Vous êtes sur la page 1sur 13

Conditional Obligations

(1) (Javier v. Court of Appeals, G.R. No. 48194, March 15, 1990)
(5) (Naga Telephone Co., Inc. v. Court of Appeals, G.R. No. 107112, February 24, 1994)

(Javier v. Court of Appeals, G.R. No. 48194, March Code). A contract with a false consideration is not
15, 1990) null and void per se. [Concepcion vs. Sta. Ana, 87
Phil. 787 (1950)] Under Article 1346 of the Civil Code,
SECOND DIVISION a relatively simulated contract, when it does not
[G.R. No. 48194. March 15, 1990.] prejudice a third person and is not intended for any
JOSE M. JAVIER and ESTRELLA F. JAVIER, petitioners, purpose contrary to law, morals, good customs,
vs. COURT OF APPEALS and LEONARDO TIRO, public order or public policy binds the parties to
respondents. their real agreement.
Eddie Tamondong for petitioners.
Lope Adriano and Emmanuel Pelaez, Jr. for private 4. ID.; ID.; BILATERAL CONTRACT; GIVES RISE TO
respondent. RECIPROCAL OBLIGATION. The agreement is a
bilateral contract which gave rise to reciprocal
SYLLABUS obligations, that is, the obligation of private
1. REMEDIAL LAW; RULES OF PROCEDURE; MUST BE respondent to transfer his rights in the forest
APPLIED WITH LIBERALITY TO PROMOTE SUBSTANTIAL concession over the additional area and, on the
JUSTICE. The one (1) day delay in the filing of the other hand, the obligation of petitioners to pay
said motion for extension can justifiably be excused, P30,000.00. The demandability of the obligation of
considering that aside from the change of counsel, one party depends upon the fulfillment of the
the last day for filing the said motion fell on a obligation of the other. In this case, the failure of
holiday following another holiday, hence, under private respondent to comply with his obligation
such circumstances, an outright dismissal of the negates his right to demand performance from
petition would be too harsh. Litigations should, as petitioners. Delivery and payment in a contract of
much as possible, be decided on their merits and sale, are so interrelated and intertwined with each
not on technicalities. In a number of cases, this other that without delivery of the goods there is no
Court, in the exercise of equity jurisdiction, has corresponding obligation to pay. The two
relaxed the stringent application of technical rules complement each other.
in order to resolve the case on its merits. Rules of
procedure are intended to promote, not to defeat, 5. ID.; OBLIGATIONS; WITH SUSPENSIVE CONDITION;
substantial justice and, therefore, they should not EFFECT. As to the alleged nullity of the
be applied in a very rigid and technical sense. agreement dated February 28, 1966, we agree with
petitioners that they cannot be held liable thereon.
2. CIVIL LAW; CONTRACTS; PREVIOUS, The efficacy of said deed of assignment is subject
SIMULTANEOUS AND SUBSEQUENT ACTS OF THE to the condition that the application of private
PARTIES; INDICATIVE OF PARTIES' TRUE INTENTION respondent for an additional area for forest
WHICH MAY BE CONSIDERED BY THE COURT IN concession be approved by the Bureau of Forestry.
CONSTRUING THE CONTRACT. The Since private respondent did not obtain that
contemporaneous and subsequent acts of approval, said deed produces no effect. When a
petitioners and private respondent reveal that the contract is subject to a suspensive condition, its
cause stated in the questioned deed of assignment birth or effectivity can take place only if and when
is false. It is settled that the previous and the event which constitutes the condition happens
simultaneous and subsequent acts of the parties or is fulfilled. If the suspensive condition does not
are properly cognizable indicia of their true take place, the parties would stand as if the
intention. Where the parties to a contract have conditional obligation had never existed.
given it a practical construction by their conduct as
by acts in partial performance, such construction 6. ID.; SALE OF A MERE HOPE OR EXPECTANCY;
may be considered by the court in construing the EFFICACY THEREOF DEEMED SUBJECT TO THE
contract, determining its meaning and ascertaining CONDITION THAT THE THING WILL COME INTO
the mutual intention of the parties at the time of EXISTENCE. Under the second paragraph of
contracting. The parties' practical construction of Article 1461 of the Civil Code, the efficacy of the
their contract has been characterized as a clue or sale of a mere hope or expectancy is deemed
index to, or as evidence of, their intention or subject to the condition that the thing will come
meaning and as an important, significant, into existence. In this case, since private respondent
convincing, persuasive, or influential factor in never acquired any right over the additional area
determining the proper construction of the for failure to secure the approval of the Bureau of
agreement. Forestry, the agreement executed therefor, which
had for its object the transfer of said right to
3. ID.; ID.; WITH FALSE CAUSE OR CONSIDERATION; petitioners, never became effective or
NOT CONSIDERED NULL AND VOID PER SE. The enforceable.
deed of assignment of February 15, 1966 is a
relatively simulated contract which states a false DECISION
cause or consideration, or one where the parties REGALADO, J p:
conceal their true agreement. (Art. 1345 of the Civil
1|OBLICON_Chapter 3_Conditional Obligations
Petitioners pray for the reversal of the decision of forever, to TIMBERWEALTH CORPORATION, a
respondent Court of Appeals in CA-G.R. No. 52296- corporation duly organized and existing under the
R, dated March 6, 1978, 1 the dispositive portion laws of the Philippines, over a forest concession
whereof decrees: which is now pending application and approval as
additional area to his existing licensed area under
"WHEREFORE, the judgment appealed from is O.T. License No 391-103166, situated at Medina,
hereby set aside and another one entered ordering Misamis Oriental;
the defendants-appellees, jointly and solidarily, to
pay plaintiff-appellant the sum of P79,338.15 with "2. That for and in consideration of the
legal interest thereon from the filing of the aforementioned transfer of rights over said
complaint, plus attorney's fees in the amount of additional area to TIMBERWEALTH CORPORATION,
P8,000.00. Costs against defendants-appellees." 2 ESTRELLA F. JAVIER and JOSE M. JAVIER, both
directors and stockholders of said corporation, do
As found by respondent court or disclosed by the hereby undertake to pay LEONARDO TIRO, as soon
records, 3 this case was generated by the following as said additional area is approved and transferred
antecedent facts. cdphil to TIMBERWEALTH CORPORATION the sum of THIRTY
THOUSAND PESOS (P30,000.00), which amount of
Private respondent is a holder of an ordinary timber money shall form part of their paid up capital stock
license issued by the Bureau of Forestry covering in TIMBERWEALTH CORPORATION; llcd
2,535 hectares in the town of Medina, Misamis
Oriental. On February 15, 1966 he executed a "3. That this Agreement is subject to the approval
"Deed of Assignment" 4 in favor of herein petitioners of the members of the Board of Directors of the
the material parts of which read as follows: TIMBERWEALTH CORPORATION."

