5 Smoke Extraction Test

a) Is the fire compartment maintained at all times? *Yes/No/N.A. *Yes/No/N.A.

b) Are the system and associated components of a fail *Yes/No/N.A. *Yes/No/N.A.


safe design to ensure a free passage of smoke?

c) Is the travel of smoke in counter-flow direction to that of *Yes/No/N.A. *Yes/No/N.A.


the egress / escape route?

d) Are egress / escape routes kept free from smoke (i.e. *Yes/No/N.A. *Yes/No/N.A.
smoke flow shall be away from the escape route)?

e) Are air / smoke flow paths under scouring or cross- *Yes/No/N.A. *Yes/No/N.A.
flow effect in all areas within the fire compartment as
approved?

f) Is the smoke travelling distance shorter than 30 m before *Yes/No/N.A. *Yes/No/N.A.


entering the nearest point of intake of the extraction
system?

g) Is smoke extraction point provided within each unit of *Yes/No/N.A. *Yes/No/N.A.


floor area of 500 m2?

h) Is smoke extraction point located at high level? *Yes/No/N.A. *Yes/No/N.A.

i) Are points of smoke extraction evenly distributed and *Yes/No/N.A. *Yes/No/N.A.


located at high level in the space?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 176 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

j) Does makeup air supply follow an air path as direct and *Yes/No/N.A. *Yes/No/N.A.
short as possible, and enter at low level in order to avoid
premature mixing with the hot gases?

k) Is the smoke contained effectively within the smoke *Yes/No/N.A. *Yes/No/N.A.


reservoirs?

3.15.3.6 Mode of Operation

a) Is smoke extraction system automatically activated *Yes/No/N.A. *Yes/No/N.A.


whenever any fire fighting system activated?

b) Does the system actuate directly from the local automatic *Yes/No/N.A. *Yes/No/N.A.
fire alarm control panel and remain in operation? (Refer
to Para. 5.22 in FSDCOP)

c) Are manually reset and monitor by audio & visual *Yes/No/N.A. *Yes/No/N.A.
indication function provided? (Refer to Para. 5.22 in
FSDCOP)

d) Are designated smoke detection system / detector(s) *Yes/No/N.A. Yes/No/N.A.


provided for smoke extraction system?

e) Is smoke extraction system monitored by *Yes/No/N.A. *Yes/No/N.A.


BMS/BAS/CCMS under normal mode?

f) Is control of smoke extraction system isolated from *Yes/No/N.A. *Yes/No/N.A.


BMS/BAS/CCMS under fire mode?

g) Can the fan just be stopped by switching off at the fan *Yes/No/N.A. *Yes/No/N.A.
control rather than by any automatic means?

h) Are non-return damper(s) provided to prevent back-flow *Yes/No/N.A. *Yes/No/N.A.


between parallel connected multiple fans?

i) Is alarm signal repeated to fire control room or status *Yes/No/N.A. *Yes/No/N.A.


panel at the main entrance of the building?

j) No transmission of actuating signals from the automatic *Yes/No/N.A. *Yes/No/N.A.


fire alarm panel for the operation of the smoke extraction
systems shall be effected by multiplex or similar devices
unless such devices have the approval or certification of
one of the Testing Authorities recognized by the Fire
Services Department.

k) Where a sprinkler system is provided, a flow switch on *Yes/No/N.A. *Yes/No/N.A.


the main sprinkler feed pipe serving the area shall
activate the system.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 177 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

3.16 Hot Smoke Test

Working / Design Drawing Ref. :

System Design Calculation Ref. :

System Operating Principles & Sequence Ref. :

3.16.1 Requirements of Hot Smoke Test

Zone / Location : _______________

Application / Usage : _______________

Volume of compartment : _____________m3 Atrium height : ___________m

Operating air flow pattern : *Scouring pattern / Cross flow effect with low level supply
and high level extraction

Minimum smoke removal rate : ___________________m3/s

Method of integration between smoke extraction and detection ___________________


systems :
Maximum airflow velocity based on free area of grille :

(a) make-up air inlets not mechanically propelled : ___________________m/s

(b) make-up air inlets mechanically propelled : ___________________m/s

(c) extract grilles or outlet : ___________________m/s

Details of fire trays (quantity & size) : ________ nos.; _________mm x mm

Total fuel consumption : ________ kg _________ g

Approximate heat output : ________ kW/m2

Details of water bath trays (quantity & size) ________ mm x mm

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 178 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.16.2 Instrument for Hot Smoke Test

Model Manufacturer Serial No. Calibration Calibration


Instrument
No. Date Expiry Date

1) *Smoke Generator(s)

2) *Tracer Smoke

3) *Fire Chamber

4) *Combustion Fuel

5) *Thermal Couples

6) *Temperature Sensor(s)

7) *Anemometer

8) *Clamp-on Ammeter

9) *Voltmeter

10) *Tachometer

11) *Pitot-Static Tubes

12) *Inclined Manometers

13) *U gauges

14) *Fire Fighting


Equipment

15) *Breathing Apparatus

16) *Static Photo Camera

17) *Video Camera

18) Others (please specify)

* Delete if not applicable

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 179 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

3.16.3 Visual Inspection

3.16.3.1 General

a) Are FSD approved working / design drawings available? *Yes/No/N.A. *Yes/No/N.A.

b) Does general layout tally with F.S.I. drawings? *Yes/No/N.A. *Yes/No/N.A.

c) Does occupancy tally with that mentioned in approved *Yes/No/N.A. *Yes/No/N.A.


building plans?

d) Does compartmentation of protected premises tally with *Yes/No/N.A. *Yes/No/N.A.


that marked in approved building plans?

e) Does system layout tally with that in approved building *Yes/No/N.A. *Yes/No/N.A.
plans and F.S.I. drawings?

f) Are all wet fire service installations completed with full *Yes/No/N.A. *Yes/No/N.A.
testing & commissioning?

g) Are all automatic fire alarm installations completed with *Yes/No/N.A. *Yes/No/N.A.
full testing & commissioning?

h) Are all static & dynamic smoke extracting installations *Yes/No/N.A. *Yes/No/N.A.
completed with full testing & commissioning?

i) Is smoke zone boundary and auto smoke curtain location *Yes/No/N.A. *Yes/No/N.A.
in accordance to approved smoke control layout?

j) Is approved system design calculation enclosed? *Yes/No/N.A. *Yes/No/N.A.

k) Are the system operating principles / sequence enclosed? *Yes/No/N.A. *Yes/No/N.A.

l) Are technical catalogues enclosed? *Yes/No/N.A. *Yes/No/N.A.

m) Is approved computer programme enclosed? *Yes/No/N.A. *Yes/No/N.A.

n) Are all finishes of building envelop completed with full *Yes/No/N.A. *Yes/No/N.A.
inspection?

o) Are FSD approved procedures and set up details for *Yes/No/N.A. *Yes/No/N.A.
Testing & Commissioning available?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 180 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked by
by Contractor PBSE/PBSI

p) Is mock-up test with set up details for Testing & *Yes/No/N.A. *Yes/No/N.A.
Commissioning available and approved by Architect?

q) Is detail of approved organization chart available for *Yes/No/N.A. *Yes/No/N.A.


