Vous êtes sur la page 1sur 11

LARGE DIAMETER SHAFTS YOUGHIOGHENY RESERVOIR BRIDGE

Paul J. Lewis, P.E., Gannett Fleming, Inc., Harrisburg, PA, USA


David R. Scherer, P.E., Gannett Fleming, Inc., Harrisburg, PA, USA

Estimation of the axial side shear resistance of drilled shaft rock sockets is directly
related to the unconfined compressive strength of the bedrock. Commonly, the
mean unconfined compressive strength value is calculated from a range of
laboratory test results and is used to estimate the side shear of the bedrock. This
paper presents the results from a full scale axial load test performed on an 8.5-feet-
diameter drilled shaft rock socket, and compares measured side shear values to
estimated values for two different rock strata. Measured side shear values
correlated well with the design value calculated for the strong rock stratum, but
did not correlate well with the design value calculated for the weak rock stratum.
The mean unconfined compressive strength was used to calculate the side shear
in both strata, but review of the laboratory data indicates that this value may not
have been appropriate for the weak stratum due to a large variation in the
laboratory test results. Also included in this paper is a discussion of the subsurface
conditions, the laboratory test results, and the methodology used to design the
drilled shaft rock sockets for axial and lateral resistance.

INTRODUCTION The existing structure that carries S.R. 0040


over the Youghiogheny Reservoir is a 15 span
The project involves replacement of the existing bridge consisting of 9 simple spans of steel truss
structure that carries S.R. 0040 over the with floor beams and stringers, 1 simple span of
Youghiogheny Reservoir in Fayette and rolled steel I-beams, and 5 spans of continuous
Somerset Counties, Pennsylvania. A Site rolled steel I-beams. Construction of this bridge
Location Map is included as Figure 1. District began in 1939 concurrent with construction of a
12-0 of the Pennsylvania Department of United States Army Corps of Engineers
Transportation (PENNDOT) retained HDR (USACE) dam downstream. Construction was
Engineering, Inc. to design and prepare contract halted in 1941 due to the need for steel for
drawings for this conventional design/bid/build military operations during World War II. Bridge
project. G.A. & F.C. Wagman, Inc. elected to bid construction resumed in the mid 1940s and was
an alternate structure and was awarded the completed in 1948. Since this structure was
contract. Subsequently, G.A. & F.C. constructed prior to flooding the river valley,
Wagman, Inc. retained Gannett Fleming, Inc. to spread footings founded on relatively shallow
design and prepare the construction drawings bedrock were used to support the piers and west
for the alternate structure. abutment. The east abutment was supported on
14-inch diameter steel concrete-filled pipe piles
driven through the approach fill.

The replacement structure is an 8-span


continuous steel girder bridge and has a total
length of 1,730 feet. It is located immediately
north (downstream) of the existing bridge. The
foundations include driven H-piles to support
both abutments and drilled shaft pier bents.
Each pier bent consists of two 9-feet-diameter
drilled shafts with 8.5-feet-diameter rock
sockets. The total lengths of the drilled shafts
range from approximately 50 to 130 feet. The
shafts were constructed by Case Foundation
Company.

