Document Number

Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 1 / 15
RAPID P0030 CPP PMG WPR 0001 0020

PETRONAS RAPID PROJECT, PENGERANG


(P30A-EPCC OF RAPID ADDITIONAL OLEFINS STORAGE FACILITIES)

Package 30A
WEEKLY PROGRESS REPORT NO. 0020
9th Sep 15th Sep2017

OWNER Approval: PRPC Refinery and Cracker Sdn.Bhd


Name:
Date (DD-MMM-YY):

Signature:

Document Class: O

Pages modified under this revision: -

0 15-Sep-2017 INF Issued for Information Ji Yuan Li Caixian Wan Rui


DATE WRITTEN BY CHECKED BY APPROVED BY
REV. STATUS REVISION MEMO
DD-MMM-YY (name & signature) (name & signature) (name & signature)

Sections changed in last revision are identified by a vertical line in the right margin.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 2 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

HOLDs

HOLD No. REF. DESCRIPTION ACTIONS

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 3 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

TABLE OF CONTENTS
1. HSSE STATISTIC.......................................................................................................................... 4
2. PROJECT HIGHLIGHTS............................................................................................................... 4
2.1 PROJECT MANAGEMENT................................................................................................4

2.2 ENGINEERING.................................................................................................................. 5

2.3 PROCUREMENT............................................................................................................... 6

2.4 BULLET TANK WEEKLY ACTIVITY REPORT....................................................................6

2.5 CONSTRUCTION / COMMISSIONING..............................................................................8

3. SCHEDULE AND PROGRESS.....................................................................................................9


3.1 SCHEDULE ANALYSIS......................................................................................................9

4. PLAN FOR NEXT 2 WEEKS.......................................................................................................10


4.1 PROJECT MANAGEMENT................................................................................................10

4.2 ENGINEERING.................................................................................................................. 11

4.3 PROCUREMENT............................................................................................................... 11

4.4 BULLET TANKS:................................................................................................................ 11

4.5 CONSTRUCTION / COMMISSIONING..............................................................................12

5. AREA OF CONCERNS................................................................................................................ 13
5.1 PROJECT MANAGEMENT................................................................................................13

5.2 ENGINEERING.................................................................................................................. 14

5.3 PROCUREMENT............................................................................................................... 14

5.4 CONSTRUCTION / COMMISSIONING..............................................................................14

6. MAJOR OUTSTANDING CORRESPONDENCE.........................................................................15


7. Attachments................................................................................................................................. 15

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 4 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

1. HSSE STATISTIC

Description This Week Cumulative Total


Safe Work Hours (w/o) LTI 9,213 82,723
Total Work Hours 9,213 82,723
Lost Time Incident (LTI) Nil Nil
Restricted Workday Cases (RWDC) Nil Nil
Medical Treatment Cases (MTC) Nil Nil
First Aid Cases (FAC) Nil Nil
Total Incidents Nil Nil
Total Incidents Rate Nil Nil
Near Miss to Date Nil Nil
Environmental Nil Nil
Property Damage Nil Nil

Total Open Closed


Non-Conformance Reports (NCRs) 00 00 00
Surveillance Reports (SR) 00 00 00

2. PROJECT HIGHLIGHTS

2.1 PROJECT MANAGEMENT

2.1.1 HSE
Significant Accomplishments W/E 15-Sep-2017
Inspection 2 pile machines, 1 black hole, 2 mobile crane. (11/9/2017)
Mass Toolbox Meeting and Walkabout. (14/9/2017)
Support work for piling work. (on progress)
Daily safety briefing for piling workers. (on progress)

2.1.2 QA/QC

Piling point Testing work in progress


PDA-11 nos completed, PIT test 2 nos MLT 2 nos
For Piling PRPC middle of revising the EPCC/EPCM Final Documentation Procedure
PRPC has informed us that the Final Documentation Procedure still under review and yet to be finalize. Table of contain for Piling
has sent to PRPC for review.

Site inspection done on Peck Chew documentation status and compiling system on 8th Sept
Underlined the inspection document requirement with CCM/Peck Chew as per PRPC project
documentation requirement.
Civil inspector already arrived site on 15 Sept

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 5 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

2.1.3 Subcontracting

Research Subcontractors for GRE drainage pipeline (September 12, 2017).


