Vous êtes sur la page 1sur 6

Designation: D 4435 04

Standard Test Method for


Rock Bolt Anchor Pull Test1
This standard is issued under the fixed designation D 4435; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.

1. Scope* D 6167 Guide for Conducting Borehole Geophysical Log-


1.1 The objective of this test method is to measure the ging: Mechanical Caliper
working and ultimate capacities of a rock bolt anchor. This 3. Terminology
method does not measure the entire roof support system. This
method also does not include tests for pretensioned bolts or 3.1 See Terminology D 653 for general definitions.
mine roof support system evaluation. 3.2 Definitions of Terms Specific to This Standard:
1.2 This test method is applicable to mechanical, cement 3.2.1 displacementThe movement of the rock bolt head.
grout, resin, (epoxy, polyester, and the like), or other similar 3.2.2 failurethe inability of the anchor system or rock to
anchor systems. sustain increased load without rapidly increasing deformation.
1.3 The values stated in inch-pound units are to be regarded In some instances, the peak load itself cannot be sustained.
as the standard. 3.2.3 loadthe total axial force on the rock bolt.
1.4 All observed and calculated values shall conform to the 3.2.4 pressure, stressthe force per unit area.
guidelines for significant digits and rounding established in 3.2.5 ultimate capacitythe maximum load sustained by
Practice D 6026. the anchor system.
1.4.1 The method used to specify how data are collected, 3.2.6 working capacitythe load on the anchor system at
calculated, or recorded in this standard is not directly related to which significantly increasing displacement begins.
the accuracy to which the data can be applied in design or other 4. Summary of Test Method
uses, or both. How one applies the results obtained using this
standard is beyond its scope. 4.1 A rock bolt is installed in the same manner and in the
1.5 This standard does not purport to address all of the same material as its intended construction use. The bolt is
safety concerns, if any, associated with its use. It is the pulled hydraulically and the displacement of the bolt head is
responsibility of the user of this standard to establish appro- measured concurrently. The bolt is pulled until the anchor
priate safety and health practices and determine the applica- system or rock fails. The ultimate and working capacities of the
bility of regulatory limitations prior to use. bolt are calculated from the plot of load versus displacement.

2. Referenced Documents 5. Significance and Use


2.1 ASTM Standards: 2 5.1 Rock bolts are used for support in a variety of mining
D 653 Terminology Relating to Soil, Rock and Contained and civil engineering situations3. The pull test may be used to
Fluids provide a quantitative measure of the relative performance of
D 3740 Practice for Minimum Requirements for Agencies different anchor systems in the same rock type. Anchor systems
Engaged in the Testing and/or Inspection of Soil and Rock may be different mechanical anchors or different bond materi-
as Used in Engineering Design and Construction als or lengths for grouted anchors. Such data can be used to
D 4436 Method for Rock Bolt Anchor Long Term Retention choose an anchor type and determine bolt length, spacing, and
Tests size.
D 6026 Practice for Using Significant Digits in Geotechni- 5.2 The objective of the method is to measure anchor
cal Data performance, and not the performance of the rock bolt itself.
Thus, to ensure that the bolt response during the test is minimal
and predictable, high strength, short-length (6 to 8 ft (1.8 to 2.5
1
m)) bolts have been specified. The bolt should be just long
This test method is under the jurisdiction of ASTM Committee D18 on Soil and
Rock and is the direct responsibility of Subcommittee D18.12 on Rock Mechanics.
enough to ensure that no failure of the rock/mass occurs.
Current edition approved July 1, 2004. Published July 2004. Originally approved
in 1984. Last previous edition approved in 1998 as D 4435 84 (1998).
2 3
For referenced ASTM standards, visit the ASTM website, www.astm.org, or For additional information see, Suggested Method for Determining the
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Strength of a Rock Bolt Anchor (Pull Test),Suggested Methods for Rock Bolt
Standards volume information, refer to the standards Document Summary page on Testing, International Society for Rock Mechanics Commission on Standardization
the ASTM website. of Laboratory and Field Tests, 1974.

