CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL


PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %

01 QOCHAPAMPA 1,129,926.03 #REF!


01.01 OBRAS PRELIMINARES 91,360.32
01.01.01 OBRAS PROVISIONALES 15,861.86
01.01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M und 1.00 1,059.19 1,059.19 1,059.19 1.00 1,059.19 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.01.02 PLACA RECORDATORIA und 1.00 379.74 379.74 379.74 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 379.74 100.00%
01.01.01.03 POZA DE AGUA PARA LA CONSTRUCCIN m2 4.50 397.43 1,788.44 1,788.44 4.50 1,788.44 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.01.04 ALMACEN PROVISIONAL DE OBRA m2 60.00 44.92 2,695.20 2,695.20 60.00 2,695.20 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.01.05 CASETA P/GUARDIANIA m2 12.00 93.24 1,118.88 1,118.88 12.00 1,118.88 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.01.06 EQUIPOS DE PROTECCION Y SEGURIDAD GLB 1.00 6,266.52 6,266.52 6,266.52 0.30 1,879.96 30.00% 0.20 1,253.30 20.00% 0.20 1,253.30 20.00% 0.20 1,253.30 20.00% 0.10 626.65 10.00% - - 0.00%
01.01.01.07 CONSTRUCCION DE CERCO PROVISIONAL m 180.00 10.56 1,900.80 1,900.80 180.00 1,900.80 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.01.08 CONEXION DEL SERVICIO ELECTRICO TEMPORAL und 1.00 653.09 653.09 653.09 1.00 653.09 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.02 TRABAJOS GENERALES Y COMPLEMENTARIOS 19,026.25
01.01.02.01 LIMPIEZA DE TERRENO MANUAL m2 2,269.00 0.50 1,134.50 1,134.50 2,269.00 1,134.50 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.02.02 MOVILIZACION Y DESMOVILIZACIN DE MAQUINARIAS Y EQUIPOS GLB 1.00 8,406.78 8,406.78 8,406.78 0.50 4,203.39 50.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.50 4,203.39 50.00%
01.01.02.03 TRAZO Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO mes 3.00 2,978.04 8,934.12 8,934.12 0.60 1,786.82 20.00% 0.60 1,786.82 20.00% 0.60 1,786.82 20.00% 0.60 1,786.82 20.00% 0.30 893.41 10.00% 0.30 893.41 10.00%
01.01.02.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 550.85 550.85 550.85 0.30 165.26 30.00% 0.30 165.26 30.00% 0.30 165.26 30.00% 0.10 55.09 10.00% - - 0.00% - - 0.00%
01.01.03 MOVIMIENTO DE TIERRAS 28,152.22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.01.03.01 CORTE DE TERRENO CON MAQUINARIA MATERIAL SUELTO m3 730.72 6.77 4,946.97 4,946.97 730.72 4,946.97 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.03.02 PERFILADO Y COMPACTADO DE LA SUBRRASANTE m2 320.00 6.60 2,112.00 2,112.00 - 0.00 0.00% 320.00 2,112.00 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.03.03 RELLENO COMPACTADO C/MATERIAL DE PRESTAMO m3 346.08 33.87 11,721.73 11,721.73 - - 0.00% 346.08 11,721.73 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.03.04 ACARREO MATERIAL AFIRMADO HASTA D<=50 M m3 432.60 7.44 3,218.54 3,218.54 - - 0.00% 432.60 3,218.54 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.03.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 1,023.79 6.01 6,152.98 6,152.98 204.76 1,230.60 20.00% 819.03 4,922.38 80.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.04 DEMOLICION DE INFRAESTRUCTURA EXISTENTE 2,011.99 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.01.04.01 DEMOLICION DE OBRAS DE CONSTRUCCION AULAS RSTICAS m2 164.00 4.70 770.80 770.80 164.00 770.80 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.04.02 DESMONTAJE DE TECHO Y VANOS m2 219.68 5.65 1,241.19 1,241.19 219.68 1,241.19 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.01.05 FLETE 26,308.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.01.05.01 TRANSPORTE A LA OBRA GLB 1.00 26,308.00 26,308.00 26,308.00 0.20 5,261.60 20.00% 0.20 5,261.60 20.00% 0.20 5,261.60 20.00% 0.20 5,261.60 20.00% 0.20 5,261.60 20.00% - - 0.00%
01.02 MODULO DE AULAS PEDAGOGICAS 373,895.36 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01 CONSTRUCCION DE 02 AULAS Y SS.HH. 211,114.52 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01 ESTRUCTURAS 117,245.89 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.01 TRABAJOS PRELIMINARES 341.68 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 183.70 1.36 249.83 249.83 183.70 249.83 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 183.70 0.50 91.85 91.85 183.70 91.85 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02 MOVIMIENTO DE TIERRAS 8,009.36 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.02.01 PERFILADO MANUAL EN ZONA DE CORTE m2 187.70 2.35 441.10 441.10 187.70 441.10 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.02 EXCAVACION PARA ZAPATAS m3 84.06 23.66 1,988.86 1,988.86 84.06 1,988.86 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.03 EXCAVACION DE ZANJA PARA CIMENTACION m3 28.08 23.66 664.37 664.37 28.08 664.37 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.04 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVAC m2 75.60 2.72 205.63 205.63 75.60 205.63 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.05 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO E m3 50.38 16.90 851.42 851.42 - - 0.00% 50.38 851.42 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.06 RELLENO, CONFORMACION Y COMPACTACION DE BASE E=10 m2 139.07 8.46 1,176.53 1,176.53 - - 0.00% 139.07 1,176.53 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 140.17 12.06 1,690.45 1,690.45 - - 0.00% - - 0.00% 140.17 1,690.45 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2m3 140.17 7.07 991.00 991.00 - - 0.00% - - 0.00% 140.17 991.00 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.03 OBRAS DE CONCRETO SIMPLE 12,277.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.03.01 CONCRETO EN FALSA ZAPATAS ;FC= 140 KG/CM2 m3 10.79 376.00 4,057.04 4,057.04 10.79 4,057.04 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.03.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 14.07 244.74 3,443.49 3,443.49 - - 0.00% 14.07 3,443.49 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.03.03 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 5.39 318.13 1,714.72 1,714.72 - - 0.00% 5.39 1,714.72 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.03.04 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 58.05 51.69 3,000.60 3,000.60 - - 0.00% 58.05 3,000.60 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.03.05 CURADO DE CONCRETO m2 58.05 1.06 61.53 61.53 - - 0.00% 29.03 30.77 50.00% 29.03 30.77 50.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04 OBRAS DE CONCRETO ARMADO 96,617.47 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.01 ZAPATAS 16,828.68 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.01.01 CONCRETO EN ZAPATAS F'C= 210 kg/cm2 m3 32.37 411.48 13,319.61 13,319.61 12.95 5,327.84 40.00% 19.42 7,991.77 60.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.01.02 ACERO EN ZAPATAS FY= 4200 KG/CM2 kg 722.03 4.86 3,509.07 3,509.07 288.81 1,403.63 40.00% 433.22 2,105.44 60.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.02 VIGAS DE CIMENTACION 8,175.22 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 5.12 377.08 1,930.65 1,930.65 - - 0.00% 5.12 1,930.65 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION m2 34.14 62.30 2,126.92 2,126.92 - - 0.00% 34.14 2,126.92 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.02.03 ACERO EN VIGAS DE CIMENTACIN FY= 4200 KG/CM2 kg 875.85 4.66 4,081.46 4,081.46 - - 0.00% 875.85 4,081.46 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.02.04 CURADO DE CONCRETO m2 34.14 1.06 36.19 36.19 - - 0.00% 34.14 36.19 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.03 COLUMNAS 14,765.51 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 7.85 411.48 3,230.12 3,230.12 - - 0.00% 3.14 1,292.05 40.00% 4.71 1,938.07 60.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 88.75 53.62 4,758.78 4,758.78 - - 0.00% 35.50 1,903.51 40.00% 53.25 2,855.27 60.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.03.03 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 1,415.79 4.72 6,682.53 6,682.53 566.32 2,673.01 40.00% 849.47 4,009.52 60.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.03.04 CURADO DE CONCRETO m2 88.75 1.06 94.08 94.08 - - 0.00% 35.50 37.63 40.00% 53.25 56.45 60.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.04 COLUMNETAS 2,151.41 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.04.01 CONCRETO EN COLUMNETAS F'C=175 KG/CM2 m3 1.01 432.69 437.02 437.02 - - 0.00% - - 0.00% 1.01 437.02 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 26.88 49.06 1,318.73 1,318.73 - - 0.00% - - 0.00% 26.88 1,318.73 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.04.03 ACERO FY=4200 Kg/cm2 kg 77.79 4.72 367.17 367.17 - - 0.00% - - 0.00% 77.79 367.17 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.04.04 CURADO DE CONCRETO m2 26.88 1.06 28.49 28.49 - - 0.00% - - 0.00% 26.88 28.49 100.00% - - 0.00% - - 0.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.02.01.01.04.05 VIGAS 22,555.12 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 13.16 448.88 5,907.26 5,907.26 - - 0.00% - - 0.00% - - 0.00% 13.16 5,907.26 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.05.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 154.85 53.62 8,303.06 8,303.06 - - 0.00% - - 0.00% 154.85 8,303.06 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.05.03 ACERO FY=4200 Kg/cm2 kg 1,733.19 4.72 8,180.66 8,180.66 - - 0.00% - - 0.00% 1,733.19 8,180.66 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.05.04 CURADO DE CONCRETO m2 154.85 1.06 164.14 164.14 - - 0.00% - - 0.00% - - 0.00% 154.85 164.14 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.06 VIGUETAS 571.85 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.06.01 CONCRETO EN VIGUETAS F'C=175 KG/CM2 m3 0.39 398.54 155.43 155.43 - - 0.00% - - 0.00% - - 0.00% 0.39 155.43 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.06.02 ENCOFRADO Y DESENCOFRADO PARA VIGUETAS DE CONFI m2 5.13 51.94 266.45 266.45 - - 0.00% - - 0.00% 5.13 266.45 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.06.03 ACERO FY=4200 Kg/cm2 kg 30.62 4.72 144.53 144.53 - - 0.00% - - 0.00% 30.62 144.53 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.06.04 CURADO DE CONCRETO m2 5.13 1.06 5.44 5.44 - - 0.00% - - 0.00% - - 0.00% 5.13 5.44 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.07 LOSA ALIGERADA 26,943.09 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.07.01 CONCRETO F'C=210 KG/CM2. PARA LOSAS ALIGERADAS m3 11.73 430.19 5,046.13 5,046.13 - - 0.00% - - 0.00% - - 0.00% 11.73 5,046.13 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGER m2 158.40 64.56 10,226.30 10,226.30 - - 0.00% - - 0.00% 158.40 10,226.30 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.07.03 ACERO FY=4200 Kg/cm2 kg 1,259.09 4.72 5,942.90 5,942.90 - - 0.00% - - 0.00% 1,259.09 5,942.90 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.07.04 LADRILLO HUECO DE ARCILLA 12X30X25 CM PARA LOSA ALI m2 165.62 33.57 5,559.86 5,559.86 - - 0.00% - - 0.00% 165.62 5,559.86 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.07.05 CURADO DE CONCRETO m2 158.40 1.06 167.90 167.90 - - 0.00% - - 0.00% - - 0.00% 158.40 167.90 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.08 CANALETA 3,852.07 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.08.01 CONCRETO F'C=210 KG/CM2. PARA CANALETA m3 2.44 430.19 1,049.66 1,049.66 - - 0.00% - - 0.00% - - 0.00% 2.44 1,049.66 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN CANALETA m2 28.20 64.56 1,820.59 1,820.59 - - 0.00% - - 0.00% 28.20 1,820.59 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.08.03 ACERO FY=4200 Kg/cm2 kg 201.68 4.72 951.93 951.93 - - 0.00% - - 0.00% 201.68 951.93 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.08.04 CURADO DE CONCRETO m2 28.20 1.06 29.89 29.89 - - 0.00% - - 0.00% - - 0.00% 28.20 29.89 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.09 TAPAS LATERALES 774.52 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.01.04.09.01 CONCRETO F'C=210 KG/CM2. PARA TAPAS LATERALES m3 0.53 430.19 228.00 228.00 - - 0.00% - - 0.00% - - 0.00% 0.53 228.00 100.00% - - 0.00% - - 0.00%