xxx xxx xxx xxx xxx xxx


"I, LEONARDO A. TIRO, of legal age, married and a
resident of Medina, Misamis Oriental, for and in On November 18, 1966, the Acting Director of
consideration of the sum of ONE HUNDRED TWENTY Forestry wrote private respondent that his forest
THOUSAND PESOS (P120,000.00), Philippine concession was renewed up to May 12, 1967 under
Currency, do by these presents, ASSIGN, TRANSFER O.T.L. No. 391-51267, but since the concession
AND CONVEY, absolutely and forever unto JOSE M. consisted of only 2,535 hectares, he was therein
JAVIER and ESTRELLA F. JAVIER, spouses, of legal informed that:
age and a resident (sic) of 2897 F.B. Harrison, Pasay
City, my shares of stocks in the TIMBERWEALTH "In pursuance of the Presidential directive of May
CORPORATION in the total amount of P120,000.00, 13, 1966, you are hereby given until May 12, 1967 to
payment of which shall be made in the following form an organization such as a cooperative,
manner: partnership or corporation with other adjoining
licensees so as to have a total holding area of not
1. Twenty thousand (P20,000.00) Pesos upon less than 20,000 hectares of contiguous and
signing of this contract; compact territory and an aggregate allowable
annual cut of not less than 25,000 cubic meters,
2. The balance of P100,000.00 shall be paid otherwise, your license will not be further renewed."
P10,000,00 every shipment of export logs actually 6
produced from the forest concession of
Timberwealth Corporation. Consequently, petitioners, now acting as timber
license holders by virtue of the deed of assignment
"That I hereby agree to sign and endorse the stock executed by private respondent in their favor,
certificate in favor of Mr. & Mrs. Jose M. Javier, as entered into a Forest Consolidation Agreement 7 on
soon as stock certificates are issued." April 10, 1967 with other ordinary timber license
holders in Misamis Oriental, namely, Vicente L. De
xxx xxx xxx Lara, Jr., Salustiano R. Oca and Sanggaya Logging
Company. Under this consolidation agreement,
At the time the said deed of assignment was they all agreed to pool together and merge their
executed, private respondent had a pending respective forest concessions into a working unit, as
application, dated October 21, 1965, for an envisioned by the aforementioned directives. This
additional forest concession covering an area of consolidation agreement was approved by the
2,000 hectares southwest of and adjoining the area Director of Forestry on May 10, 1967. 8 The working
of the concession subject of the deed of unit was subsequently incorporated as the North
assignment. Hence, on February 28, 1966, private Mindanao Timber Corporation, with the petitioners
respondent and petitioners entered into another and the other signatories of the aforesaid Forest
"Agreement" 5 with the following stipulations: Consolidation Agreement as incorporators. 9

xxx xxx xxx


"1. That LEONARDO TIRO hereby agrees and
binds himself to transfer, cede and convey On July 16, 1968, for failure of petitioners to pay the
whatever rights he may acquire, absolutely and balance due under the two deeds of assignment,
2|OBLICON_Chapter 3_Conditional Obligations
private respondent filed an action against petitioners fifteen (15) days from March 28, 1978
petitioners, based on the said contracts, for the within which to file said motion for reconsideration,
payment of the amount of P83,138.15 with interest provided that the subject motion for extension was
at 6% per annum from April 10, 1967 until full filed on time. 14 On April 11, 1978, petitioners filed
payment, plus P12,000.00 for attorney's fees and their motion for reconsideration in the Court of
costs. Appeals. 15 On April 21, 1978, private respondent
filed a consolidated opposition to said motion for
On September 23, 1968, petitioners filed their reconsideration on the ground that the decision of
answer admitting the due execution of the respondent court had become final on March 27,
contracts but interposing the special defense of 1978, hence the motion for extension filed on March
nullity thereof since private respondent failed to 28, 1978 was filed out of time and there was no
comply with his contractual obligations and, further, more period to extend. However, this was not
that the conditions for the enforceability of the acted upon by the Court of Appeals for the reason
obligations of the parties failed to materialize. As a that on April 20, 1978, prior to its receipt of said
counterclaim, petitioners sought the return of opposition, a resolution was issued denying
P55,586.00 which private respondent had received petitioners' motion for reconsideration, thus:
from them pursuant to an alleged management
agreement, plus attorney's fees and costs. prLL "The motion for reconsideration filed on April 11,
1978 by counsel for defendants-appellees is
On October 7, 1968, private respondent filed his denied. They did not file any brief in this case. As a
reply refuting the defense of nullity of the contracts matter of fact this case was submitted for decision
in this wise: without appellees' brief. In their said motion, they
merely tried to refute the rationale of the Court in
"What were actually transferred and assigned to deciding to reverse the appealed judgment." 16
the defendants were plaintiffs rights and interest in
a logging concession described in the deed of Petitioners then sought relief in this Court in the
assignment, attached to the complaint and present petition for review on certiorari. Private
marked as Annex A, and agreement Annex E; that respondent filed his comment, reiterating his stand
the 'shares of stocks' referred to in paragraph II of that the decision of the Court of Appeals under
the complaint are terms used therein merely to review is already final and executory. cdphil
designate or identify those rights and interests in
said logging concession. The defendants actually Petitioners countered in their reply that their petition
made use of or enjoyed not the 'shares of stocks' for review presents substantive and fundamental
but the logging concession itself; that since the questions of law that fully merit judicial
proposed Timberwealth Corporation was owned determination, instead of being suppressed on
solely and entirely by defendants, the personalities technical and insubstantial reasons. Moreover, the
of the former and the latter are one and the same. aforesaid one (1) day delay in the filing of their
Besides, before the logging concession of the motion for extension is excusable, considering that
plaintiff or the latter's rights and interests therein petitioners had to change their former counsel who
were assigned or transferred to defendants, they failed to file their brief in the appellate court, which
never became the property or assets of the substitution of counsel took place at a time when
Timberwealth Corporation which is at most only an there were many successive intervening holidays.
association of persons composed of the
defendants." 10 On July 26, 1978, we resolved to give due course to
the petition.
and contending that the counterclaim of
petitioners in the amount of P55,586.39 is actually The one (1) day delay in the filing of the said motion
only a part of the sum of P69,661.85 paid by the for extension can justifiably be excused, considering
latter to the former in partial satisfaction of the that aside from the change of counsel, the last day
latter's claim. 11 for filing the said motion fell on a holiday following
After trial, the lower court rendered judgment another holiday, hence, under such circumstances,
dismissing private respondent's complaint and an outright dismissal of the petition would be too
ordering him to pay petitioners the sum of harsh. Litigations should, as much as possible, be
P33,161.85 with legal interest at six percent per decided on their merits and not on technicalities. In
annum from the date of the filing of the answer until a number of cases, this Court, in the exercise of
complete payment. 12 equity jurisdiction, has relaxed the stringent
application of technical rules in order to resolve the
As earlier stated, an appeal was interposed by case on its merits. 17 Rules of procedure are
private respondent to the Court of Appeals which intended to promote, not to defeat, substantial
reversed the decision of the court of a quo. justice and, therefore, they should not be applied in
a very rigid and technical sense.
On March 28, 1978, petitioners filed a motion in
respondent court for extension of time to file a We now proceed to the resolution of this case on
motion for reconsideration, for the reason that they the merits.
needed to change counsel. 13 Respondent court,
in its resolution dated March 31, 1978, gave
3|OBLICON_Chapter 3_Conditional Obligations
The assignment of errors of petitioners hinges on the convincing, persuasive, or influential factor in
central issue of whether the deed of assignment determining the proper construction of the
dated February 15, 1966 and the agreement of agreement. 24
February 28, 1966 are null and void, the former for
total absence of consideration and the latter for The deed of assignment of February 15, 1966 is a
non-fulfillment of the conditions stated therein. relatively simulated contract which states a false
cause or consideration, or one where the parties
Petitioners contend that the deed of assignment conceal their true agreement. 25 A contract with a
conveyed to them the shares of stocks of private false consideration is not null and void per se. 26
respondent in Timberwealth Corporation, as stated Under Article 1346 of the Civil Code, a relatively
in the deed itself. Since said corporation never simulated contract, when it does not prejudice a
came into existence, no share of stocks was ever third person and is not intended for any purpose
transferred to them, hence the said deed is null and contrary to law, morals, good customs, public order
void for lack of cause or consideration. or public policy binds the parties to their real
agreement. prcd
We do not agree. As found by the Court of
Appeals, the true cause or consideration of said The Court of Appeals, therefore, did not err in
deed was the transfer of the forest concession of holding petitioners liable under the said deed and
private respondent to petitioners for P120,000.00. in ruling that
This finding is supported by the following
considerations, viz: LLjur ". . . In view of the analysis of the first and second
assignment of errors, the defendants-appellees are
1. Both parties, at the time of the execution of the liable to the plaintiff-appellant for the sale and
deed of assignment knew that the Timberwealth transfer in their favor of the latter's forest
Corporation stated therein was non-existent. 18 concessions. Under the terms of the contract, the
parties agreed on a consideration of P120,000.00.
