Vous êtes sur la page 1sur 9

Eng&ering rrtd Process Economics 2(!

911) 259-261 259


@Elsevier Scientific Publishing Company, Amsterdam -- Printed in The Netherlands

THE PROCESS STEP SCORING METHOD FOR MAKING QUICK CAPITAL ESTIMATES

J.H. Taylor

ICI Ltd., Mond Division, The Heath, Runcom, Cheshire (U.K.)

Abstract

Preliminary screening of the many alternative The method is based on a system in which a
proposals that arise in R & D requires economic complexity score accounting for factors such
assessment methods that are quick, can be as throughput, corrosion problems and reaction
carried out with a minimum of information time is estimated for each process step, and
and yet are reasonably reliable. The Process these are combined to give an overall costliness
Step Scoring method described here requires index. The capital is then derived from a rela-
only outline information about the process tionship between this index, capacity and
and has an accuracy within 95% confidence capital cost which was based on experience ot
limits of +36% to -26% which is good enough 45 recent projects in the U.K., covering a
for many preliminary evaluations. broad spectrum of plant sizes and technology.

INTRODUCTION

Preliminary screening of the many alternative their associated capital costs. The dissemination
proposals that arise in R & D requires capital of detailed capital and process information, even
estimating methods that are quick, can be within a company, is normally restricted for
carried out with a minimum of information security reasons and the movement of staff
and yet are reasonably reliable. For most situa- poses problems in identifying a source of the
tions the traditional engineering methods of necessary expertise. There is therefore a need
estimating capital are too cumbersome, since for a quick, yet reasonably reliable, estimating
to achieve a reliable result, detailed flowsheeting method which incorporates the knowledge of
and equipment sizing of all the main plant a broad spectrum of achieved costs on past
items is required, necessitating considerable projects and yet can be used by relatively inex-
chemical engineering effort. A more practical perienced people. The Process Step Scoring
way of making a quick capital estimate for method described here aims to fulfil this need.
research decision purposes at an eady stage is The basic principle of the Process Step
to seek out a similar process of known capital Scoring method is the postulation that the
cost and then make appropriate modifications capital cost of a plant is related to a costhness
for the differences in detail using various rules index (I), expressing the complexity and
of thumb. This direct analogy approach can nature of the chemistry involved in the process,
be very effective but it requires experienced and to its size by a relationship of the form:
staff who have extensive and detailed knowledge Capital cost = constant X costliness index X (capacity)P
of a wide variety of chemical processes and where p is a fractional power.
The costliness Index, which is a unique func- out a regression analysis on 45 U.K. projects
tion for a particular process, is determined by completed during the past 12 years. These
the expression: cover a broad spectrum of the types of process
N encountered in the Chemical Industry. They
I = c cl.39 (1) include processes for organic solvents, inter-
mediates and monomers, complex biologically
where IVis the number of significant process active compounds, polymeric materials and
steps (e.g. filter, react, distill and S is a com- inorganic materials. Most of the common chem-
plexity score determined for each process step ical reactions are covered, for example, chlorina-
to take account of factors such as throughput, tion, fluorination, oxidation, hydrolysis, amina-
materials of construction, reaction time, temper- tion, hydrogenation, dimerisation, addition and
ature, pressure and multistreaming. Costliness cracking reactions. Plant sizes are evenly dis-
indexes normally range from about 10 for a tributed over the range 300 to 250 000 ton/year.
plant to make a simple chemical such as formal- No extrapolations on the basis of assumed
dehyde up to 200 or more for a plant for a scale-up power factors were made; in fact an
complex drug or pesticide. important finding from the work has been that
In principle the Process Step Scoring meth- the traditional 0.6 power factor for scale-up is
od relates capital cost directly to the chemistry too high for correlations of this type. (This is
involved in the process without considering to be discussed in a subsequent communication.)
engineering aspects on the type of equipment
required. DESCRIPTION
In this respect it differs from other published
quick costing methods [ l-51.Another tignifi- The method 1sexplained below step-by-step
cant feature is that each process step is s:ored and is then exemplified by a worked sample.
independently for throughput, corrosion etc.
The relationship between capital, costliness Step 1 /IDefine the process to be by a
index and plant size was derived by carrying diagram like the one in Fig.