Issue the RFQ for Sphere Tank Fabrication Work. (September 12, 2017): Because the RFQ
document delay. The award date is unchanged.
Research Subcontractors for pre-cast manhole (September 13, 2017).

2.2 ENGINEERING

Significant Accomplishments W/E 15-SEP-2017

Engineering Progress measurement Summary


Data Date: 15-Sep-17
Last Week Cumm This Period This Period Cumm
Description WTG
Plan Actual Variance Plan Actual Plan Actual Variance
SI work 10.00% 100.00% 100.00% 0.00% 0.00% 0.00% 100.00% 100.00% 0.00%
Study 10.00% 13.00% 13.00% 0.00% 6.00% 3.00% 19.00% 16.00% -3.00%
Deliverables 80.00% 31.58% 32.62% 1.04% 5.73% 5.56% 37.30% 38.18% 0.88%
Engineering 100% 36.56% 37.40% 0.83% 5.18% 4.75% 41.74% 42.14% 0.40%

Note
Two items of delay for the Engineering study
1) Hazardous Area Classification will start on 25th Sep 2017
2) Corrosion Design Base Memoranda (CDBM)-CPP and the third party company had
disagreements with the scope of work, CDBM havent got a recovery plan date.

2.2.1 Drawings Status


This Week:
IFR IFA IFC/IFD/IFE
Disc Amou Pla Actu Reply Pla Actu Reply Pla Actu Reply
N
iplin Weight nt of n al Varian from n al Varian from n al Varian from
o e Doc's Iss Issu ce OWN Iss Issu ce OWN Iss Issu ce OWN
ue e ER ue e ER ue e ER
1 CVS 14.35% 132 4 2 -2 0 1 2 1 0 1 1 0 2
2 ELE 13.48% 124 3 1 -2 7 0 1 1 0 3 14 11 10
3 HSE 6.74% 62 1 1 0 1 5 1 -4 0 3 1 -2 0
4 HVA 1.85% 17 0 0 0 0 0 0 0 0 0 0 0 0
5 INC 11.96% 110 12 10 -2 0 0 0 0 0 0 2 2 0
6 MCI 1.52% 14 0 0 0 1 0 0 0 0 0 0 0 2
7 MEC 13.04% 120 9 8 -1 4 1 4 3 0 4 15 11 2
8 NVT 5.11% 47 6 5 -1 0 0 1 1 0 5 3 -2 3
9 PIP 10.33% 95 11 8 -3 4 1 5 4 3 5 3 -2 0
1
PRO 17.83% 164 4 6 2 2 39 33 -6 9 7 8 1 0
0
1
ROT 3.80% 35 3 3 0 1 1 1 0 0 1 4 3 5
1
Total 100.00% 920 53 44 -9 20 48 48 0 12 29 51 22 24

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 6 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

Total
IFR IFA IFC/IFD/IFE
Amou Pla Actu Reply Pla Actu Reply Pla Actu Reply
N Discipli
Weight nt of n al Varian from n al Varian from n al Varian from
o ne
Doc's Issu Issu ce OWNE Issu Issu ce OWNE Issu Issu ce OWNE
e e R e e R e e R
1 CVS 14.35% 132 34 40 6 38 23 26 3 24 21 27 6 26
2 ELE 13.48% 124 55 51 -4 49 2 2 0 1 21 39 18 34
3 HSE 6.74% 62 22 26 4 13 14 10 -4 7 8 9 1 5
4 HVA 1.85% 17 0 0 0 0 0 0 0 0 0 0 0 0
5 INC 11.96% 110 30 28 -2 18 13 13 0 13 13 17 4 14
6 MCI 1.52% 14 8 9 1 9 2 0 -2 0 2 3 1 3
7 MEC 13.04% 120 40 42 2 35 8 5 -3 1 15 19 4 6
8 NVT 5.11% 47 35 35 0 29 1 2 1 1 18 20 2 17
9 PIP 10.33% 95 33 31 -2 19 13 11 -2 3 8 7 -1 1
1
PRO 17.83% 164 134 137 3 111 94 74 -20 12 18 13 -5 0
0
1
ROT 3.80% 35 19 18 -1 15 3 3 0 2 6 10 4 9
1
100.00
Total 920 410 417 7 336 173 146 -27 64 130 164 34 115
%