*A Summary of Changes section appears at the end of this standard.


Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.

1
D 4435 04
5.3 Ideally, the rock bolt anchor should fail by shear at the shall have an accuracy of at least 60.001 in. (0.025 mm), a
anchor-rock interface or bond. Therefore, the local character- resolution of at least 0.0005 in. (0.013 mm), and a range of at
istics of the rock, such as roughness and induced fractures, are least 2 in. (50 mm). It shall be mounted along the axis of the
significant factors in the anchor strength. To obtain realistic rock bolt within 5. The end of the rock bolt, or pulling rod if
strength values, the test holes should be drilled using the same used, shall be smooth with a counter-sink area approximately
methods as the construction rock bolt holes. 14 in. (6 mm) in diameter to accommodate the measuring tip of

5.4 Rocks with significant time-dependent behavior, such as the dial gage. Other types of displacement transducers may be
rock salt or shale, may respond to the anchor system itself and used provided they satisfy the requirements of this section.
change the anchor strength. In these cases, consideration 6.4 Displacement Transducer Support The displacement
should be given to testing bolts over a period of time. transducer shall be supported from a point no closer than 3 ft
5.5 In establishing a testing program, the following factors (0.9 mm) to the reaction frame, if attached to the same rock
should be considered: face. The support shall be sufficiently rigid that no deflection or
5.5.1 Anchor pull tests should be conducted in all rock types instability occurs during testing.
in which construction bolts will be installed. If the rock is 6.5 Anchor SystemsThe anchors used for testing shall be
anisotropic, for example, bedded or schistose, the tests should from the manufacturers standard production stock. Mechani-
be conducted in various orientations relative to the anisotropy, cal anchors shall be inspected to ensure that no defective
including those at which the construction bolt may be installed. anchors are tested. Grout or resin shall be fresh (within the
5.5.2 In each rock type, at each orientation, and for each shelf life) and obtained from unopened containers. If grouted
anchor system, a sufficient number of tests should be con- anchors are to be tested, ensure resin cartridge sizes are
ducted to determine the average bolt capacities within a fixed compatible with hole diameter, rock bolt bar diameter and
uncertainty at the 95 % confidence level. The allowable uncer- length of anchorage required. For anchorages utilizing injected
tainty band depends on the project and involves such factors as grout, ensure mixing and injection equipment and systems are
the rock quality, expected project lifetime, and importance of compatible with manufacturers recommendations.
the areas to be bolted. Its determination will require consider- 6.6 Rock Bolt and AccessoriesThe rock bolt shall be of
able engineering judgment. As a rough guideline, at least 10 to sufficient diameter and strength that its elastic range is not
12 pull tests for a single set of variables have been found exceeded during testing. Standard bearing plates, washers, and
necessary to satisfy the statistical requirements. the like may be used as required.
6.7 Drilling EquipmentThe same type of drilling equip-
NOTE 1Notwithstanding the statements on precision and bias con- ment and drill bits that will be used for installing rock bolts
tained in this test method; the precision of this test method is dependent
on the competence of the personnel performing it, and the suitability of the
during the construction phase of the project shall be used as far
equipment and facilities used. Agencies that meet the criteria of Practice as possible to drill the test holes.
D 3740 are generally considered capable of competent and objective 6.8 Torque WrenchIf expandable shell mechanical an-
testing. Users of this test method are cautioned that compliance with chors are used, a torque wrench shall be used to set them. The
Practice D 3740 does not in itself assure reliable testing. Reliable testing wrench shall have a capacity at least 20 % greater than the
depends on many factors; Practice D 3740 provides a means of evaluating manufacturers recommended anchor-setting torque. The
some of those factors.
torque wrench shall have an accuracy of at least 62 % of the
6. Apparatus full-scale reading, and a resolution of at least 1 % of the
full-scale reading.
6.1 Loading SystemThe system for pulling the rock bolts 6.9 Borehole Diameter Measuring Gage A gage shall be
shall consist of a hollow-center hydraulic ram and mounting/ used to measure the diameter of the borehole at the anchor
reaction frame. The hydraulic ram shall be of sufficient location. It shall have an accuracy of at least 60.02 in. (0.05
capacity to fail the anchor and shall have a travel range of at mm) and resolution of at least 0.01 in. (0.25 mm)
least 2 in. (50 mm). The mounting/reaction frame shall be 6.10 ThermometerA thermometer shall be used to mea-
usable against uneven rock surfaces. The loading system shall sure temperature in the borehole, within the anchor zone if
apply a force that deviates by no more than 5 from the long resin or cement grout anchorages are being tested. The tem-
axis of the bolt during the test. perature of the resin or grout shall also be measured at the time
6.2 Load TransducerAn electronic load cell is recom- of injection. The thermometer should have an accuracy of at
mended to measure the load on the rock bolt. The cell shall least + 0.5F (0.28C) and a resolution of at least 1F (0.56C).
have an accuracy of at least 6200 lbf (6890 N), including 6.11 Fig. 1 shows a typical test setup.
errors introduced by the excitation and readout system, and a
resolution of at least 100 lbf (445 N). Other types of load 7. Procedure
transducers may be used if their performance meets these 7.1 Drilling the Test Hole:
specifications. Alternatively, a pressure gage or electronic 7.1.1 Drill the test hole using the same procedure that will
transducer may be used to measure the pressure applied to the be used during construction. Wash or blow the borehole clean
ram, provided that the load measurement requirements above of all cuttings.
are satisfied, including the effects of friction in the hydraulic 7.1.2 The hole need not be as deep as the proposed length of
ram, and the like. the rock bolts. It shall, however, be deep enough to set the
6.3 Displacement TransducerA dial gage is recom- anchor past the zone of disturbance caused by the excavation
mended to measure the displacement of the rock bolt head. It and the zone of stress concentration caused by the reaction of

