DIPP1510

Daily Activity & Achievement


Log

Start End Break No. of


DATE ACTIVITY / ACHIEVEMENT
Time Time Period Hours

Co-ordinated reinforcement delivery from steel supplier,


coordinated crane crew and steel fixers to unload and
26/7/17 6:30 5 30min 10 install.
Coordination of subcontractors.

Site engineering tasks including steel inspection and sign


off from Engineer, liaising with formworkers regarding set
27/7/17 1 6 (Uni) 5
out of formwork decks and liaising with boilermakers
regarding welding and structural steel removal.

Basement slab steel and column steel installation


28/7/17 6:30 5 30min 10 including coordination of structures trades formwork and
steelfixers.

Continued slab and column steel installation liaising with


29/7/17 7 2 30 6.5 steelfixers and engineer regarding correct installation.

Complete the Short-Range Programme for the following 3


weeks, including review with Site Manager, Senior Project
31/7/17 6:30 6 30 11
Engineer and Senior Project Manager. BluBeam mark ups
which refer to the short-range programme.

Subcontractor co-ordination meeting and weekly Team


meeting including short overview of weekly programme
1/8/17 6:30 6 4hr (uni) 8
activities and update on previous weeks programme
activities.

Co-ordinate concrete cutters for core holing, co-ordinate


2/8/17 6:30 5 30 10 services trades to install conduit in slab and engineer
inspection for columns.

Pre-Pour inspection checklist as part of Quality


3/8/17 1 6 Uni 5 Management for columns including steel, formwork,
services and concrete.

Concrete pour for columns, finalising pre-pour checklist


4/8/17 6:30 6 30 11 including ITP sign off, internal sign off and pre-pour
checklist with concreters.
Concrete pour for suspended slab, finalising pre-pour
checklist including ITP sign off, internal sign off and pre-
5/8/17 6:30 3 30 9
pour checklist with concreters. Liaising with concreters
regarding pour heights and RLs.

Project Review meeting with early works reinforcement


supplier including delivery and scheduling discussions.
7/8/17 6:30 6 30 11
Weekly team and short range programme review including
updating dates and activities.

Subcontractor coordination meeting including review of


Short Range Programme outlining activities and critical
8/7/17 6:30 6 4hr (uni) 8 milestones to be met. Implementing programme on site by
reviewing with leading hands of each site and discussing
what needs to be done to meet dates.

Project start up meeting with subcontractors for contract


works including formworkers and steelfixers. Discussing
9/8/17 6:30 5 30 10
start dates, HSE requirements and materials handling
requirements.

Site coordination of early works structure including


columns, slabs and beams. Liaising with subcontractors
10/8/17 1 6 Uni 5
regarding design implementation and buildability.
Coordinate reinforcement delivery.

Project Start up meeting with reinforcement supplier


11/8/17 6:30 5 30 10 discussing logistics of delivery to Greenland Centre
Sydney and items to schedule for first contract delivery.

Beams reinforcement installation including quality checks


to ensure they installed to engineering details. Structural
12/8/17 6:30 2 30 7
steel removal to engineers details completed by
boilermakers.

Team meeting and weekly Short Range Programme


review including updating activities to complete in the
14/8/17 6:30 6 30 11 coming weeks and incorporating the 3 monthly programme
activities with a focus on beating the 3 monthly programme
dates.

Concrete Pre-Pour inspection including ITP sign offs from


15/8/17 6:30 11 Uni 4.5 subcontractors and internal inspections of reinforcement,
services, formwork profiles and access for concreters.

Completion of concrete pre-pour inspection including


16/8/17 6:30 6 30 11 engineer sign off and internal sign off. Concrete pour to
basement slab including concrete subcontractor checklist.

Follow up meeting with Engineer and reinforcement


supplier to facilitate steel scheduler queries and ensure all
17/8/17 1 6 5
parties on the same page. Included taking minutes and
raising my own queries for review.

18/8/17 6:30 6 30 11 Site meeting with Client Project Engineer to discuss


programme, engineer sign offs and sequencing of works.
Discussion of Probuild subcontractor commencement
dates.

Site coordination including reinforcement quality


19/8/17 6:30 2 30 7
management and formwork profile check.

Weekly team meeting and short range programme review


including meeting minutes and updating activities to be
21/8/17 6:30 6 30 11
completed in the coming weeks. Incorporation of 3
monthly programme dates.

Subcontractors meeting including programme review,


22/8/17 6:30 11 4.5 safety, quality, site logistics and deliveries. Recap of
previous weeks work and areas to be improved on.

Internal HSE training with Group Safety Manager including


23/8/17 6:30 5 30 10 overview of system and procedures to follow and how to
implement them in the project office and on site.

Concrete pour to numerous mass concrete columns


24/8/17 12 6 30 5.5 including concrete pre-pour check and liaising with
concreters for pour method.

Concrete pour to basement slab including reinforcement


25/8/17 6:30 6 30 11 check, formwork check, services check and finalisation of
Pre-Pour quality management including ITP sign off.

Curing of concrete including chemical compound


application. Core wall pour including infill slab
26/8/17 6:30 2 30 7
coordination of slab reinforcement install and services
install whilst walls were being poured.

