This document outlines the 8 step procedure for conducting mechanical push-/pull tests of an Icone vane using a clamp. The steps include:
1) Positioning the Icone vane in the hyson feed cable and lowering it.
2) Placing casing tubes and lowering the vane further.
3) Adding additional casing tubes and clamping the vane.
4) Pushing the vane to the desired depth and performing tests by rotating it between quadrants.
5) Repeating the testing by adding additional casing tubes and pushing the vane to deeper depths.
This document outlines the 8 step procedure for conducting mechanical push-/pull tests of an Icone vane using a clamp. The steps include:
1) Positioning the Icone vane in the hyson feed cable and lowering it.
2) Placing casing tubes and lowering the vane further.
3) Adding additional casing tubes and clamping the vane.
4) Pushing the vane to the desired depth and performing tests by rotating it between quadrants.
5) Repeating the testing by adding additional casing tubes and pushing the vane to deeper depths.
This document outlines the 8 step procedure for conducting mechanical push-/pull tests of an Icone vane using a clamp. The steps include:
1) Positioning the Icone vane in the hyson feed cable and lowering it.
2) Placing casing tubes and lowering the vane further.
3) Adding additional casing tubes and clamping the vane.
4) Pushing the vane to the desired depth and performing tests by rotating it between quadrants.
5) Repeating the testing by adding additional casing tubes and pushing the vane to deeper depths.
PLACE CASING TUBE 500 mm LOWER Icone VANE WITH HYSON STEP 3 STEP 4
PLACE CASING TUBE 1000 mm + INNER CASING 56 REMOVE CASING TUBE
LOWER Icone VANE AND CLAMP WITH CATCHING CLAMP PLACE SLOTTED PUSH-/PULL ROD Icone VANE SLIDE PUSHING PIECE 56 TO CENTER CONNECT SLOTTED PUSH-/PULL ROD TO PUSHING PIECE
STEP 6
PULL VANE INSIDE PROTECTION TUBE
REMOVE SLOTTED PUSH-/PULL ROD Icone VANE SLIDE PUSHING PIECE 56 BACK IN CARRIAGE PLACE CPT ROD + CASING TUBE STEP 7 THE SYSTEM IS NOW READY FOR MULTIPLE VANE TESTS STEP 5 PUSH Icone VANE TILL DESIRED DEPTH STEP 8 CLAMP CASING TUBE ADD CPT-RODS AND CASING TUBES WHEN NEEDED PUSH VANE OUT OF PROTECTION TUBE PLACE SLOTTED PUSH-/PULL ROD Icone MAKE SURE THE VANE IS IDLE FROM ANY LOAD SLIDE PUSHING PIECE 56 TO CENTER PERFORM "ZERO-READING" PUSH VANE OUT OF PROTECTION TUBE MAKE SURE VANE ROTATES TILL NEXT QUADRANT PERFORM VANE TEST
ROTATE VANE TO NEXT QUADRANT
PULL VANE INSIDE PROTECTION TUBE REMOVE ROD/PUSHING PIECE PUSH Icone VANE TO NEXT DEPTH
TEST PROCEDURE CONFIGURATION 2