Figure 1: Site Location Map


SITE GEOLOGY SUBSURFACE CONDITIONS

General Geology Numerous borings were performed to


investigate the subsurface conditions at the
The bridge is located in the Allegheny Mountain project site. Fifty-four borings were performed
Section of the Appalachian Plateaus under the direction of HDR Engineering, Inc.,
Physiographic Province. The Allegheny and fifteen borings were performed under the
Mountain Section typically consists of broad, direction of Gannett Fleming, Inc. Soil samples
rounded ridges separated by broad valleys. The were obtained with a 2-inch outside diameter
ridges occur on the crests of anticlines that have split-spoon and a 140-pound hammer. Rock
been eroded enough to expose the very coring was performed with NX, NQ2 and HQ
resistant rocks that form the crests of the ridges. core barrels with split inner barrels. Both land
The valleys are broad, undulating surfaces with and barge borings were required. The
shallow to deep stream incision. The topography information obtained from the borings was
in the area of the bridge is rugged and the minor generally consistent throughout the project site.
streams are entrenched in deep, steep-sided
valleys. The borings conducted under the direction of
Gannett Fleming, Inc., designated GF-1 through
Stratigraphy GF-15, were performed to investigate the
subsurface conditions at the proposed pier
The bridge is underlain by Pennsylvanian aged locations for the alternate 8 span structure. A
bedrock. The east and west abutments are generalized subsurface profile developed from
founded in the Glenshaw Formation of the these borings is shown in Figure 2. A detailed
Conemaugh Group. A key marker bed, the discussion of the subsurface conditions
Upper Freeport Coal, was encountered in the encountered in these borings is included below.
borings drilled in the valley floor. This marker
bed delineates the overlying Glenshaw Pier 1
Formation from the Freeport Formation of the
Allegheny Group below. These formations Borings GF-1 and GF-2 were drilled at Pier 1.
consist of alternating layers of shale, siltstone, The ground surface elevation ranged from
sandstone, limestone, minor coals and clay. 1426.4 feet to 1418.9 feet. The overburden
Marine limestone and shales are abundant in thickness varied between 5.0 feet and 7.5 feet.
the Glenshaw Formation. Shaulis (1994) Bedrock was encountered in these borings at
indicates that the Brush Creek coal and marine elevations ranging from 1418.9 feet to
zone interval of the Glenshaw formation is 1413.9 feet. Rock core recoveries in the borings
exposed at the water level of the Youghiogheny were typically 100%, and were not less than
River in the area of the western abutment of the 83%. An upper stratum of medium hard, fine-
bridge. grained, silty sandstone varying in thickness
from 5.9 feet to 9.0 feet was encountered in the
Structural Geology borings. The rock quality designation (RQD) of
this stratum ranged from 0% to 89%. Hard,
The eastern portion of Fayette County and the coarse-grained sandstone was encountered in
western portion of Somerset County lie in the the borings at approximately Elevation
Appalachian Plateau where the bedrock has 1408 feet. The RQD for this stratum ranged from
been deformed into broad open folds. The great 97% to 99%.
open folds of the Allegheny Mountain section
have amplitudes of as much as 3,000 feet. The Piers 2 through 5
general trend of the folds is in a northeast-
southwest direction. The Youghiogheny
Reservoir Bridge is situated between the Laurel Borings GF-3 through GF-8 were drilled at Piers
Hills anticline and the Johnstown syncline. The 2, 3 and 5. Borings NP6-1 and NP6-2, which
Laurel Hills anticline is approximately 4.4 miles were drilled under the direction of HDR, were
to the west of the west bridge abutment. The located at Pier 4. The ground surface elevation
Johnstown syncline is a rather broad-bottomed at these borings ranged from approximately
structure located approximately 0.7 miles east of
the east bridge abutment.
Figure 2: Subsurface Profile along the Youghiogheny Reservoir Bridge (sheet 1 of 3).
Figure 2: Subsurface Profile along the Youghiogheny Reservoir Bridge (sheet 2 of 3).
Figure 3: Subsurface Profile along the Youghiogheny Reservoir Bridge (sheet 3 of 3).
1367 feet to 1363 feet. The overburden encountered from a depth to 67.5 feet to
thickness was approximately 30 feet and 70.7 feet
included up to approximately 10 feet of very
loose silt (lake sediment). Bedrock was Pier 7
encountered in these borings at elevations
ranging from 1339.7 feet to 1332.5 feet. Three Borings GF-11 and GF-12 were drilled at Pier 7.
rock strata were typically encountered in these The ground surface elevation at both of these
borings. Rock core recoveries in the strata were borings was 1406.4 feet. The overburden in
typically greater than 90%. The upper stratum these borings had a thickness of 8.9 feet, and
was generally described as medium to hard, bedrock was encountered at Elevation
sandy siltstone. The thickness of this layer 1397.5 feet. Rock core recoveries in the borings
ranged from 8.9 feet to 14.6 feet, and its RQD were generally 100%. The upper rock stratum
ranged from 51% to 85%. A relatively thin encountered in the borings was described as
stratum of soft to medium hard argillaceous medium hard, fine-grained, silty sandstone. The
siltstone was encountered below the upper thickness of this stratum ranged from 5.5 feet to
siltstone stratum. The thickness of this layer 9.0 feet, and its RQD ranged from 0% to 23%.
ranged from 3.7 feet to 6.7 feet, and its RQD Hard, coarse-grained sandstone was
ranged from 16% to 92%. A lower stratum of encountered below the upper rock stratum. The
siltstone was encountered beneath the thickness of this stratum ranged from 33.4 feet
argillaceous stratum. This lower stratum was to 35.6 feet, and its RQD ranged from 86% to
generally described as medium to hard sandy 94%. Boring GF-11 was terminated in the
and shaly siltstone with occurrences of coarse-grained sandstone. Boring GF-12
carbonaceous siltstone. The thickness of this encountered a 5.6-feet-thick layer of medium
layer ranged from 21.8 feet to 33.4 feet and its hard, carbonaceous siltstone in the bottom of
RQD ranged from 75% to 99%. the boring, and its RQD was 89%.