2. In their subsequent agreement, private P20,000.00 of which was paid, upon the signing of
respondent conveyed to petitioners his inchoate the contract and the balance of P100,000.00 to be
right over a forest concession covering an paid at the rate of P10,000.00 for every shipment of
additional area for his existing forest concession, export logs actually produced from the forest
which area he had applied for, and his application concessions of the appellant sold to the appellees.
was then pending in the Bureau of Forestry for Since plaintiff-appellant's forest concessions were
approval. consolidated or merged with those of the other
timber license holders by appellees' voluntary act
3. Petitioners, after the execution of the deed of under the Forest Consolidation Agreement (Exhibit
assignment, assumed the operation of the logging D), approved by the Bureau of Forestry (Exhibit D-3),
concessions of private respondent. 19 then the unpaid balance of P49,338.15 (the amount
of P70,661.85 having been received by the plaintiff-
4. The statement of advances to respondent appellant from the defendants-appellees) became
prepared by petitioners stated: "P55,186.39 due and demandable." 27
advances to L.A. Tiro be applied to succeeding
shipments. Based on the agreement, we pay
P10,000.00 every after (sic) shipment. We had only 2
shipments." 20 As to the alleged nullity of the agreement dated
February 28, 1966, we agree with petitioners that
5. Petitioners entered into a Forest Consolidation they cannot be held liable thereon. The efficacy of
Agreement with other holders of forest concessions said deed of assignment is subject to the condition
on the strength of the questioned deed of that the application of private respondent for an
assignment. 21 additional area for forest concession be approved
by the Bureau of Forestry. Since private respondent
The aforesaid contemporaneous and subsequent did not obtain that approval, said deed produces
acts of petitioners and private respondent reveal no effect. When a contract is subject to a
that the cause stated in the questioned deed of suspensive condition, its birth or effectivity can take
assignment is false. It is settled that the previous and place only if and when the event which constitutes
simultaneous and subsequent acts of the parties the condition happens or is fulfilled. 28 If the
are properly cognizable indicia of their true suspensive condition does not take place, the
intention. 22 Where the parties to a contract have parties would stand as if the conditional obligation
given it a practical construction by their conduct as had never existed. 29
by acts in partial performance, such construction
may be considered by the court in construing the The said agreement is a bilateral contract which
contract, determining its meaning and ascertaining gave rise to reciprocal obligations, that is, the
the mutual intention of the parties at the time of obligation of private respondent to transfer his rights
contracting. 23 The parties' practical construction in the forest concession over the additional area
of their contract has been characterized as a clue and, on the other hand, the obligation of
or index to, or as evidence of, their intention or petitioners to pay P30,000.00. The demandability of
meaning and as an important, significant, the obligation of one party depends upon the
4|OBLICON_Chapter 3_Conditional Obligations
fulfillment of the obligation of the other. In this case, innovation was explained, thus: "The general rule is
the failure of private respondent to comply with his that impossibility of performance releases the
obligation negates his right to demand obligor. However, it is submitted that when the
performance from petitioners. Delivery and service has become so difficult as to be manifestly
payment in a contract of sale, are so interrelated beyond the contemplation of the parties, the court
and intertwined with each other that without should be authorized to release the obligor in whole
delivery of the goods there is no corresponding or in part. The intention of the parties should govern
obligation to pay. The two complement each and if it appears that the service turns out to be so
other. 30 difficult as to have been beyond their
contemplation, it would be doing violence to that
Moreover, under the second paragraph of Article intention to hold the obligor still responsible." In
1461 of the Civil Code, the efficacy of the sale of a other words, fair and square consideration
mere hope or expectancy is deemed subject to the underscores the legal precept therein.
condition that the thing will come into existence. In
this case, since private respondent never acquired 2. ID.; ID.; "SERVICE" UNDER ART. 1267 REFERS TO THE
any right over the additional area for failure to PERFORMANCE OF AN OBLIGATION; CASE AT BAR.
secure the approval of the Bureau of Forestry, the Petitioners assert earnestly that Article 1267 of the
agreement executed therefor, which had for its New Civil Code is not applicable primarily because
object the transfer of said right to petitioners, never the contract does not involve the rendition of
became effective or enforceable. prLL service or a personal prestation and it is not for
future service with future unusual change. Instead,
WHEREFORE, the decision of respondent Court of the ruling in the case Occea, et al. v. Jabson, etc,
Appeals is hereby MODIFIED. The agreement of the et al., (G.R. No. L-44349, October 29, 1976, 73 SCRA
parties dated February 28, 1966 is declared without 637) which interpreted the article, should be
force and effect and the amount of P30,000.00 is followed in resolving this case. Besides, said article
hereby ordered to be deducted from the sum was never raised by the parties in their pleadings
awarded by respondent court to private and was never the subject of trial and evidence.
respondent. In all other respects, said decision of Article 1267 speaks of "service" which has become
respondent court is affirmed. so difficult. Taking into consideration the rationale
behind this provision, the term "service" should be
SO ORDERED. understood as referring to the "performance" of the
obligation. In the present case, the obligation of
Melencio-Herrera, Paras, Padilla and Sarmiento, JJ., private respondent consists in allowing petitioners to
concur. use its posts in Naga City, which is the service
contemplated in said article. Furthermore, a bare
(Naga Telephone Co., Inc. v. Court of Appeals, G.R. reading of this article reveals that it is not a
No. 107112, February 24, 1994) requirement thereunder that the contract be for
future service with future unusual change.
SECOND DIVISION According to Senator Arturo M. Tolentino, Article
[G.R. No. 107112. February 24, 1994.] 1267 states in our law the doctrine of unforeseen
NAGA TELEPHONE CO., INC. (NATELCO) AND events. This is said to be based on the discredited
LUCIANO M. MAGGAY, petitioners, vs. THE COURT theory of rebus sic stantibus in public international
OF APPEALS AND CAMARINES SUR II ELECTRIC law; under this theory, the parties stipulate in the
COOPERATIVE, INC. (CASURECO II), respondents. light of certain prevailing conditions, and once
these conditions cease to exist the contract also
SYLLABUS ceases to exist. Considering practical needs and
1. CIVIL LAW; OBLIGATION AND CONTRACTS; RULE the demands of equity and good faith, the
WHERE A PERSON BY HIS CONTRACT CHARGES disappearance of the basis of a contract gives rise
HIMSELF WITH AN OBLIGATION POSSIBLE TO BE to a right to relief in favor of the party prejudiced.
