Unit Estimate for Septic Tank

(For Household of 7 Persons)


BSR Item
Rate
No. - S.No. Description Quantity Unit Amount
(Rs.)
Page No.

3.9 1 Earth work in excavation in foundation, trenches


manholes, road side chambers etc. including
dressing of sides and ramming of bottoms, including
getting out the excavated material, refilling after
laying pipe foundation and disposal of surplus excavated
material at a lead upto 50m suitable site as per
direction of Engineer for following depths, below
natural ground / Road top level.

In all types soils 1.27 113.00


0.05
1.32 cu m 148.78
5.1.7 2 Providing & laying in position cement concrete
including curing, compaction etc. complete in specified
grade excluding the cost of centering & shuttering - all
work upto plinth level.
- using 1 cement : 4 coarse sand : 8 graded stone
40mm nominal size
0.26
0.02
0.29 cu m 2283.00 653.57

5.1.7 3 Brick masonry in foundation & plinth with bricks of


class designation 75 in cement sand mortar 1:6 (1
cement : 6 coarse sand).
0.25
0.12
0.16
0.09
0.03
0.27
0.15
0.21
1.28 cu m 1994.00 2555.67
6.17.1 4 Supplying & fixing stone lintels/bed plates of
approved quarry rough dressed in cement mortar 1:4

0.008
0.006
0.015 cu m 8540.00 124.10

11.3.3 5 Cement concrete flooring grade 1:2:4 (1 cement : 2


coarse sand : 4 graded stone aggregrate) rounding off
edges etc. but excluding the cost of nosing of steps
etc. complete including floating coat of neat cement:
50mm thick with 20mm thick nominal size
aggregrates.

1.200
0.096
1.296 sq m 213.00 276.05

4.12.2 6 Centring and shuttering with plywood for steel sheets


including strutting propping bracing bothway with wooden
members & removal of form work. For superstructure
upto 4.5M above plinth level for: suspended floors, roofs
landing, staircase, balconies girders, cantilevers bends,
coping, bed plats, anchor, blocks, stills or chajjas, lintel,
beams etc.

1.20 sq m 137.00 164.40

12.8.2 - 7 Plaster on new surface on walls including raking of


12.17 joints etc. complete broom finish ( sandia to be done on
top surface)
20mm thick in CSM 1:4
2.19
2.02
0.86
0.58
0.82
6.47 sq m 86.50 559.34

12.15 8 Finishing with neat cement punning. 6.47 sq m 15.00 97.00

1
BSR Item No.
Rate
- Page No. S.No. Description Quantity Unit Amount
(Rs.)

4.3.1 9
Providing & laying RCC work in suspended floors, roofs, girders,
cantilevers,staircases, landings, balconies, chhajja, lintel, bends, coping
bed plates, anchor blocks, sill & beams etc upto floor three level
including curing, compaction, finishing & rendering in cement sand
mortar 1:3 (1 cement : 3 coarse sand) and making good the joints,
excluding cost of centering & shuttering & reinforcement.
Mix M20

0.20
0.01
0.22 cu m 3527.00 759.08
19.19.1 28 Making soak pit 2.5 m diameter 3.0 metre deep with 0.50
45 x 45 cm dry brick honey comb shaft with bricks of class designation
75 and S.W. drain pipe 100 mm diameter, 1.8 m long complete as Unit 10473.55 5236.78
per standard design

Total Cost 10574.76


per unit

Total Cost for 75 Nos. Septic Tank 793107


N.K. Buildcon Pvt. Ltd., Jaipur 2