5 (WCYCLE3)

t 4t

AQ SOLN OF BY PRODUCTS
(EFFLLENT-TO WORL(S
DISPOSAL NIT)

t
C~IMPOUNDC~

Fig. 1. Hypothetical flow diagram for the reaction:


A+B-rCinAsohrentS,
261

The diagram should show the mam process flow and not to the equipment that is neces-
steps, relative throughputs (ton/ton product), sary. The fact, for example, that sevoral reac-
temperatures, pressures, materials of construc- tions or unit operations could be done in the
tion, reaction times, multi-streaming and any same vessel is of no significance from the point
special conditions such as explosion hazards. of view of this method; similarly the need in
some continuous processes for several reactors
Step 2. List the significant process steps. in series is ignored. This is because the method
The following unit operations/unit processes relates the number of process steps/complexity
would usually be regarded as significant pro- directly to the capital costs for the optimum
cess steps: process at the scale concerned. Therefore, it is
- Chemical reactions, such as chlorination, most important when listing the significant
oxidation, nitration. process steps to disassociate ones mind com-
- Neutralise or acidify (but not minor pH ad- pletely from the equipment that might be used.
justment). If any special process steps not covered
- Storage/handling of a raw material, product, above are encountered, such as electrolysis,
by-product, intermediate or recycle stream. fibre spinning and extrusion, these should be
Also effluents when these are not assumed costed separately either by direct analogy or
to be discharged directly to outside the an engineering estimate.
battery limits (e.g. to river or Works effluent Step 3. Score each significant process step on
disposal system). throughput, materials of construction, temper-
- Filter, screen or centrifuge. ature, pressure, multi-streaming, reaction (or
- Distil, evaporate, fractionate or strip. storage) time and any special conditions, ac-
- Crystallise or precipitate. cording to Table 1.
- Formulate. (i) Relative throughput: This is the totai
- Compress. weight flow into the process step per unit
-- Vaporise. weight of final product. Internal recycles
- Dry or spray dry. such as those in stills or absorbers are
- Mill or grind. ignored. The throughput score i I dsuatly
- Scrub or absorb. dominant compared to those for the other
- Pack into special small containers (not sacks factors.
or drums). (ii) Materials of construction: For a single
- Dissolve, mix, slurry or blend when required process step there can be several construc-
as a specific pre- or post-treatment, e.g. tion materials involved (e.g. ELMS vessel
dissolving before spray drying. (But not with Ti stirrer). The score is based on the
when an integral part of another process dominant material (ELMS). Knowledge
step such as, say, solvent extraction). of the precise materials of construction
- Quench (but not normal cooling of a reac- required is not necessary; the score can be
tion mixture). based on a subjective judgement as to the
- Condense when used to separate a compo- magnitude of the corrosion problem e.g.
nent from a gaseous stream containing inerts no problem - mild steel, score 0; major
(but not for normal condensation in stills, problem - titanium, score 3.
quenches or reactors). (iii) Temperature: Score based on the temper-
- Phase separation of a reaction mixture (but ature extreme.
not when part of a still or extraction system). (iv) Pressure: Score based on the pressure ex-
- Extract or leach. treme. With gas phase reactions, elevated
The si,gnificant process step refers to the pressures up to about 50 atms are assumed
operation that is performed on the material to have no effect on the cost of a process
TABLE 1

Scoring for complexity of signiticant process steps


--- -- .---.. - . -- . -
Score
--~-
-3 -2 -1 0 3 4 5 6 I 8 9
-___
Relative thm * put (t/t product) 0.2 0.35 0.6 r 1.7 3 5 8 14 23 40 67 110
Reaction time in h (reaction, crystallisation, etc) 3 5 9 14 25 42 69 120
Storage time in weeks 2 8
Temperature extreme CC) Uin 20 -25 -7.5 -125
Temperature extreme CC) Max 500 1100 1700 2330
Pressure extreme (atm) Uin 0.1 0.01
Pressure extreme (atm) Max 100 50 200 700 !SOO
Materials of construction usb SSc, Keebusb ELMSf Titanium Precious
RLusd,EbLUSe, Hastelloy metals
PVC Nickel Tantallum
Uonel
PbLUSg
Multistreaming. No. of streams 2 s 11

Special conditions:
(a! E*p!csic!!, da-tI odom o: tcxicity prblems.
, Stoic 1 if a major problem.
(b) Reactions in tluid beds. Score 1.