01.02.01.01.04.09.02 ENCOFRADO Y DESENCOFRADO NORMAL EN TAPAS LATERAL m2 7.01 64.56 452.57 452.57 - - 0.00% - - 0.00% 7.01 452.57 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.09.03 ACERO FY=4200 Kg/cm2 kg 18.33 4.72 86.52 86.52 - - 0.00% - - 0.00% 18.33 86.52 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.01.04.09.04 CURADO DE CONCRETO m2 7.01 1.06 7.43 7.43 - - 0.00% - - 0.00% - - 0.00% 7.01 7.43 100.00% - - 0.00% - - 0.00%
01.02.01.02 ARQUITECTURA 81,469.98 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.01 MUROS Y TABIQUES DE ALBAILERIA 7,146.16 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.01.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 JUNTA 1.5 CM m2 53.04 76.76 4,071.35 4,071.35 - - 0.00% 26.52 2,035.68 50.00% 26.52 2,035.68 50.00% - - 0.00% - - 0.00% - - 0.00%
01.02.01.02.01.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 60.19 50.64 3,048.02 3,048.02 - - 0.00% - - 0.00% 30.10 1,524.01 50.00% 30.10 1,524.01 50.00% - - 0.00% - - 0.00%
01.02.01.02.01.03 JUNTA DE CONSTRUCCION CON TEKNOPORT E=1" m2 7.61 3.52 26.79 26.79 - - 0.00% - - 0.00% 3.81 13.40 50.00% 3.81 13.40 50.00% - - 0.00% - - 0.00%
01.02.01.02.02 REVOQUES Y ENLUCIDOS 14,676.93 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.02.01 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 169.85 19.46 3,305.28 3,305.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 169.85 3,305.28 100.00% - - 0.00%
01.02.01.02.02.02 TARRAJEO EN MURO EXTERIORES MEZCLA 1:5, E=1.50CM m2 66.72 19.46 1,298.37 1,298.37 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 66.72 1,298.37 100.00% - - 0.00%
01.02.01.02.02.03 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.5CM INC. VESTIDU m2 104.19 22.60 2,354.69 2,354.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 104.19 2,354.69 100.00% - - 0.00%
01.02.01.02.02.04 TARRAJEO DE VIGAS Y VIGUETAS MEZCLA 1:5, E=1.5CM m2 106.52 22.60 2,407.35 2,407.35 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 106.52 2,407.35 100.00% - - 0.00%
01.02.01.02.02.05 TARRAJEO MEZCLA 1:5 EN DERRAMES DE PUERTAS Y VENTANAm 110.60 19.32 2,136.79 2,136.79 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 110.60 2,136.79 100.00% - - 0.00%
01.02.01.02.02.06 TARRAJEO DE CIELO RASO MEZCLA 1:5, E=1.50CM m2 147.56 20.61 3,041.21 3,041.21 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 147.56 3,041.21 100.00% - - 0.00%
01.02.01.02.02.07 BRUA DE 1/2" m 90.64 1.47 133.24 133.24 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 90.64 133.24 100.00% - - 0.00%
01.02.01.02.03 PISOS Y PAVIMENTOS 23,068.53 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.03.01 PISOS 17,679.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.03.01.01 FALSO PISO CON CONCRETO F'C=140 KG/CM2 E=5CM m2 128.05 38.25 4,897.91 4,897.91 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 128.05 4,897.91 100.00% - - 0.00%
01.02.01.02.03.01.02 CONTRAPISO DE 48 MM. m2 128.05 25.36 3,247.35 3,247.35 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 128.05 3,247.35 100.00% - - 0.00%
01.02.01.02.03.01.03 PISO DE MADERA MACHIHEMBRADA (1.20X0.12 M) m2 90.00 77.79 7,001.10 7,001.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 90.00 7,001.10 100.00% - - 0.00%
01.02.01.02.03.01.04 PISO DE CERAMICO DE 40X40CM m2 27.05 80.88 2,187.80 2,187.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 27.05 2,187.80 100.00% - - 0.00%
01.02.01.02.03.01.05 PISO DE CEMENTO PULIDO E= 5 cm m2 11.00 31.38 345.18 345.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.00 345.18 100.00% - - 0.00%
01.02.01.02.03.02 VEREDAS 5,389.19 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.03.02.01 CONCRETO FC=175 KG/CM2 EN VEREDAS m3 10.85 403.13 4,373.96 4,373.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.85 4,373.96 100.00% - - 0.00%
01.02.01.02.03.02.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 10.78 49.06 528.87 528.87 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.78 528.87 100.00% - - 0.00%
01.02.01.02.03.02.03 BRUA EN VEREDA m 164.64 1.47 242.02 242.02 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 164.64 242.02 100.00% - - 0.00%
01.02.01.02.03.02.04 JUNTA DE ASFALTICA m2 19.50 12.53 244.34 244.34 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.50 244.34 100.00% - - 0.00%
01.02.01.02.04 ZOCALOS Y CONTRAZOCALOS 2,261.76 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.04.01 ZOCALO DE CERAMICO DE 30X30CM SSHH-COCINA m2 39.00 20.50 799.50 799.50 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 39.00 799.50 100.00% - - 0.00%
01.02.01.02.04.02 CONTRAZOCALO DE MADERA H=10 CM m 50.00 21.69 1,084.50 1,084.50 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 50.00 1,084.50 100.00% - - 0.00%
01.02.01.02.04.03 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM FROTACH m 48.00 7.87 377.76 377.76 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 48.00 377.76 100.00% - - 0.00%
01.02.01.02.05 COBERTURAS 7,122.66 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.05.01 COBERTURA CON TEJA ANDINA TIPO ETERNIT m2 165.62 36.65 6,069.97 6,069.97 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 165.62 6,069.97 100.00% - - 0.00%
01.02.01.02.05.02 CUMBRERA DE TEJA ANDINA INDUSTRIAL m 18.94 55.58 1,052.69 1,052.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.94 1,052.69 100.00% - - 0.00%
01.02.01.02.06 CARPINTERIA DE MADERA 9,391.93 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.06.01 PUERTA DE MADERA APANELADA m2 19.11 318.00 6,076.98 6,076.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.11 6,076.98 100.00%
01.02.01.02.06.02 PUERTA DE MELAMINA CON MARCO DE ALUMINIO m2 2.72 264.81 720.28 720.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.72 720.28 100.00%
01.02.01.02.06.03 TABIQUERIA DE MELAMINE Y ALUMINIO PARA BAOS SUEGUN m2 8.10 320.33 2,594.67 2,594.67 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.10 2,594.67 100.00%
01.02.01.02.07 CARPINTERIA METALICA Y HERRERIA 6,584.84 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.07.01 VENTANA DE ALUMINIO m2 18.79 231.79 4,355.33 4,355.33 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.79 4,355.33 100.00%
01.02.01.02.07.02 BISAGRA CAPUCHINA DE 4" X 4" und 49.00 13.32 652.68 652.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 49.00 652.68 100.00%
01.02.01.02.07.03 CERRADURA DE 3 GOLPES PARA PUERTA pza 9.00 82.97 746.73 746.73 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.00 746.73 100.00%
01.02.01.02.07.04 CERRADURA PTA.BAO SEG.INT.PER.MANIJ.CERRAD.GOAL 42 pza 5.00 72.81 364.05 364.05 - 0.00% 0.00% 0.00% 0.00% - - 0.00% 5.00 364.05 100.00%
01.02.01.02.07.05 MANIJA DE BRONCE PARA PUERTAS und 13.00 35.85 466.05 466.05 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.00 466.05 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.02.01.02.08 VENTANAS, CRISTALERIA Y SIMILARES 3,044.31 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.08.01 VIDRIOS SEMIDOBLES INCOLORO CRUDO p2 202.28 15.05 3,044.31 3,044.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 202.28 3,044.31 100.00%
01.02.01.02.09 PINTURA 8,172.86 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.02.09.01 PINTURA EN MUROS INTERIORES AL LATEX ACABADO MATE m2 169.85 8.54 1,450.52 1,450.52 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 169.85 1,450.52 100.00%
01.02.01.02.09.02 PINTURA EN MUROS EXTERIOR AL LATEX AGRILICO 2 MANOS m2 64.78 8.54 553.22 553.22 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 64.78 553.22 100.00%
01.02.01.02.09.03 PINTURA EN LATEX EN COLUMNAS Y COLUMNETAS m2 104.19 13.91 1,449.28 1,449.28 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 104.19 1,449.28 100.00%
01.02.01.02.09.04 PINTURA EN LATEX VIGAS Y VIGUETAS m2 101.84 14.53 1,479.74 1,479.74 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 101.84 1,479.74 100.00%
01.02.01.02.09.05 PINTURA EN CIELO RASO AL LATEX 2 MANOS m2 145.99 15.73 2,296.42 2,296.42 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 145.99 2,296.42 100.00%
01.02.01.02.09.06 PINTURA ESMALTE EN CONTRA ZOCALO DE CEMENTO m 48.00 19.66 943.68 943.68 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 48.00 943.68 100.00%
01.02.01.03 INSTALACIONES SANITARIAS 7,108.37 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.03.01 DRENAJE PLUVIAL 2,280.92 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.03.01.01 CONCRETO EN COLUMNETAS DE BAJADA PLUVIAL F'C=175 KG/ m3 0.38 425.18 161.57 161.57 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.38 161.57 100.00%
01.02.01.03.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETA m2 4.50 42.06 189.27 189.27 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.50 189.27 100.00%
01.02.01.03.01.03 DESAGUE PLUVIAL CON TUBERIA PVC SAL DE 3" m 16.00 120.63 1,930.08 1,930.08 - - 0.00% - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.00 1,930.08 100.00%
01.02.01.03.02 INSTALACIONES DE RED DE AGUA 984.24 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.03.02.01 SALIDA PUNTO DE AGUA pto 11.00 61.06 671.66 671.66 - - 0.00% - 0.00% - - 0.00% - - 0.00% 11.00 671.66 100.00% - - 0.00%
01.02.01.03.02.02 TUBERIA PVC SAP DE 1/2" m 19.00 2.03 38.57 38.57 - - 0.00% - 0.00% - - 0.00% - - 0.00% 19.00 38.57 100.00% - - 0.00%
01.02.01.03.02.03 VALVULA DE COMPUERTA 1/2" und 2.00 73.86 147.72 147.72 - - 0.00% - 0.00% - - 0.00% - - 0.00% 2.00 147.72 100.00% - - 0.00%
01.02.01.03.02.04 PRUEBA HIDRAULICA + DESINFECCION m 19.00 3.19 60.61 60.61 - - 0.00% - 0.00% - - 0.00% - - 0.00% 19.00 60.61 100.00% - - 0.00%
01.02.01.03.02.05 CAJA PARA VALVULAS DE AGUA und 2.00 32.84 65.68 65.68 - - 0.00% - 0.00% - - 0.00% - - 0.00% 2.00 65.68 100.00% - - 0.00%
01.02.01.03.03 INSTALACIONES DE RED DE DESAGUE 1,401.92 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.03.03.01 SALIDA DE DESAGUE 4" PARA INODORO pto 5.00 37.41 187.05 187.05 - - 0.00% - 0.00% - - 0.00% - - 0.00% 5.00 187.05 100.00% - - 0.00%
01.02.01.03.03.02 SALIDA DE DESAGUE 2", PARA LAVATORIO, URINARIO pto 4.00 177.67 710.68 710.68 - - 0.00% - 0.00% - - 0.00% - - 0.00% 4.00 710.68 100.00% - - 0.00%
01.02.01.03.03.03 SALIDA DE DESAGUE 2" PARA SUMIDERO pto 2.00 43.92 87.84 87.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 87.84 100.00% - - 0.00%
01.02.01.03.03.04 SALIDA PARA VENTILACION EN PVC 2" pto 2.00 32.10 64.20 64.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 64.20 100.00% - - 0.00%
01.02.01.03.03.05 TUBERIA DE PVC SAL 4" m 14.00 12.73 178.22 178.22 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.00 178.22 100.00% - - 0.00%
01.02.01.03.03.06 TUBERIA DE PVC SAL 2" m 22.50 7.73 173.93 173.93 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 22.50 173.93 100.00% - - 0.00%