CHARACTERIZATION OF ROCK STRATA


Pier 6
As indicated in the Foundation Report for the as-
Borings GF-9 and GF-10 were drilled at Pier 6.
designed structure prepared by HDR
The ground surface elevation at these borings
Engineering, Inc., the rock types encountered at
ranged from 1393.3 feet to 1391.0 feet. The
the proposed piers were geologically grouped
thickness of the overburden in these borings
into two formations or units. The upper unit,
varied between 6.4 feet and 10.9 feet. Bedrock
which provides foundation support for Piers 1, 6
was encountered at elevations ranging from
(North) and 7, is the Mahoning Sandstone
1384.6 feet to 1382.4 feet. Rock core recoveries
Formation. The lower unit, which provides
in the borings were typically 100%. The upper
foundation support for Piers 2 through 5 and
rock stratum encountered in the borings was
Pier 6 (South), is the Freeport Formation.
described as hard sandstone and ranged in
Furthermore, these units were subdivided to
thickness from 28.3 feet to 32.9 feet. The RQD
distinguish between rock strata with slight
of this stratum ranged from 83% to 85%.
variations and are summarized below in Table 1.
Beneath this stratum a medium hard,
carbonaceous siltstone stratum was
encountered. This layer varied in thickness from Table 1: Summary of Rock Strata
5.1 feet to 9.0 feet, and its RQD was 84%. The Rock
Formation Rock Type Pier
Upper Freeport Coal, ranging in thickness from Unit
5.2 feet to 6.1 feet, was encountered beneath
Shaly 6 (North) &
the carbonaceous siltstone. Beneath the coal B1
Sandstone 7
Mahoning
very soft to medium hard argillaceous siltstone Sandstone 1, 6 (North)
was encountered. This stratum was 6.5-feet- B2 Sandstone
&7
thick and had an RQD of 69%. Medium hard to
hard siltstone, which had an RQD of 100% was Upper &
C1 & 2 thru 5 & 6
Lower
generally encountered in the remainder of C3
Siltstone
(South)
Boring GF-10. A very soft interbed of Freeport
argillaceous siltstone with an RQD of 97% was Argillaceous 2 thru 5 & 6
C2
Siltstone (South)
Information recorded from the rock core Compressive Strength of Rock Strata
samples, which were obtained during the
subsurface investigations directed by Gannett Approximately 100 rock core samples obtained
Fleming, Inc. and HDR Engineering, Inc., from the borings drilled at the project site were
included RQD and discontinuity measurements. tested in the laboratory to estimate the
The discontinuity measurements characterize unconfined compressive strength of the bedrock.
the condition and spacing of discontinuities and The majority of the tests were performed in
are used in the determination of rock mass accordance with ASTM D 2938, Unconfined
rating (RMR). Average values were calculated Compressive Strength of Intact Rock Core
for individual rock units at each pier. Tables 2, 3 Specimens. Some samples were tested in
and 4 below summarize these average RQD accordance with ASTM D 5731, Determination
values, discontinuity ratings and RMR values, of the Point Load Strength Index of Rock.
respectively. Based on the results of these tests, the
unconfined compressive strength of the rock
strata were estimated for the calculation of axial
Table 2: Summary of Average Rock Quality
and lateral resistances of the drilled shaft rock
Designation (RQD) Values
sockets. Table 5 below summarizes the results
Average Rock Quality Designation
(RQD) Values of the laboratory tests, and graphical
Rock presentations of the data are included in Figures
Rock Type Std.
Unit # of Min. Max. Mean
Values (%) (%) (%)
Dev. 3 and 4.
(%)
Shaly
B1 5 10 63 42 20
Sandstone
Sandstone B2 7 92 98 96 3 Table 5: Rock Compressive Strength Test
Upper & Results
C1 &
Lower 25 60 100 84 13 Rock Compressive Strength Test Results
C3
Siltstone
Argillaceous Rock Std.
C2 12 30 99 71 20 Rock Type # of Min. Max. Mean
Siltstone Unit
Tests
Dev.
(psi) (psi) (psi)
(psi)

