PROJECT CHARTER....................................................................................................................2
ASSUMPTIONS, CONSTRAINTS AND RISKS.............................................................................2
ASSUMPTIONS: ................................................................................................................................................2
CONSTRAINTS: ................................................................................................................................................3
RISKS: ...........................................................................................................................................................3
APPROACH...................................................................................................................................4
RESOURCES, ROLES AND RESPONSIBILITIES........................................................................5
DELIVERABLES............................................................................................................................7
PHASE I..........................................................................................................................................................7
PHASE II.........................................................................................................................................................7
PHASE III........................................................................................................................................................7
PHASE IV.......................................................................................................................................................7
PHASE V.........................................................................................................................................................7
PHASE VI.......................................................................................................................................................7
PHASE VII......................................................................................................................................................8
PROJECT CLOSE DOWN.....................................................................................................................................8
WORK BREAK DOWN STRUCTURE:..........................................................................................9
......................................................................................................................................................11
RISK MANAGEMENT PLAN........................................................................................................12
PROJECT REPORTING STRATEGY..........................................................................................14
PROJECT BOARD:...........................................................................................................................................14
PROJECT TEAM:.............................................................................................................................................15
AUTHORIZE PROJECT REPORT:.........................................................................................................................15
PROJECT / STAGE LOG / DIARY:.......................................................................................................................15
CHECKPOINT REPORT:.....................................................................................................................................15
ISSUES LOG:..................................................................................................................................................15
PROJECT ISSUES REPORT:.................................................................................................................................15
PROJECT RISK LOG:.......................................................................................................................................16
EXCEPTION REPORT:.......................................................................................................................................16
END STAGE/ PHASE REPORT:...........................................................................................................................16
PROJECT PROGRESS REPORT:...........................................................................................................................16
END PROJECT REPORT:...................................................................................................................................16
CUSTOMER ACCEPTANCE REPORT:....................................................................................................................16
AUTHORIZE CLOSURE:....................................................................................................................................16
CRITICAL REVIEW......................................................................................................................17
REFERENCE LIST:......................................................................................................................21
Project Charter
Risks:
The following list provides an overview of the potential risk associated with this
project.
• The organization is not able to provide all funding at once before the start
of project and funds will be available over the period of two years that can
slow the progress of project (will result in project delays according to the
time line define in project plan).
• The staff is not happy with the changes and a resistance can be shown by
them to accept the new infrastructure.
• The political landscape may be changed after the next three years and
after this time there is no guarantee that the existing ownership /
management of the organization will be same as it is now.
• The project can face unseen issues as during the progress of project and
have to be resolved
• The Natural disasters or acts of war can be happened during the curse of
project completion.
• The project can face security issues like data theft, virus attacks and
system hacking.
Approach
This project is divided into different phases that will be completed within the time
limit of two years. During these phases the organizations new Network
infrastructure, Hardware Infrastructure and Information Management System will
be implemented. The following is the brief description of work carried out during
the different phases of this project.
Phase I:
The first phase in this project will be analysis phase. A statement of business
objectives will be the outcome of this analysis process. The next major tasks in
this phase is recruiting the project team and present a final project plan to Project
Board for the official acceptance for the start of the project.
Phase II:
The Phase II is design phase that will start with review of current system design.
A detailed proposed design will be the outcome of this phase. The software,
hardware and network proposed design will be presented to Project Board for the
official acceptance.
Phase III:
The first major task in this phase is developing Information Management software
with the help of 3rd party contractor (Software Developers). Along with this the
Head Quarter is the first site where the new network and hardware infrastructure
will be implemented. All other sites (13 Public Access Offices and Remote Users)
will be connected to this main site to perform their daily tasks. The new system
will be rolled out parallel to the old system that will not affect the daily business
routine as old system will work until the completion of all phases.
Phase IV:
As on the completion of phase III the Head Quarter staff will get their training on
the newly implemented system and IT department will responsible of this task.
The network department will start implementing network changes to first four
sites (Public Access Offices) and then IT department will join them to upgrade the
hardware / software.
Phase V:
After the complete testing of network, hardware and software in-between HQ to 4
Sites (Public Access Offices) the Phase V will be started. The IT department
conduct training workshop for the Public Access Offices staff on newly
implemented infrastructure. As the training is going along the network
department will move on to next 4 sites for the implementation of new network
resources. The IT department will join them to complete their part of hardware
and software changes.
Phase VI:
In this phase the approach will remain same as in phase V and all task will be
carried out in similar fashion on last 5 sites (Public Access Offices).
Phase VII:
In the last phase the final testing will be performed and project documentation will
be finalized. The project close will be done and that will complete the all tasks of
this project plan.
Project Manager:
• Plan and Execute Project According to Project Plan
• Member of the Steering Committee (Change Control Board)
• Main Contact Person for Contactors
• Main Contact Person for Vendors
• Monitor the Project Progress at all Phases of Project with Accordance to
Project Budget
• Provide Guidance for Project Goal and Objectives to all Team Members
• Main Contact Person For Problem Resolution
Network Administrator:
• Responsible for Design and Implementation of Network Infrastructure of all
Organization (HQ and 13 Public Access Offices).