01.02.01.03.04 ACCESORIOS SANITARIOS 2,441.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.03.04.01 LAVATORIO TIPO OVALIN PARA EMPOTRAR EN MESA DE CONC und 4.00 202.49 809.96 809.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 809.96 100.00%
01.02.01.03.04.02 INODORO TANQUE BAJO NACIONAL pza 5.00 256.28 1,281.40 1,281.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 1,281.40 100.00%
01.02.01.03.04.03 URINARIO TIPO BAMBI PARA NIOS und 1.00 147.95 147.95 147.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 147.95 100.00%
01.02.01.03.04.04 OTROS ACCESORIOS und 1.00 201.98 201.98 201.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 201.98 100.00%
01.02.01.04 INSTALACIONES ELECTRICAS 5,290.28 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01 SALIDA PARA ALUMBRADO, INTERUPTOR Y TOMACORRIENTES 5,290.28 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.01 SALIDA DE ILUMINACION MODULOS 1,311.80 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.01.01 SALIDA PARA CENTROS DE LUZ pto 20.00 65.59 1,311.80 1,311.80 - - 0.00% - - 0.00% - - 0.00% 10.00 655.90 50.00% - - 0.00% 10.00 655.90 50.00%
01.02.01.04.01.02 SALIDA PARA INTERRUPTORES SIMPLES 575.60 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.02.01 SALIDA DE INTERRUPTORES SIMPLES pto 8.00 71.95 575.60 575.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.00 575.60 100.00%
01.02.01.04.01.03 SALIDA DE INTERRUPTORES DOBLES 294.56 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.03.01 SALIDA DE INTERRUPTORES DOBLES pto 4.00 73.64 294.56 294.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 294.56 100.00%
01.02.01.04.01.04 SALIDA PARA TOMACORRIENTES 1,653.12 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.04.01 SALIDA PARA TOMACORRIENTE C/LINEA A TIERRA pto 21.00 78.72 1,653.12 1,653.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.00 1,653.12 100.00%
01.02.01.04.01.05 ARTEFACTOS DE ILUMINACION 847.00 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.05.01 ARTEFACTO FLUORESCENTE 1X36W TIPO CM JOSFEL und 10.00 61.22 612.20 612.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 612.20 100.00%
01.02.01.04.01.05.02 LAMPARA AHORRADORA DE 12W und 10.00 23.48 234.80 234.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 234.80 100.00%
01.02.01.04.01.06 TABLEROS 340.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TABLERO DE DISTRIBUCION TD-2, 3,4... (20X40Cm)
01.02.01.04.01.06.01 und 1.00 340.08 340.08 340.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 340.08 100.00%
01.02.01.04.01.07 INTERRUPTORES TERMOMAGNETICOS DE SALIDA EN TDs 268.12 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.01.04.01.07.01 INTERRUPTOR THERMOMAGNETICO 2 X 15A und 4.00 56.55 226.20 226.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 226.20 100.00%
01.02.01.04.01.07.02 INTERRUPTOR DIFERENCIAL 2x25A und 1.00 41.92 41.92 41.92 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 41.92 100.00%
01.02.02 CONSTRUCCION DE 01 AULAS Y SS.HH. 162,780.84 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01 ESTRUCTURAS 85,607.73 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.01 TRABAJOS PRELIMINARES 234.64 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 126.15 1.36 171.56 171.56 - - 0.00% 126.15 171.56 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 126.15 0.50 63.08 63.08 - - 0.00% 126.15 63.08 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02 MOVIMIENTO DE TIERRAS 5,972.03 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.02.01 PERFILADO MANUAL EN ZONA DE CORTE m2 126.15 2.35 296.45 296.45 - - 0.00% 126.15 296.45 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.02 EXCAVACION PARA ZAPATAS H=1.70M m3 61.00 23.66 1,443.26 1,443.26 - - 0.00% 61.00 1,443.26 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.03 EXCAVACION DE ZANJA PARA CIMENTACION m3 21.69 23.66 513.19 513.19 - - 0.00% 21.69 513.19 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.04 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVAC m2 52.57 2.72 142.99 142.99 - - 0.00% 52.57 142.99 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.05 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO E m3 33.60 16.90 567.84 567.84 - - 0.00% - - 0.00% 33.60 567.84 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.06 RELLENO, CONFORMACION Y COMPACTACION DE BASE E=10 m2 121.87 8.46 1,031.02 1,031.02 - - 0.00% - - 0.00% 121.87 1,031.02 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 103.36 12.06 1,246.52 1,246.52 - - 0.00% - - 0.00% 103.36 1,246.52 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2m3 103.36 7.07 730.76 730.76 - - 0.00% - - 0.00% - - 0.00% 103.36 730.76 100.00% - - 0.00% - - 0.00%
01.02.02.01.03 OBRAS DE CONCRETO SIMPLE 8,451.88 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.03.01 CONCRETO EN FALSA ZAPATAS ;FC= 140 KG/CM2 m3 7.66 376.00 2,880.16 2,880.16 - - 0.00% 7.66 2,880.16 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.03.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 11.74 244.74 2,873.25 2,873.25 - - 0.00% - - 0.00% 11.74 2,873.25 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.03.03 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 4.02 318.13 1,278.88 1,278.88 - - 0.00% - - 0.00% 4.02 1,278.88 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.03.04 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 25.66 51.69 1,326.37 1,326.37 - - 0.00% - - 0.00% 25.66 1,326.37 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.03.05 CURADO DE CONCRETO m2 87.94 1.06 93.22 93.22 - - 0.00% - - 0.00% 87.94 93.22 100.00% - - 0.00% - - 0.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.02.02.01.04 OBRAS DE CONCRETO ARMADO 70,949.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.01 ZAPATAS 12,282.07 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.01.01 CONCRETO EN ZAPATAS F'C= 210 kg/cm2 m3 22.97 411.48 9,451.70 9,451.70 - - 0.00% 11.49 4,725.85 50.00% 11.49 4,725.85 50.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.01.02 ACERO EN ZAPATAS FY= 4200 KG/CM2 kg 582.38 4.86 2,830.37 2,830.37 - - 0.00% 291.19 1,415.19 50.00% 291.19 1,415.19 50.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.02 VIGAS DE CIMENTACION 5,245.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.02.01 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 6.29 377.08 2,371.83 2,371.83 - - 0.00% - - 0.00% 6.29 2,371.83 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION m2 12.58 62.30 783.73 783.73 - - 0.00% - - 0.00% 12.58 783.73 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.02.03 ACERO EN VIGAS DE CIMENTACIN FY= 4200 KG/CM2 kg 445.58 4.66 2,076.40 2,076.40 - - 0.00% - - 0.00% 445.58 2,076.40 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.02.04 CURADO DE CONCRETO m2 12.58 1.06 13.33 13.33 - - 0.00% - - 0.00% 12.58 13.33 100.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.03 COLUMNAS 11,346.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 6.06 411.48 2,493.57 2,493.57 - - 0.00% - - 0.00% 3.03 1,246.79 50.00% 3.03 1,246.79 50.00% - - 0.00% - - 0.00%
01.02.02.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 76.56 53.62 4,105.15 4,105.15 - - 0.00% - - 0.00% 38.28 2,052.58 50.00% 38.28 2,052.58 50.00% - - 0.00% - - 0.00%
01.02.02.01.04.03.03 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 988.63 4.72 4,666.33 4,666.33 - - 0.00% 494.32 2,333.17 50.00% 494.32 2,333.17 50.00% - - 0.00% - - 0.00% - - 0.00%
01.02.02.01.04.03.04 CURADO DE CONCRETO m2 76.56 1.06 81.15 81.15 - - 0.00% - - 0.00% 38.28 40.58 50.00% 38.28 40.58 50.00% - - 0.00% - - 0.00%
01.02.02.01.04.04 COLUMNETAS 1,382.62 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.04.01 CONCRETO EN COLUMNETAS F'C=175 KG/CM2 m3 0.69 432.69 298.56 298.56 - - 0.00% - - 0.00% - - 0.00% 0.69 298.56 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 18.43 49.06 904.18 904.18 - - 0.00% - - 0.00% - - 0.00% 18.43 904.18 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.04.03 ACERO FY=4200 Kg/cm2 kg 33.97 4.72 160.34 160.34 - - 0.00% - - 0.00% - - 0.00% 33.97 160.34 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.04.04 CURADO DE CONCRETO m2 18.43 1.06 19.54 19.54 - - 0.00% - - 0.00% - - 0.00% 18.43 19.54 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.05 VIGAS 16,479.21 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.05.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 9.42 448.88 4,228.45 4,228.45 - - 0.00% - - 0.00% - - 0.00% 9.42 4,228.45 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.05.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 129.15 53.62 6,925.02 6,925.02 - - 0.00% - - 0.00% - - 0.00% 129.15 6,925.02 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.05.03 ACERO FY=4200 Kg/cm2 kg 1,099.33 4.72 5,188.84 5,188.84 - - 0.00% - - 0.00% - - 0.00% 1,099.33 5,188.84 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.05.04 CURADO DE CONCRETO m2 129.15 1.06 136.90 136.90 - - 0.00% - - 0.00% - - 0.00% 129.15 136.90 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.06 VIGUETAS DE CONFINAMIENTO 772.55 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.06.01 CONCRETO EN VIGUETAS F'C=175 KG/CM2 m3 0.21 398.54 83.69 83.69 - - 0.00% - - 0.00% - - 0.00% 0.21 83.69 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.06.02 ENCOFRADO Y DESENCOFRADO PARA VIGUETAS DE CONFI m2 10.95 51.94 568.74 568.74 - - 0.00% - - 0.00% - - 0.00% 10.95 568.74 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.06.03 ACERO FY=4200 Kg/cm2 kg 22.99 4.72 108.51 108.51 - - 0.00% - - 0.00% - - 0.00% 22.99 108.51 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.06.04 CURADO DE CONCRETO m2 10.95 1.06 11.61 11.61 - - 0.00% - - 0.00% - - 0.00% 10.95 11.61 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.07 LOSA ALIGERADA 18,821.36 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.07.01 CONCRETO F'C=210 KG/CM2. PARA LOSAS ALIGERADAS m3 8.37 430.19 3,600.69 3,600.69 - - 0.00% - - 0.00% - - 0.00% 8.37 3,600.69 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGER m2 109.81 64.56 7,089.33 7,089.33 - - 0.00% - - 0.00% - - 0.00% 109.81 7,089.33 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.07.03 LADRILLO HUECO DE ARCILLA 12X30X25 CM PARA LOSA ALI m2 116.49 33.57 3,910.57 3,910.57 - - 0.00% - - 0.00% - - 0.00% 116.49 3,910.57 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.07.04 ACERO FY=4200 Kg/cm2 kg 869.57 4.72 4,104.37 4,104.37 - - 0.00% - - 0.00% - - 0.00% 869.57 4,104.37 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.07.05 CURADO DE CONCRETO m2 109.81 1.06 116.40 116.40 - - 0.00% - - 0.00% - - 0.00% 109.81 116.40 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.08 CANALETA 3,413.92 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.08.01 CONCRETO F'C=210 KG/CM2. PARA CANALETA m3 1.51 472.87 714.03 714.03 - - 0.00% - - 0.00% - - 0.00% 1.51 714.03 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGER m2 32.00 64.56 2,065.92 2,065.92 - - 0.00% - - 0.00% - - 0.00% 32.00 2,065.92 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.08.03 ACERO FY=4200 Kg/cm2 kg 127.13 4.72 600.05 600.05 - - 0.00% - - 0.00% - - 0.00% 127.13 600.05 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.08.04 CURADO DE CONCRETO m2 32.00 1.06 33.92 33.92 - - 0.00% - - 0.00% - - 0.00% 32.00 33.92 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.09 TAPAS LATERALES 1,205.96 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.01.04.09.01 CONCRETO F'C=210 KG/CM2. EN TAPA LATERAL m3 1.39 472.87 657.29 657.29 - - 0.00% - - 0.00% - - 0.00% 1.39 657.29 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.09.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGER m2 7.04 64.56 454.50 454.50 - - 0.00% - - 0.00% - - 0.00% 7.04 454.50 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.09.03 ACERO FY=4200 Kg/cm2 kg 18.37 4.72 86.71 86.71 - - 0.00% - - 0.00% - - 0.00% 18.37 86.71 100.00% - - 0.00% - - 0.00%