2.2.2 TEQ Status


N/A

2.2.3 Geotechnical Status


NIL

2.3 PROCUREMENT
1) Issue the official Purchase Order of GRE Pipes to NOV Singapore Pet Ltd. (Sep 9, 2017)
2) Receive approve PIV MR (Sept 15, 2017)
3) Send out official RFQ of Carbon Steel Pipe(Sep 13,2017)
4) Issue the official Purchase Order of liquid refrigerant compressor.(Sep 15,2017)
5) Issue official RFQ to approved vendors for Fittings( Sep 9, 2017)

2.4 BULLET TANK WEEKLY ACTIVITY REPORT

2.4.1 Procurement
1) PO for Flange/ forging and elbow tentatively to be issue on 1st October 2017. CPP
confirmation reply is required.
2) PO for CS/SS pipe tentatively will be issue on October 2017, detail will be confirmed on
next week.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 7 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

2.4.2 Expediting
1) Blind test had performed on 14th September 2017 at MMHE-ATB. PRPC had joined the
testing.
2) CPP received official tax invoice for the 20% claim payment milestone from MMHE-ATB.
3) Engineering meeting on all the engineering document had carried out on 11th September
2017. MOM will be Distribute out on 15th September 2017.
4) MOM Monthly progress meeting No 7 distributed out on 12th September 2017.
5) Site weekly progress meeting had carry out on 13th September 2017.
6) CPP and MMHE-ATB meet on 11th October 2017 to align the method of measurement for
the schedule, CPP commented current weightage proposed by MMHE-ATB is not
reasonable, MMHE-ATB will readjust the weightage and propose after project execution
schedule REV D submit on 20th September 2017.
7) Daily short meeting with MMHE-ATB project engineer to follow up with document and
fabrication status.
8) Fabrication report as of 14thSeptember 2017.

2.4.3 Fabrication Report as of 15th Sep 2017.


N Descript Durato Schedule Schedule End Actual Actual End Unit Planne Actual Ahead/Dela
o on n (Days) Start Start d Unit Unit y (Days)
5220-
1 231 0 0 -
101A 17/7/2017 4/3/2018 PCS
Hemi
2 26 0 0 +60
Head#2 28/10/2017 26/11/2017 24/8/2017 PCS
Hemi
3 33 0 0 +54
Head#1 28/10/2017 26/11/2017 4/9/2017 PCS
Marking
4 12 54 54 -
& Cutting 17/7/2017 26/7/2017 28/7/2017 15/8/2017 PCS
5 Rolling 12 27/7/2017 2/8/2017 31/7/2017 16/8/2017 Can 54 54 -
L (LWL
Fit-up &
6 15 27 19 -5
Welding)
+ NDE 3/8/2017 6/9/2017 11/8/2017 Unit
Web &
7 31 18 10 -3
Flange 10/8/2017 8/9/2017 11/8/2017 Unit
Web +
Flange to
11 24 16 5 -
1 Can +
NDE 17/8/2017 15/9/2017 24/8/2017 Unit
3 Can
(CWL Fit-
12 31 1 0 -
up &
Welding) 31/8/2017 23/10/2017 27/8/2017 PCS
5220-
13 231 0 0 -
101B 27/7/2017 14/3/2018 PCS
Marking
14 9 54 54 -
& Cutting 27/8/2017 5/8/2017 15/8/2017 27/8/2017 PCS
15 Rolling 9 6/8/2017 12/8/2017 18/8/2017 30/8/2017 PCS 54 54 -
L (LWL
Fit-up &
16 15 18 0 -
Welding)
+ NDE 13/8/2017 16/9/2017 PCS
Web &
17 35 1 0 -
Flange 20/8/2017 18/9/2017 PCS

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 8 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

5220-
19 231 0 0 -
101C 2/10/2017 20/5/2018 PCS
Marking
20 9 -32
& Cutting 2/10/2017 11/10/2017 28/8/2017 PCS 54 29
21 Rolling 9 12/10/2017 18/10/2017 5/9/2017 PCS 54 13 -34

