Method Statement For Installation

of Electrical DB, SMDB and MDB


Panelboards

Method Statement For Installation of DB, SMDB and MDB.

1. Introduction and Scope


This statement is written for the purpose of establishing method and procedures for the
Installation of DB, SMDB and MDB.
2. Applicable Projects Specification
Section: SWITCHBOARD DISTRIBUTION PANELS AND MCCs.
Division: INSTALLATION
Sub Division: Subdivision

3. Location of Activity
Low Voltage Room and Electrical Rooms

4. Health and Safety Hazards


Specific safety measures have to follow as applicable, and all the safety measures are
covered separately in the project safety plan.
5. Operation
1. Materials: Materials used will be as per the material submittal approved by the
engineer and will be as per the approved drawings in coordination with other services.
2. Storage / Protection: DB, SMDB, and MDB and Accessories shall be unloaded with
care to avoid any damages. If they are shipped in packs or pallets, each pack of pallet
shall be lifted individually with suitable lifting equipment. Every precaution shall be
taken to preserve their cleanliness before installation. Store in accordance with
manufacturers instructions, Properly protected from construction activities and
weather conditions.
3. Installation:
a. To make sure that the entire installation is in conformance and in accordance with
the design intent of the project for the Electrical and Low Voltage System in addition
to the specification and as per approved shop drawings and comply.
b. with local and International Standards.
c. All the switchboards shall be fabricated at the manufacturers works.
d. Before beginning installation in any area, examine all parts of the adjoining works
into which applicable work is to be placed. Should any condition be found which will
prevent the proper execution of the work, installation shall not proceed in that area
until such conditions are corrected by the contractor.
e. Fix all equipment independently of wiring system. Use cadmium of zinc
electroplated bolts, nuts, washers and screw.
f. Mount single DB at 1800mm from finish floor level to top of equipment, unless
shown otherwise on drawing / schedules.
g. Ensures that clearance in front of switchgear is not less than 1m, or as indicated.
h. Number terminals, cables and component parts to correspond with manufacturer
have certified drawings.
i. Terminate PVC, SWA PVC and MICS cables inside enclosure by securing cables to
switchboards with gland bracket; and enclosure with glanding plates or fabricated
steel extension boxes.
j. For flush installation, DBs all conductors shall terminate behind the board in an
adaptable box. For surface mounting, trunking shall be fixed between the board and
ceiling or floor level, or conduit run directly into Trunking which prevent correct
installation of the Trunking lid. Adequate earth continuity shall be made between the
various components.
6. Responsibilities
1. Project Manager
a. To ensure that all the preparation and application works are carried out according to
the Contract Specification.
b. To ensure that the progressing of works is carried out according to the planned
program and as per the approved method statement.
c. To ensure that all equipment and material required executing the work are available
according to the planned Construction Programme.
d. To co-ordinate with the Main Contractor, MEP co-coordinator, and Safety Officer for
a safe and proper execution of the works.
2. Site Engineer
a. To ensure that the works are carried out according to the Contract Specifications
approved method statement.
b. To provide all necessary information and distribute responsibilities to his
construction team.
c. To monitor the progress of work in relation with the work program and to report to
the Project Manager.
d. To co-ordinate with the safety officer and to ensure that the works are carried out in
safe practicing methods.
3. Foreman
a. The foreman will carry out his duties by maintaining continuous coordination with
the site engineer on daily basis, and ensure proper distribution of the workforce in
the required and planned locations.
b. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
c. To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
d. To ensure that the daily work is progressing as planned and advise the Site
Engineer for any requirement of the additional resources.
e. To control disposal of waste materials to the instructions received from the site
engineer.
f. To ensure full coordination with the safety officer to maintain safe working and
proper house keeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
g. After completion of works, Foreman shall inform the site engineer for inspection of
works.
h. Distribution and the control of materials shall be monitored by foreman and
storekeeper.
4. Safety Engineer
a. Ensure the implementation of all the safety measures in accordance with the HSE
plan and everybody aware of it for its proper implementation.
b. Ensure all the implemented safety measures are adequate to maintain safe working
on the site.
c. Inspect all the site activities and train the person to prevent accidents and its
proper implementation.
d. Ensure that the site is maintained clean and tidy.
7. Manpower Required
Charge hand and Experienced Technicians

8. Materials Requirements
DB, SMDB, MDB and accessories

9. Equipment Requirement
The equipment that will be engaged for Installation of DB, SMDB and MDB works will be
as follows:
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool
10. Health and Safety
Strictly follow as per the manufacturers Health and Safety recommendations for
handling and use of the materials. Ensure all involved personal shall be aware of the
same.

11. Supporting Documentation


This method Statement should be read in conjunction with the below referenced
documentations.
ITP for Anti termite Treatment
Insulation Resistance and continuity Test Report
12. Distribution
Copy of this method statement shall be issued to the following for information/ action/
comments:
1. Project Manager
2. Site Engineer
3. Foremen
13. Inspection And Test Plan For Installation of DB,
SMDB and MDB
ITP Verifying /
Inspection Type of Reference Testing Requirement/
Clause Control Data
Description Inspection Document Acceptance Criteria
No Forms
Design drawings
Design and Review of Design Authorities
1 All the Drawings
Drawings Documents Drawings Departments
Requirements.
Approved Should be as per the
Material Review of Submittals
2 Drawing and approved drawing and
Approval Documents Documents
Specification Specification
Proper location
Check Visual, Approved Approved
installation, termination
3 Switchgear Insulation Method Drawing Method
etc Material should
installation and Resistance Statement Statement
have minimum status
cable and Continuity of NO Objection with
terminations. Test Report comments
Visual,
Request for Insulation No obstructions Level,
Approved Approved
4 inspection of Resistance and it is in proper
Drawing Drawings
works and Continuity position
Test report.