Project : AVIC Mixed Development Project

Daily Diary : By Supervision Consultant, CECB. (Zone A)

Date : 18/01/2016

1.0 Weather:

Duration 06hrs 08hrs- 10hrs 12hrs 14hrs 16hrs 18hrs 22hrs 24hrs 02hrs 04hrs
_
08hrs 10hrs 12hrs 14hrs 16hrs 18hrs 20hrs 24hrs 02hrs 04hrs 06hrs
Weather S S S S S S
* S Sun Shine, HR-Heavy Rain, LR Light Rain, G- Gloomy, W Windy

2.0 Manpower:
A: Main contractor:

Category Nos. Category Nos. Category Nos.


Project manager 1 Masonry workers 7 Surveyor 1
Site Manager 1 R/f fabricators 44 Carpenters 59
Site Engineer 2 Mech. Workers 1 Welders 3
Tech. assistant 4 Operators 4 General workers 19
Foreman 10 Concreters 6 Survey Helper 03
B: Nominated sub-contractor:

Category Nos. Category Nos. Category Nos.

3.0 Machineries & Equipment:

Category Nos. Category Nos. Category Nos.


Tower crane 2 Breakers 0 Excavators 0
Mobile crane 0 Vibrators 0 Mixers 0
Bar bending machines 2 Pump car 1 water pumps 1
Bar cutting machines 2 Survey instruments 2 Jack Hammers 2
compressors 1 Welding plants 1

4.0 Inspection Carried out:

Location Element Works inspected By whom Status


L04 at grid 2- Beam r/f work and f/w Mahinda Inprogress
5/A-D inspected Lasitha
Sampatha
L04 at grid 7- Beam Scaffolding erection Lasitha Inprogress
10/A-D & slab formwork Sampath
L03 at grid Columns f/w inspection Mahinda Inprogress
31A-32/A-B
L03 at grid Columns Concrete pouring Mahinda Inprogress
31A-32/A-B supervision Lasitha
BS at grid D- Basement Water proofing Mahinda Completed
E/32-29 outer wall
North North Inspected electrical Asanka Inprogress
boundary at boundary earthling system(28
grid ( 7-27) points)

1 of 2
Tower T2 Lift wall f/w fixing Lasitha Inprogress
Sampath
L03-L04 at Column Concrete pouring Sampath Completed
grid 31A-
A,B/32-A,B

5.0 Drawings / Sketches referred for inspection:

Description Construction Shop Sketches/


Issue Drawings Log note
Podium Level -Civil X X
Transfer Level-Civil X X

6.0 Effects of work (accidents, breakdown, delay etc...):

7.0 Details of Material used for construction:

Material Status of Approval Reference No


R/F (Lanwa) Approved CSCEC/AVIC/REPORT/265
Water proofing (Volttex DS) Approved CSCEC/AVIC/PLAN/021

8.0 Defects observed:

Location Element Type of defects Action taken Status


BS at grid Retaining Lap length of Water Instructed to Not yet
E-D/32 wall proofing membrane was rectify
not according to approved
method of statement

9.0 Site Instruction / Defect Notification issued:

Description Instruction Ref No Remarks

10.0 Approved Method statements referred and received:


A: referred
Water proofing method statement WF-66

B: received

11.0 General Comments:

Prepared By: S.M.J.M.T.Situge Date: 19/01/2016


2 of 2