2.5 CONSTRUCTION / COMMISSIONING

2.5.1 Construction
The main work this week includes:
Piling work for butadiene vessel foundation (5220-V-101A/B/C/D), 3 piling rigs working.
Butadiene vessel foundation (5220-V-101A/B/C/D) piles PDA activities.
Piling work for propylene vessel foundation (5220-V-104C), 1 piling rig working.
Mobilized the new 1 piling rig to site for propylene vessel (5220-V-104A) piles driving.
P30A area low point backfilling and levelling, 1 backhoe working.
ICP piles delivery to site for butadiene and propylene pile driving.
TCF office area levelling and compaction.
Week Total
SN. Work Description Work Duration Complete Complete Remarks

5220-V-101A/B/C/D Piles
1 8th Sep-14th Sep 137 219/405
driving activity
Piles for butadiene delivery to
2 8th Sep-14th Sep 35% 60%
site.
5220-V-101A/B/C/D Piles
3 8th Sep-14th Sep 6 9/21
PDA
Propylene vessels piles
4 8th Sep-14th Sep 37 43/320
driving
Piles for propylene delivery to
5 8th Sep-14th Sep 12% 20%
site.
6 P30A area low point levelling 8th Sep-14th Sep 30% 60%
7 TCF area levelling 8th Sep-14th Sep 65% 80%
th th
8 TCF area compaction 8 Sep-14 Sep 50% 50%
th th
9 TCF area fabrication 8 Sep-14 Sep 35% 75%

2.5.2 Commissioning
Nil

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 9 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

3. SCHEDULE AND PROGRESS

3.1 SCHEDULE ANALYSIS

Milestone status
Milestone Description Baseline Date Actual Date
EFFECTIVE DATE of Contract 28-Apr-17 28-Apr-17
MC- Butadiene 30-Sep-18
RFSU- Butadiene 30-Nov-18
MC-Propylene 31-Jan-19
RFSU- Propylene 31-Mar-19
MC-Ethylene 31-Jul-19
RFSU- Ethylene 30-Sep-19
Certificate Of Provisional Acceptance signed by OWNER 31-Dec-19

Overall progress
Last Week Cumm This Period This Period Cumm
Description WTG
Plan Actual Variance Plan Actual Plan Actual Variance
Engineering 11.22% 36.71% 37.70% 0.99% 5.06% 4.45% 41.77% 42.14% 0.37%
Procurement 39.22% 9.42% 8.60% -0.81% 0.10% 1.37% 9.52% 9.97% 0.45%
Construction 44.67% 0.43% 0.37% -0.06% 0.36% 0.75% 0.79% 1.11% 0.32%
Commissioning 4.89% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Overall 100.00% 8.00% 7.77% -0.24% 0.77% 1.37% 8.77% 9.13% 0.36%

Manpower
Indirect Manpower
Indirect Manpower(Site office ) Direct Manpower
(Home office & Engineering office )
Plan Actual Plan Actual Plan Actual

Total to Date 133 126 8 24 23 44

Man-hours
Indirect Man-hours
Indirect Man-hours (Site office ) Direct Man-hours (Site work)
(Home office & Engineering office )
Plan Actual Plan Actual Plan Actual

This Period 1,952 5003 60 1550 1380 2660

Total to Date 33,659 61,578 4,046 8931 3,240 12,214

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 10 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

4. PLAN FOR NEXT 2 WEEKS

4.1 PROJECT MANAGEMENT

4.1.1 HSE

Planned Significant Objectives W/E 29-Sep-2017


Inspection machinery for site work. (29/9/2017)
Employ EO (Environmental Officer) and Trainer for site. (29/9/2017)
Daily safety briefing for piling work. (on progress)
Mass Toolbox Meeting and Walkabout. (on progress)

4.1.2 QA/QC
16/9/2017-22/9/2017
To submit the Lateral Testing Procedure
Inspect and monitor that MMHE-ATB fabrication
Inspection and monitor at site for piling work
Monitor the PDA and Lateral test
Discussion with PRPC on the Table of Contain for final documentation on next quality meeting
Preparation of procedures on other disciplines as per the site requirement
23/9/2017-29/9/2017
Quality Walkabout on MMHE ATB on 25th Sept
Inspect and monitor that MMHE-ATB fabrication
Inspection and monitor at site for piling work
Monitor the PDA and Lateral test

4.1.3 Subcontracting
Complete the technical and commercial evaluation of Civil and Structure Sub-Contractor for
Butadiene and Propylene Tank Foundation Work. (September 21, 2017): Bidders believe that
need to clarify and request to extend the date of submission of proposals. Contractor want to
have a face-to-face communication with bidders on September 18-19, 2017, Make sure that the
award date is unchanged.