01.02.02.01.04.09.04 CURADO DE CONCRETO m2 7.04 1.06 7.46 7.46 - - 0.00% - - 0.00% - - 0.00% 7.04 7.46 100.00% - - 0.00% - - 0.00%
01.02.02.02 ARQUITECTURA 65,985.45 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.01 MUROS Y TABIQUES DE ALBAILERIA 4,589.21 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.01.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 JUNTA 1.5 CM m2 21.80 76.76 1,673.37 1,673.37 - - 0.00% - - 0.00% 10.90 836.69 50.00% 10.90 836.69 50.00% - - 0.00% - - 0.00%
01.02.02.02.01.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 56.20 50.64 2,845.97 2,845.97 - - 0.00% - - 0.00% - - 0.00% 56.20 2,845.97 100.00% - - 0.00% - - 0.00%
01.02.02.02.01.03 JUNTA DE CONSTRUCCION CON TEKNOPORT E=1" m2 19.85 3.52 69.87 69.87 - - 0.00% - - 0.00% - - 0.00% 19.85 69.87 100.00% - - 0.00% - - 0.00%
01.02.02.02.02 REVOQUES Y ENLUCIDOS 8,308.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.02.01 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 91.42 19.46 1,779.03 1,779.03 - - 0.00% - - 0.00% - - 0.00% 36.57 711.61 40.00% 54.85 1,067.42 60.00% - - 0.00%
01.02.02.02.02.02 TARRAJEO EN MURO EXTERIORES MEZCLA 1:5, E=1.50CM m2 44.58 19.46 867.53 867.53 - - 0.00% - - 0.00% - - 0.00% 17.83 347.01 40.00% 26.75 520.52 60.00% - - 0.00%
01.02.02.02.02.03 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.5CM INC. VESTIDU m2 31.50 22.60 711.90 711.90 - - 0.00% - - 0.00% - - 0.00% 12.60 284.76 40.00% 18.90 427.14 60.00% - - 0.00%
01.02.02.02.02.04 TARRAJEO EN COLUMNETAS DE CONFINAMIENTO m2 9.76 23.65 230.82 230.82 - - 0.00% - - 0.00% - - 0.00% 3.90 92.33 40.00% 5.86 138.49 60.00% - - 0.00%
01.02.02.02.02.05 TARRAJEO DE VIGAS Y VIGUETAS MEZCLA 1:5, E=1.5CM m2 60.36 22.60 1,364.14 1,364.14 - - 0.00% - - 0.00% - - 0.00% 24.14 545.66 40.00% 36.22 818.48 60.00% - - 0.00%
01.02.02.02.02.06 TARRAJEO MEZCLA 1:5 EN DERRAMES DE PUERTAS Y VENTANAm 69.40 19.32 1,340.81 1,340.81 - - 0.00% - - 0.00% - - 0.00% 27.76 536.32 40.00% 41.64 804.49 60.00% - - 0.00%
01.02.02.02.02.07 BRUA DE 1/2" m 54.92 1.47 80.73 80.73 - - 0.00% - - 0.00% - - 0.00% 21.97 32.29 40.00% 32.95 48.44 60.00% - - 0.00%
01.02.02.02.02.08 TARRAJEO DE CIELO RASO MEZCLA 1:5, E=1.50CM m2 93.81 20.61 1,933.42 1,933.42 - - 0.00% - - 0.00% - - 0.00% 37.52 773.37 40.00% 56.29 1,160.05 60.00% - - 0.00%
01.02.02.02.03 PISOS Y PAVIMENTOS 10,216.90 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.03.01 FALSO PISO CON CONCRETO F'C=140 KG/CM2 E=5CM m2 86.87 38.25 3,322.78 3,322.78 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 86.87 3,322.78 100.00% - - 0.00%
01.02.02.02.03.02 PISO DE MADERA MACHIHEMBRADA (1.20X0.12 M) m2 40.34 77.79 3,138.05 3,138.05 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 40.34 3,138.05 100.00% - - 0.00%
01.02.02.02.03.03 PISO DE CERAMICO DE 40X40CM m2 46.44 80.88 3,756.07 3,756.07 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 46.44 3,756.07 100.00% - - 0.00%
01.02.02.02.04 VEREDAS 16,209.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.04.01 CONCRETO FC=175 KG/CM2 EN VEREDAS m3 36.75 403.13 14,815.03 14,815.03 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 36.75 14,815.03 100.00% - - 0.00%
01.02.02.02.04.02 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 22.07 49.06 1,082.75 1,082.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 22.07 1,082.75 100.00% - - 0.00%
01.02.02.02.04.03 JUNTA DE ASFALTICA m2 14.30 12.53 179.18 179.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.30 179.18 100.00% - - 0.00%
01.02.02.02.04.04 BRUA EN VEREDA m 90.02 1.47 132.33 132.33 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 90.02 132.33 100.00% - - 0.00%
01.02.02.02.05 ZOCALOS Y CONTRAZOCALOS 2,013.10 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.05.01 ZOCALO DE CERAMICO DE 20X30CM SSHH m2 38.52 20.50 789.66 789.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 38.52 789.66 100.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.02.02.02.05.02 CONTRAZOCALO DE MADERA H=10 CM m 43.38 21.69 940.91 940.91 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 43.38 940.91 100.00% - - 0.00%
01.02.02.02.05.03 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM EN EXTER m 35.90 7.87 282.53 282.53 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.90 282.53 100.00% - - 0.00%
01.02.02.02.06 COBERTURAS 4,949.66 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.06.01 COBERTURA CON TEJA ANDINA INDUSTRIAL m2 116.49 36.65 4,269.36 4,269.36 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 116.49 4,269.36 100.00% - - 0.00%
01.02.02.02.06.02 CUMBRERA DE TEJA ANDINA INDUSTRIAL m 12.24 55.58 680.30 680.30 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.24 680.30 100.00% - - 0.00%
01.02.02.02.07 CARPINTERIA DE MADERA 10,875.53 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.07.01 PUERTA DE MADERA APANELADA m2 13.51 318.00 4,296.18 4,296.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.51 4,296.18 100.00%
01.02.02.02.07.02 PUERTA DE MELAMINA CON MARCO DE ALUMINIO m2 6.12 264.81 1,620.64 1,620.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.12 1,620.64 100.00%
01.02.02.02.07.03 TABIQUERIA DE MELAMINE Y ALUMIO PARA BAOS SUEGUN DI m2 15.48 320.33 4,958.71 4,958.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.48 4,958.71 100.00%
01.02.02.02.08 CARPINTERIA METALICA Y HERRERIA 1,695.65 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.08.01 VENTANA DE ALUMINIO m2 1.66 231.79 384.77 384.77 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.66 384.77 100.00%
01.02.02.02.08.02 BISAGRA CAPUCHINA DE 4" X 4" und 28.00 13.32 372.96 372.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 28.00 372.96 100.00%
01.02.02.02.08.03 CERRADURA DE 3 GOLPES PARA PUERTA pza 6.00 82.97 497.82 497.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 497.82 100.00%
01.02.02.02.08.04 CHAPA PARA BAO, CON SEGURO INTERIOR Y PERILLA O MANI und 5.00 45.00 225.00 225.00 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 225.00 100.00%
01.02.02.02.08.05 MANIJA DE BRONCE PARA PUERTAS und 6.00 35.85 215.10 215.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 215.10 100.00%
01.02.02.02.09 VENTANAS, CRISTALERIA Y SIMILARES 1,757.39 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.09.01 VIDRIOS SEMIDOBLES INCOLORO CRUDO p2 116.77 15.05 1,757.39 1,757.39 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 116.77 1,757.39 100.00%
01.02.02.02.10 PINTURA 5,370.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.02.10.01 PINTURA EN MUROS INTERIORES AL LATEX ACABADO MATE m2 91.42 8.54 780.73 780.73 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 91.42 780.73 100.00%
01.02.02.02.10.02 PINTURA EN MUROS EXTERIOR AL LATEX AGRILICO 2 MANOS m2 44.58 8.54 380.71 380.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 44.58 380.71 100.00%
01.02.02.02.10.03 PINTURA EN VIGAS Y COLUMNAS LATEX ACABADO MATE, 2 MA m2 94.12 13.91 1,309.21 1,309.21 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 94.12 1,309.21 100.00%
01.02.02.02.10.04 PINTURA EN DERRAME DE PUERTAS Y VENTANAS Y VANOS L m 69.40 5.82 403.91 403.91 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 69.40 403.91 100.00%
01.02.02.02.10.05 PINTURA EN CIELO RASO AL LATEX 2 MANOS m2 95.62 15.73 1,504.10 1,504.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 95.62 1,504.10 100.00%
01.02.02.02.10.06 PINTURA ESMALTE EN CONTRA ZOCALO DE CEMENTO m 35.90 19.66 705.79 705.79 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.90 705.79 100.00%
01.02.02.02.10.07 PINTURA EN PUERTAS C/BARNIZ 2 MANOS m2 19.11 14.96 285.89 285.89 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.11 285.89 100.00%
01.02.02.03 INSTALACIONES SANITARIAS 7,478.89 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.03.01 DRENAJE PLUVIAL 2,621.89 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.03.01.01 CONCRETO EN COLUMNETAS DE BAJADA PLUVIAL F'C=175 KG/ m3 0.13 425.18 55.27 55.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.13 55.27 100.00%
01.02.02.03.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETA m2 2.40 42.06 100.94 100.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.40 100.94 100.00%
01.02.02.03.01.03 DESAGUE PLUVIAL CON TUBERIA PVC SAL DE 3" m 20.44 120.63 2,465.68 2,465.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 20.44 2,465.68 100.00%
01.02.02.03.02 INSTALACIONES DE RED DE AGUA 966.12 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.03.02.01 SALIDA PUNTO DE AGUA pto 10.00 61.06 610.60 610.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 610.60 100.00%
01.02.02.03.02.02 TUBERIA PVC SAP DE 1/2" m 18.00 2.03 36.54 36.54 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.00 36.54 100.00%
01.02.02.03.02.03 TUBERIA PVC SAP DE 3/4" m 1.40 7.07 9.90 9.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.40 9.90 100.00%
01.02.02.03.02.04 VALVULA DE COMPUERTA 1/2" und 2.00 73.86 147.72 147.72 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 147.72 100.00%
01.02.02.03.02.05 PRUEBA HIDRAULICA + DESINFECCION m 19.70 3.19 62.84 62.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.70 62.84 100.00%
01.02.02.03.02.06 CAJA PARA VALVULAS DE AGUA und 3.00 32.84 98.52 98.52 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 98.52 100.00%
01.02.02.03.03 INSTALACIONES DE RED DE DESAGUE 1,449.59 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.03.03.01 SALIDA DE DESAGUE 4" PARA INODORO pto 5.00 37.41 187.05 187.05 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 187.05 100.00%
01.02.02.03.03.02 SALIDA DE DESAGUE 2", PARA LAVATORIO, URINARIO pto 5.00 177.67 888.35 888.35 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 888.35 100.00%
01.02.02.03.03.03 SALIDA DE DESAGUE 2" PARA SUMIDERO pto 2.00 43.92 87.84 87.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 87.84 100.00%
01.02.02.03.03.04 SALIDA PARA VENTILACION EN PVC 2" pto 2.00 32.10 64.20 64.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 64.20 100.00%
01.02.02.03.03.05 TUBERIA DE PVC SAL 4" m 13.20 12.73 168.04 168.04 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.20 168.04 100.00%
01.02.02.03.03.06 TUBERIA DE PVC SAL 2" m 7.00 7.73 54.11 54.11 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.00 54.11 100.00%
01.02.02.03.04 ACCESORIOS SANITARIOS 2,441.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.03.04.01 LAVATORIO TIPO OVALIN PARA EMPOTRAR EN MESA DE CONC und 4.00 202.49 809.96 809.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 809.96 100.00%
01.02.02.03.04.02 INODORO TANQUE BAJO NACIONAL pza 5.00 256.28 1,281.40 1,281.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 1,281.40 100.00%
01.02.02.03.04.03 URINARIO TIPO BAMBI PARA NIOS und 1.00 147.95 147.95 147.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 147.95 100.00%