PERFORMED. The case of Reyes v. Caltex
(Philippines), Inc. enunciated the doctrine that 3. ID.; ID.; POTESTATIVE CONDITION; MEANING
where a person by his contract charges himself with THEREOF; APPLICATION IN CASE AT BAR. A
an obligation possible to be performed, he must potestative condition is a condition, the fulfillment
perform it, unless its performance is rendered of which depends upon the sole will of the debtor,
impossible by the act of God, by the law, or by the in which case, the conditional obligation is void.
other party, it being the rule that in case the party Based on this definition, respondent court's finding
desires to be excused from performance in the that the provision in the contract, to wit: "(a) That
event of contingencies arising thereto, it is his duty the term or period of this contract shall be as long
to provide the basis therefor in his contract. With the as the party of the first part (petitioner) has need for
enactment of the New Civil Code, a new provision the electric light posts of the party of the second
was included therein namely, Article 1267 which part (private respondent) . . ." is a potestative
provides: "When the service has become so difficult condition, is correct. However, it must have
as to be manifestly beyond the contemplation of overlooked the other conditions in the same
the parties, the obligor may also be released provision, to wit: ". . . it being understood that this
therefrom, in whole or in part." In the report of the contract shall terminate when for any reason
Code Commission, the rationale behind this whatsoever, the party of the second part (private
5|OBLICON_Chapter 3_Conditional Obligations
respondent) is forced to stop, abandoned (sic) its service turns out to be so difficult as to have been
operation as a public service and it becomes beyond their contemplation, it would be doing
necessary to remove the electric light post (sic);" violence to that intention to hold the obligor still
which are casual conditions since they depend on responsible." 2
chance, hazard, or the will of a third person. In sum,
the contract is subject to mixed conditions, that is, In other words, fair and square consideration
they depend partly on the will of the debtor and underscores the legal precept therein.
partly on chance, hazard or the will of a third Naga Telephone Co., Inc. remonstrates mainly
person, which do not invalidate the against the application by the Court of Appeals of
aforementioned provision. Article 1267 in favor of Camarines Sur II Electric
Cooperative, Inc. in the case before us. Stated
4. ID.; PRESCRIPTION OF ACTIONS; RULE ON WRITTEN differently, the former insists that the complaint
CONTRACT. Article 1144 of the New Civil Code should have been dismissed for failure to state a
provides, inter alia, that an action upon a written cause of action. prLL
contract must be brought within ten (10) years from
the time the right of the action accrues. Clearly, the The antecedent facts, as narrated by respondent
ten (10) year period is to be reckoned from the time Court of Appeals are, as follows:
the right of action accrues which is not necessarily
the date of execution of the contract. As correctly Petitioner Naga Telephone Co., Inc. (NATELCO) is a
ruled by respondent court, private respondent's telephone company rendering local as well as long
right of action arose "sometime during the latter distance service in Naga City while private
part of 1982 or in 1983 when according to Atty. Luis respondent Camarines Sur II Electric Cooperative,
General, Jr. . . ., he was asked by (private Inc. (CASURECO II) is a private corporation
respondent's) Board of Directors to study said established for the purpose of operating an electric
contract as it already appeared disadvantageous power service in the same city.
to (private respondent). (Private respondent's)
cause of action to ask for reformation of said On November 1, 1977, the parties entered into a
contract should thus be considered to have arisen contract (Exh. "A") for the use by petitioners in the
only in 1982 or 1983, and from 1982 to January 2, operation of its telephone service the electric light
1989 when the complaint in this case was filed, ten posts of private respondent in Naga City. In
(10) years had not yet elapsed." consideration therefor, petitioners agreed to install,
free of charge, ten (10) telephone connections for
DECISION the use by private respondent in the following
places:
NOCON, J p:
"(a) 3 units The Main Office of (private
The case of Reyes v. Caltex (Philippines), Inc. 1 respondent);
enunciated the doctrine that where a person by his
contract charges himself with an obligation possible (b) 2 Units The Warehouse of (private
to be performed, he must perform it, unless its respondent);
performance is rendered impossible by the act of
God, by the law, or by the other party, it being the (c) 1 Unit The Sub-Station of (private respondent)
rule that in case the party desires to be excused at Concepcion Pequea;
from performance in the event of contingencies
arising thereto, it is his duty to provide the basis (d) 1 Unit The Residence of (private respondent's)
therefor in his contract. LibLex President;

With the enactment of the New Civil Code, a new (e) 1 Unit The Residence of (private respondent's)
provision was included therein namely, Article 1267 Acting General Manager; &
which provides:
(f) 2 Units To be determined by the General
"When the service has become so difficult as to be Manager. 3
manifestly beyond the contemplation of the
parties, the obligor may also be released therefrom, Said contract also provided:
in whole or in part." "(a) That the term or period of this contract shall be
as long as the party of the first part has need for the
In the report of the Code Commission, the rationale electric light posts of the party of the second part it
behind this innovation was explained, thus: being understood that this contract shall terminate
when for any reason whatsoever, the party of the
"The general rule is that impossibility of performance second part is forced to stop, abandoned [sic] its
releases the obligor. However, it is submitted that operation as a public service and it becomes
when the service has become so difficult as to be necessary to remove the electric lightpost;" (sic) 4
manifestly beyond the contemplation of the
parties, the court should be authorized to release It was prepared by or with the assistance of the
the obligor in whole or in part. The intention of the other petitioner, Atty. Luciano M. Maggay, then a
parties should govern and if it appears that the member of the Board of Directors of private
6|OBLICON_Chapter 3_Conditional Obligations
respondent and at the same time the legal counsel had refused to comply with private respondent's
of petitioner. demands for payment for the use of the posts
After the contract had been enforced for over ten outside Naga City, it was probably because what is
(10) years, private respondent filed on January 2, due to them from private respondent is more than
1989 with the Regional Trial Court of Naga City (Br. its claim against them.
28) C.C. No. 89-1642 against petitioners for
reformation of the contract with damages, on the And with respect to the third cause of action,
ground that it is too one-sided in favor of petitioners claimed, inter alia, that their telephone
petitioners; that it is not in conformity with the service had been categorized by the National
guidelines of the National Electrification Telecommunication Corporation (NTC) as "very
Administration (NEA) which direct that the high" and of "superior quality."
reasonable compensation for the use of the posts is
P10.00 per post, per month; that after eleven (11) During the trial, private respondent presented the
years of petitioners' use of the posts, the telephone following witnesses:
cables strung by them thereon have become much
heavier with the increase in the volume of their (1) Dioscoro Ragragio, one of the two officials who
subscribers, worsened by the fact that their linemen signed the contract in its behalf, declared that it
bore holes through the posts at which points those was petitioner Maggay who prepared the contract;
posts were broken during typhoons; that a post now that the understanding between private
costs as much as P2,630.00; so that justice and respondent and petitioners was that the latter
equity demand that the contract be reformed to would only use the posts in Naga City because at
abolish the inequities thereon. prLL that time, petitioners' capability was very limited
and they had no expectation of expansion
because of legal squabbles within the company;
that private respondent agreed to allow petitioners
As second cause of action, private respondent to use its posts in Naga City because there were
alleged that starting with the year 1981, petitioners many subscribers therein who could not be served
have used 319 posts in the towns of Pili, Canaman, by them because of lack of facilities; and that while
Magarao and Milaor, Camarines Sur, all outside the telephone lines strung to the posts were very
Naga City, without any contract with it; that at the light in 1977, said posts have become heavily
rate of P10.00 per post, petitioners should pay loaded in 1989. LLphil
private respondent for the use thereof the total
amount of P267,960.00 from 1981 up to the filing of (2) Engr. Antonio Borja, Chief of private
its complaint; and that petitioners had refused to respondent's Line Operation and Maintenance
pay private respondent said amount despite Department, declared that the posts being used by
demands. petitioners totalled 1,403 as of April 17, 1989, 192 of
which were in the towns of Pili, Canaman, and
And as third cause of action, private respondent Magarao, all outside Naga City (Exhs. "B" and "B-1");
complained about the poor servicing by petitioners that petitioners' cables strung to the posts in 1989
of the ten (10) telephone units which had caused it are much bigger than those in November, 1977;
great inconvenience and damages to the tune of that in 1987, almost 100 posts were destroyed by
not less than P100,000.00 typhoon Sisang: around 20 posts were located
between Naga City and the town of Pili while the
In petitioners' answer to the first cause of action, posts in barangay Concepcion, Naga City were
they averred that it should be dismissed because broken at the middle which had been bored by
(1) it does not sufficiently state a cause of action for petitioner's linemen to enable them to string bigger
reformation of contract; (2) it is barred by telephone lines; that while the cost per post in 1977
prescription, the same having been filed more than was only from P700.00 to P1,000.00, their costs in
ten (10) years after the execution of the contract; 1989 went up from P1,500.00 to P2,000.00,
and (3) it is barred by estoppel, since private depending on the size; that some lines that were
respondent seeks to enforce the contract in the strung to the posts did not follow the minimum
same action. Petitioners further alleged that their vertical clearance required by the National Building
utilization of private respondent's post could not Code, so that there were cases in 1988 where,
have caused their deterioration because they have because of the low clearance of the cables,
already been in use for eleven (11) years; and that passing trucks would accidentally touch said cables
the value of their expenses for the ten (10) causing the posts to fall and resulting in brown-outs
telephone lines long enjoyed by private respondent until the electric lines were repaired.