Submit the documents of proposed Sub-contractor list for GRE drainage pipeline work, for
OWNERs approval (September 21, 2017): Up to now only one Sub-contractor has not yet been
submitted the company profile, the others had submitted, Contractor has reminded.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 11 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

Issue the LOA to the Civil and Sub-Contractor for Butadiene and Propylene Tank Foundation
Work. (September 23, 2017): Contractor will submit the TBE to OWNER for review, if approval
by OWNER, Contractor will issue the LOA.

Submit the documents of proposed Sub-contractor list for pre-cast manhole, for OWNERs
approval (September 23, 2017): Up to now only one Sub-contractor has submitted the company
profile, the others has not yet been submitted, Contractor has reminded them.

Issue RFQ for Civil Sub-Contractor for pre-cast manhole for UG FW and AOC (September 25,
2017)

Issue RFQ for GRE drainage pipeline work (September 25, 2017)

Prepare and issue the RFQ for the Civil Work of Electrical Substation and Field Auxiliary Room.
(Sep 28, 2017)

4.2 ENGINEERING
Planned Significant Objectives W/E 22-SEP-2017
HAZOP study will be held during 18th to 22nd Sep
The drawing status
Amount Weekly(16-sep~22-Sep) Cumm
No Discipline Weight of Progres Progres
Doc's IFR IFA IFC/IFD/IFE IFR IFA IFC/IFD/IFE
s s
1 CVS 14.35% 132 4 0 1 2.16% 38 23 22 25.45%
2 ELE 13.48% 124 0 0 3 0.52% 55 2 24 37.70%
3 HSE 6.74% 62 6 3 0 7.42% 28 17 8 37.10%
4 HVA 1.85% 17 1 0 0 4.41% 1 0 0 4.41%
5 INC 11.96% 110 4 1 2 3.18% 34 14 15 26.23%
6 MCI 1.52% 14 0 0 1 1.79% 8 2 3 48.93%
7 MEC 13.04% 120 2 0 6 2.25% 42 8 21 30.63%
8 NVT 5.11% 47 2 0 5 5.85% 37 1 23 70.85%
9 PIP 10.33% 95 9 0 7 8.42% 42 13 15 35.42%
10 PRO 17.83% 164 10 10 4 5.55% 144 104 22 72.62%
11 ROT 3.80% 35 1 0 1 2.57% 20 3 7 47.57%
Total 100.00% 920 39 14 30 3.92% 449 187 160 41.22%

4.3 PROCUREMENT
1) Send out the Quantity Clarification of Pipes, Fittings (Sep 20,2017)
2) Send out official RFQ of MAC (Sep 18,2017)
3) Arrange the Production of GRE Pipes, assist the Training of GRE Welder
4) Mill Audit of Stainless Steel Plate and MOVs proposed vendor

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 12 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

4.4 BULLET
TANKS:

4.4.1 Procurement
1) Follow up for PO for Flange/ forging and elbow.
2) MMHE-ATB will confirm the date on PO for CS/SS pipe next week.

4.4.2 Expediting
1) COP 2 - Separate meeting will be arranged to discuss between PRPC, CPP and
MMHE-ATB. Date from 2nd October 2017 onwards.
2) Official tax invoice for the 20% claim payment milestone to be submit to CPP finance
department next Tuesday.
3) Expedite on fabrication schedule delay and to catch up the delay.
4) Expedite on outstanding document from PRPC and MMHE-ATB.
5) MMHE-ATB to provide inspection document status.