Safety system online training including run through of


28/8/17 6:30 6 30 11 sectors and how to use them i.e. people, plant and
equipment and insurances.

Weekly team meeting and short range programme review


including meeting minutes and update of activities to be
29/8/17 6:30 6 4 7.5 completed in the coming weeks. Liaison with new
subcontractors regarding start dates and delivery of
materials.

Coordination and quality management of ground floor


suspended slab formwork and reinforcement installation to
30/8/17 6:30 5 30 10
ensure RLs are as per drawing and steel is as per
structural specification.

Ground floor suspended slab pour including quality check


31/8/17 12 6 5
of steel, structural steel block outs to allow removal later.

Structural Engineer meeting with steel supplier ensure all


1/9/17 6:30 6 30 11 queries are answered in terms of buildability and
installation around existing steel structure.

Steel installation and liaising with Engineer regarding site


4/9/17 6:30 6 30 11 defects and rectification details. Receive rectification
details and implement with site team to rectify.
Continue steel installation and commence closing core
5/9/17 6:30 6 4 (uni) 7
walls ready for concrete pour.

Complete concrete pre pour checklist and supervise core


6/9/17 6:30 5 30 11 wall concrete pour. Complete document control tasks and
fill in concrete test register.

Document control and safety paperwork organisation.


7/9/17 12 6 6
Official start day of contract works.

Organise and run internal pre-start meeting with


management and labour hire. Ensure activities raised in
8/9/17 6:30 6 30 11
pre-start are completed through-out day, main priority
being safety.

Health Safety and Environment training course


11/9/17 6:30 6 30 11
familiarising employees with Probuild systems.

Create reinforcement delivery programme and liaise with


12/9/17 6:30 6 4 (uni) 7.5
supplier regarding delivery times and lay out of truck.

Structural steel removal meeting including requirements


13/9/17 6:30 5 30 10 for removal such as concrete strength of new structure
and temporary propping details.

Weekly team meeting reviewing all facets of project


14/9/17 12 6 6 including safety, design, contracts, council, construction
and culture.

3 weekly programme review and update, liaising with


15/9/17 6:30 6 30 11
subcontractors to buy into durations and completion dates.

Internal shutter installation for lift core walls including


18/9/17 6:30 6 30 11 supervising works and liaising with formworkers regarding
set up pockets for jump form.

Continue jumpform installation to core walls including wide


19/9/17 6:30 6 4 7.5
load delivery coordination and safe handling of crane lifts.

Weekly team meeting and short range programme review


20/9/17 6:30 5 30 10
and update.

Continue delivery of jumpform equipment and hardware


21/9/17 12 6 6 and continuation of install. Liaise with formworkers
regarding set out of walls and jumpform delivery order.

Basement defects walk including delegating defects to


22/9/17 6:30 6 30 11
relevant subcontractors and identifying areas incomplete.

Design review for concrete profile drawing set out, mainly


25/9/17 6:30 6 30 11 regarding column set outs off survey grids. Quality
assurance including site drawing review.

Risk Management training including real life scenario


26/9/17 6:30 6 4 (uni) 7.5 analysis. Complete reinforcement register and assist
contracts team to implement budget into register.
Commence reinforcement installation to Ground floor to
27/9/17 6:30 5 30 10 level 1 core walls, liaise with steelfixer foreman regarding
set out of reo and installation sequence.

Liaise with formworker foreman regarding set out of


28/9/17 12 6 6 services cast ins for core walls and jumpform pocket set
out. Update reinforcement delivery programme.

Plant Induction training including evaluation of Plant and


operator, review of licences and competencies and review
29/9/17 6:30 6 30 11
of engineering certifications for specific plant i.e. Tower
Crane.

Finalise reinforcement install for core walls including pre


4/10/17 6:30 6 30 11 pour checklist and structural engineer sign off. Finalise
closing of walls ready for concrete.

Pour concrete to core walls, ensure concrete flow rate is


5/10/17 6:30 6 4 7.5 adhered to by concreters preventing blow out in wall.
Ensured curing would take place.

Chase concrete tests to confirm core walls is strong


enough to land jumpform onto. Jumpform engineer
6/10/17 6:30 5 30 10 inspection to certify system is structurally sound to jump
crack walls and jump system landing onto new concrete
walls.

Coordinate jumpform deliveries to finalise installation of


9/10/17 12 6 6
jumpform including external cladding and trailing stairs.

Commence reinforcement installation to ground floor


columns including coordination of delivery and liaising with
10/10/17 6:30 6 30 11
steelfixers regarding set out and installation sequence.
Send RFIs to engineer regarding set out detail.

Liaise with structural steel engineer and structural


engineer regarding building columns around existing
11/10/17 6:30 6 30 11
structural steel discussing welding and cutting steel to
allow install.

Input data into concrete test register and update 3 weekly


12/10/17 6:30 6 4 7.5
programme including review with senior management.

Weekly project team meeting reviewing design, contracts,


13/10/17 12 6 6
authority approvals, programme and site progression.

Reinforcement delivery coordination and concrete pour to


16/10/17 6:30 6 30 11 ground floor to level 1 columns including pre pour checklist
and engineer inspection and sign off.

Total number of Placement Hours: 553 hours