free of charge are far in excess of the amounts
claimed by the latter for the use of the posts, so (3) Dario Bernardez, Project Supervisor and Acting
that if there was any inequity, it was suffered by General Manager of private respondent and
them. Manager of Region V of NEA, declared that
according to NEA guidelines in 1985 (Exh. "C"), for
Regarding the second cause of action, petitioners the use by private telephone systems of electric
claimed that private respondent had asked for cooperatives' posts, they should pay a minimum
telephone lines in areas outside Naga City for which monthly rental of P4.00 per post, and considering
its posts were used by them; and that if petitioners the escalation of prices since 1985, electric
7|OBLICON_Chapter 3_Conditional Obligations
cooperatives have been charging from P10.00 to (3) Concerning the second cause of action, the
P15.00 per post, which is what petitioners should intention of the parties when they entered into the
pay for the use of the posts. contract was that the coverage thereof would
include the whole area serviced by petitioners
(4) Engineer Antonio Macandog, Department Head because at that time, they already had subscribers
of the Office of Services of private respondent, outside Naga City. Private respondent, in fact, had
testified on the poor service rendered by asked for telephone connections outside Naga City
petitioners' telephone lines, like the telephone in for its officers and employees residing there in
their Complaints Section which was usually out of addition to the ten (10) telephone units mentioned
order such that they could not respond to the calls in the contract. Petitioners have not been charging
of their customers. In case of disruption of their private respondent for the installation, transfers and
telephone lines, it would take two to three hours for re-connections of said telephones so that naturally,
petitioners to reactivate them notwithstanding their they use the posts for those telephone lines.
calls on the emergency line.
(4) With respect to the third cause of action, the
(5) Finally, Atty. Luis General, Jr., private NTC has found petitioners cable installations to be
respondent's counsel, testified that the Board of in accordance with engineering standards and
Directors asked him to study the contract sometime practice and comparable to the best in the
during the latter part of 1982 or in 1983, as it had country.
appeared very disadvantageous to private
respondent. Notwithstanding his recommendation On the basis of the foregoing countervailing
for the filing of a court action to reform the evidence of the parties, the trial court found, as
contract, the former general managers of private regards private respondents first cause of action,
respondent wanted to adopt a soft approach with that while the contract appeared to be fair to both
petitioners about the matter until the term of parties when it was entered into by them during the
General Manager Henry Pascual who, after failing first year of private respondents operation and
to settle the matter amicably with petitioners, finally when its Board of Directors did not yet have any
agreed for him to file the present action for experience in that business, it had become
reformation of contract. disadvantageous and unfair to private respondent
because of subsequent events and conditions,
On the other hand, petitioner Maggay testified to particularly the increase in the volume of the
the following effect: subscribers of petitioners for more than ten (10)
years without the corresponding increase in the
(1) It is true that he was a member of the Board of number of telephone connections to private
Directors of private respondent and at the same respondent free of charge. The trial court
time the lawyer of petitioner when the contract was concluded that while in an action for reformation of
executed, but Atty. Gaudioso Tena, who was also a contract, it cannot make another contract for the
member of the Board of Directors of private parties, it can, however, for reasons of justice and
respondent, was the one who saw to it that the equity, order that the contract be reformed to
contract was fair to both parties. abolish the inequities therein. Thus, said court ruled
that the contract should be reformed by ordering
(2) With regard to the first cause of action: petitioners to pay private respondent
compensation for the use of their posts in Naga
(a) Private respondent has the right under the City, while private respondent should also be
contract to use ten (10) telephone units of ordered to pay the monthly bills for the use of the
petitioners for as long as it wishes without paying telephones also in Naga City. And taking into
anything therefor except for long distance calls consideration the guidelines of the NEA on the
through PLDT out of which the latter get only 10% of rental of posts by telephone companies and the
the charges. LLpr increase in the costs of such posts, the trial court
opined that a monthly rental of P10.00 for each
(b) In most cases, only drop wires and not post of private respondent used by petitioners is
telephone cables have been strung to the posts, reasonable, which rental it should pay from the
which posts have remained erect up to present; filing of the complaint in this case on January 2,
1989. And in like manner, private respondent should
(c) Petitioners' linemen have strung only small pay petitioners from the same date its monthly bills
messenger wires to many of the posts and they for the use and transfers of its telephones in Naga
need only small holes to pass through; and City at the same rate that the public are paying.
cdll
(d) Documents existing in the NTC show that the
stringing of petitioners' cables in Naga City are On private respondent's second cause of action,
according to standard and comparable to those of the trial court found that the contract does not
PLDT. The accidents mentioned by private mention anything about the use by petitioners of
respondent involved trucks that were either private respondent's posts outside Naga City.
overloaded or had loads that protruded upwards, Therefore, the trial court held that for reason of
causing them to hit the cables. equity, the contract should be reformed by
including therein the provision that for the use of
8|OBLICON_Chapter 3_Conditional Obligations
private respondent's posts outside Naga City, future service with future unusual change. Instead,
petitioners should pay a monthly rental of P10.00 the ruling in the case Occea, et al. v. Jabson, etc,
per post, the payment to start on the date this case et al., 7 which interpreted the article, should be
was filed, or on January 2, 1989, and private followed in resolving this case. Besides, said article
respondent should also pay petitioners the monthly was never raised by the parties in their pleadings
dues on its telephone connections located outside and was never the subject of trial and evidence.
Naga City beginning January, 1989.