4.5 CONSTRUCTION / COMMISSIONING

4.5.1 Construction
Piling work for butadiene vessel foundation (5220-V-101A/B/C/D), 3 piling rigs working.
Butadiene vessel foundation (5220-V-101A/B/C/D) piles PDA activities.
Butadiene vessel foundation (5220-V-101A/B/C/D) piles cutting works.
Butadiene vessel foundation (5220-V-101A/B/C/D) piles PIT activities.
Piling work for propylene vessel foundation (5220-V-104C), 1 piling rig working.
Piling work for propylene vessel foundation (5220-V-104A), 2 piling rigs working.
Propylene vessel foundation (5220-V-104A/C) piles PDA activities.
Propylene vessel foundation (5220-V-104A/C) piles cutting works.
Propylene vessel foundation (5220-V-104A/C) piles PIT activities.
Piling work for propylene vessel foundation (5220-V-104B/D), 2 piling rigs working.
Ethylene tank foundation (5220-T-101) trial pile lateral load test.
Piling work for ethylene tank foundation (5220-T-101), 1 piling rig working at beginning.
P30A area low point backfilling and levelling, 1 backhoe working.
ICP piles delivery to site for butadiene and propylene and ethylene piles driving.
TCF office area levelling and compaction.
TCF office foundation construction.
TCF office fabricated materials delivery.
Temporary road and drainage.
Precast valve pit for firefighting system.
Precast U-Ditch for drainage.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 13 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

SN. Work Plan Description Work Plan Plan Total to Remarks


Duration Complete Complete
1 Butadiene vessel piles driving 15th Sep -28th Sep 113 405/405
th th
2 Piles for butadiene vessel 15 Sep -28 Sep 40% 100%
delivery to site.
3 5220-V-101A/B/C/D Piles PDA 15th Sep -28th Sep 12 21/21
4 5220-V-101A/B/C/D Piles cut 20th Sep -28th Sep 160 160/405
5 5220-V-101A/B/C/D Piles PIT 21st Sep-28th Sep 32 32/81
6 Propylene vessel piles driving 15th Sep -28th Sep 157 200/320
th th
7 Piles for Propylene vessel 15 Sep -28 Sep 60% 80%
delivery to site.
8 Propylene vessel piles PDA 19th Sep -28th Sep 8 8/16
9 Propylene vessel piles cut 20th Sep -28th Sep 120 120/320
10 Ethylene tank trial pile PIT & 8th Sep -21st Sep 100% 100%
LLT test
11 Piles for ethylene vessel 15th Sep -28th Sep 17% 20%
delivery to site.
12 Ethylene tank pile driving 21st Sep-28th Sep 35 35/301
13 P30A area low point levelling 15th Sep -28th Sep 40% 100%
14 TCF office area levelling 15th Sep -28th Sep 20% 100%
th th
15 TCF office area compaction 15 Sep -28 Sep 50% 100%
16 TCF office fabrication 15th Sep -28th Sep 25% 100%
15th Sep -28th Sep
17 TCF office area foundation 100% 100%
15th Sep -28th Sep
18 TCF office area road and 100% 100%
drainage
19 Temporary road and drainage 15th Sep -28th Sep 15% 15%
th th
20 Precast valve pit 23 Sep -28 Sep 20% 20%
23th Sep -28th Sep
21 Precast U-Ditch 15% 15%

4.5.2 Commissioning
The mound effect the piling at east of butadiene vessel area need to be removed.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 14 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

5. AREA OF CONCERNS

5.1 PROJECT MANAGEMENT


Nil

5.2 ENGINEERING
Documents should be reviewed and feedback to CPP on time.
Provide the relevant document for reference as the agreement in last high-level meeting.
Civil work, such as FAR and Substation, will be constructed on 1 st Nov. We had start the
work based on experience, there is some risk for future design and construction.
Pleases feedback comments for PTA of refrigerant compressor as soon as possible.

5.3 PROCUREMENT
Nil

5.4 CONSTRUCTION / COMMISSIONING


P14 site workshop at the P30A area need to be dismantled and removed.

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx


Document Number
Rev. Page
Unit n
Project Package Originator Discipline Doc. Type Serial n
Serial n
0 15 / 15
RAPID P0030 CPP PMG WPR 0001 0020

WEEKLY PROGRESS REPORT NO.0020

6. MAJOR OUTSTANDING CORRESPONDENCE

Letter to PETRONAS
Nil

Letter from PETRONAS


Nil

7. ATTACHMENTS
7.1 Project overall progress
7.2 Engineering progress
7.3 The list of delay deliverables
7.4 Procurement progress
7.5 Subcontractor Matrix
7.6 Three Weeks look ahead schedule of site work
7.7 60 Days Concrete Demand Form
7.8 Site picture

Electronic Filename: RAPID-P0030-CPP-PMG-WPR-0001-0020_0.docx