Shaly B1 17 2,680 7,830 4,831 1,452


Table 3: Summary of Average Discontinuity Sandstone
Values Sandstone B2 22 6,279 15,910 11,295 2,869
Average Discontinuity Values Upper & C1/C3 34 1,340 7,642 3,785 1,543
Rock Lower
Rock Type # of Std.
Unit Min. Max. Mean Siltstone
Values Dev.
Argillaceous C2 21 55 3,353 938 931
Shaly Siltstone
B1 5 17 19 18 1
Sandstone
Sandstone B2 7 19 21 20 1
Upper &
C1 &
Lower 25 17 23 21 1
C3
Siltstone 1420

Argillaceous Mean = 4831 psi


C2 12 14 21 18 2 (Unit B1)
Siltstone 1410
Mean = 11295 psi
(Unit B2)
1400
Sample Elevation (ft)

Table 4: Summary of Average Rock Mass


Rating (RMR) Values 1390

Average Rock Mass Rating (RMR) 1380


Rock Values
Rock Type
Unit # of Std.
Min. Max. Mean 1370

Values Dev. SANDSTONE (UNIT B2)


SHALEY SANDSTONE (UNIT B1)
Shaly 1360
B1 5 44 59 53 6 2000 4000 6000 8000 10000 12000 14000 16000 18000
Sandstone Unconfined Compressive Strength (psi)

Sandstone B2 7 72 75 74 1
Upper &
Lower
C1 &
25 56 70 65 4
Figure 3: Laboratory Unconfined
C3 Compression Test Results (Rock Unit B)
Siltstone
Argillaceous
C2 12 47 67 58 6
Siltstone
1340
UPPER AND LOWER SILTSTONE (UNITS C1/C3)
The factored axial resistance of the rock sockets
ARGILLACEOUS SILTSTONE (UNIT C2)
was calculated by multiplying the factored unit
1330
UPPER side resistance (qsr) by the surface area of the
Mean = 3785 psi
SILTSTONE
drilled shaft rock socket. In accordance with
Sample Elevation (ft)

ARGILLACEOUS
DM-4, Section C.10.8.5.3, rock zones/stratum
(Units C1/C3)
SILTSTONE

1320
LOWER
SILTSTONE
with an RQD less than 20% were neglected in
the calculation of side resistance. The side
Mean = 938 psi
resistance from the overlying soils was also
1310
(Unit C2)
neglected.

