DAYS
1-2 1 Relocation of boundaries-cleaning
2-3 3 Construction of bunk houses/ field office
2-4 6 Delivery of construction materials
2-5 2 Lay-outing, skating and batter boards
3-5 8 Excavation
4-5 10 Assemble Steel Reinforcement
4-7 0 Dummy
3-6 12 Preparing form and door jambs
5-6 9 Placing steel reinforcement
5-7 6 Locating forms and scaffolding
5-8 6 Ensuring electrical, plumbing and water pipe
connections
6-8 0 Dummy
6-9 4 Pouring of footing and columns
7-8 1 Removal of forms
7-10 13 Concrete Hollow Blocks laying
8-10 8 Structural (Beams, slabs, etc) reinforcement and
various piping installations
8-9 0 Dummy
8-11 8 Roof framing and roofing sheet
9-11 6 Pouring of beam and slabs
10-11 2 Construction of stairways
10-13 12 Plastering and Tiling works
11-12 2 Doors and windows installation
9-14 3 Plumbing and drainage system
12-14 2 Plumbing fixtures installation
12-13 3 Electrical wiring and fixture installation
13-15 9 Painting and varnishing works
14-15 2 Cleaning up