testing & commissioning?

r) Are details of members of approved fire fighting team *Yes/No/N.A. *Yes/No/N.A.


and auxiliary team available for testing &
commissioning?

s) Are formal evacuation procedures for all approved *Yes/No/N.A. *Yes/No/N.A.


visiting personnel available?

t) Is endorsed proposal for recording / monitoring *Yes/No/N.A. *Yes/No/N.A.


equipment and associated provisions enclosed?

u) Is design of the complete testing & commissioning *Yes/No/N.A. *Yes/No/N.A.


setup, including all equipment, components and wiring,
approved by Architect and accepted by the FSD
available?

v) Are all systems completed and tested to ensure that they *Yes/No/N.A. *Yes/No/N.A.
are functioning correctly before the final full test and
demonstration take place with FSD Officers in
attendance?

w) Has a full set of test and functional operation check *Yes/No/N.A. *Yes/No/N.A.
records submitted accompanying Register Professional
Engineers signature confirming or otherwise that he is
satisfied that the installation(s) are operating in
accordance with his design and the requirements of
F.S.D?

x) Have the format / methods of the required operational *Yes/No/N.A. *Yes/No/N.A.


and functional test been agreed with FSD before the
work commences?

y) Are all fire fighting squads available throughout the *Yes/No/N.A. *Yes/No/N.A.
testing process?

z) Is the safety arrangement and precautions for the test *Yes/No/N.A. *Yes/No/N.A.
approved by Architect and accepted by the FSD?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 181 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

3.16.3.2 Smoke Detector

a) Is the smoke collection probe installed? *Yes/No/N.A. *Yes/No/N.A.

b) Is approved type of smoke detector provided? *Yes/No/N.A. *Yes/No/N.A.

c) Is the pair of smoke collecting and releasing probes *Yes/No/N.A. *Yes/No/N.A.


installed correctly in relative positions as recommended
by the manufacturers and that adequate pressure
difference can be achieved for effective smoke
collection?

d) Are the filters at the end of the smoke collecting / *Yes/No/N.A. *Yes/No/N.A.
releasing probes clean and properly installed?

e) Do(es) designated smoke detector(s) be provided at the *Yes/No/N.A. *Yes/No/N.A.


air intake for smoke management system?

f) Is the smoke management supply fan tripped off upon *Yes/No/N.A. *Yes/No/N.A.
the sensing of smoke at the air intake passage by the
designated smoke detector?

g) Is the smoke detector connected with fire resisting cable *Yes/No/N.A. *Yes/No/N.A.
to the control panel?

h) Is the functioning of smoke detector tested satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

3.16.3.3 Miscellaneous

a) Are warning / instruction notices provided at areas of *Yes/No/N.A. *Yes/No/N.A.


testing?

b) Are warning / instruction notices provided inside the *Yes/No/N.A. *Yes/No/N.A.


testing area(s) which is(are) normally occupied?

c) Are warning/instruction notices provided at entrance & *Yes/No/N.A. *Yes/No/N.A.


inside the protected areas, which are normally occupied?

d) Is static photo recording carried out to record the smoke *Yes/No/N.A. *Yes/No/N.A.
movement upon the hot smoke test?

e) Is video recording carried out to record the smoke *Yes/No/N.A. *Yes/No/N.A.


movement upon the hot smoke test?

f) Is the smoke contained effectively within the smoke *Yes/No/N.A. *Yes/No/N.A.


reservoirs?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 182 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

3.16.4 Testing and Commissioning

3.16.4.1 Mechanical Test

a) Are the ductwork and all relevant parts of the systems for *Yes/No/N.A. *Yes/No/N.A.
the hot smoke test tested satisfactorily in accordance
with the T & C Procedure No. 1 for Air-conditioning,
Refrigeration, Ventilation and Central Monitoring
Control System Installation?

b) Are preliminary and visual test on the sealing of all *Yes/No/N.A. *Yes/No/N.A.
openings in the ductwork using chemical white smoke
generators be carried out?

c) Has mechanical check for motorized smoke / fire damper *Yes/No/N.A. *Yes/No/N.A.
been conducted and accepted by Registered Professional
Engineer under CAP 409?

d) Are smoke curtains dropped down smoothly and the *Yes/No/N.A. *Yes/No/N.A.
bottom bars stop at the correct position?

e) Is electro-thermal link properly installed & reinstated *Yes/No/N.A. *Yes/No/N.A.


and accepted by Registered Professional Engineer under
CAP 409?

3.16.4.2 Functional Test of System (System in MANUAL mode)

a) Does AUTO/MANUAL selector key switch function *Yes/No/N.A. *Yes/No/N.A.


properly and switched to manual mode upon the test?

b) Do smoke detectors operate satisfactorily? *Yes/No/N.A. *Yes/No/N.A.

c) Does operating alarm / indication function properly? *Yes/No/N.A. *Yes/No/N.A.

d) Is the shutdown of mechanical ventilation and air- *Yes/No/N.A. *Yes/No/N.A.


conditioning system satisfactorily accomplished?

e) Do fire damper opening / closing devices operate *Yes/No/N.A. *Yes/No/N.A.


satisfactorily?

f) Is the start-up / operation of smoke management system *Yes/No/N.A. *Yes/No/N.A.


satisfactorily accomplished and remained in operation
until manually reset?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 183 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

g) Is the static/dynamic smoke extraction system tested and *Yes/No/N.A. *Yes/No/N.A.


found satisfactorily in accordance with the T&C
requirements of smoke extraction system?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 184 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/ Items witnessed


Checked By
by Contractor PBSE/PBSI

3.16.4.3 Smoke test

a) Is the fire size identified with total heat output estimated *Yes/No/N.A. *Yes/No/N.A.
to ensure the test to be carried out without damage to the
building?

b) Does the submission provide details on the selection *Yes/No/N.A. *Yes/No/N.A.


process for the safe fire size?

c) Does the submission provide details on the configuration *Yes/No/N.A. *Yes/No/N.A.


of thermocouple tree ?

d) Are the plume temperature reading data logged with *Yes/No/N.A. *Yes/No/N.A.
computer programme and linked to trigger the alarm
signal for executing fire suppression, if required?

e) Is the smoke contained effectively within the smoke *Yes/No/N.A. *Yes/No/N.A.


reservoirs?

f) Are all smoke management systems and controls *Yes/No/N.A. *Yes/No/N.A.


functioned properly as designed and co-ordinated?

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 185 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

3.17 Comments (if any)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 186 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Part 4 : Test Records attached to the Test Certificate

4.1 Record of Tests on Hydrant and Hose Reel System

Project title (with location) :

P.W.P. / Project No. :

*Contract/Sub-contract/Quotation No. :

Date of Test :

Type, Model & Serial No. of Instrument used :

Date of calibration :

4.1.1 System Data

Type of building : *Industrial/godown/domestic/others

FSI Drawing Ref. : _____________________________

Water tank capacity :

(a) Supply tank : *9/18/27/36 m3 Location: ________________________

(b) Transfer tank : _________ m3 Location: ________________________

Height of topmost hydrant and lowest F.S. Inlet : m


(if exceeds 60 m, intermediate booster pumps/supply tank are required)

Total No. of twin type F.S. inlet : Nos.