In applying Article 1267, respondent court
rationalized:

And with respect to private respondent's third "We agree with appellant that in order that an
cause of action, the trial court found the claim not action for reformation of contract would lie and
sufficiently proved. may prosper, there must be sufficient allegations as
well as proof that the contract in question failed to
Thus, the following decretal portion of the trial express the true intention of the parties due to error
court's decision dated July 20, 1990: or mistake, accident, or fraud. Indeed, in
embodying the equitable remedy of reformation of
"WHEREFORE, in view of all the foregoing, decision is instruments in the New Civil Code, the Code
hereby rendered ordering the reformation of the Commission gave its reasons as follows:
agreement (Exh. A); ordering the defendants to
pay plaintiff's electric poles in Naga City and in the 'Equity dictates the reformation of an instrument in
towns of Milaor, Canaman, Maragao and Pili, order that the true intention of the contracting
Camarines Sur and in other places where parties may be expressed. The courts by the
defendant NATELCO uses plaintiff's electric poles, reformation do not attempt to make a new
the sum of TEN (P10.00) PESOS per plaintiff's pole, contract for the parties, but to make the instrument
per month beginning January, 1989 and ordering express their real agreement. The rationale of the
also the plaintiff to pay defendant NATELCO the doctrine is that it would be unjust and inequitable
monthly dues of all its telephones including those to allow the enforcement of a written instrument
installed at the residence of its officers, namely; which does not reflect or disclose the real meeting
Engr. Joventino Cruz, Engr. Antonio Borja, Engr. of the minds of the parties. The rigor of the legalistic
Antonio Macandog, Mr. Jesus Opiana and Atty. Luis rule that a written instrument should be the final
General, Jr. beginning January, 1989. Plaintiff's and inflexible criterion and measure of the rights
claim for attorney's fees and expenses of litigation and obligations of the contracting parties is thus
and defendants' counterclaim are both hereby tempered to forestall the effects of mistake, fraud,
ordered dismissed. Without pronouncement as to inequitable conduct, or accident.' (pp. 55-56,
costs." llcd Report of Code Commission)

Disagreeing with the foregoing judgment, Thus, Articles 1359, 1361, 1362, 1363 and 1364 of the
petitioners appealed to respondent Court of New Civil Code provide in essence that where
Appeals. In the decision dated May 28, 1992, through mistake or accident on the part of either or
respondent court affirmed the decision of the trial both of the parties or mistake or fraud on the part of
court, 5 but based on different grounds to wit: (1) the clerk or typist who prepared the instrument, the
that Article 1267 of the New Civil Code is true intention of the parties is not expressed therein,
applicable and (2) that the contract was subject to then the instrument may be reformed at the
a potestative condition which rendered said instance of either party if there was mutual mistake
condition void. The motion for reconsideration was on their part, or by the injured party if only he was
denied in the resolution dated September 10, 1992. mistaken. cdphil
6 Hence, the present petition.
Petitioners assign the following pertinent errors Here, plaintiff-appellee did not allege in its
committed by respondent court: complaint, nor does its evidence prove, that there
was a mistake on its part or mutual mistake on the
1) in making a contract for the parties by invoking part of both parties when they entered into the
Article 1267 of the New Civil Code; agreement Exh. "A", and that because of this
mistake, said agreement failed to express their true
2) in ruling that prescription of the action for intention. Rather, plaintiff's evidence shows that said
reformation of the contract in this case agreement was prepared by Atty. Luciano
commenced from the time it became Maggay, then a member of plaintiff's Board of
disadvantageous to private respondent; and Directors and its legal counsel at that time, who was
also the legal counsel for defendant-appellant, so
3) in ruling that the contract was subject to a that as legal counsel for both companies and
potestative condition in favor of petitioners. presumably with the interests of both companies in
mind when he prepared the aforesaid agreement,
Petitioners assert earnestly that Article 1267 of the Atty. Maggay must have considered the same fair
New Civil Code is not applicable primarily because and equitable to both sides, and this was affirmed
the contract does not involve the rendition of by the lower court when it found said contract to
service or a personal prestation and it is not for have been fair to both parties at the time of its
9|OBLICON_Chapter 3_Conditional Obligations
execution. In fact, there were no complaints on the 'Our understanding at that time is that we will allow
part of both sides at the time of and after the NATELCO to utilize the posts of CASURECO II only in
execution of said contract, and according to 73- the City of Naga because at that time the
year old Justino de Jesus, Vice President and capability of NATELCO was very limited, as a matter
General manager of appellant at the time who of fact we do [sic] not expect to be able to expand
signed the agreement Exh. "A" in its behalf and who because of the legal squabbles going on in the
was one of the witnesses for the plaintiff (sic), both NATELCO. So, even at that time there were so many
parties complied with said contract 'from the very subscribers in Naga City that cannot be served by
beginning' (p. 5, tsn, April 17, 1989). the NATELCO, so as a matter of public service we
allowed them to sue (sic) our posts within the Naga
That the aforesaid contract has become iniquitous City.' (p. 8, tsn April 3, 1989)
or unfavorable or disadvantageous to the plaintiff
with the expansion of the business of appellant and Ragragio also declared that while the telephone
the increase in the volume of its subscribers in Naga wires strung to the electric posts of plaintiff were
City and environs through the years, necessitating very light and that very few telephone lines were
the stringing of more and bigger telephone cable attached to the posts of CASURECO II in 1977, said
wires by appellant to plaintiff's electric posts without posts have become 'heavily loaded' in 1989 (tsn,
a corresponding increase in the ten (10) telephone id.).
connections given by appellant to plaintiff free of
charge in the agreement Exh. "A" as consideration In truth, as also correctly found by the lower court,
for its use of the latter's electric posts in Naga City, despite the increase in the volume of appellant's
appear, however, undisputed from the totality of subscribers and the corresponding increase in the
the evidence on record and the lower court so telephone cables and wires strung by it to plaintiff's
found. And it was for this reason that in the later electric posts in Naga City for the more 10 years
(sic) part of 1982 or 1983 (or five or six years after the that the agreement Exh. "A" of the parties has been
subject agreement was entered into by the in effect, there has been no corresponding
parties), plaintiff's Board of Directors already asked increase in the ten (10) telephone units connected
Atty. Luis General who had become their legal by appellant free of charge to plaintiff's offices and
counsel in 1982, to study said agreement which other places chosen by plaintiff's general manager
they believed had become disadvantageous to which was the only consideration provided for in
their company and to make the proper said agreement for appellant's use of plaintiff's
recommendation, which study Atty. General did, electric posts. Not only that, appellant even started
and thereafter, he already recommended to the using plaintiff's electric posts outside Naga City
Board the filing of a court action to reform said although this was not provided for in the
contract, but no action was taken on Atty. agreement Exh. "A" as it extended and expanded
General's recommendation because the former its telephone services to towns outside said city.
general managers of plaintiff wanted to adopt a Hence, while very few of plaintiff's electric posts
soft approach in discussing the matter with were being used by appellant in 1977 and they
appellant, until, during the term of General were all in the City of Naga, the number of plaintiff's
Manager Henry Pascual, the latter, after failing to electric posts that appellant was using in 1989 had
settle the problem with Atty. Luciano Maggay who jumped to 1,403,192 of which are outside Naga City
had become the president and general manager (Exh. "B"). Add to this the destruction of some of
of appellant, already agreed for Atty. General's plaintiff's poles during typhoons like the strong
filing of the present action. The fact that said typhoon Sisang in 1987 because of the heavy
contract has become iniquitous or telephone cables attached thereto, and the
disadvantageous to plaintiff as the years went by escalation of the costs of electric poles from 1977 to
did not, however, give plaintiff a cause of action for 1989, and the conclusion is indeed ineluctable that
reformation of said contract, for the reasons the agreement Exh. "A" has already become too
already pointed out earlier. But this does not mean one-sided in favor of appellant to the great
that plaintiff is completely without a remedy, for we disadvantage of plaintiff, in short, the continued
believe that the allegations of its complaint herein enforcement of said contract has manifestly gone
and the evidence it has presented sufficiently make far beyond the contemplation of plaintiff, so much
out a cause of action under Art. 1267 of the New so that it should now be released therefrom under
Civil Code for its release from the agreement in Art. 1267 of the New Civil Code to avoid appellant's
question. LibLex unjust enrichment at its (plaintiff's) expense. As
stated by Tolentino in his commentaries on the Civil
xxx xxx xxx Code citing foreign civilist Ruggiero, 'equity
demands a certain economic equilibrium between
The understanding of the parties when they entered the prestation and the counter-prestation, and
into the Agreement Exh. "A" on November 1, 1977 does not permit the unlimited impoverishment of
and the prevailing circumstances and conditions at one party for the benefit of the other by the
the time, were described by Dioscoro Ragragio, the excessive rigidity of the principle of the obligatory
President of plaintiff in 1977 and one of its two force of contracts (IV Tolentino, Civil Code of the
officials who signed said agreement in its behalf, as Philippines, 1986 ed., pp. 247-248). LexLib
follows:

10 | O B L I C O N _ C h a p t e r 3 _ C o n d i t i o n a l O b l i g a t i o n s
proceeds from the sales of subdivided lots of
We therefore, find nothing wrong with the ruling of subject subdivision'. The cited article (Article 1267)
the trial court, although based on a different and does not grant the courts (the) authority to remake,
wrong premise (i.e., reformation of contract), that modify or revise the contract or to fix the division of
from the date of the filing of this case, appellant shares between the parties as contractually
must pay for the use of plaintiff's electric posts in stipulated with the force of law between the
Naga City at the reasonable monthly rental of parties, so as to substitute its own terms for those
P10.00 per post, while plaintiff should pay appellant covenanted by the parties themselves.