01.02.02.03.04.04 OTROS ACCESORIOS und 1.00 201.98 201.98 201.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 201.98 100.00%
01.02.02.04 INSTALACIONES ELECTRICAS 3,708.77 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01 SALIDA PARA ALUMBRADO, INTERUPTOR Y TOMACORRIENTES 3,708.77 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.01 SALIDA DE ILUMINACION MODULOS 918.26 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.01.01 SALIDA PARA CENTROS DE LUZ pto 14.00 65.59 918.26 918.26 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.00 918.26 100.00%
01.02.02.04.01.02 SALIDA PARA INTERRUPTORES SIMPLES 647.55 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.02.01 SALIDA DE INTERRUPTORES SIMPLES pto 9.00 71.95 647.55 647.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.00 647.55 100.00%
01.02.02.04.01.03 SALIDA DE INTERRUPTORES DOBLES 73.64 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.03.01 SALIDA DE INTERRUPTORES DOBLES pto 1.00 73.64 73.64 73.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 73.64 100.00%
01.02.02.04.01.04 SALIDA PARA TOMACORRIENTES 1,023.36 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.04.01 SALIDA PARA TOMACORRIENTE C/LINEA A TIERRA pto 13.00 78.72 1,023.36 1,023.36 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.00 1,023.36 100.00%
01.02.02.04.01.05 ARTEFACTOS DE ILUMINACION 479.68 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.05.01 ARTEFACTO FLUORESCENTE 1X36W TIPO CM JOSFEL und 4.00 61.22 244.88 244.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 244.88 100.00%
01.02.02.04.01.05.02 LAMPARA AHORRADORA DE 12W und 10.00 23.48 234.80 234.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 234.80 100.00%
01.02.02.04.01.06 TABLEROS 340.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TABLERO DE DISTRIBUCION TD-2, 3,4... (20X40Cm)
01.02.02.04.01.06.01 und 1.00 340.08 340.08 340.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 340.08 100.00%
01.02.02.04.01.07 INTERRUPTORES TERMOMAGNETICOS DE SALIDA EN TDs 226.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.02.02.04.01.07.01 INTERRUPTOR THERMOMAGNETICO 2 X 15A und 4.00 56.55 226.20 226.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 226.20 100.00%
01.03 MODULO 02: ADMINISTRATIVO 111,257.44 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01 ESTRUCTURAS 56,406.89 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.01 TRABAJOS PRELIMINARES 148.45 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 79.81 1.36 108.54 108.54 - - 0.00% - - 0.00% 79.81 108.54 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 79.81 0.50 39.91 39.91 - - 0.00% - - 0.00% 79.81 39.91 100.00% - - 0.00% - - 0.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.03.01.02 MOVIMIENTO DE TIERRAS 2,575.89 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.02.01 PERFILADO MANUAL EN ZONA DE CORTE m2 79.81 2.35 187.55 187.55 - - 0.00% - - 0.00% 79.81 187.55 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.02.02 EXCAVACION PARA ZAPATAS m3 35.85 23.66 848.21 848.21 - - 0.00% - - 0.00% 35.85 848.21 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.02.03 EXCAVACION DE ZANJA PARA CIMENTACION m3 15.65 23.66 370.28 370.28 - - 0.00% - - 0.00% 15.65 370.28 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.02.04 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACIO m2 24.72 2.72 67.24 67.24 - - 0.00% - - 0.00% 24.72 67.24 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.02.05 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m3 23.01 16.90 388.87 388.87 - - 0.00% - - 0.00% - - 0.00% 23.01 388.87 100.00% - - 0.00% - - 0.00%
01.03.01.02.06 RELLENO, CONFORMACION Y COMPACTACION DE BASE E=10CM m2 0.91 8.46 7.70 7.70 - - 0.00% - - 0.00% - - 0.00% 0.91 7.70 100.00% - - 0.00% - - 0.00%
01.03.01.02.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 37.00 12.06 446.22 446.22 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 37.00 446.22 100.00% - - 0.00%
01.03.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2.0m3 36.75 7.07 259.82 259.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 36.75 259.82 100.00% - - 0.00%
01.03.01.03 OBRAS DE CONCRETO SIMPLE 5,120.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.03.01 CONCRETO EN FALSA ZAPATAS ;FC= 140 KG/CM2 m3 4.94 376.00 1,857.44 1,857.44 - - 0.00% - - 0.00% 4.94 1,857.44 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.03.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 7.19 244.74 1,759.68 1,759.68 - - 0.00% - - 0.00% 7.19 1,759.68 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 13.36 51.69 690.58 690.58 - - 0.00% - - 0.00% - - 0.00% 13.36 690.58 100.00% - - 0.00% - - 0.00%
01.03.01.03.04 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 2.51 318.13 798.51 798.51 - - 0.00% - - 0.00% - - 0.00% 2.51 798.51 100.00% - - 0.00% - - 0.00%
01.03.01.03.05 CURADO DE CONCRETO m2 13.20 1.06 13.99 13.99 - - 0.00% - - 0.00% - - 0.00% 13.20 13.99 100.00% - - 0.00% - - 0.00%
01.03.01.04 OBRAS DE CONCRETO ARMADO 48,562.35 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.01 ZAPATAS 8,590.58 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.01.01 ACERO EN ZAPATAS FY= 4200 KG/CM2 kg 367.61 4.86 1,786.58 1,786.58 - - 0.00% - - 0.00% 367.61 1,786.58 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.01.02 CONCRETO PARA ZAPATAS F'C=210 KG/CM2 m3 14.83 458.80 6,804.00 6,804.00 - - 0.00% - - 0.00% 14.83 6,804.00 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.02 VIGAS DE CIMENTACION 4,741.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.02.01 ACERO EN VIGAS DE CIMENTACIN FY= 4200 KG/CM2 kg 628.28 4.66 2,927.78 2,927.78 - - 0.00% - - 0.00% 628.28 2,927.78 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION m2 9.86 64.29 633.90 633.90 - - 0.00% - - 0.00% 9.86 633.90 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.02.03 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 3.10 377.08 1,168.95 1,168.95 - - 0.00% - - 0.00% 3.10 1,168.95 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.02.04 CURADO DE CONCRETO m2 9.86 1.06 10.45 10.45 - - 0.00% - - 0.00% 9.86 10.45 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.03 COLUMNAS 9,855.64 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.03.01 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 988.58 4.72 4,666.10 4,666.10 - - 0.00% - - 0.00% 988.58 4,666.10 100.00% - - 0.00% - - 0.00% - - 0.00%
01.03.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 62.85 53.62 3,370.02 3,370.02 - - 0.00% - - 0.00% - - 0.00% 62.85 3,370.02 100.00% - - 0.00% - - 0.00%
01.03.01.04.03.03 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 4.26 411.48 1,752.90 1,752.90 - - 0.00% - - 0.00% - - 0.00% 4.26 1,752.90 100.00% - - 0.00% - - 0.00%
01.03.01.04.03.04 CURADO DE CONCRETO m2 62.85 1.06 66.62 66.62 - - 0.00% - - 0.00% - - 0.00% 62.85 66.62 100.00% - - 0.00% - - 0.00%
01.03.01.04.04 COLUMNETAS 889.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.04.01 ACERO FY=4200 Kg/cm2 kg 10.26 4.72 48.43 48.43 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.26 48.43 100.00% - - 0.00%
01.03.01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 11.94 49.06 585.78 585.78 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.94 585.78 100.00% - - 0.00%
01.03.01.04.04.03 CONCRETO EN COLUMNETAS F'C=175 KG/CM2 m3 0.56 432.69 242.31 242.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.56 242.31 100.00% - - 0.00%
01.03.01.04.04.04 CURADO DE CONCRETO m2 11.94 1.06 12.66 12.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.94 12.66 100.00% - - 0.00%
01.03.01.04.05 VIGAS 12,617.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.05.01 ACERO FY=4200 Kg/cm2 kg 873.37 4.72 4,122.31 4,122.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 873.37 4,122.31 100.00% - - 0.00%
01.03.01.04.05.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 85.91 53.62 4,606.49 4,606.49 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 85.91 4,606.49 100.00% - - 0.00%
01.03.01.04.05.03 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 8.46 448.88 3,797.52 3,797.52 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.46 3,797.52 100.00% - - 0.00%
01.03.01.04.05.04 CURADO DE CONCRETO m2 85.91 1.06 91.06 91.06 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 85.91 91.06 100.00% - - 0.00%
01.03.01.04.06 VIGUETAS 608.32 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.06.01 ACERO FY=4200 Kg/cm2 kg 53.69 4.72 253.42 253.42 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 53.69 253.42 100.00% - - 0.00%
01.03.01.04.06.02 ENCOFRADO Y DESENCOFRADO PARA VIGUETAS DE CONFINA m2 4.29 51.94 222.82 222.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.29 222.82 100.00% - - 0.00%
01.03.01.04.06.03 CONCRETO EN VIGUETAS F'C=175 KG/CM2 m3 0.32 398.54 127.53 127.53 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.32 127.53 100.00% - - 0.00%
01.03.01.04.06.04 CURADO DE CONCRETO m2 4.29 1.06 4.55 4.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.29 4.55 100.00% - - 0.00%
01.03.01.04.07 LOSA ALIGERADA 10,925.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.07.01 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERAD m2 66.31 64.56 4,280.97 4,280.97 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 66.31 4,280.97 100.00% - - 0.00%
01.03.01.04.07.02 LADRILLO HUECO DE ARCILLA 12X30X25 CM PARA LOSA ALIGE m2 59.03 33.57 1,981.64 1,981.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 59.03 1,981.64 100.00% - - 0.00%
01.03.01.04.07.03 ACERO FY=4200 Kg/cm2 kg 500.83 4.72 2,363.92 2,363.92 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 500.83 2,363.92 100.00% - - 0.00%
01.03.01.04.07.04 CONCRETO F'C=210 KG/CM2. PARA LOSAS ALIGERADAS m3 5.18 430.19 2,228.38 2,228.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.18 2,228.38 100.00% - - 0.00%
01.03.01.04.07.05 CURADO DE CONCRETO m2 66.31 1.06 70.29 70.29 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 66.31 70.29 100.00% - - 0.00%
01.03.01.04.08 MUEBLE DE CONCRETO REVESTIDO EN CERMICO 334.97 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.01.04.08.01 ACERO FY=4200 KG/CM2 kg 32.09 4.48 143.76 143.76 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 32.09 143.76 100.00% - - 0.00%
01.03.01.04.08.02 ENCOFRADO Y DESENCOFRADO DE MUEBLE DE SS.HH. m2 2.76 49.06 135.41 135.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.76 135.41 100.00% - - 0.00%
01.03.01.04.08.03 CONCRETO EN MUEBLE DE CONICA F'C=175 KG/CM2 m3 0.12 440.60 52.87 52.87 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.12 52.87 100.00% - - 0.00%
01.03.01.04.08.04 CURADO DE CONCRETO m2 2.76 1.06 2.93 2.93 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.76 2.93 100.00% - - 0.00%
01.03.02 ARQUITECTURA 47,617.09 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.01 MUROS Y TABIQUES DE ALBAILERIA 4,704.26 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.01.01 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 JUNTA 1.5 CM m2 26.17 76.76 2,008.81 2,008.81 - - 0.00% - - 0.00% - - 0.00% 26.17 2,008.81 100.00% - - 0.00% - - 0.00%
01.03.02.01.02 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 53.09 50.64 2,688.48 2,688.48 - - 0.00% - - 0.00% - - 0.00% 26.55 1,344.24 50.00% 26.55 1,344.24 50.00% - - 0.00%
01.03.02.01.03 JUNTA DE CONSTRUCCION CON TEKNOPORT E=1" m2 1.98 3.52 6.97 6.97 - - 0.00% - - 0.00% - - 0.00% 0.99 3.49 50.00% 0.99 3.49 50.00% - - 0.00%