Total No. of hydrant riser : Nos.

Intermediate booster pumps : Nos.

Transfer pumps : Nos.

Fixed fire pumps : Nos.

Jockey pumps : Nos.

Total No. of hydrant outlet (single type) : Nos.

Total No. hydrant outlet (double type) : Nos.

Total No. of hose reel (30 m) : Nos.

Size of incoming water main : mm dia.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 187 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Size of hydrant rising main : *80/100 mm dia.


(Industrial/godown - 100 mm, Others - 80 mm)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 188 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.1.2 Records

Table 1 Record of Hydraulic Test of Pipeworks

Date Location/Section Start End Duration


(min)
Time Pressure (kPa) Time Pressure (kPa)

(This form can also be used for hydraulic test carried out during the construction period)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 189 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Test Records on Pressure Reducing Set

Pressure (bars)
Pressure Reducing Riser/Stair No. Floor Level
Set No. Upstream Downstream

Table 3 Test Record of Pump/Motor Set

Pump/Motor Set Pump Discharge Pressure Motor Current


(kPa) (Amp)
Fixed Fire Pump Duty

Standby

Intermediate Booster Duty

Pump Standby

Transfer Pump Duty

Standby

Jockey Pump Duty

Table 4 Fire Service Pump Pressure Switch Setting

Cut-in Pressure Cut-out Pressure


(bars) (bars)
Jockey Pump

Duty Pump

Standby Pump

Table 5 Test Records on Flow Capacity and Range of Hose reel

Location of Hose reel Floor Level Riser/Stair No. Range (m) Flow rate
(L/min)

Highest hose reel of a

Branch

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 190 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 6 Test Records on Flow Capacity and Pressure of Hydrant

Location of Hydrant Floor Level Riser/Stair No. Pressure (bars) Flow rate (L/min)

Topmost outlet

Bottom outlet

Intermediate outlet

Table 7 Test Records on Static Pressure without Pump at the Topmost Hydrant Outlet

Floor Level Riser/Stair No. Pressure (bars)

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 191 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.2 Record of Tests on Automatic Sprinkler Installation

Project title (with location) :

P.W.P. / Project No. :

*Contract/Sub-contract/Quotation No. :

Date of Test :

Type, Model & Serial No. of Instrument used :

Date of calibration :

4.2.1 System Data

Hazard classification: *LH/OH(I)/ OH(II)/ OH(III)/ OH(III S)/ HH

Type of town mains: *single end feed/ double end feed/ direct feed/ unrestricted

Height of highest sprinkler above lowest sprinkler : m

Water tank capacity :

1. Sprinkler tank : m3 Location :

2. Transfer tank : m3 Location :

3. Priming tank : m3 Location :

Type of system : *wet/ dry/ pre-action/ pre-action /re-cycling/ deluge

Total Nos. of sprinkler head : Types Nos.

Total Nos. of installation control valve set : ______ __ Nos.

Total Nos. of subsidiary stop valve : ______ __ Nos.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 192 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Nos. of sprinkler head connected to each subsidiary stop valve :

Subsidiary Stop Valve Nos. of Sprinkler Head Total


(Zone)
Types Concealed Exposed

6
Use separate sheet for large installation.

4.2.2 Records

Table 1 Record of Hydraulic Test of Pipeworks

Date Location/Section Start End Duration


(min)
Time Pressure (kPa) Time Pressure (kPa)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 193 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Test Record of Pump/Motor Set

Pump/Motor Set Pump Discharge Pressure Motor Current


(kPa) (A)

Jockey Pump

Sprinkler Duty
Pump
Standby

Transfer Duty
Pump
Standby

Table 3 Sprinkler Pump Pressure Switch Setting

Cut-in Pressure Cut-out Pressure


(bars) (bars)

Jockey Pump

Duty Pump

Standby Pump

Note : Duty pump cut-in pressure shall be not less than 80% of the design/maintained pressure in
the trunk main.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 194 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 4 Test Records for Operation of Flow Switch

Zone Controlled Floor Level or Sprinkler Annunciation Panel


By Flow Switch Area where Alarm Indication Buzzer Sprinkler Pump
(Floor level or Bells Sound Cut-in
Area) Items tested Items witnessed Items tested Items witnessed Items tested Items witnessed
by Contractor By BS site staff by Contractor by BS site staff by Contractor by BS site staff
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No
*Yes/No *Yes/No *Yes/No *Yes/No *Yes/No *Yes/No

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 195 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 5 Test Record of Proving of Water Supplies with Measuring Orifice Fitted

Installation Valve No. Flow Rate Installation Pressure # Actual Minimum


(L/min) (bar) Running Pressure
(bar)
1

#- Actual minimum running pressure = Installation pressure - Static pressure of highest sprinkler

Table 6 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted

Installation Valve No. Installation Pressure (bar) Running Flow


Rate
(L/min)
Standing Running

Note: These records are reference for future testing.

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 196 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.3 Record of Tests on Manual and Automatic Fire Alarm System and Fire Alarm Control
System

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of Calibration :

4.3.1 System Data

Quantity Zone Total


(Nos.) 1 2 3 4 5 6 7 8

Manual Call Point

Alarm Bell

Heat

Fire Smoke
Detector
Probe Unit

Sprinkler Flow
Switch

System voltage : V d.c. Battery Ah

4.3.1.1 Type of Equipment


4.3.1.1.1 Alarm annunciation panel
Manufacturer/Model No. of Alarm annunciation panel:
(Main panel : _____________________________________)
(Sub-panel, if any : ________________________________)
a) FSD approved type *Yes/No
b) Conventional (electronic) type *Yes/No
Addressable type *Yes/No

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 197 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.3.1.1.2 Detectors
a) Heat detector:
Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________

b) Smoke detector : ____________________________________


Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________

c) Multi-sensor detector : ____________________________________


Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________

e) Others (please specify) : ____________________________________


Manufacturer/model No. : ____________________________________
Type : ____________________________________
Location : ____________________________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 198 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.3.2 Records

Table 1 Test Record of Manual Call Points, Alarm Bells and Control Panel

Control Panel
Location of Manual Floor on which
Call Point Alarm Bell Sound Zone No. and Buzzer Fire Pump
Indication Cut-in
(No./NO/OFF) (ON/OFF) (ON/OFF)

Table 2 Test Record of Detector and Control Panel

Control Panel
Location/ LED Indicator Floor on which
Identification Local/Remote Alarm Bell Zone No. and Buzzer
of Detector (ON/0FF) Sounds Indication
(Heat/Smoke) (No./ON/OFF) (ON/OFF)

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 199 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.4 Record of Tests on Gaseous Extinguishing Installation

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of Calibration :

4.4.1 System Data

Location/Room :
Type of Gas : *CO2 / FM200 / ________________

Type of System :

Total Flooding ( ) Local Application ( )

Modular ( ) Cylinder ( )

Pre-engineered ( ) Engineered ( )

High Pressure ( ) Low Pressure ( )

Single Hazard ( ) Multiple Hazard ( )

Primary Bank Only ( ) With Reserve Bank ( )

Working/Design Drawing Ref. : _______________________________________________

Approved Computer Programme Ref. : __________________________________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 200 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.4.2 Records