for the telephones in the same City that it was Respondent's complaint for modification of
formerly using free of charge under the terms of the contract manifestly has no basis in law and
agreement Exh. "A" at the same rate being paid by therefore states no cause of action. Under the
the general public. In affirming said ruling, we are particular allegations of respondent's complaint
not making a new contract for the parties herein, and the circumstances therein averred, the courts
but we find it necessary to do so in order not to cannot even in equity the relief sought." 11
disrupt the basic and essential services being
rendered by both parties herein to the public and The ruling in the Occea case is not applicable
to avoid unjust enrichment by appellant at the because we agree with respondent court that the
expense of plaintiff, said arrangement to continue allegations in private respondent's complaint and
only until such time as said parties can re-negotiate the evidence it has presented sufficiently made out
another agreement over the same subject-matter a cause of action under Article 1267. We, therefore,
covered by the agreement Exh. "A". Once said release the parties from their correlative obligations
agreement is reached and executed by the under the contract. However, our disposition of the
parties, the aforesaid ruling of the lower court and present controversy does not end here. We have to
affirmed by us shall cease to exist and shall be take into account the possible consequences of
substituted and superseded by their new merely releasing the parties therefrom: petitioners
agreement. . . ." 8 will remove the telephone wires/cables in the posts
of private respondent, resulting in disruption of their
Article 1267 speaks of "service" which has become essential service to the public; while private
so difficult. Taking into consideration the rationale respondent, in consonance with the contract 12 will
behind this provision, 9 the term "service" should be return all the telephone units to petitioners, causing
understood as referring to the "performance" of the prejudice to its business. We shall not allow such
obligation. In the present case, the obligation of eventuality. Rather, we require, as ordered by the
private respondent consists in allowing petitioners to trial court: 1) petitioners to pay private respondent
use its posts in Naga City, which is the service for the use of its posts in Naga City and in the towns
contemplated in said article. Furthermore, a bare of Milaor, Canaman, Magarao and Pili, Camarines
reading of this article reveals that it is not a Sur and in other places where petitioners use
requirement thereunder that the contract be for private respondent's posts, the sum of ten (P10.00)
future service with future unusual change. pesos per post, per month, beginning January,
According to Senator Arturo M. Tolentino, 10 Article 1989; and 2) private respondent to pay petitioner
1267 states in our law the doctrine of unforeseen the monthly dues of all its telephones at the same
events. This is said to be based on the discredited rate being paid by the public beginning January,
theory of rebus sic stantibus in public international 1989. The peculiar circumstances of the present
law; under this theory, the parties stipulate in the case, as distinguished further from the Occea
light of certain prevailing conditions, and once case, necessitates exercise of our equity jurisdiction.
these conditions cease to exist the contract also 13 By way of emphasis, we reiterate the
ceases to exist. Considering practical needs and rationalization of respondent court that: cdll
the demands of equity and good faith, the ". . . In affirming said ruling, we are not making a
disappearance of the basis of a contract gives rise new contract for the parties herein, but we find it
to a right to relief in favor of the party prejudiced. necessary to do so in order not to disrupt the basic
and essential services being rendered by both
In a nutshell, private respondent in the Occea parties herein to the public and to avoid unjust
case filed a complaint against petitioner before the enrichment by appellant at the expense of plaintiff
trial court praying for modification of the terms and . . . ." 1 4
conditions of the contract that they entered into by
fixing the proper shares that should pertain to them Petitioners' assertion that Article 1267 was never
out of the gross proceeds from the sales of raised by the parties in their pleadings and was
subdivided lots. We ordered the dismissal of the never the subject of trial and evidence has been
complaint therein for failure to state a sufficient passed upon by respondent court in its well
cause of action. We rationalized that the Court of reasoned resolution, which we hereunder quote as
Appeals misapplied Article 1267 because: our own:

". . . respondent's complaint seeks not release from "First, we do not agree with defendant-appellant
the subdivision contract but that the court 'render that in applying Art. 1267 of the New Civil Code to
judgment modifying the terms and conditions of this case, we have changed its theory and decided
the contract . . . by fixing the proper shares that the same on an issue not invoked by plaintiff in the
should pertain to the herein parties out of the gross lower court. For basically, the main and pivotal issue
11 | O B L I C O N _ C h a p t e r 3 _ C o n d i t i o n a l O b l i g a t i o n s
in this case is whether the continued enforcement construction thereon and adjudicating the issues
of the contract Exh. "A" between the parties has, accordingly.' (Alzua v. Johnson, 21 Phil. 308)
through the years (since 1977), become too
iniquitous or disadvantageous to the plaintiff and And in the fairly recent case of Caltex Phil. Inc. v.
too one-sided in favor of defendant-appellant, so IAC, 176 SCRA 741, the Honorable Supreme Court
that a solution must be found to relieve plaintiff also held:
from the continued operation of said agreement
and to prevent defendant-appellant from further 'We rule that the respondent court did not commit
unjustly enriching itself at plaintiff's expense. It is any error in taking cognizance of the aforesaid
indeed unfortunate that defendant had turned issues, although not raised before the trial court. The
deaf ears to plaintiff's requests for renegotiation, presence of strong consideration of substantial
constraining the latter to go to court. But although justice has led this Court to relax the well-
plaintiff cannot, as we have held, correctly invoke entrenched rule that, except questions on
reformation of contract as a proper remedy (there jurisdiction, no question will be entertained on
having been no showing of a mistake or error in appeal unless it has been raised in the court below
said contract on the part of any of the parties so as and it is within the issues made by the parties in their
to result in its failure to express their true intent), this pleadings (Cordero v. Cabral, L-36789, July 25, 1983,
does not mean that plaintiff is absolutely without a 123 SCRA 532). . . .'