01.03.02.02 REVOQUES Y ENLUCIDOS 8,747.57 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.02.01 TARRAJEO DE CIELO RASO MEZCLA 1:5, E=1.50CM m2 65.72 20.61 1,354.49 1,354.49 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 32.86 677.25 50.00% 32.86 677.25 50.00%
01.03.02.02.02 TARRAJEO DE VIGAS Y VIGUETAS MEZCLA 1:5, E=1.5CM m2 72.39 22.60 1,636.01 1,636.01 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 36.20 818.01 50.00% 36.20 818.01 50.00%
01.03.02.02.03 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 122.58 19.46 2,385.41 2,385.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 61.29 1,192.71 50.00% 61.29 1,192.71 50.00%
01.03.02.02.04 TARRAJEO EN MURO EXTERIORES MEZCLA 1:5, E=1.50CM m2 38.87 19.46 756.41 756.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.44 378.21 50.00% 19.44 378.21 50.00%
01.03.02.02.05 TARRAJEO DE COLUMNAS Y COLUMNETAS MEZCLA 1:5, E=1.5CM m2 63.03 22.60 1,424.48 1,424.48 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 31.52 712.24 50.00% 31.52 712.24 50.00%
01.03.02.02.06 TARRAJEO MEZCLA 1:5 EN DERRAMES DE PUERTAS Y VENTANAS m 46.98 19.32 907.65 907.65 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 23.49 453.83 50.00% 23.49 453.83 50.00%
01.03.02.02.07 BRUA DE 1/2" m 192.60 1.47 283.12 283.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 96.30 141.56 50.00% 96.30 141.56 50.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.03.02.03 PISOS Y PAVIMENTOS 5,911.05 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.03.01 FALSO PISO CON CONCRETO F'C=140 KG/CM2 E=5CM m2 44.71 38.25 1,710.16 1,710.16 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 44.71 1,710.16 100.00%
01.03.02.03.02 CONTRAPISO DE 48 MM. m2 35.31 25.36 895.46 895.46 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.31 895.46 100.00%
01.03.02.03.03 PISO DE CERAMICO DE 40X40CM m2 35.31 80.88 2,855.87 2,855.87 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.31 2,855.87 100.00%
01.03.02.03.04 PISO CEMENTO PULIDO m2 9.40 29.39 276.27 276.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.40 276.27 100.00%
01.03.02.03.05 JUNTA DE DILATACION CON TEKNOPORT m2 49.23 3.52 173.29 173.29 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 49.23 173.29 100.00%
01.03.02.04 VEREDAS 4,421.12 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.04.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 9.93 49.06 487.17 487.17 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.93 487.17 100.00%
01.03.02.04.02 CONCRETO FC=175 KG/CM2 EN VEREDAS m3 9.09 403.13 3,664.45 3,664.45 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.09 3,664.45 100.00%
01.03.02.04.03 BRUA EN VEREDA m 86.16 1.47 126.66 126.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 86.16 126.66 100.00%
01.03.02.04.04 JUNTA DE ASFALTICA m2 11.40 12.53 142.84 142.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.40 142.84 100.00%
01.03.02.05 ZOCALOS Y CONTRAZOCALOS 1,274.37 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.05.01 ZOCALO DE CERAMICO DE 30X30CM m2 51.78 20.50 1,061.49 1,061.49 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 51.78 1,061.49 100.00%
01.03.02.05.02 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM FROTACHAD m 27.05 7.87 212.88 212.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 27.05 212.88 100.00%
01.03.02.06 COBERTURAS 2,592.53 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.06.01 COBERTURA CON TEJA ANDINA INDUSTRIAL m2 59.03 36.65 2,163.45 2,163.45 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 59.03 2,163.45 100.00%
01.03.02.06.02 CUMBRERA DE TEJA ANDINA INDUSTRIAL m 7.72 55.58 429.08 429.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.72 429.08 100.00%
01.03.02.07 CARPINTERIA DE MADERA 2,938.32 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.07.01 PUERTA DE MADERA APANELADA m2 9.24 318.00 2,938.32 2,938.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.24 2,938.32 100.00%
01.03.02.08 CARPINTERIA METALICA Y HERRERIA 793.90 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.08.01 BISAGRA CAPUCHINA DE 4" X 4" und 15.00 13.32 199.80 199.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.00 199.80 100.00%
01.03.02.08.02 CERRADURA DE 3 GOLPES PARA PUERTA pza 5.00 82.97 414.85 414.85 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 414.85 100.00%
01.03.02.08.03 MANIJA DE BRONCE PARA PUERTAS und 5.00 35.85 179.25 179.25 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 179.25 100.00%
01.03.02.09 VENTANAS, CRISTALERIA Y SIMILARES 9,497.06 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.09.01 VENTANA DE ALUMINIO m2 24.13 231.79 5,593.09 5,593.09 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 24.13 5,593.09 100.00%
01.03.02.09.02 VIDRIOS SEMIDOBLES INCOLORO CRUDO p2 259.40 15.05 3,903.97 3,903.97 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 259.40 3,903.97 100.00%
01.03.02.10 PINTURA 6,736.91 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.02.10.01 PINTURA EN CIELO RASO AL LATEX 2 MANOS m2 61.20 15.73 962.68 962.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 61.20 962.68 100.00%
01.03.02.10.02 PINTURA EN MUROS INTERIORES AL LATEX ACABADO MATE m2 78.51 8.54 670.48 670.48 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 78.51 670.48 100.00%
01.03.02.10.03 PINTURA EN MUROS EXTERIOR AL LATEX AGRILICO 2 MANOS m2 40.82 8.54 348.60 348.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 40.82 348.60 100.00%
01.03.02.10.04 PINTURA EN VIGAS Y COLUMNAS LATEX ACABADO MATE, 2 MANOm2 303.62 13.91 4,223.35 4,223.35 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 303.62 4,223.35 100.00%
01.03.02.10.05 PINTURA ESMALTE EN CONTRA ZOCALO DE CEMENTO m 27.05 19.66 531.80 531.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 27.05 531.80 100.00%
01.03.03 INSTALACIONES SANITARIAS 4,113.92 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.03.01 DRENAJE PLUVIAL 2,513.06 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.03.01.01 ENCOFRADO Y DESENCOFRADO DE COLUMNETA m2 5.40 42.06 227.12 227.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.40 227.12 100.00%
01.03.03.01.02 CONCRETO EN COLUMNETAS DE BAJADA PLUVIAL F'C=175 KG/CMm3 0.61 425.18 259.36 259.36 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.61 259.36 100.00%
01.03.03.01.03 DESAGUE PLUVIAL CON TUBERIA PVC SAL DE 3" m 16.80 120.63 2,026.58 2,026.58 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.80 2,026.58 100.00%
01.03.03.02 INSTALACIONES DE RED DE AGUA DE FRIA 460.56 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.03.02.01 SALIDA PUNTO DE AGUA pto 4.00 61.06 244.24 244.24 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 244.24 100.00%
01.03.03.02.02 TUBERIA PVC SAP DE 1/2" m 21.00 2.03 42.63 42.63 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.00 42.63 100.00%
01.03.03.02.03 VALVULA DE COMPUERTA 1/2" und 1.00 73.86 73.86 73.86 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 73.86 100.00%
01.03.03.02.04 PRUEBA HIDRAULICA + DESINFECCION m 21.00 3.19 66.99 66.99 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.00 66.99 100.00%
01.03.03.02.05 CAJA PARA VALVULAS DE AGUA und 1.00 32.84 32.84 32.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 32.84 100.00%
01.03.03.03 INSTALACIONES DE RED DE DESAGUE 479.04 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.03.03.01 SALIDA DE DESAGUE 4" PARA INODORO pto 1.00 37.41 37.41 37.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 37.41 100.00%
01.03.03.03.02 SALIDA DE DESAGUE 2" PARA LAVATORIO pto 2.00 79.27 158.54 158.54 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 158.54 100.00%
01.03.03.03.03 SALIDA DE DESAGUE 2" PARA SUMIDERO pto 2.00 43.92 87.84 87.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 87.84 100.00%
01.03.03.03.04 TUBERIA DE PVC SAL 4" m 5.50 12.73 70.02 70.02 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.50 70.02 100.00%
01.03.03.03.05 TUBERIA DE PVC SAL 2" m 16.20 7.73 125.23 125.23 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.20 125.23 100.00%
01.03.03.04 APARATOS Y ACCESORIOS SANITARIOS 661.26 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.03.04.01 LAVATORIO DE PARED BLANCO 1 LLAVE und 2.00 202.49 404.98 404.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 404.98 100.00%
01.03.03.04.02 INODORO TANQUE BAJO NACIONAL pza 1.00 256.28 256.28 256.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 256.28 100.00%
01.03.04 INSTALACIONES ELECTRICAS 3,119.54 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01 SALIDA PARA ALUMBRADO, INTERUPTOR Y TOMACORRIENTES 3,119.54 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.01 SALIDA DE ILUMINACION MODULOS 655.90 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.01.01 SALIDA PARA CENTROS DE LUZ pto 10.00 65.59 655.90 655.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 655.90 100.00% - - 0.00%
01.03.04.01.02 SALIDA PARA INTERRUPTORES 510.41 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.02.01 SALIDA DE INTERRUPTORES SIMPLES pto 3.00 71.95 215.85 215.85 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 215.85 100.00% - - 0.00%
01.03.04.01.02.02 SALIDA DE INTERRUPTORES DOBLES pto 4.00 73.64 294.56 294.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 294.56 100.00% - - 0.00%
01.03.04.01.03 SALIDA PARA TOMACORRIENTES 944.64 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.03.01 SALIDA PARA TOMACORRIENTE C/LINEA A TIERRA pto 12.00 78.72 944.64 944.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.00 944.64 100.00%
01.03.04.01.04 ARTEFACTOS DE ILUMINACION 385.76 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.04.01 ARTEFACTO FLUORESCENTE 1X36W TIPO CM JOSFEL und 4.00 61.22 244.88 244.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 244.88 100.00%
01.03.04.01.04.02 LAMPARA AHORRADORA DE 12W und 6.00 23.48 140.88 140.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 140.88 100.00%
01.03.04.01.05 TABLEROS 340.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TABLERO DE DISTRIBUCION TD-2, 3,4... (20X40Cm)
01.03.04.01.05.01 und 1.00 340.08 340.08 340.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 340.08 100.00%
01.03.04.01.06 INTERRUPTORES TERMOMAGNETICOS DE SALIDA EN TDs 282.75 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.03.04.01.06.01 INTERRUPTOR THERMOMAGNETICO 2 X 15A und 5.00 56.55 282.75 282.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 282.75 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.04 MODULO 03: SUM Y PSICOMOTRICIDAD 186,681.85 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01 ESTRUCTURAS 104,302.53 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.01 TRABAJOS PRELIMINARES 240.71 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 129.41 1.36 176.00 176.00 - 0.00 0.00% 129.41 176.00 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 129.41 0.50 64.71 64.71 - 0.00 0.00% 129.41 64.71 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02 MOVIMIENTO DE TIERRAS 6,096.54 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.02.01 PERFILADO MANUAL EN ZONA DE CORTE m2 129.41 2.35 304.11 304.11 - 0.00 0.00% 129.41 304.11 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.02 EXCAVACION PARA ZAPATAS m3 57.41 23.66 1,358.32 1,358.32 - 0.00 0.00% 57.41 1,358.32 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.03 EXCAVACION DE ZANJA PARA CIMENTACION m3 30.61 23.66 724.23 724.23 - 0.00 0.00% 30.61 724.23 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.04 EXCAVACION DE ZANJA PARA VIGAS DE CIMENTACIN m3 1.69 24.12 40.76 40.76 - 0.00 0.00% 1.69 40.76 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.05 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACIO m2 54.40 2.72 147.97 147.97 - 0.00 0.00% 54.40 147.97 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.06 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m3 20.78 16.90 351.18 351.18 - - 0.00% - - 0.00% 20.78 351.18 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.07 RELLENO, CONFORMACION Y COMPACTACION DE BASE E=10CM m2 137.00 8.46 1,159.02 1,159.02 - - 0.00% - - 0.00% 137.00 1,159.02 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.02.08 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 105.12 12.06 1,267.75 1,267.75 - - 0.00% - - 0.00% - - 0.00% 105.12 1,267.75 100.00% - - 0.00% - - 0.00%