Table 1 Automatic Gas Flooding System

Test System System Alarm Yod- Indication Test Remarks


Condition Action Bell alarm on Panel Result

1 Normal 1.1 No OFF OFF Supply *Yes/No


healthy

2 Detection 2.1 System actuated ON OFF Zone fire *Yes/No


zone 1 or
2
actuated

3 Detection 3.1 Warning sign ON ON Zone fire *Yes/No


Zone 1 actuated
and 2
actuated 3.2 Discharge ON ON Zone fire *Yes/No
actuating and gas
solenoid operated discharged
or gas discharged
after a time delay
of
sec.
3.3 Fire dampers/ ON ON Zone fire *Yes/No
openings closing and gas
devices operated discharged
3.4 Gas totally ON ON Zone fire *Yes/No For
discharged within and gas practical
sec. discharged discharge
test only
3.5 Restore gas ON OFF Zone fire *Yes/No
discharge and gas
mechanism discharged
3.6 Press the Reset OFF OFF Supply *Yes/No
button on the healthy
control panel

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 201 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 1 Automatic Gas Flooding System (Contd)

Test System System Alarm Yod- Indication Test Remarks


Condition Action Bell alarm on Panel Result

4 Manual 4.1 Pull the manual ON ON Zone fire *Yes/No


operation pull handle
outside the
protected
compartment

4.2 Warning sign ON ON Zone fire *Yes/No


actuated

4.3 Discharge ON ON Zone fire *Yes/No


actuating and gas
solenoid operated discharged
or gas discharged
after a time delay
of
sec.

4.4 Fire dampers/ ON ON Zone fire *Yes/No


opening closing and gas
devices operated discharged

4.5 Gas totally ON ON Zone fire *Yes/No For


discharged within and gas practical
sec. discharged discharge
test only

4.6 Restore gas ON OFF Zone fire *Yes/No


discharge and gas
mechanism discharged

4.7 Press the Reset OFF OFF Supply *Yes/No


button on the healthy
control panel

5 Look-off 5.1 Turn key switch OFF OFF System *Yes/No


condition to Manual mode manual

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 202 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.5 Record of Tests on Street Hydrant

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of Calibration :

4.5.1 System Data

Water supply : *Town main/pump and sump tank


Sump tank : m3
Total No. of hydrant : Nos..
Type of hydrant : *Swam-neck/Pedestal

4.5.2 Records
Table 1 Record of Hydraulic Test of Pipeworks

Date Location/Section Start End Duration


(min)
Time Pressure (kPa) Time Pressure (kPa)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 203 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Test Record of Pump/Motor Set

Pump/Motor Set Pump Discharge Pressure Motor Current


(A)

Jockey Pump

Street Hydrant Duty


Pump
Standby

Table 3 Test Record of Pressure and Flow of Street Hydrant

Street Hydrant Outlet Flow Rate Pressure


(L/s) (kPa)
Two farthest outlet discharge
simultaneously

Others

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 204 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.6 Record of Tests on Drencher System

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of calibration :

4.6.1 System Data

Type of town mains : *single end feed/ double end feed/ direct feed/ unrestricted
Water tank capacity : m at Location :
Total Nos. of drencher head/water spray nozzle : Nos.
Total Nos. of deluge valve set : Nos.
Nos. of drencher head/water spray nozzle connected to each deluge valve set :

Deluge Types/Nos. of Drencher Head/ Area of opening


Valve Water Spray Nozzle Total protected by
(Zone) Drencher (sq m)
Types No.

9
Use separate sheet for large installation.
4.6.2 Records

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 205 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 1 Record of Hydraulic Test of Pipeworks

Date Location/Section Start End Duration


(min)
Time Pressure (kPa) Time Pressure (kPa)

Table 2 Test Record of Pump/Motor Set

Pump/Motor Set Pump Discharge Pressure Motor Current


(A)

Duty

Standby

Table 3 Drencher Pump Pressure Switch Setting

Pump/Motor Set Cut-in Pressure Cut-out Pressure


(bars) (bars)

Duty

Standby

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 206 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 4 Test Record of Proving of Water Supplies with Measuring Orifice Fitted

Deluge Valve No. Flow Rate Installation Pressure # Actual Minimum


(L/min) (bar) Running Pressure
(bar)
1

Note : # - Actual minimum running pressure = Installation pressure - Static pressure of highest nozzle

Discharge density = Flow rate /Area of opening = __________________________ L/min/m2


Time of discharge = Effective tank size / Flow rate = ________________________ min

Table 5 Test Record of Proving of Water Supplies with Standard Test Orifice Fitted

Installation Valve No. Installation Pressure (bar) Running Flow Rate


(L/min)
Standing Running

Note : These records are reference for future testing.

Remark:
4.7 Record of Tests on Audio/Visual Advisory System

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 207 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of Calibration :

Table 1 Test Record of Loudspeakers

Control Panel
Location of Floor on which
Loudspeakers Loudspeakers Zone No. and Loudspeaker
Operated Indication
(No./NO/OFF) (ON/OFF)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 208 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Test Record of Flashing Light/Flashing Directional Sign

Control Panel
Location/ Flashing Lights
Identification (ON/OFF) Zone No. and Flashing
of Flashing Lights Indication Light
(No./ON/OFF) (ON/OFF)

Note: Flashing lights in the same area shall operate in synchronous mode.
Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 209 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.8 Record of Tests on Portable Hand-Operated Approved Appliance

4.8.1 System Data

Type of Zone/Quantity Total Expiry


Appliance F F F F F F F F Date
1 2 3 4 5 6 7 8
Fire
Extinguishers

(a) Water
kg
kg

(b) Foam (*)

(c) Dry powder (*)

(d) Carbon dioxide (*)

(e) FM200 (*)

(f) NAFSIII (*)

Fire blanket (*)

Sand bucket (*)

Automatic Fixed
Sprayer Unit
(Type: )
(*)
Others (please specify)

Note: *Capacity and type of fire extinguishers and their locations shall be stated.
Remark:

Checked/Certified by : ______________________________ Certificate No.:___________________


(Name of person holding class 3 registration)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 210 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.9 Record of Tests on Fire Shutters

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of Calibration :

Table 1 Test Record of Fire Shutters

Operation

Location of Fire
Shutters Zone No. and Buzzer Fire Shutters Fire Shutters
Indication (Close by fire signal (Re-open after fire
(No./NO/OFF) (ON/OFF) automatically signal cleared
Yes/No) Yes/No)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 211 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Test Record of Detector and Control Panel

Control Panel
Location/ LED Indicator Floor on which
Identification Local/Remote Alarm Bell Sound Zone No. and Buzzer
of Detector (ON/OFF) Indication
(Heat/Smoke) (No./ON/OFF) (ON/OFF)

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 212 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10 Record of Tests on Emergency Generator Installation

Project title :
*P.W.P./Project No. :
*Contract/Sub-contract/Quotation No. :
Date of test :
Test instruments used :

Type Model Serial No. Date of Calibration

4.10.1 Equipment Details


4.10.1.1 Generator Set
a) Manufacturer :
b) Model :
c) Net prime rating (MCR) (kW) :

4.10.1.2 Diesel Engine


a) Make :
b) Model :
c) Serial No. :
d) Rated power (kW) :
e) Speed (rpm) :
f) Governor :
g) Turbocharger (type/model) :