remedy in order to relieve itself from a contract that
has gone far beyond its contemplation and has
become highly iniquitous and disadvantageous to it
through the years because of the expansion of We believe that the above authorities suffice to
defendant-appellant's business and the increase in show that this Court did not err in applying Art. 1267
the volume of its subscribers. And as it is the duty of of the New Civil Code to this case. Defendant-
the Court to administer justice, it must do so in this appellant stresses that the applicability of said
case in the best way and manner it can in the light provision is a question of fact, and that it should
of the proven facts and the law or laws applicable have been given the opportunity to present
thereto. cdphil evidence on said question. But defendant-
appellant cannot honestly and truthfully claim that
It is settled that when the trial court decides a case it (did) not (have) the opportunity to present
in favor of a party on a certain ground, the evidence on the issue of whether the continued
appellate court may uphold the decision below operation of the contract Exh. "A" has now become
upon some other point which was ignored or too one-sided in its favor and too iniquitous, unfair,
erroneously decided by the trial court (Garcia and disadvantageous to plaintiff. As held in our
Valdez v. Tuazon, 40 Phil. 943; Relativo v. Castro, 76 decision, the abundant and copious evidence
Phil. 563; Carillo v. Salak de Paz, 18 SCRA 467). presented by both parties in this case and
Furthermore, the appellate court has the discretion summarized in said decision established the
to consider an unassigned error that is closely following essential and vital facts which led us to
related to an error properly assigned (Paterno v. apply Art. 1267 of the New Civil Code to this case:
Jao Yan, 1 SCRA 631; Hernandez v. Andal, 78 Phil. Cdpr
196). It has also been held that the Supreme Court
(and this Court as well) has the authority to review xxx xxx xxx." 15
matters, even if they are not assigned as errors in
the appeal, if it is found that their consideration is On the issue of prescription of private respondent's
necessary in arriving at a just decision of the case action for reformation of contract, petitioners
(Saura Import & Export Co., Inc. v. Phil. International allege that respondent court's ruling that the right of
Surety Co. and PNB, 8 SCRA 143). For it is the action "arose only after said contract had already
material allegations of fact in the complaint, not become disadvantageous and unfair to it due to
the legal conclusion made therein or the prayer, subsequent events and conditions, which must be
that determines the relief to which the plaintiff is sometime during the latter part of 1982 or in 1983 . .
entitled, and the plaintiff is entitled to as much relief ." 16 is erroneous. In reformation of contracts, what
as the facts warrant although that relief is not is reformed is not the contract itself, but the
specifically prayed for in the complaint (Rosales v. instrument embodying the contract. It follows that
Reyes and Ordoveza, 25 Phil. 495; Cabigao v. Lim, whether the contract is disadvantageous or not
50 Phil. 844; Baguioro v. Barrios, 77 Phil. 120). To irrelevant to reformation and therefore, cannot be
quote an old but very illuminating decision of our an element in the determination of the period for
Supreme Court through the pen of American jurist prescription of the action to reform.
Adam C. Carson:
Article 1144 of the New Civil Code provides, inter
'Under our system of pleading it is the duty of the alia, that an action upon a written contract must
courts to grant the relief to which the parties are be brought within ten (10) years from the time the
shown to be entitled by the allegations in their right of the action accrues. Clearly, the ten (10)
pleadings and the facts proven at the trial, and the year period is to be reckoned from the time the
mere fact that they themselves misconstrue the right of action accrues which is not necessarily the
legal effects of the facts thus alleged and proven date of execution of the contract. As correctly
will not prevent the court from placing the just ruled by respondent court, private respondent's
12 | O B L I C O N _ C h a p t e r 3 _ C o n d i t i o n a l O b l i g a t i o n s
right of action arose "sometime during the latter
part of 1982 or in 1983 when according to Atty. Luis The above can also be said of the agreement Exh.
General, Jr. . . ., he was asked by (private "A" between the parties in this case. There is no
respondent's) Board of Directors to study said mutuality and equality between them under the
contract as it already appeared disadvantageous afore-quoted provision thereof since the life and
to (private respondent) (p. 31, tsn, May 8, 1989). continuity of said agreement is made to depend as
(Private respondent's) cause of action to ask for long as appellant needs plaintiff's electric posts.
reformation of said contract should thus be And this is precisely why, since 1977 when said
considered to have arisen only in 1982 or 1983, and agreement was executed and up to 1989 when this
from 1982 to January 2, 1989 when the complaint in case was finally filed by plaintiff, it could do nothing
this case was filed, ten (10) years had not yet to be released from or terminate said agreement
elapsed." 17 notwithstanding that its continued effectivity has
become very disadvantageous and iniquitous to it
Regarding the last issue, petitioners allege that due to the expansion and increase of appellant's
there is nothing purely potestative about the telephone services within Naga City and even
prestations of either party because petitioner's outside the same, without a corresponding increase
permission for free use of telephones is not made to in the ten (10) telephone units being used by
depend purely on their will, neither is private plaintiff free of charge, as well as the bad and
respondent's permission for free use of its posts inefficient service of said telephones to the
dependent purely on its will. llcd prejudice and inconvenience of plaintiff and its
customers. . . ." 18
Apart from applying Article 1267, respondent court
cited another legal remedy available to private Petitioners' allegations must be upheld in this
respondent under the allegations of its complaint regard. A potestative condition is a condition, the
and the preponderant evidence presented by it: fulfillment of which depends upon the sole will of
the debtor, in which case, the conditional
". . . we believe that the provision in said agreement obligation is void. 19 Based on this definition,
respondent court's finding that the provision in the
contract, to wit:
'(a) That the term or period of this contract shall be
as long as the party of the first part [herein "(a) That the term or period of this contract shall be
appellant] has need for the electric light posts of as long as the party of the first part (petitioner) has
the party of the second part [herein plaintiff] it need for the electric light posts of the party of the
being understood that this contract shall terminate second part (private respondent) . . ." LLjur
when for any reason whatsoever, the party of the
second part is forced to stop, abandoned [sic] its is a potestative condition, is correct. However, it
operation as a public service and it becomes must have overlooked the other conditions in the
necessary to remove the electric light post [sic]'; same provision, to wit:
(Emphasis supplied) ". . . it being understood that this contract shall
terminate when for any reason whatsoever, the
is invalid for being purely potestative on the part of party of the second part (private respondent) is
appellant as it leaves the continued effectivity of forced to stop, abandoned (sic) its operation as a
the aforesaid agreement to the latter's sole and public service and it becomes necessary to remove
exclusive will as long as plaintiffs is in operation. A the electric light post (sic);"
similar provision in a contract of lease wherein the
parties agreed that the lessee could stay on the which are casual conditions since they depend on
leased premises 'for as long as the defendant chance, hazard, or the will of a third person. 20 In
needed the premises and can meet and pay said sum, the contract is subject to mixed conditions,
increases' was recently held by the Supreme Court that is, they depend partly on the will of the debtor
in Lim v. C.A., 191 SCRA 150, citing the much earlier and partly on chance, hazard or the will of a third
case of Encarnacion v. Baldomar, 77 Phil. 470, as person, which do not invalidate the
invalid for being 'a purely potestative condition aforementioned provision. 21 Nevertheless, in view
because it leaves the effectivity and enjoyment of of our discussions under the first and second issues
leasehold rights to the sole and exclusive will of the raised by petitioners, there is no reason to set aside
lessee.' Further held the High Court in the Lim case: the questioned decision and resolution of
llcd respondent court.
WHEREFORE, the petition is hereby DENIED. The
'The continuance, effectivity and fulfillment of a decision of the Court of Appeals dated May 28,
contract of lease cannot be made to depend 1992 and its resolution dated September 10, 1992
exclusively upon the free and uncontrolled choice are AFFIRMED.
of the lessee between continuing the payment of
the rentals or not, completely depriving the owner SO ORDERED.
of any say in the matter. Mutuality does not obtain
in such a contract of lease of no equality exists Narvasa, C .J ., Padilla, Regalado and Puno, JJ .,
between the lessor and the lessee since the life of concur.
the contract is dictated solely by the lessee.'
13 | O B L I C O N _ C h a p t e r 3 _ C o n d i t i o n a l O b l i g a t i o n s

Vous aimerez peut-être aussi