01.04.01.02.09 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2.0m3 105.12 7.07 743.20 743.20 - - 0.00% - - 0.00% - - 0.00% 105.12 743.20 100.00% - - 0.00% - - 0.00%
01.04.01.03 OBRAS DE CONCRETO SIMPLE 16,747.40 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.03.01 CONCRETO EN FALSA ZAPATAS ;FC= 140 KG/CM2 m3 22.95 376.00 8,629.20 8,629.20 - - 0.00% 22.95 8,629.20 100.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.03.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 15.77 244.74 3,859.55 3,859.55 - - 0.00% - - 0.00% 15.77 3,859.55 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.03.03 SOLADO PARA VIGAS DE CIMENTACIN DE 2" DE ESPESOR; M m2 3.34 24.75 82.67 82.67 - - 0.00% - - 0.00% 3.34 82.67 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.03.04 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 52.75 51.69 2,726.65 2,726.65 - - 0.00% - - 0.00% 52.75 2,726.65 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.03.05 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 4.38 318.13 1,393.41 1,393.41 - - 0.00% - - 0.00% 4.38 1,393.41 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.03.06 CURADO DE CONCRETO m2 52.75 1.06 55.92 55.92 - - 0.00% - - 0.00% 52.75 55.92 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04 OBRAS DE CONCRETO ARMADO 81,217.88 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.01 ZAPATAS 11,415.62 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.01.01 ACERO EN ZAPATAS FY= 4200 KG/CM2 kg 526.02 4.86 2,556.46 2,556.46 - - 0.00% 210.41 1,022.58 40.00% 315.61 1,533.88 60.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.01.02 CONCRETO EN ZAPATAS F'C= 210 kg/cm2 m3 21.53 411.48 8,859.16 8,859.16 - - 0.00% 8.61 3,543.66 40.00% 12.92 5,315.50 60.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.02 VIGAS DE CIMENTACION 10,272.45 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.02.01 ACERO EN VIGAS DE CIMENTACIN FY= 4200 KG/CM2 kg 897.11 4.66 4,180.53 4,180.53 - - 0.00% - - 0.00% 897.11 4,180.53 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION m2 45.68 62.30 2,845.86 2,845.86 - - 0.00% - - 0.00% 45.68 2,845.86 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.02.03 CONCRETO EN VIGAS DE CIMENTACION F'C= 210 KG/CM2 m3 8.48 377.08 3,197.64 3,197.64 - - 0.00% - - 0.00% 8.48 3,197.64 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.02.04 CURADO DE CONCRETO m2 45.68 1.06 48.42 48.42 - - 0.00% - - 0.00% 45.68 48.42 100.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.03 COLUMNAS 11,704.26 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.03.01 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 1,103.24 4.72 5,207.29 5,207.29 - - 0.00% 441.30 2,082.92 40.00% 661.94 3,124.37 60.00% - - 0.00% - - 0.00% - - 0.00%
01.04.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 64.26 53.62 3,445.62 3,445.62 - - 0.00% - - 0.00% 32.13 1,722.81 50.00% 32.13 1,722.81 50.00% - - 0.00% - - 0.00%
01.04.01.04.03.03 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 7.25 411.48 2,983.23 2,983.23 - - 0.00% - - 0.00% 3.63 1,491.62 50.00% 3.63 1,491.62 50.00% - - 0.00% - - 0.00%
01.04.01.04.03.04 CURADO DE CONCRETO m2 64.26 1.06 68.12 68.12 - - 0.00% - - 0.00% 32.13 34.06 50.00% 32.13 34.06 50.00% - - 0.00% - - 0.00%
01.04.01.04.04 COLUMNETAS 2,400.74 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.04.01 ACERO FY=4200 Kg/cm2 kg 76.71 4.72 362.07 362.07 - - 0.00% - - 0.00% - - 0.00% 76.71 362.07 100.00% - - 0.00% - - 0.00%
01.04.01.04.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2 29.28 49.06 1,436.48 1,436.48 - - 0.00% - - 0.00% - - 0.00% 29.28 1,436.48 100.00% - - 0.00% - - 0.00%
01.04.01.04.04.03 CONCRETO EN COLUMNETAS F'C=175 KG/CM2 m3 1.32 432.69 571.15 571.15 - - 0.00% - - 0.00% - - 0.00% 1.32 571.15 100.00% - - 0.00% - - 0.00%
01.04.01.04.04.04 CURADO DE CONCRETO m2 29.28 1.06 31.04 31.04 - - 0.00% - - 0.00% - - 0.00% 29.28 31.04 100.00% - - 0.00% - - 0.00%
01.04.01.04.05 VIGAS 23,079.22 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.05.01 ACERO FY=4200 Kg/cm2 kg 1,735.51 4.72 8,191.61 8,191.61 - - 0.00% - - 0.00% - - 0.00% 1,735.51 8,191.61 100.00% - - 0.00% - - 0.00%
01.04.01.04.05.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 144.04 53.62 7,723.42 7,723.42 - - 0.00% - - 0.00% - - 0.00% 144.04 7,723.42 100.00% - - 0.00% - - 0.00%
01.04.01.04.05.03 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 15.62 448.88 7,011.51 7,011.51 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.62 7,011.51 100.00% - - 0.00%
01.04.01.04.05.04 CURADO DE CONCRETO m2 144.04 1.06 152.68 152.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 144.04 152.68 100.00% - - 0.00%
01.04.01.04.06 VIGUETAS 1,653.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.06.01 ACERO FY=4200 Kg/cm2 kg 24.37 4.72 115.03 115.03 - - 0.00% - - 0.00% - - 0.00% 24.37 115.03 100.00% - - 0.00% - - 0.00%
01.04.01.04.06.02 ENCOFRADO Y DESENCOFRADO PARA VIGUETAS DE CONFINA m2 14.81 51.94 769.23 769.23 - - 0.00% - - 0.00% - - 0.00% 14.81 769.23 100.00% - - 0.00% - - 0.00%
01.04.01.04.06.03 CONCRETO EN VIGUETAS F'C=175 KG/CM2 m3 1.89 398.54 753.24 753.24 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.89 753.24 100.00% - - 0.00%
01.04.01.04.06.04 CURADO DE CONCRETO m2 14.81 1.06 15.70 15.70 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.81 15.70 100.00% - - 0.00%
01.04.01.04.07 LOSA ALIGERADA 20,061.22 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.01.04.07.01 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERAD m2 132.89 64.56 8,579.38 8,579.38 - - 0.00% - - 0.00% - - 0.00% 132.89 8,579.38 100.00% - - 0.00% - - 0.00%
01.04.01.04.07.02 LADRILLO HUECO DE ARCILLA 12X30X25 CM PARA LOSA ALIGE m2 118.16 33.57 3,966.63 3,966.63 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 118.16 3,966.63 100.00% - - 0.00%
01.04.01.04.07.03 ACERO FY=4200 Kg/cm2 kg 617.22 4.72 2,913.28 2,913.28 - - 0.00% - - 0.00% - - 0.00% 617.22 2,913.28 100.00% - - 0.00% - - 0.00%
01.04.01.04.07.04 CONCRETO F'C=210 KG/CM2. PARA LOSAS ALIGERADAS m3 10.37 430.19 4,461.07 4,461.07 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.37 4,461.07 100.00% - - 0.00%
01.04.01.04.07.05 CURADO DE CONCRETO m2 132.89 1.06 140.86 140.86 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 132.89 140.86 100.00% - - 0.00%
01.04.01.04.08 TABLERO DE CONCRETO 631.17 - 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00%
01.04.01.04.08.01 ACERO FY=4200 KG/CM2 EN TABLERO DE CONCRETO kg 34.12 4.72 161.05 161.05 - - 0.00% - - 0.00% - - 0.00% 34.12 161.05 100.00% - - 0.00% - - 0.00%
01.04.01.04.08.02 ENCOFRADO Y DESENCOFRADO EN TABLERO DE CONCRETO m2 6.47 40.46 261.78 261.78 - - 0.00% - - 0.00% - - 0.00% 6.47 261.78 100.00% - - 0.00% - - 0.00%
01.04.01.04.08.03 CONCRETO FC=175 KG/CM2 EN TABLERO m3 0.49 425.18 208.34 208.34 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.49 208.34 100.00% - - 0.00%
01.04.02 ARQUITECTURA 74,486.19 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.01 MUROS Y TABIQUES DE ALBAILERIA 6,194.73 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 62.20 50.64 3,149.81 3,149.81 - - 0.00% - - 0.00% - - 0.00% 31.10 1,574.91 50.00% 31.10 1,574.91 50.00% - - 0.00%
01.04.02.01.02 MURO DE LADRILLO KK ARCILLA CABEZA M:1:5 JUNTA 1.5 CM m2 39.36 76.76 3,021.27 3,021.27 - - 0.00% - - 0.00% - - 0.00% 39.36 3,021.27 100.00% - - 0.00% - - 0.00%
01.04.02.01.03 JUNTA DE CONSTRUCCION CON TEKNOPORT m2 6.72 3.52 23.65 23.65 - - 0.00% - - 0.00% - - 0.00% 3.36 11.83 50.00% 3.36 11.83 50.00% - - 0.00%
01.04.02.02 REVOQUES Y ENLUCIDOS 17,172.91 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.02.01 TARRAJEO DE CIELO RASO MEZCLA 1:5, E=1.50CM m2 138.15 20.61 2,847.27 2,847.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 69.08 1,423.64 50.00% 69.08 1,423.64 50.00%
01.04.02.02.02 TARRAJEO DE VIGAS Y VIGUETAS MEZCLA 1:5, E=1.5CM m2 144.04 22.60 3,255.30 3,255.30 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 72.02 1,627.65 50.00% 72.02 1,627.65 50.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.04.02.02.03 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.5CM INC. VESTIDURA m2 51.01 22.60 1,152.83 1,152.83 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 25.51 576.42 50.00% 25.51 576.42 50.00%
01.04.02.02.04 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 209.83 19.46 4,083.29 4,083.29 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 104.92 2,041.65 50.00% 104.92 2,041.65 50.00%
01.04.02.02.05 TARRAJEO EN MURO EXTERIORES MEZCLA 1:5, E=1.50CM m2 172.41 19.46 3,355.10 3,355.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 86.21 1,677.55 50.00% 86.21 1,677.55 50.00%
01.04.02.02.06 TARRAJEO MEZCLA 1:5 EN DERRAMES DE PUERTAS Y VENTANAS m 119.87 19.32 2,315.89 2,315.89 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 59.94 1,157.95 50.00% 59.94 1,157.95 50.00%
01.04.02.02.07 BRUA DE 1/2" m 111.04 1.47 163.23 163.23 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 55.52 81.62 50.00% 55.52 81.62 50.00%
01.04.02.03 PISOS Y PAVIMENTOS 13,208.45 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.03.01 FALSO PISO CON CONCRETO F'C=140 KG/CM2 E=5CM m2 95.97 38.25 3,670.85 3,670.85 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 47.99 1,835.43 50.00% 47.99 1,835.43 50.00%
01.04.02.03.02 CONTRAPISO DE 48 MM. m2 91.02 25.36 2,308.27 2,308.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 45.51 1,154.14 50.00% 45.51 1,154.14 50.00%
01.04.02.03.03 PISO DE CERAMICO DE 40X40CM m2 20.71 80.88 1,675.02 1,675.02 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.36 837.51 50.00% 10.36 837.51 50.00%
01.04.02.03.04 PISO DE MADERA MACHIHEMBRADA (1.20X0.12 M) m2 70.31 77.79 5,469.41 5,469.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.16 2,734.71 50.00% 35.16 2,734.71 50.00%
01.04.02.03.05 JUNTA DE DILATACION CON TEKNOPORT m2 24.12 3.52 84.90 84.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.06 42.45 50.00% 12.06 42.45 50.00%
01.04.02.04 VEREDAS 3,798.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.04.01 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 20.13 49.06 987.58 987.58 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 20.13 987.58 100.00%
01.04.02.04.02 CONCRETO FC=175 KG/CM2 EN VEREDAS m3 6.14 403.13 2,475.22 2,475.22 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.14 2,475.22 100.00%