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 213 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.1.3 Alternator

a) Make :
b) Model :
c) Serial No. :
d) Rated kVA :
e) Voltage (V) / Full load current (A) :
f) Phase / Rated p.f. :
g) Insulation class :

4.10.1.4 Starting Battery

a) Manufacturer :
b) Make/Model No. :
c) No(s). of battery / Voltage (V) :
d) Ampere hour :
e) Starting time (sec) :

4.10.1.5 Lifting Hoist

a) Manufacturer :
b) Make / Model No. :
c) Safe working load (kg) :
d) Lifting height (m) :
e) Test Certificate : *Yes/No

4.10.1.6 Other Accessories

a) Name plate of manual bypass switch : _______________________________________


b) Name plate of auto-changeover switch : ______________________________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 214 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.2 Type of Control

4.10.2.1 Starting *Automatic/Manual


4.10.2.2 Loading Transfer to Generator *Automatic/Manual
4.10.2.3 Stopping *Automatic/Manual
4.10.2.4 Load Transfer to Mains *Automatic/Manual

4.10.3 Insulation Resistance Test (Temporarily open alternator star point)

4.10.3.1 Red phase to earth Megaohm


4.10.3.2 Yellow phase to earth Megaohm
4.10.3.3 Blue phase to earth Megaohm
4.10.3.4 Red phase to yellow phase Megaohm
4.10.3.5 Yellow phase to blue phase Megaohm
4.10.3.6 Blue phase to red phase Megaohm

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 215 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.4 Installations and Equipment Connected

Peak Starting Rated Input Starting


Current (IL) Power Method

(a) Fire service installation

Fixed fire pump No. x A No. x kW


Intermediate booster pump No. x A No. x kW
Sprinkler pump No. x A No. x kW
Firemans lift No. x A No. x kW
Fire detection system No. x A No. x kW
Smoke extraction system No. x A No. x kW
Staircase pressurization No. x A No. x kW
Exit sign/emergency lighting No. x A No. x kW
Others : No. x A No. x kW

(b) Other equipment (please specify)


. A kW
. A kW
A kW
A kW
A kW
A kW

Estimated maximum simultaneous Remarks :


starting and running load kW/ kVA D.O.L. /
Star-delta/
Auto-
transformer/
others

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 216 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.5 Control Function Test

Control Function Test Function Test Setting Remarks

a. Starting Manual
Simulate Test 1 ^
Mains Failure
Test 2 **
Delay Start Timer
Delay Repeat Start
b. Stopping Manual
Resumption of Mains ***
Delay Stop Timer ****
c. Engine Overload Trip (MCCB)
Protection
Engine HL
Overspeed
LL
Low Lub-oil HL
Pressure (kPa) LL
High Water HL
Temp.
(oC) LL
Under Voltage Trip
Overvoltage Trip

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 217 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Control Function Test Function Test Setting Remarks

d. Others Response Time from Mains


Failure to Changeover (sec)
Battery 3 Attempt Start
Quick closing Mechanism
Governor Function
Voltage Regulator (346V -
380V)
Auto-starting of Vent. Fan
Manual Override Facilities
Phase Sequence of Alternator
Output
Frequency Setting

Note : ^ Refer to function test on capability to start and transfer load to generator automatically.
** Refer to function test on capability to start but without load transfer if mains resumes
during engine starting.
*** Refer to function test on capability to automatic transfer load back to mains automatically
after a preset time delay and immediately back to generator if mains fails within the above
time delay period.
**** Refer to function test on capability to cool engine for a preset period after load is
transferred to mains.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 218 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.6 On Load Test

4.10.6.1 All loadings connected : *Yes/No


4.10.6.2 Frequency (Hz) : _______________________________________________________
4.10.6.3 Maximum starting current (ILMAX):
R: ______________ A Y: ___________A B: ______________ A
4.10.6.4 Voltage dip: ______ % Voltage recovery time: ___________________seconds
4.10.6.5 Running (Current (IL)
R: ______________ A Y: ______________ A B: _______________A
4.10.6.6 Voltage (Volts)
R-Y: _____________ Y-B: ______________ B-R: ______________
R-N: _____________ Y-N: ______________ B-N: ______________
4.10.6.7 Engine speed (RPM) : ____________________________________________________
4.10.6.8 Duration of on-load test (hr) : ______________________________________________

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 219 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.7 Dummy Load Test

Time from start


Duration (HR) (minimum) 1/2 1/2 1 1 1 1/2
Duration (HR) (actual)
Frequency (Hz)
R
Current (Amp) Y
B
B-Y / R-N
Voltage (Volt) Y-B / Y-N
B-R / B-N
Dummy Load KW
% Full Load 0 25% 50% 75% 100% 110%
Engine Speed (RPM)
Cooling Water Temp.
Engine Oil Temp. (oC)
Engine Oil Pressure (kPa)
Fuel Consumption (L)
Engine Room Temperature (oC)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 220 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.10.8 Earthing Protection Test

Measured Earthing Resistance : __________________________

Earthing Relay : Current Setting :

Make : ________________ Time Setting : __________________

Model : ________________ Function Test : ___________________

Serial No. : ________________

Rated Current : ________________

Remark:

Checked/Certified by : Certificate No.:


(Name of electrical worker) Class

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 221 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.11 Record of Tests on Fireman's Lift

Project title (with location) :


P.W.P. / Project No. :
*Contract/Sub-contract/Quotation No. :
Date of Test :
Type, Model & Serial No. of Instrument used :
Date of calibration:

4.11.1 Lift Data

Lift No.

Manufacturer

Speed (m/s)

Floor served to to to

Pattern of floor served #

Internal size of lift car (m2)

Rated load of lift car (kg)

Size of lift car/ width of landing


opening WxH (mm)

#- Alternate odd/alternate even/all

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 222 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.11.2 Records

Items tested/checked

When Fireman's Switch ON

4.11.2.1 The following devices/switches are inoperative

a) Attendance switch? *Yes/No/N.A.

b) Service switch inside car? *Yes/No/N.A.

c) Operation ON/OFF switch inside car? *Yes/No/N.A.

d) All hall calls? *Yes/No/N.A.

e) All registered car calls? *Yes/No/N.A.

f) Ventilation fan once car stop hatch is opened? *Yes/No/N.A.

4.11.2.2 The following devices/switches are still operative :

a) Overload device? *Yes/No/N.A.

b) All safety circuit except photo cell? *Yes/No/N.A.

c) Car stop station? *Yes/No/N.A.

d) Fan/light switch? *Yes/No/N.A.

e) Alarm? *Yes/No/N.A.

f) Intercom? *Yes/No/N.A.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 223 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/checked

4.11.2.3 When lift NOT at main floor and running UP :

a) Lift stops at nearest floor without opening door? *Yes/No/N.A.

b) Door open button is inoperative? *Yes/No/N.A.

c) Lift reverses direction and returns to main floor? *Yes/No/N.A.

4.11.2.4 When lift NOT at main floor and running DOWN :

a) Door open button is inoperative? *Yes/No/N.A.

b) Lift returns to main floor? *Yes/No/N.A.