2
D 4435 04

FIG. 1 Typical Rock Bolt Pull Test Schematic

the pulling frame. For mechanical shell anchors, drill the hole temperature of the resin or grout at the time of injection and the
1 ft (0.9 m) past the end of the anchor. A hole approximately 6 ambient air temperature. Ideally the test anchorages should be
ft. (1.8 m) in length has generally been found to be adequate. installed under the same temperature conditions as expected
7.1.3 Inspect the test hole visually using a flashlight or during construction. The time required for resin or grout
mirror to reflect sunlight down the hole. If more than one half anchorages to reach their design strengths is temperature
of the bottom of the hole cannot be seen, the hole is not dependent and may vary significantly. Consult the resin or
sufficiently straight for a pull test and shall not be used. grout manufacturers literature for recommended curing times
7.1.4 Measure the test hole diameter in two perpendicular under various temperature conditions. Curing times may be
directions at the top and bottom of the anchor location borehole varied between 1 to 5 days under similar temperature condi-
using a diameter measuring gage for a total of four measure- tions to assess the effects of curing time on strength. To
ments. evaluate the influence of grouted bond length on anchor
7.2 Preparation of AnchorsIf any anchor preparations, strength, several anchorage lengths should be tested, ideally
such as degreasing or rust removal, will be done during under similar temperature conditions and curing times.
construction, prepare the test anchors in the same way. If no 7.4.2 On at least half of the tests, perform three loading and
special preparation will be done during construction, do not unloading cycles to check for pre-failure anchor movements.
prepare the test anchors. Apply the load with the hydraulic ram in cycles to 14, 12, and
7.3 Setting the Anchor: 34 of the estimated failure load. Load the bolt in ten equal

