Project : AVIC Mixed Development Project

Daily Diary : By Supervision Consultant, CECB. (Zone A)

Date : 11/03/2016

1.0 Weather:

Duration 06hrs 08hrs- 10hrs 12hrs 14hrs 16hrs 18hrs 22hrs 24hrs 02hrs 04hrs
_
08hrs 10hrs 12hrs 14hrs 16hrs 18hrs 20hrs 24hrs 02hrs 04hrs 06hrs
Weather S S S S S S LR
* S Sun Shine, HR-Heavy Rain, LR Light Rain, G- Gloomy, W Windy

2.0 Manpower:
A: Main contractor:

Category Nos. Category Nos. Category Nos.


Project manager 01 Masonry workers - Surveyor 01
Site Manager 02 R/f fabricators 33 Carpenters 51
Site Engineer 03 Mech. Workers 01 Welders 03
Tech. assistant 04 Operators 04 General workers 23
Foreman 12 Concreters 09 Survey Helper 01
B: Nominated sub-contractor:

Category Nos. Category Nos. Category Nos.


Kents officers 7 Kents workers 14

3.0 Machineries & Equipment:

Category Nos. Category Nos. Category Nos.


Tower crane 2 Breakers 0 Excavators 0
Mobile crane 0 Vibrators 0 Mixers 0
Bar bending machines 2 Pump car 1 water pumps 1
Bar cutting machines 2 Survey instruments 2 Jack Hammers 2
compressors 1 Welding plants 1

4.0 Inspection Carried out:

Location Element Works inspected By whom Status


TF at 5- Arch fin Reinforcement Mahinda,Situge Done
16/A-D
TF at 2-5/A- Slab Reinforcement Mahinda,Situge In progress
E ,Heshan
TF at 5- Slab Curing Situge In progress
16/A-D
TF at 32/A- Arch fin Formwork Situge In progress
D
TF at 2-5/A- Slab Conduit Asanka In progress
D
TF at 23A- Staircase Reinforcement Mahinda In progress
27/B-C landing
(+17.4)

1 of 2
Site Cube Crushing Heshan Done
laboratory

5.0 Drawings / Sketches referred for inspection:

Description Construction Shop Sketches/


Issue Drawings Log note
Transfer Level-Civil X X X
Column drawing-Civil X X

6.0 Effects of work (accidents, breakdown, delay etc...):

7.0 Details of Material used for construction:

Material Approved Brand Material Approved Brand


Reinforcement Plumbing
R/f Melwa/Lanwa Upvc puddle National
Concrete collar
Electrical
Conduits Polycon-pro(S-Lon)
Water proofing Accessories

8.0 Defects observed:

Location Element Type of defects Action taken Status


2/E Column Damaged conduits Kent Cant
rectify
4-5/B-B1 Beam Damaged one lighting Kent Cant
point rectify
9.0 Site Instruction / Defect Notification issued:

Description Instruction Ref No Remarks

10.0 Approved Method statements referred and received:


A: referred

B: received
Description Ref. No By whom
no

11.0 General Comments:

Prepared By: S.M.J.M.T.Situge Date: 13/03/2016