4.11.2.5 When lift NOT at main floor and stopping at other floor with
door OPEN :

a) Door closes automatically with door open button still *Yes/No/N.A.


operative ?

b) Door open button is inoperative when door is fully closed ? *Yes/No/N.A.

c) Lift returns to main floor ? *Yes/No/N.A.

4.11.2.6 When lift NOT at main floor and stopping at other floor with
door CLOSE :

a) Door open button is inoperative ? *Yes/No/N.A.

b) Lift returns to main floor ? *Yes/No/N.A.

4.11.2.7 When lift at main floor :

a) Door keeps open ? *Yes/No/N.A.

b) Door open button is inoperative ? *Yes/No/N.A.

c) All car calls are operative ? *Yes/No/N.A.

d) Door starts closing when car call button pressed ? *Yes/No/N.A.

e) Door is totally closed with car call button or door close button *Yes/No/N.A.
pressed continuously otherwise door opened ?

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 224 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Items tested/checked

f) Other car calls can be registered ? *Yes/No/N.A.

g) Lift stops at nearest car call and all other car calls cancelled ? *Yes/No/N.A.

h) Door remains closed ? *Yes/No/N.A.

4.11.2.8 When lift at desired floor :

a) Door starts opening when door open button pressed ? *Yes/No/N.A.

b) Door opens fully when door open button is pressed *Yes/No/N.A.


continuously, otherwise door will close ?

c) Door remains fully opened and car call can be registered again ? *Yes/No/N.A.

d) Lift remains at the floor ? *Yes/No/N.A.

4.11.2.9 When Fireman's switch OFF

a) Lift resumes normal operating conditions ? *Yes/No/N.A.

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 225 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.12 Record of Tests on Emergency Lighting & Exit Signs

4.12.1 System Data

Quantity Floor Total


(Nos.)
1 2 3 4 5 6 7 8
Emergency Light

Exit Sign

Directional Sign

Type of emergency lighting :


Floor 1 Type : ____________________________ Battery operating Hours: _________
Test facilities: *Auto/Self/Remote/Manual
Floor 2 Type: _____________________________ Battery operating Hours: _________
Test facilities: *Auto/Self/Remote/Manual

Note: 1. Add more floors where necessary


2. Specify self-contained or centrally supplied, maintained or non-maintained, etc.

Type of exit sign :


Floor 1 Type: ____________________________ Battery operating Hours: _________
Test facilities: *Auto/Self/Remote/Manual
Floor 2 Type: ____________________________ Battery operating Hours: _________
Test facilities: *Auto/Self/Remote/Manual

Note: 1. Add more floors where necessary


2. Specify self-contained or centrally supplied, maintained or non-maintained, etc.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 226 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.12.2 Record of Test

4.12.2.1 Emergency Lighting

Location Type (self- Quantity Operating Voltage Current Lux Test


contained/central hours facilities
battery system, (if tested) checked
battery type, etc.) (Yes/No)
Floor 1

Floor 2

Floor 3

Floor 4

Floor 5

Floor 6

Floor 7

Floor 8

Floor 9

Floor 10

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 227 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.12.2.2 Exit Signs

Location Type (self- Number Operating Voltage Current Lux Test


contained/battery hours facilities
kit/central battery (if tested) checked
system, battery (Yes/No)
type, etc.)
Floor 1

Floor 2

Floor 3

Floor 4

Floor 5

Floor 6

Floor 7

Floor 8

Floor 9

Floor 10

Remark:
Checked/Certified by : Certificate No.:
(Name of electrical worker) Class

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 228 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.13 Record of Tests on Ventilation and Air-conditioning (VAC) Control System

Table 1. Test Records on Overall Performance of VAC Control System

Ref. No. Method of Shut down Fire signal MVAC Operate Other
and type of Tripping by smoke registered in system Manual MVAC
MVAC off detector FS Panel unable to override system
system and type restart while switch to shut interlocked
fire signal off the MVAC
exists system and
test on FAIL
SAFE

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 229 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.14 Record of Tests on Pressurization of Staircases System

Project title (with location) :

*P.W.P. / Project No. :

*Contract/Sub-contract/Quotation No. :

Date of Test :

Type, Model & Serial No. of Instrument used :

Date of calibration :

4.14.1 System Data

Type of building : *Industrial/Godown/Domestic/Others

FSI Drawing Ref. :

Staircase pressurization fan room : (Location)

Total nos. of staircase pressurization fan : No(s).

Total nos. of floor level : Nos.

Total nos. of door opening (single leaf) : Nos.

Total nos. of discharge outlet : Nos.

Total nos. pressure relief damper : Nos.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 230 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.14.2 Records

Table 1 Record of Air Velocity Across Smoke Lobby to Corridor / Plant Room

Staircase Ref. No : S. P. Fan Ref. No. :

Equipment Location : Total Pages of Records :

Open Door Air Velocity from Staircase to Lobby (Remarks (ii) referred)
Location
Velocity 1 Velocity 2 Velocity 3 Velocity 4 Average Door Velocity Remarks
Remarks (i)
(m/s) (m/s) (m/s) (m/s) (Criteria : ___ m/s)
referred

Remarks :

(i) Single leaf doors on the lift lobbies of any three consecutive floors and one leaf of double-leaf
door at G/F main entrance open

(ii) Airflow across lift lobby door and corridor at the middle of the three consecutive floors are
measured by using calibrated air flow meter.

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 231 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Record of Door Opening Force and Pressure Differential Measurement Across Smoke Lobby
to Corridor

Staircase Ref. No : S. P. Fan Ref. No. :

Equipment Location : Total Pages of Records :

Floor Level Location Pressure Differential Door Opening Force Remarks


Across Door (Pa) (Newton)
(Criteria : 50 Pa) (Criteria : 133 N or as
Remarks (i), (ii) and (iii) required by FSD)
referred Remarks (iv) and (v)
referred

Remarks :

(i) Measure the differential pressure across each lift lobby and corridor by using calibrated airflow
meter with pressure measurement function.

(ii) Measure the differential pressure across staircase and lift lobby by using calibrated airflow meter
with pressure measurement function.

(iii) Inside stairwell with all doors closed and all pressure relief systems operating.

(iv) Measure the force required for opening the door from the lift lobby entrance to corridor by using
calibrated push pull gauge.

(v) Measure the force required for opening the lift lobby door entrance to staircase by using
calibrated push pull gauge.

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 232 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.15 Record of Tests on Smoke Extraction System

Project Title (with location) :

P.W.P. / Project No. :

*Contract/Sub-contract/Quotation No. :

FSI Drawing Ref. :

Date of Test :

Type, Model & Serial No. of Instrument used :

Date of calibration :

4.15.1 System Data

Type of extraction system : *Static / Dynamic/___________

Total air change per hour :

Total nos. of smoke extraction fan : No(s).

Total area of air intake opening : Nos. m2

Total nos. of discharge outlet or smoke vent : Nos.

Size of discharge outlet or smoke vent : m2

Total nos of smoke curtain : No(s).