7.3.1 If mechanical anchors are used, lightly lubricate the increments and unload it in ten equal decrements.
downhole end of the rock bolt and screw on the anchor. When 7.4.3 Apply the load smoothly and rapidly.
in position, torque the bolt to the manufacturers recommended 7.4.4 After the third cycle, pull the bolt in the same
level to set the anchor. A pair of jam-nuts on the upper end of increments as used during the last cycle or in 500 lbf (2.2 kN)
the rod may be used to apply torque without producing axial increments, whichever is less, until the anchor system fails or
load in the bolt. If the manufacturers torque cannot be the limit of the loading system is reached.
achieved because of anchor rotational slippage due to shear 7.4.5 Test non-cycled bolts to failure in 20 equal load
failure in the rock, note the maximum torque reading and increments or increments of 500 lbf (2.2 kN), whichever is
install subsequent anchors to 80 % of this value. Do not test less.
anchors where rotation occurs between the rock surface and the 7.4.6 Read and record displacement and load after each
anchor. In all cases, record any slipping or other anomalous pressure increment or decrement.
behavior as shown in Fig. 2. 7.4.7 Failure is the peak load sustained by the bolt, as shown
7.3.2 Install cement grout or resin anchors according to the on Fig. 3, or a total deflection of 0.5 in. (1.25 cm).
manufacturers recommendations. 7.4.8 Pull the bolt 0.5 in. (12.5 mm) beyond the failure
7.4 Test Method: displacement. Record the load every 0.05 in. (1 mm).
7.4.1 All tests are performed on untensioned bolts. Record 7.5 Data RecordingAs a minimum for this method,
the temperature in the borehole within the anchor zone; the record all the data shown in Fig. 2.

3
D 4435 04

FIG. 2 Rock Bolt Anchor Pull Test Sample Form

8. Calculation Uc 5 Ut 2 Ub (3)
8.1 Calculate the stress on the bolt, sb, in psi (MPa) as where:
follows: U b = elastic deformation of the bolt, and
P Ut = total displacement of bolt head.
sb 5 A (1)
8.4 Determine the working and ultimate capacities of the
anchor system from the plot of load versus anchor displace-
where: ment. A typical curve is shown in Fig. 3. Interpretation of the
P = load on the bolt, lbf (N), and curve often requires some engineering judgment.
A = cross-sectional area of the bolt, in.2(mm2).
8.5 For each group of tests on a similar rock type with the
8.2 Calculate the elastic deformation of the bolt, Ub, in in.
same anchor type and orientation (if applicable), calculate the
(mm) as follows:
mean and uncertainty of the results at the 95 % confidence
sb level4.
Ub 5 E 3 L (2)
9. Report
where:
sb = stress on the bolt, psi (MPa), 9.1 The report shall include the following:
L = exposed length of bolt between the anchor and the 9.1.1 Describe the rock material(s) in which the anchors
head, in. (mm), and were tested, including the composition, texture, and any
E = elastic modulus of the steel in the bolt, psi (MPa).
8.3 Calculate the corrected bolt head displacement, Uc, 4
To calculate the mean and uncertainty of the results see, Statistical Consid-
which is the same as the displacement of the anchor, as erations, Rock Testing Handbook, U.S. Army Corps of Engineers, Waterways
follows: Experiment Station, Vicksburg, MS, 1980, Section 104-80.