• Take care of all Technical issues during Project Implementation
• Responsible for Network Technical Support After Implementation
• Main Contact Person for all Networking Problems
• Member of the Steering Committee (Change Control Board)
• Make sure that Network Infrastructure fulfill all Business Needs( Fast,
Secure, Reliable and Fault Tolerance)
• Manage the IT Support Help Desk for whole organization (HQ and 13
Public Access Offices)
• Main Contact Person for Software Developers( 3rd Party Contactors)
• Take care of all Technical issues during Project Implementation
• Main Contact Person for all IT Problems (PC, Cabling, Printing, Remote
Access and Software issues)
• Member of the Steering Committee (Change Control Board)
• Managing / Plan the Training of all Staff Members for New Hardware
Infrastructure and Information Management Software
Deliverables
Phase I
• Statement of Business Objectives
• Project Team On Board
• Approved Project Plan
Phase II
• Current System Design Review Document
• Proposed System Design Document
Phase III
Phase IV
• Training workshop for HQ Staff and One Public Access Office.
• Network Infrastructure Implementation at First 4 sites
• Hardware Up gradation at First 4 sites
• Information Management system Implementation at First 4 sites
• Testing of all new implemented Infrastructure with HQ
Phase V
• Training workshop for staff from Phase II sites
• Network Infrastructure Implementation at 4 sites
• Hardware Up gradation at 4 sites
• Information Management system Implementation at 4 sites
• Testing of all new implemented Infrastructure with HQ
Phase VI
• Training workshop for staff from phase III sites
• Network Infrastructure Implementation at last 4 sites
• Hardware Up gradation at last 4 sites
• Information Management system Implementation at last 4 sites
• Testing of all new implemented Infrastructure with HQ
Phase VII
• Training workshop for staff from phase IV
• Final System Testing report
• Final user acceptance report
• Final operational acceptance report
Phase II Conduct
Phase VI Final
(Design) Training Documentation
Application
Project Development
Launch Project Post-
Current System Desktop Conduct Conduct
Mortem
Design Review PC Rollout Training Training
Link
Initial Installation
Review Conduct
Software Desktop Training
Proposed Rollout Desktop PC Rollout
System design Desktop PC Rollout
Acquire PC Rollout
Resources
Data Software Final
Review Migration Software Rollout System
Proposed Software Rollout Testing
Project System design Rollout
Planning
Parallel Data
Testing Data Migration
Approved & Data Migration User
Go-Ahead Migration Acceptance
Parallel
Parallel Testing
Approved & Parallel Testing
Go-Ahead Testing
Risk Management Plan
A Risk Management Plan is a key document in project plan as its outline an
overall approach to risk management. The document address the key factor like
awareness of significant risks, effective planning of resources, recognition of
accountability / responsibilities, identification of new opportunities and action plan
for the effective management of identified risks. The following is a list of identified
risks with information like Title, Risk Level, Likelihood and Mitigation Strategy.
(OGC, 2009)
Project Board:
The Project Board is responsible for the overall monitoring of the project from
start to end. The board members are all top level officials of all departments
taking part in the current implementation. All project activities are authorized and
review by Project Board before implementation. The Project Board meeting will
be held at the end of first phase to provide Authorized Start of the project. Then
after completion of every phase a progress check / review / change control
meeting will be held to discuss the current completed phase and will give go
ahead to start the new phase of the project.
Project Board
Network IT Support /
HR Manager
Administrator Training Manager
Project Team:
The Project team is act as a second tear to handle the project implementation.
The team is based on the members that are directly involved in all the phases of
project and will held meetings at regular intervals to check project progress. The
end report of this meeting will be the input to the Project Board meeting.
Project Team
Checkpoint Report:
This report records progress made on the project on weekly basis. The report is
used by department managers and showed in project team meeting.
Issues Log:
The log document will be used to record daily project issues and will show correct
status of project.
Exception Report:
The report will be produced when an exception is produced related to the cost or
timescale for an approved project phase. The cost or timescale will exceed the
forecasted figures and will not meet the tolerance levels set by the Project Board.
This will be used by project manager to inform the Project Board and to obtain
direction from them.
Authorize Closure:
All members of Project Board will sign a project closure document that states the
official close down of project.
Critical Review
System Development Lifecycle (SDLC) is a conceptual model that describes a
stage approach to manage project. It act as a helping tool with the following
stages like identify problems with existing systems , provide understanding how
business needs can be fulfill, based on that proposed new solution, design the
system , implement the system , test the system , deliver the system and at last
stage maintain the system.
Who, What,
Why When, Where
Preliminary Logical
Analysis
Investigation Design
How
How
Physical
Implementation Maintenance
Design
Waterfall Model:
The waterfall model is based on a sequential approach where output of an each
stage becomes the input for the next stage. From this classic approach most of
development approaches are derived from. The following is a list of some key
advantages and disadvantages of this model (DePaul, 2009)
Advantages Disadvantages
• Milestones are Clearly defined • The opportunity for preview of
• Easy to implement / understand the system is little for customers
• Suitable under the environment • Requirements specification must
where quality is preferred then be well defined
cost • Less flexible in terms of
• Management Control (track, deliverables for each phase
staff, plan) is easy to implement • Problem solving is not easy and
can give false view of project
progress
Waterfall Model (DePaul, 2009)
V-Shape Model:
This model is a variation of waterfall model which is designed for the validation
and verification of the product during the all phases of project. In this approach
particular development phase is planed in parallel with corresponding testing
phase. The requirements are well defined and known upfront. Best
implementation of this approach is when high system reliability is required like
hospital patient control software.
Taylor & Francis (2006), Project Managing E-Learning, [Online] Available From:
http://www.routledge.com/textbooks/9780415772204/resources/Charter_Templat
e.doc. [Accessed: 10/11/2009]