Height of smoke curtain above ground : m

Smoke removal rate : m3/s

Minimum supply or make-up air rate : m3/s

Makeup air inlet velocity : m/s

Exhaust air discharge velocity : m/s

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 233 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.15.2 Records

Table 1 Record of Static Smoke Extraction System(s)

Smoke Extraction System : Intake Louvre Ref. No. :

Equipment Location : Exhaust Louvre Ref. No. :

Locations Air Flow Volume and Velocity from Intake Points

(Intake) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )

Locations Air Flow Volume and Velocity from Exhaust Points

(Discharge) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )

Remarks :

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 234 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

Table 2 Record of Dynamic Smoke Extraction System(s)

Smoke Extraction System : Intake Fan Ref. No. :

Equipment Location : Exhaust Fan Ref. No. :

Locations Air Flow Volume and Velocity from Intake Fans

(Intake) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )

Locations Air Flow Volume and Velocity from Exhaust Fans

(Discharge) Velocity 1 Velocity 2 Velocity 3 Velocity 4 Total Air Flow Volume Remarks
3
(m/s) (m/s) (m/s) (m/s) ( m /s )

Remarks :

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 235 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.16 Record of Hot Smoke Test

Project title (with location) :

P.W.P. / Project No. :

*Contract/Sub-contract/Quotation No. :

Date of Test :

Type, Model & Serial No. of Instrument used :

Date of calibration :

4.16.1 System Data

Type of building : *Industrial / Godown / Domestic / Others

FSI Drawing Ref. :

Compartment volume : m3

Headroom height : m

Total smoke extraction rate: m3 /s

Total F.A. make up rate : m3 /s

Total air change rate:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 236 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.16.2 System Design Assumption

Yes No Remark

Air flow based on 8 air change per hour :

Air flow based on fire load calculation :

Air flow based on other method :

Natural smoke extraction system :

Natural F.A. make up system :

4.16.3 On-Site Inspection Data

Total smoke extraction rate : ( m3 / s )

Total F.A. make up rate : ( m3 / s )

Smoke clearance time : ( min / sec )

Yes No Remark

Smoke outlet less that 30 m :

Make up air velocity less that 3 m/s :

Extract air velocity less than 6 m/s :

Air inlet 5 m away from extract air


discharge to outdoor :

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 237 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.16.4 Records

Table 1 Record of Hot Smoke Test Inspection

Design fire size :

Method of simulation of fire size :

Type of fuel for fire simulation :

Type of smoke generator :

Internal building height :

Time to actuate alarm :

On-site measured temperature :

Time Ambient Smoke Plume Smoke Layer Temperature at


Elapsed Temperature Temperature at Temperature Temperature (oC) Smoke Exhaust
(minutes) (oC) Smoke Box (oC) Point (oC)
Outlet (oC)

Checked/Certified by : _________________________________ Engineer Registration No.:________


(Name of engineer satisfying FSDCOP requirements)

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 238 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.17 Record of Inspection and Witness of Tests on Works installed by Others

The following fire service installations by others, related fire service installations and related fire service
provisions are inspected and the final tests are witnessed (G.S. Clause A3.4, B12.7 and C1.12) :

Type of fire service Name of company Date(s) of Date(s) of Test records


installation/provisions and carrying out the inspection(s) witness of final and/or
brief description of the scope installation and test(s) certificates by
testing work others attached
(Yes/No)

Note: The inspection and witness of final tests on works by others should only be made on items and
aspects related to and required in FSDCOP and for fire service inspection by Fire Services
Department.

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 239 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.18 Record of Factory/Off-Site Test Certificates

Location and address of installation :

This is to certify that the following fire service installation *has/have been tested in factory/off-site with
the following test certificates and factory test certificates (G.S. Clause C1.1.1, B4.3, B5.8, A2.10, etc.) :

Date of test Type of test Test certificate and details

(Note: 1. One copy of each test certificate shall be enclosed.


2. The test certificate shall be signed and dated by a qualified person of the test agency.)

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 240 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.19 Test Equipment

(G.S. Clause A6.1.12 and C1.2)

Type Model Serial No. of Date of


Instrument Calibration
(where
applicable)

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 241 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.20 Documents required in Specification

4.20.1 Recommended spare parts and special tools lists with prices. *Yes/No/N.A.
(3 sets) (G.S. Clause A5.7 and B13.4)

4.20.2 Equipment catalogue and/or technical brochures (3 sets). *Yes/No/N.A.


(G.S. Clause A5.7 and A6.1.3)

4.20.3 As-built drawings. (G.S. Clause A5.5)

4.20.3.1 First draft *Yes/No/N.A.

4.20.3.2 Revised *Yes/No/N.A.

4.20.3.3 Final and approved

a) Micro-film (3 sets) *Yes/No/N.A.

b) Computer disk (2 sets) *Yes/No/N.A.

c) Reproducible copy (1 set) *Yes/No/N.A.

d) Print (4 sets) *Yes/No/N.A.

4.20.4 As-installed diagrams in glazed frames mounted in fire *Yes/No/N.A.


control centre, main entrance, pump room, watchmans office,
etc. (G.S. Clause A5.5)

4.20.5 As-built drawings stored in metal container at site (1 set). *Yes/No/N.A.


(G.S. Clause A5.5)

4.20.6 *Licences on intellectual property rights. (G.S. Clause A5.7) *Yes/No/N.A.

4.20.7 Key data summary sheet (3 sets). (G.S. Clause A5.7) *Yes/No/N.A.

4.20.8 *Form 501 /Fire certificate or FSD acceptance memo /Form *Yes/No/N.A.
WR1-a or equivalent by electrical workers /Certificates on
heavy load support and pressurized equipment /Certificates on
gas cylinder /Submissions for Form 314, Form 251, D.G.
store, PPE licence, restaurant licence, etc. /Batch approval
certificate for fire extinguishers /Performance based fire
engineering reports and certificates of designer and
independent checker /Certification by Ventilation Contractor
/Other certificates and licences to be included as record.
(G.S. Clause A5.7)

4.20.9 Others (please specify):

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 242 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.21 Equipment Schedule of Approved and Installed Equipment

Type of Installation : Date :

Project Title : Revision :

(*The equipment schedule should include all equipment items of the installation. Catalogues and approval
certificate/factory certificate shall be provided and attached)

Item Description Make Model No. Catalogue/Certificate/FSD Remarks


approval document
() Submitted
(X) Not submitted
(NA) Not applicable

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

Remark:

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 243 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex A

4.22 Record of Certification on Design by Contractor

Project title (with location) :

*P.W.P. / Project No. :

*Contract/sub-contract/Quotation No. :

*Contractor/Sub-Contractor :

FSD Ref. :

Drawing No. :

I certify that the following Fire Service Installations as specified in the Contract/Sub-
*contract/Quotation have been designed in accordance with relevant standards, guidelines,
codes of practice, statutory regulations, and good trade practice to meet with the functional,
performance, operation and maintenance requirements and in accordance with the
Specifications and the contract requirements. I certify that the Fire Service Installations
have been checked and tested satisfactorily to comply with the design:

1. _________________________________________________
2. _________________________________________________
3. _________________________________________________
4. _________________________________________________
5. _________________________________________________

Signature - Post :
Tested / Checked by :
(Name of Contractors Representative) Tel. No. :
( ) Date :
Signature - Post :
Witnessed by :
(Name(s) of BSB Staff) Tel. No. :
( ) Date :
Signature - Post :
Name in full :
(Designers firm) Tel. No. :
( ) Date :
Company Chop :

Note : 1. This certificate must be signed by the person responsible for the design and authorized by the
Firm/Company.
2. The person authorized by the Firm/Company shall possess the relevant qualifications
required by the Particular Specification and Fire Service General Specification.