1300 The calculations indicated that rock socket


0 1000 2000 3000 4000 5000 6000 7000 8000
Unconfined Compressive Strength (psi)
lengths ranging from 12 to 24 feet were required
to provide adequate axial resistance. The large
Figure 4: Laboratory Unconfined variation in the length of the calculated rock
Compression Test Results (Rock Unit C) sockets can be attributed to three factors. One
factor was the magnitude of the factored axial
design load, which varied at the pier bents from
AXIAL AND LATERAL DESIGN approximately 4,000 kips to 4,700 kips. Another
METHODOLOGIES factor that impacted the rock socket lengths was
the variable presence and thickness of rock
Rock Socket Axial Side Resistance strata with RQD<20%, which were neglected in
the calculations for axial support. A third factor
AASHTOs LRFD Bridge Design Specifications was the presence and thickness of Rock Unit C2
were used for the calculation of the axial side (argillaceous siltstone), which had a lower unit
resistance of the 8.5-feet-diameter drilled shaft side resistance than the other rock units.
rock sockets utilized at the piers. As indicated in
AASHTO Section C10.8.3.5, the side resistance Drilled Shaft Settlement
of shafts socketed into rock is based on the
lower value of unconfined compressive strength AASHTOs design methods were also used to
of the bedrock and drilled shaft concrete. Based calculate settlement of the drilled shafts.
on a design concrete compressive strength of AASHTO Section C10.8.3.5 indicates that the
3,500 psi, the compressive strength of concrete axial compression load on a shaft socketed into
controlled the calculation of side resistance for rock typically is carried solely in side resistance
Rock Units B1, B2, C1 and C3. However, Rock until a total shaft settlement on the order of
Unit C2 had a mean compressive strength value 0.4 inch occurs. At this displacement, the
(i.e., 938 psi) lower than the concrete, and ultimate side resistance is mobilized and slip
therefore, controlled the calculation of side occurs between the concrete and rock. As a
resistance in this rock unit. result of this slip, any additional load is
transferred to the tip and side resistance
The ultimate unit side resistance (qs) of the rock reduces to zero. Therefore, calculations were
units was calculated using AASHTO performed to estimate settlement of the rock
Equation C10.8.3.5-5, qs=0.67(qu)0.5, where qu is sockets to determine whether axial loads would
the lesser of the unconfined compressive be supported by either side or tip resistance.
strength of the rock or concrete. Note that this Calculations indicated that settlement at each
equation applies to unconfined compressive drilled shaft would not exceed 0.4 inch;
strengths greater than 20 tsf (278 psi). Ultimate therefore, the rock sockets were designed
unit side resistance values (qs) were 10.6 tsf for assuming axial resistance would be provided
Rock Units B1, B2, C1 and C3, and 5.7 tsf for solely by side resistance with no contribution
Rock Unit C2. In accordance with PENNDOTs from tip resistance.
Design Manual, Part 4 (DM-4), Table 10.5.5-3,
the ultimate unit side resistance was multiplied Rock Socket Lateral Resistance
by a resistance factor of 0.55 to obtain the
factored unit side resistance (qsr). Factored unit The computer program COM624P was used to
side resistances (qsr) were 5.8 tsf for Rock Units analyze the lateral load capacity of the drilled
B1, B2, C1 and C3, and 3.1 tsf for Rock Unit C2. shaft rock sockets. The fence posting
approach was used as discussed in the controlled by axial resistance because
COM624P manual. Using the free-head option approximately 7 feet of the rock socket was
in the program, various lengths of the rock neglected for axial resistance due to the
sockets were input for each design loading 0.8
condition. A plot of top deflection versus rock Pier 1
Piers 2-5

socket length was created from the results of the 0.7 Pier 6 South
Pier 6 North

computer analyses. The rock socket length


Pier 7
0.6

required to provide lateral resistance was 0.5

Deflection (in.)
estimated by choosing a point on the curve
0.4
where an increase in the rock socket length
provided little reduction in deflection at the top of 0.3

the rock socket. Based on engineering 0.2

judgment, a minimum rock socket length of 0.1


20 feet was required in order to have an
embedment of at least 2 to 3 shaft diameters, 0
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

irregardless of the results of the COM624P Rock Socket Embedment (ft)