Conversion of score to costliness index

(S)
scorn -3 -2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 IS 16
Cosfline=? i!+*: (I) a4 0.6 0.8 1 1.3 1.7 2.2 2.8 3.7 4.8 6.3 8.1 10.6 14 18 23 30 39 51 66
___--- ____________~_- _ ---- ~~ ---- ---__ ----- ___.. -
oFor liquid phase reactions only. All others swe = 0. b = Mild steel. cSS = Stainless steel. dRLUS = Rubber lined mild steel. eEbLMS = Ebonite lined mild steel. :v~LUS =
US
Znamel lined mild steel. @bLUS = Lead Lined mild steel.
step: this is because the increased wall
thickness is offset by reduced vessel size.
Multistreaming: This might be considered
necessary for reasons such as poor reliabil-
ity, uncertainty of market growth or
limitations on equipment size.
Reaction time/storage time: These have
different scales. The reaction time scale
refers to liquid phase process steps. The
cost of gas phase reactions are usually
effected only slightly by the residence
time; no scoring scale is therefore in-
cluded for them.
(vii) Special conditions: These could include
(a) explosion, odour, dust or toxicity
problems, (b) fractionation of materials
of similar boiling points, (c) reactions in
fluid bed+, (d) film evaporation and (e)
tight specification. At present these are
assessed on an empirical basis.

Step 4. Convert the total score for each sig-


nificant process step into a costliness index
using the conversion table (at foot of Table 1).
For a single process step the costliness index
(I) is given by:
I = 1.3s

where S is the total score for the step. Thus a

DESIGN CAPACITY IN TON / YEAR

Fig. 2. A graph of eq. 2.


includes storage) that would be needed for a of a few hundred ton/year capacity making
completely new plant in the U.K. built up non-complex chemicals, use can frequently
from the ground. The capacity is the design be made of an existing structure. This
capacity, not the achieved capacity. would reduce the capital by around 25%.
An alternative direct analogy type of ap- With small plants, further savings are
proach not employing the above derived rela- possible by using some existing equipment,
tionship is to compare the costliness index (I) manhandling of materials, less ngorous
with that (I,) of a similar process of known standards and general improvisation. Ob-
capital cost (C,) and capacity (A I); the viously the saving possible will vary con-
required capital cost (C) bging given by: siderably but a typical figure could be
taken as 50% (including structure).
(3) Cd) Plants overseas: Capital costs for plants
overseds can be substantially higher or
This has the advantage that it eliminates the lower than those in the U.K. and the cur-
personal factor in assessing the significant rent exchange rate is not therefore neces-
process steps - one of the main difficulties in sarily appropriate. Location indices have
applying the method. been discussed in this Journal.
Other possible defects in the method are Warning on sca~eupr: The costliness index, I,
also avoided, providing a closely similar process can change on scale-up as a result of more multi-
is used for the comparison. streaming, or the addition of more process
steps (e.g. to recover solvents). If I does change,
Step 7. Make allowances, where necessary, to extrapolation of the cost to other scales cannot
cover inflation, off-site facilities and site devel- be achieved by simple use of the scale exponent
opment, use of existing structure and construc- but I must be recalculated for the new stakes.
tion of plants overseas.
(a) Inflation: Appropriate infiation from Jan EXAMPLE
77 should be added using suitabie indices
such as the one published regularly in this Suppose it is required to cost the process
Jouma!. outlined in Fig. 1, for single stream plants of
tb) Off-sites and site development: Off-site 2000 and 8000 ton/year and for an 8000 ton/
facilities includes for exampie workshops, year plant with a two stream reaction stage:
supply of basic services and effluent treat- (a) Single stream plant of 2000 ton/year:
ment. Site development includes for exam- Costliness index for 2000 ton/year plant = 2 1,
ple roads, railways and drainage. The extra asshown in Table 2.
capital expenditure required for these Using eq. 2 (or Fig. 2) the battery limits
could u rider some circumstances add 50% capital for a 2000 ton/year plant at Jan 77
or more to the capital. On the other hand pricts is
it could be virtually zero if the plant is =21X42x1.31 (1000 &)
located on a suitable developed Works site =2.1.16x 10
with all the services available in ample sup- Adding 30% as a notional allowance to cover
ply. It is suggested that in preliminary esti- off-sites and site development gives f. 1.50 X lo6
mates when there are usual o indica- (Jan 77).
tions on the type of site that would be (b) Single stream plant of 8000 ton/year:
used, a notional allowance of 30% should The costliness index is 2 1 as for the 2000 ton/
be added.to cover off-sites and site devel- year plant.
opme..:. The battery limits capital = 21 X 42 X 2.25
Cc) Use of existmg structure: With small plants . =E 1.98X 10b
TABLE 2