* Delete if not applicable

Architectural Services Department Annex A Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.063 (2007) Page 244 of 244 Revision Date:
FS_TCP (2007 Edition)
Annex B

Testing and commissioning progress chart


Fire Service Installation
Contract No. :

Contract Title:

Name of Fire Service Contractor/Sub-contractor :

Contract Period : / / to / / *Revised/Actual Completion Date : / /

Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark

Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
1. Hydrant and Hose Part 3.1
Reel System
Visual Inspection
G/F
1/F
2/F
3/F
4/F
Functional and
performance test
Submission of
Record of Test

2. Automatic Part 3.2


Sprinkler System
Visual Inspection
G/F
1/F
2/F
3/F
4/F
Functional and
performance test
Submission of
Record of Test

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex B Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.023 (2007) Page 1 of 5 Revision Date:
FS_TCP (2007 Edition)
Annex B
Testing and commissioning progress chart
Fire Service Installation
Contract No. :

Contract Title:

Name of Fire Service Contractor/Sub-contractor :

Contract Period : / / to / / *Revised/Actual Completion Date : / /

Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark

Activities Reference to S A S A S A S A S A S A S A S A
Approved
T&C
Procedure
3. Manual and Part 3.3
Automatic Fire
Alarm System and
Fire Alarm Control
System
Visual Inspection
G/F
1/F
2/F
3/F
Functional and
performance test
Submission of
Record of Test

4. Gaseous Part 3.4


Extinguishing
System
Visual inspection
G/F
1/F
2/F
3/F
Functional Test
Discharge Test
Submission of
Record of Test

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex B Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.023 (2007) Page 2 of 5 Revision Date:
FS_TCP (2007 Edition)
Annex B
Testing and commissioning progress chart
Fire Service Installation
Contract No. :

Contract Title:

Name of Fire Service Contractor/Sub-contractor :

Contract Period : / / to / / *Revised/Actual Completion Date : / /

Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark

Activities Reference to S A S A S A S A S A S A S A S A
Approved
T&C
Procedure
5. Street Hydrant Part 3.5
Visual inspection
Functional and
performance test
Submission of
Record of Test

6. Drencher System Part 3.6


Visual inspection
Functional and
performance test
Submission of
Record of Test

7. Audio/Visual Part 3.7


Advisory System
Visual inspection
Functional and
performance test
Submission of
Record of Test

8. Portable Hand- Part 3.8


Operated Approved
Appliances
Visual inspection
Submission of
Record of Test

9. Fire Shutters Part 3.9


Visual inspection
Functional test

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex B Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.023 (2007) Page 3 of 5 Revision Date:
FS_TCP (2007 Edition)
Annex B

Testing and commissioning progress chart


Fire Service Installation
Contract No. :

Contract Title:

Name of Fire Service Contractor/Sub-contractor :

Contract Period : / / to / / *Revised/Actual Completion Date : / /

Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark

Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
Submission of
Record of Test

10. Emergency Generator Part 3.10


Installation
Visual inspection
Functional test
Submission of
Record of Test

11. Firemans Lift Part 3.11


Visual inspection
Functional test
Submission of
Record of Test

12. Emergency Lighting Part 3.12


& Exit Signs
Visual inspection
Functional test
Submission of
Record of Test

13. VAC Control System Part 3.13


Visual inspection
Functional test
Submission of
Record of Test

Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex B Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.023 (2007) Page 4 of 5 Revision Date:
FS_TCP (2007 Edition)
Annex B
Testing and commissioning progress chart
Fire Service Installation
Contract No. :

Contract Title:

Name of Fire Service Contractor/Sub-contractor :

Contract Period : / / to / / *Revised/Actual Completion Date : / /

Testing and Commissioning Progress Chart for Fire Service Installation (Rev. )(1)
Dates(2) Remark

Activities Reference S A S A S A S A S A S A S A S A
to
Approved
T&C
Procedure
14. Pressurization of Part 3.14
Staircases System
Visual inspection
Functional test
Performance test
Submission of
Record of Test

15. Smoke Extraction Part 3.15


System
Visual inspection
Functional test
Performance test
Submission of
Record of Test

16. Hot Smoke Test Part 3.16


Visual inspection
Functional test
Performance test
Submission of
Record of Test

17. Submission of T&C


Certificate
Notes
* Delete as appropriate
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion,
A - actual % completion
Signature - Post :
Tested / Checked by :
Tel. No. :
(Name of Contractors Representative)
( ) Date :
Signature - Post :
Witnessed by: Tel. No. :
(Name(s) of *PBSE/PBSI)
( ) Date :

Architectural Services Department Annex B Issue Date: 17 Dec 2007


BSB - Standard Form No. PBS/SR.023 (2007) Page 5 of 5 Revision Date:
FS_TCP (2007 Edition)
Annex C

Abbreviations
The following abbreviations are applicable to Annex A and Annex B:

AC - Alternating Current

Ahr - Ampere-hour

BS - BS 5839 : Part 1 : 1988 Fire Detection and Alarm Systems for Buildings, Part 1. Code of
Practice for System Design, Installation and Servicing

Cat - Category

cd - Candela

CL - F.S.D. Circular Letter No.

dB(A) - Decibel (A-weighted)

DC - Direct Current

DTL - Direct Telephone Line

EE Code - Code of Practice for the Electricity (Wiring) Regulations issued by Electrical and
Mechanical Services Department

FSCC - Fire Service Communication Centre

Code - Codes of Practice for Minimum Fire Service Installations and Equipment and Inspection,
Testing and Maintenance of Installations and Equipment issued by Hong Kong Fire
Services Department

FSI - Fire Service Installation

ft - Foot(Feet)

Hz - Hertz

F.S.D. - Hong Kong Fire Services Department

IEE - The Institution of Electrical Engineers

in - Inch(es)

KVA - Kilo-Volt-Ampere

LPC - Loss Prevention Council Rules for Automatic Fire Detection and Alarm Installations for
the Protection of Property (Schedule for the use of BS 5839:Part 1:1988)

m - Metre(s)

MICS - Mineral-Insulated Copper-Sheathed

M - Megaohm(s)

N/A - Not Applicable

Architectural Services Department Annex C Issue Date: 17 Dec 2007


Page 1 of 2 Revision Date: -
FS_TCP (2007 Edition)
Annex C

NFPA 72 or - NFPA 72 : National Fire Alarm Code, 1999 Edition


NFPA

RAM - Random Access Memory

Ref or ref - Reference(s)

VFA - Visual Fire Alarm

< - Less than

- Less than/equal to

> - More than

- More than/equal to

Architectural Services Department Annex C Issue Date: 17 Dec 2007


Page 2 of 2 Revision Date: -
FS_TCP (2007 Edition)

Vous aimerez peut-être aussi