APU
rendimiento=12m3/dia
desc cuadrilla cantidad precio parcial
operario 1.00 0.67 17.17 11.45
oficial 1.00 0.67 14.56 9.71
HH
peon 8.00 5.33 13.11 69.92
operador de equi liviano 3.00 2.00 14.56 29.12
pedra grande 0.90 62.00 55.80
agregado fino 0.40 60.00 24.00
MATERIALES cemento portland 9.00 24.50 220.50
agua 0.18 1.40 0.25
madera tornillo 0.08 3.00 0.25
HM 3.00 120.20 3.61
EQ,ERR mezcladora 1.00 0.67 20.00 13.33
vivrador 1.00 0.67 20.00 6.67
CD metrado pu parcial
100.00 444.61 S/.44,461.00
CI
GG (10%) S/.4,446.10
UTI(5%) S/.2,223.05
S/.6,669.15
SUBTOTAL S/.51,130.15
TOTAL S/.51,130.15
COEFICIENTE INCIDENCIA
parcial metrado PT CI
operario 11.45 100.00 1144.67 0.022387
oficial 9.71 100.00 970.67 0.018984
peon 69.92 100.00 6992.00 0.136749
operador de equi liviano 29.12 100.00 2912.00 0.056953
pedra grande 55.80 100.00 5580.00 0.109133
agregado fino 24.00 100.00 2400.00 0.046939
cemento portland 220.50 100.00 22050.00 0.431252
agua 0.25 100.00 25.20 0.000493
madera tornillo 0.25 100.00 24.99 0.000489
HM 3.61 100.00 360.60 0.007053
mezcladora 13.33 100.00 1333.00 0.026071
vivrador 6.67 100.00 667.00 0.013045
GG (10%) S/.4,446.10 0.086957
UTI(5%) S/.2,223.05 0.043478
CONFORMACION DE MONOMIOS
operario 0.022387
0.235
oficial 0.018984
0.235
peon 0.136749
operador de equi liviano 0.056953
cemento portland 0.431252 0.431
pedra grande 0.109133
agregado fino 0.046939
agua 0.000493
madera tornillo 0.000489 0.203
HM 0.007053
mezcladora 0.026071
vivrador 0.013045
GG (10%) 0.086957
0.130
UTI(5%) 0.043478
k= 0.235 0.431
0.235
0.588
0.046
0.130
E GG
0.203 0.130
AGREG AGA MADE MEZ VIVR
77.28% 0.48% 22.72%
0.77 0.00 0.23 1.00 0.23584363