results. presence of low (<20%) RQD rock. The majority


of the drilled shaft rock sockets were 20 feet in
The lateral analyses were performed using length, and the longest recommended rock
service loads and moments multiplied by a socket length was 28 feet.
factor of two. As determined by the structural
engineer, axial and shear loads and a moment Figure 5: COM624P Results of Deflection
were applied at the top of the rock socket. Cyclic versus Rock Socket Length
loading was used to model repeated loadings
from wind and traffic (not seismic), and lateral FULL SCALE AXIAL LOAD TEST
resistance from soils overlying bedrock was
neglected. Load-deflection (p-y) curve options A 133-foot-long technique shaft was constructed
included in the COM624P program were utilized to the north of Pier 5 prior to construction of the
to model the soil-structure interaction in the production shafts. The technique shaft and its
analyses. The vuggy limestone p-y curves rock socket had the same diameters as the
were used for the majority of the rock sockets. production shafts. As presented in the 2004
However, stiff clay below the water table p-y report, an axial load test was performed by
curves were used at Pier 1 and Pier 6 (South) LOADTEST, Inc. on the technique shaft to verify
due to sloping bedrock adjacent to the rock the design side shear values and production
sockets. The vuggy limestone curves did not drilled shaft lengths. Three 34-inch diameter
appear to adequately account for the sloping Osterberg load cells located approximately
rock condition. Parameters used for all rock 2 feet above the rock socket tip were used for
units included an internal angle of friction of 0 the load test. The shaft was instrumented with
degrees, a cohesion of 10% of the design Linear Vibrating Wire Displacement Transducers
unconfined compressive strength, a modulus of and telltales to measure displacement, and with
subgrade reaction of 2,000 pci, and a saturated vibrating wire strain gauges to measure side
unit weight of 0.0536 pci. E50 values ranged from shear load transfer. Load increments were
0.001 for Rock Units B1 and B2 to 0.003 for applied using the Quick Load Test Method for
Rock Unit C2. Based on the results of the Individual Piles per ASTM D 1143.
COM624P analyses plots of rock socket length
versus deflection were developed for each Load Test Results
design case as shown below in Figure 5.
The maximum bi-directional load applied to the
Recommended Rock Socket Lengths shaft was approximately 12,000 kips. At this
maximum load 1.3 inches of displacement was
Recommended rock socket lengths were measured above the O-cells, and 2.2 inches of
determined based on the results of the axial and settlement was measured below the O-cells. At
lateral analyses. Lateral resistance controlled these noted displacements an average unit side
the rock socket lengths for all the drilled shafts shear of 10.75 tsf was calculated for the rock
except Pier 3 (North). This rock socket was above the O-cells, and a maximum applied end
bearing pressure of 98.25 tsf was calculated. samples was higher (3,785 psi). A review of the
LOADTEST, Inc. developed an equivalent top unconfined compressive strength test data
load curve from the test results. Based on this presented previously in Table 5 indicates that
curve a top loading of approximately 5,600 kips the standard deviation for Rock Units C1 and C3
would result in approximately 0.25 inch of is 1,543 psi, which is approximately 40% of the
settlement, and a top loading of approximately mean value. Additionally, Figure 4 indicates that
10,200 kips would result in approximately approximately 60% of the samples tested had
0.5 inch of settlement. Note that these unconfined compressive strengths greater than
settlements include elastic compression over the that of the design strength of the concrete.
unsupported section of the shaft from the top of Conversely, the design unit side shear value for
the drilled shaft to the top of rock, which Rock Unit C2 was controlled by its mean
exceeded 100 feet for this load test. unconfined compressive strength (938 psi).
Table 5 indicates that the standard deviation for
Comparison of Rock Side Shear Values this rock unit is 931 psi, or approximately equal
(Design vs Load Test) to the mean value, and Figure 4 indicates that
approximately 60% of the samples tested had
Unit side shear values used during the design unconfined compressive strengths less than that
phase were compared to values measured with of the mean value. This review of the unconfined
strain gauges during the load test. These compressive strength test results indicates that
gauges were positioned in the three rock units Rock Unit C2 values are more variable than
(i.e., C1, C2, and C3) penetrated by the rock Rock Units C1 and C3. Therefore, it is
socket of the technique drilled shaft. The drilled reasonable that the measured and design side
shaft rock sockets for Piers 2, 3, 4, 5 and 6 shear values for Rock Units C1 and C3 more
(South) are founded in these rock units. Based closely matched compared to the values for
on the results of the load test, the measured Rock Unit C2.
ultimate unit side shear values corresponding to
0.4 inch of deflection were approximately 1.5 tsf The unconfined compressive strength of Rock
for Rock Unit C2 (i.e., argillaceous siltstone) and Unit C2 (argillaceous siltstone) was estimated
10 tsf for Rock Units C1 and C3 (i.e., upper and based on the unit side shear value of 1.5 tsf
lower siltstone). The ultimate unit side shear measured during the load test. Using the
value used during design for Rock Units C1 equation qs=0.67(qu)0.5, an unconfined
and C3 was 10.6 tsf, which corresponds well compressive strength of 70 psi was back-
with the 10 tsf value measured from the load calculated. This strength is less than the
test. However, the ultimate unit side shear value minimum value of 278 psi recommended for use
used during design for Rock Unit C2 was 5.7 tsf, with this equation. Therefore, using the equation
which is nearly four times greater than the 1.5 tsf qs=0.15(qu), which is recommended by AASHTO
value measured from the load test. for this range of unconfined compressive
strengths, the back-calculated unconfined
CONCLUSIONS compressive strength is approximately 140 psi.
This value is roughly 7 times lower than the
As indicated above, ultimate unit side shear mean unconfined compressive strength value
values measured during the load test correlated from laboratory test results for Rock Unit C2;
well with the design unit side shear value used however, 3 of the 21 rock core samples tested
for Rock Units C1 and C3 (upper and lower from this rock unit had values lower than
siltstone), but did not correlate well with the 140 psi. Although this low unconfined
design unit side shear value used for Rock compressive strength value may not be
Unit C2 (argillaceous siltstone). The design unit representative of the rock strength at other
side shear values (qs) were based solely on the drilled shaft locations, it is probable that this
mean unconfined compressive strength (qu) of value is indicative of the rock strength at the
the rock units using the equation qs=0.67(qu)0.5. technique shaft location.