Calculation
_-__ of costliness index for plocess in Fig. 1
Throughput MofC Rractionl Pressure/ Other Total
storage temp. score index

0 1 (toxic) 1 1.3
0 0 1 1.3
0 0 3 2.2
0 0 3% 2.5
0 0 -I 0.8

1 0 7 6.3
0 0 4 2.8
0 0 0 1.0
0 0 4 2.8
21.0

Adding 30% for off-sites, the capital = about 5 process steps (N.B. the more steps
.E 2.57 X 10t (Jan 77) the better).
(c) 8000 ton/year plant with twin <dream (ii) Modification or extension of axisting
reaction stage: plants.
In this case the costliness index needs to be (iii) Fully batch operated plants of abnormally
recalculated to allow for twin streaming on the high capacity (3000 ton/year or more).
reaction s$ge. (iv) FuHy continuous plants of abnormally
Assume. that only the reaction stage is two low capacity (500 ton/year or less).
streamed. (vl Plants involving appreciable solids handling
Score for single stream reaction = 7, costliness on the large scale (5000 + ton/year).
index 6.3 (vi) Plants involving special operations such as
Score for two stream reaction = 8, costliness electrolysis, fibre spinning, extrusion, when
index 8.1 these are likely to represent a substantial
Increase in costliness index = 1.8 proportion of the cost.
.. Modified costliness index = 1.8+ 2 1.O = 2Z.8
Battery limits capital =22.8X42x2.Z5
ACCURACY
=g2.15x 106
Adding 30% for off-sites, the capital =
E 2.80 X lo6 (Jan 77) The accuracy of the method, for a specified
process definition, determined from the regres-
sion analysis, is as follows:
LIMITATIONS
Y5% Confidence limits +36% and -26%
Standard deviation 1.5%
The method can be used for complete new
plants of capacities ranging from 300 to This order of accuracy is generally adequate
250 000 ton/year. However, at the current for the preliminary screening of R & D projects.
level of development, It cannot be used for the If, for example, there are several proposed
following: routes to a new compound, the method can be
(i) Very simple plants involving less than used to reduce these to a short list of two
which can then be evaluated in depth using not significant. Also, surprisingly, the improved
engineering type estimating methods. accuracy was obtained by giving more weight
In the early stages of an R & D project when to storage/handling and less to reactions.
the process is poorly defined the Process Step The main source of error in estimating the
Scoring method can in many cases give a more capital for a specified plant is likely to arise
reliable result than engineering type estimates. from personal differences as to what constitutes
This is because cursory assessment of the plant a significant process step. Though the list of
equipment required, often grossly underesti- these given on page 261 is intended to be as fbll
mates the complexity of the process, thus lead- as possible, it is recognised that difficulties can
ing to an estimated cost which is much too low. still arise. However, unless the plant being con-
Errors of thi? type are less likely with the Pro- sidered only in rolves a few process steps, this
cess Step Scoring method, because costs for a personal facto] need not represent a sizeable
specified process step are determined by corre- error.
lating directly with costs achieved in practice
for steps of analogous complexity - thus anal- SHORT-CUT METHODS
ysis of the fine details of the step are already
built into the method. It is also noteworthy Sometimes there is not sufficient time or the
that preliminary engineering type estimates data available to apply the Process Step Scoring
are essentially based on analogy, in that usually method as described. Accordingly, relationships
20% of the cost (the main plant equipment have been derived for capital cost as a function
items (it rlgorosly estimated and then the Of:

remaining 80% (foundations, structure, instru- (i) the number of reactions, and
ment, piping, design etc.) is estimated by mul- (ii) the number of significant process steps.
tiplying by a factor based on experience. These short-cut but cruder relationships are
Though the Process Step Scoring method outlined below:
gives reasonably satisfactory results for com- (i) Number of reactions:
plete plants, it can lead to an answer which is Capital in 1000 E
grossly in error (e.g. by a factor of 2), if ap- - - = 1120 (Capacity in 1000 ton) (6)
Number of reactions
plied to a single process step. The factorial
type of engineering methods can also give 95% Confidence limits +155%
similarly inaccurate results when applied to Standard deviation = 52%
a single step and deficiency in this respect
should not be considered to invalidate the N.B. Subsidiary reactions such as pH adjust-
ment are not taken as reactions.
method. Satisfactory results are obtained
fii) Number of significant process steps
with complete plants primarily because of
the swings and roundabouts effect. Accuracy Capital in 1000 f
- = 115 (Capacity in 1000 tonjo* (7)
will tend to be best for plants with a large Number of process steps
number of process steps. 95% Confidence limits +96% and -49%
In its present form the Process Step Scoring
Standard deviation = 44%
method assumes that all process steps are equal
in cost for given throughputs, temperatures In some assessments of R & D projects an
etc. An attempt has been made to improve indication of the minimum likry capital cost
accuracy by employing different . ghting is all that is necessary. In these circumstances
factors with respect to reactions, separations the short-cut relationships can prove useful.
and storage/handling. The improvement in For example, say it was known that a new
accuracy obtained was only marginal (standard product requiring 4 reactions stages could only
deviation from 15.2% to 14.1%), and probably be viable if the capital cost (battery limits) for
a i 000 ton/yearpiantWBS iP,:ISthan E 1.5 mil- 3 Wilson, G.T., 1971. Capital lnrestment for Chemical Plant,
lion. From eq. 6, the most likely capital cost British Chemical Engineering and Process Technology,
16(10): 931.
is f. 4.5 million and from the 55% confidence 4 Allen, D.H. and Page, R.C., 1975. Revised ischniquo for
limits there is only a 5% chance of the capital Tredesigu Cost Estimating, Chemical Engineer&g, March 2.
being less than 2 1.8 million. On this basis, it S Bridgwater, A.V.. 1974. Rapid Cost Estimation in the
Chemical Process Industrits, Paper presented at 3rd
would be concluded that the new product was International Cost Engineering Symposiuc, The A ,ocirtiotr
very unlikely to be an economic proposition. of Cost Engineers.

ACKNOWLEDGEMENTS BIOGRAPHICAL NOTE

The author is indebted for helpful discussions John Taylor is a chemist by training, with
to many colleagues within ICI Ltd, particularly the degrees of R.Sc. and Ph.D. from Liverpool
those in Mond Divisions Research Economics Un.versity. He is employed in the Research bi
Section. Development Department of ICIs Mond
Division. For uea-rly 10 years he has had the
REFERENCES position of Research Economist, in which he
1 Zevnik, F.C. and Iluchanan, ILL., 1963. GeneraIised is responsible for the economic evaluation of
Correlation of Process Investment, Chemical Engineering a range of the Divisions R&D projects. in this
Progress, 59(2): 70. activity he has gained a Sroad spectrum of ex-
2 Stallworthy, EA., 1970. The Viewpoint of a Large Chem-
ical Manufacturing Company, The Chemicai Engineer,
perience on the costs of chemical orocesses
June. 182. and the factors affecting them.

Vous aimerez peut-être aussi