No Principle of Engineering Economy Example Issue

1 Develop the alternatives

Problem
1. Expand alternative road from KESAS to Federal
road.
2. Traffic congestion during peak hours.
Propose all decision alternative
1. To up grade from 1 lane to 2 lane.
2. Sampling & lab testing for others action approval
from authorities.
3. New improvement method design
2 Focus on the differences Choose expected decision alternative
(1) & (2)
1. To up grade from 1 lane to 2 lane.
2. Sampling & lab testing for others action approval
from authorities
3 Use a consistent viewpoint 1. To upgrade from 1 lane to 2 lane.
a. To find utilities maps to relocated after the new lane.
b. take time to design and prepare report and must submit
& approve by the local authorities.
2. Sampling & lab testing for others action approval from
authorities
a. take time to design and prepare report and must
submit & approve by the local authorities.
Recognize type of soil which is suitable
4 Use a common unit of measure 2. Sampling & lab testing for others action approval from
authorities
a. take time to design and prepare report and must
submit & approve by the local authorities.
b. Recognize type of soil which is suitable for the
construction method used.
3. New improvement method design
a. Change design used for support slope at river from sheet
pile to gabion wall.
5 Consider all relevant criteria Review again all criteria
6 Make uncertainty explicit risk Advantages
a. Cost saving than using sheet pile
b. Vibrating machine cost

Disadvantages
a. Take a long time to construct gabion wall