The design unit side shear value for Rock In summary, the rock units encountered at the
Units C1 and C3 was controlled by the Youghiogheny bridge replacement site had fairly
unconfined compressive strength of the concrete consistent unconfined compressive strength
(3,500 psi), since the mean value from the values, and the values were generally equal to
unconfined compression tests on the rock or greater than the design strength of the
concrete. Thus, selection of design unconfined Flint, N.K., 1965, Geology and Mineral
compressive strength values was not critical Resources of Southern Somerset County,
since it did not control the design. However, one Pennsylvania, County Report C56A,
rock unit was considerably weaker in strength, Commonwealth of Pennsylvania, Bureau of
and laboratory unconfined compressive strength Topographic and Geologic Survey.
results varied dramatically. The mean Gannett Fleming, Inc., November 2003,
compressive strength value for this rock unit was Addendum to Structure Foundation
used for axial design of the drilled shaft rock Geotechnical Report, S.R. 0040 over
sockets, but measured side shear values from a Youghiogheny Reservoir, prepared for
full scale load test indicated that this design PENNDOT District 12-0.
value was extremely high, at least at the load
test shaft location. This difference between HDR Engineering, Inc., April 2003, Final
design and measured values had little impact on Geotechnical Engineering Report for Foundation
this project. Minimal resistance was anticipated Submission, Youghiogheny Dam Bridge
from this rock unit during design because this Replacement, prepared for PENNDOT District
rock unit was thin, and the design unit side 12-0.
shear value of this rock unit was nearly half that
of the other rock units. Furthermore, lateral Hickok, W.O. and Moyer, F.T., 1971 (reprinted
capacity typically controlled the drilled shaft rock 1973), Geology and Mineral Resources of
socket length, so additional side resistance was Fayette County, Pennsylvania, County Report
available at most locations without increasing 26, Pennsylvania Geological Survey, Fourth
rock socket lengths. Nevertheless, the selection Series.
of design values for calculating side shear
resistance of drilled shaft rock sockets requires Loadtest, Inc., May 12, 2004, Report on Drilled
careful consideration of the range of the Shaft Load Testing (Osterberg Method),
laboratory test values as well as the sensitivity of prepared for Case Foundation Company.
these values with respect to calculated rock
socket lengths, particularly at sites where weak Shaulis, J.R., 1985, Coal Resources of Fayette
rock is encountered. County, Pennsylvania, Part 1. Coal Crop Lines,
Mined-out Areas, and Structure Contours,
REFERENCES Mineral Resource Report 91, Part 1,
Pennsylvania Geological Survey, Fourth Series.
American Association of Highway And
Transportation Officials, 1998, AASHTO LRFD Shaulis J.R., 1994, Hooked on the Rocks:
Bridge Design Specifications, 2nd Edition. Exploring the Geology of the Youghiogheny
River Lake-A Boating Field Trip, Pennsylvania
American Society of Testing And Materials, Geology Volume 25, No. 2, Commonwealth of
2004, Standards on Disc, Volumes 4.08 Soil and Pennsylvania, Bureau of Topographic and
Rock (I) and 4.09 Soil and Rock (II), ASTM Geologic Survey.
International.
U.S. Department Of Transportation, Federal
Commonwealth of Pennsylvania, Department of Highway Administration, August 1993,
Transportation, April 2000, Design Manual Part COM624P-Laterally Loaded Pile Analysis
4, with revisions to April 2001. Program for the Microcomputer, Version 2.0,
Publication No. FHWA-SA-91-048.

Vous aimerez peut-être aussi