4
D 4435 04
9.1.6 Prepare summary tables of results, including the
working and ultimate capacity of each anchor type in each rock
type, with anchor type, number of tests, mean working capac-
ity, range, and uncertainty of the mean. If resin or grouted
anchorages were tested, record the measurements made during
installation of borehole, grout and ambient temperatures,
9.1.7 Include a plot of load versus corrected bolt head
displacement for each test, a description of the nature of any
failures or any other observations pertinent to the test, and
9.1.8 Append the data sheets for each test.
9.1.9 For the evaluation of grouted rock bolts, the results of
several tests should be presented graphically to show the
influence of grout cure time and bond length on anchor
strength. Data concerning temperature effects should be pre-
sented to indicate the effects of temperature on cure times and
the recommended installation procedures to be followed during
construction.
10. Precision and Bias
10.1 PrecisionDue to the nature of rock materials tested
FIG. 3 Typical Load versus Deflection Curve for Rock Bolt Pull by this test method, it is, at this time, either not feasible or too
Test costly to produce multiple specimens which have uniform
physical properties. Therefore, since specimens which would
yield the same test results cannot be tested, Subcommittee
structural features which could affect anchor capacities, such as D18.12 cannot determine the variation between tests since any
joints, weathering, and the like, variation observed is just as likely to be due to specimen
9.1.2 Briefly describe the types of anchors tested, variation as to operator or laboratory testing variation. Sub-
9.1.3 A summary table of the test program including test committee D18.12 welcomes proposals to resolve this problem
number, anchor type, rock type, orientation, and test depth, that would allow for development of a valid precision state-
9.1.4 List the equipment, other than anchors, with model ment.
numbers or dimensions as appropriate. Include the range, 10.2 BiasThere is no accepted reference value for this test
accuracy, and resolution of any devices used to make measure- method; therefore, bias cannot be determined.
ments,
9.1.5 Present the equations used to reduce the data, includ- 11. Keywords
ing those required to convert transducer output into engineer- 11.1 anchors (rock); displacement; field testing; loading
ing units, tests; mines; pull testing; rock; shear testing

SUMMARY OF CHANGES

In accordance with Committee D18 policy, this section identifies the location of changes to this standard since
the last edition 1998 that may impact the use of this standard.

(1) Added footnote to scope about a summary of changes (8) Added to first sentence in section 7.1.3 or mirror to reflect
section. sunlight down the hole.
(2) Inserted missing caveat in Section 1 on significant figures. (9) Added to 7.1.4 using a diameter measuring gage.
(3) Inserted referenced standards D 653, D 3740, D 6026, and (10) Added to section 7.4.1, Record the temperature in the
D 6167 in Section 2. borehole within the anchor zone; the temperature of the resin or
(4) Inserted Item 3.1 referring to D 653. grout at the time of injection and the ambient air temperature.
(5) After subsection 5.5.2, added caveat statement as per Ideally the test anchorages should be installed under the same
D 3740 which requires balloting. temperature conditions as expected during construction. The
(6) Added to section 6.5, If grouted anchors are to be tested, time required for resin or grout anchorages to reach their
ensure resin cartridge sizes are compatible with hole diameter, design strengths is temperature dependent and may vary
rock bolt bar diameter and length of anchorage required. For significantly. Consult the resin or grout manufacturers litera-
anchorages utilizing injected grout, ensure mixing and injec- ture for recommended curing times under various temperature
tion equipment and systems are compatible with manufactur- conditions. Curing times may be varied between 1 to 5 days
ers recommendations. under similar temperature conditions to assess the effects of
(7) Added a section 6.10 under apparatus, for a thermometer. curing time on strength. To evaluate the influence of grouted

5
D 4435 04
bond length on anchor strength, several anchorage lengths (14) Added to 9.1.7, a description of the nature of any
should be tested, ideally under similar temperature conditions failures or any other observations pertinent to the test.
and curing times. (15) Added section 9.1.9. For the evaluation of grouted rock
(11) Section 7.4.4 was re-worded so that the loading to failure bolts, the results of several tests should be presented graphi-
is referring to the anchor system and not the rock bolt. cally to show the influence of grout cure time and bond length
(12) In section 9.1.4, deleted transducer and added any on anchor strength. Data concerning temperature effects should
devices used to make measurements. be presented to indicate the effects of temperature on cure
(13) Added to 9.1.6, If resin or grouted anchorages were times and the recommended installation procedures to be
tested, record the measurements made during installation of followed during construction.
borehole, grout and ambient temperatures. (16) Added Summary of Changes.

ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website
(www.astm.org).

Vous aimerez peut-être aussi