01.04.02.04.03 BRUAS EN VEREDA m 111.48 1.47 163.88 163.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 111.48 163.88 100.00%
01.04.02.04.04 JUNTA DE ASFALTICA m2 13.70 12.53 171.66 171.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.70 171.66 100.00%
01.04.02.05 ZOCALOS Y CONTRAZOCALOS 3,886.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.05.01 ZOCALO DE CERAMICO DE 30X30CM SSHH-COCINA m2 23.15 20.50 474.58 474.58 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 23.15 474.58 100.00%
01.04.02.05.02 CONTRAZOCALO DE CERMICO H=0.10M m 35.78 57.38 2,053.06 2,053.06 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 35.78 2,053.06 100.00%
01.04.02.05.03 CONTRAZOCALO CEMENTO S/COLOREAR H = 30 CM FROTACHAD m 45.10 7.87 354.94 354.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 45.10 354.94 100.00% - - 0.00%
01.04.02.05.04 CONTRAZOCALO DE MADERA H=10 CM m 46.27 21.69 1,003.60 1,003.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 46.27 1,003.60 100.00%
01.04.02.06 COBERTURAS 5,296.63 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.06.01 COBERTURA CON TEJA ANDINA INDUSTRIAL m2 118.86 36.65 4,356.22 4,356.22 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 118.86 4,356.22 100.00%
01.04.02.06.02 CUMBRERA DE TEJA ANDINA INDUSTRIAL m 16.92 55.58 940.41 940.41 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.92 940.41 100.00%
01.04.02.07 CARPINTERIA DE MADERA 4,741.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.07.01 PUERTA DE MADERA APANELADA m2 14.91 318.00 4,741.38 4,741.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.91 4,741.38 100.00%
01.04.02.08 CARPINTERIA METALICA Y HERRERIA 1,204.70 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.08.01 BISAGRA CAPUCHINA DE 4" X 4" und 28.00 13.32 372.96 372.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 28.00 372.96 100.00%
01.04.02.08.02 CERRADURA DE 3 GOLPES PARA PUERTA pza 7.00 82.97 580.79 580.79 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.00 580.79 100.00%
01.04.02.08.03 MANIJA DE BRONCE PARA PUERTAS und 7.00 35.85 250.95 250.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.00 250.95 100.00%
01.04.02.09 VENTANAS, CRISTALERIA Y SIMILARES 9,828.74 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.09.01 VENTANA DE ALUMINIO m2 19.69 231.79 4,563.95 4,563.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.69 4,563.95 100.00%
01.04.02.09.02 VIDRIOS SEMIDOBLES INCOLORO CRUDO p2 349.82 15.05 5,264.79 5,264.79 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 349.82 5,264.79 100.00%
01.04.02.10 PINTURA 9,154.13 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.02.10.01 PINTURA EN CIELO RASO AL LATEX 2 MANOS m2 138.15 15.73 2,173.10 2,173.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 138.15 2,173.10 100.00%
01.04.02.10.02 PINTURA EN MUROS INTERIORES AL LATEX ACABADO MATE m2 209.83 8.54 1,791.95 1,791.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 209.83 1,791.95 100.00%
01.04.02.10.03 PINTURA EN MUROS EXTERIOR AL LATEX AGRILICO 2 MANOS m2 172.41 8.54 1,472.38 1,472.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 172.41 1,472.38 100.00%
01.04.02.10.04 PINTURA EN VIGAS Y COLUMNAS INTERIOR LATEX ACABADO MA m2 97.52 13.91 1,356.50 1,356.50 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 97.52 1,356.50 100.00%
01.04.02.10.05 PINTURA EN VIGAS Y COLUMNAS EXTERIOR LATEX AGRILICO 2 m2 97.52 15.11 1,473.53 1,473.53 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 97.52 1,473.53 100.00%
01.04.02.10.06 PINTURA ESMALTE EN CONTRA ZOCALO DE CEMENTO m 45.10 19.66 886.67 886.67 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 45.10 886.67 100.00%
01.04.03 INSTALACIONES SANITARIAS 4,081.79 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.03.01 DRENAJE PLUVIAL 2,199.16 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.03.01.01 ACERO FY=4200 Kg/cm2 PARA COLUMNETAS kg 21.21 4.72 100.11 100.11 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.21 100.11 100.00%
01.04.03.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETA m2 2.40 42.06 100.94 100.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.40 100.94 100.00%
01.04.03.01.03 CONCRETO EN COLUMNETAS DE BAJADA PLUVIAL F'C=175 KG/CMm3 0.16 425.18 68.03 68.03 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.16 68.03 100.00%
01.04.03.01.04 DESAGUE PLUVIAL CON TUBERIA PVC SAL DE 3" m 16.00 120.63 1,930.08 1,930.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.00 1,930.08 100.00%
01.04.03.02 INSTALACIONES DE RED DE AGUA 900.72 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.03.02.01 SALIDA PUNTO DE AGUA pto 11.00 61.06 671.66 671.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.00 671.66 100.00% - - 0.00%
01.04.03.02.02 TUBERIA PVC SAP DE 1/2" m 3.00 2.03 6.09 6.09 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 6.09 100.00% - - 0.00%
01.04.03.02.03 VALVULA DE COMPUERTA 1/2" und 2.00 73.86 147.72 147.72 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 147.72 100.00% - - 0.00%
01.04.03.02.04 PRUEBA HIDRAULICA + DESINFECCION m 3.00 3.19 9.57 9.57 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 9.57 100.00% - - 0.00%
01.04.03.02.05 CAJA PARA VALVULAS DE AGUA und 2.00 32.84 65.68 65.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 65.68 100.00% - - 0.00%
01.04.03.03 INSTALACIONES DE RED DE DESAGUE 397.90 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.03.03.01 SALIDA DE DESAGUE 4" PARA INODORO pto 4.00 37.41 149.64 149.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 149.64 100.00%
01.04.03.03.02 SALIDA DE DESAGUE 2", PARA LAVATORIO, URINARIO pto 1.00 177.67 177.67 177.67 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 177.67 100.00%
01.04.03.03.03 SALIDA DE DESAGUE 2" PARA SUMIDERO pto 1.00 43.92 43.92 43.92 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 43.92 100.00%
01.04.03.03.04 TUBERIA DE PVC SAL 2" m 3.45 7.73 26.67 26.67 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.45 26.67 100.00%
01.04.03.04 ACCESORIOS SANITARIOS 584.01 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.03.04.01 LAVADERO DE COCINA DE ACERO INOXIDABLE und 1.00 382.03 382.03 382.03 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 382.03 100.00%
01.04.03.04.02 OTROS ACCESORIOS und 1.00 201.98 201.98 201.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 201.98 100.00%
01.04.04 INSTALACIONES ELECTRICAS 3,811.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01 SALIDA PARA ALUMBRADO, INTERUPTOR Y TOMACORRIENTES 3,811.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.01 SALIDA DE ILUMINACION MODULOS 983.85 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.01.01 SALIDA PARA CENTROS DE LUZ pto 15.00 65.59 983.85 983.85 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.00 983.85 100.00%
01.04.04.01.02 SALIDA PARA INTERRUPTORES SIMPLES 503.65 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.02.01 SALIDA DE INTERRUPTORES SIMPLES pto 7.00 71.95 503.65 503.65 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.00 503.65 100.00%
01.04.04.01.03 SALIDA PARA INTERRUPTORES DOBLES 147.28 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.03.01 SALIDA DE INTERRUPTORES DOBLES pto 2.00 73.64 147.28 147.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 147.28 100.00%
01.04.04.01.04 SALIDA PARA TOMACORRIENTES 1,102.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.04.01 SALIDA PARA TOMACORRIENTE C/LINEA A TIERRA pto 14.00 78.72 1,102.08 1,102.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 14.00 1,102.08 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.04.04.01.05 ARTEFACTOS DE ILUMINACION 508.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.05.01 ARTEFACTO FLUORESCENTE 1X36W TIPO CM JOSFEL und 6.00 61.22 367.32 367.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 367.32 100.00%
01.04.04.01.05.02 LAMPARA AHORRADORA DE 12W und 6.00 23.48 140.88 140.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 140.88 100.00%
01.04.04.01.06 TABLEROS 340.08 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TABLERO DE DISTRIBUCION TD-2, 3,4... (20X40Cm)
01.04.04.01.06.01 und 1.00 340.08 340.08 340.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 340.08 100.00%
01.04.04.01.07 INTERRUPTORES TERMOMAGNETICOS DE SALIDA EN TDs 226.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.04.04.01.07.01 INTERRUPTOR THERMOMAGNETICO 2 X 15A und 4.00 56.55 226.20 226.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.00 226.20 100.00%
01.05 TANQUE ELEVADO Y CISTERNA 25,513.46 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01 ESTRUCTURAS 14,315.82 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.01 TRABAJOS PRELIMINARES 11.88 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 2.85 1.36 3.88 3.88 - - 0.00% - - 0.00% - - 0.00% 2.85 3.88 100.00% - - 0.00% - - 0.00%
01.05.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 16.00 0.50 8.00 8.00 - - 0.00% - - 0.00% - - 0.00% 16.00 8.00 100.00% - - 0.00% - - 0.00%
01.05.01.02 MOVIMIENTO DE TIERRAS 386.50 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.02.01 EXCAVACIONES 212.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.02.01.01 EXCAVACION DE ZANJAS PARA CISTERNA m3 7.54 28.14 212.18 212.18 - - 0.00% - - 0.00% - - 0.00% 7.54 212.18 100.00% - - 0.00% - - 0.00%
01.05.01.02.02 RELLENOS 14.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.02.02.01 RELLENO COMPACTADO C/EQUIPO MAT/PROPIO PARA ZANJAS m3 0.84 16.90 14.20 14.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.84 14.20 100.00% - - 0.00%
01.05.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE 160.12 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.02.03.01 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 8.37 12.06 100.94 100.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.37 100.94 100.00% - - 0.00%
01.05.01.02.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2m3 8.37 7.07 59.18 59.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.37 59.18 100.00% - - 0.00%
01.05.01.03 OBRAS DE CONCRETO SIMPLE 295.16 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.03.01 SOLADO 89.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.03.01.01 SOLADO e=7 cm, 1:12 CEM/HORM m2 2.85 31.36 89.38 89.38 - - 0.00% - - 0.00% - - 0.00% 2.85 89.38 100.00% - - 0.00% - - 0.00%
01.05.01.03.02 SOBRECIMIENTO 205.78 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.03.02.01 SOBRECIMIENTO CORRIDO MEZCLA 1:8 CEMENTO-HORMIGON 2m3 0.20 318.13 63.63 63.63 - - 0.00% - - 0.00% - - 0.00% 0.20 63.63 100.00% - - 0.00% - - 0.00%
01.05.01.03.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 2.75 51.69 142.15 142.15 - - 0.00% - - 0.00% - - 0.00% 2.75 142.15 100.00% - - 0.00% - - 0.00%
01.05.01.04 OBRAS DE CONCRETO ARMADO 13,622.28 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.01 COLUMNAS 2,789.61 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.01.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 1.00 411.48 411.48 411.48 - - 0.00% - - 0.00% - - 0.00% 0.60 246.89 60.00% 0.40 164.59 40.00% - - 0.00%
01.05.01.04.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 17.60 53.62 943.71 943.71 - - 0.00% - - 0.00% - - 0.00% 10.56 566.23 60.00% 7.04 377.48 40.00% - - 0.00%
01.05.01.04.01.03 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 299.95 4.72 1,415.76 1,415.76 - - 0.00% - - 0.00% - - 0.00% 179.97 849.46 60.00% 119.98 566.30 40.00% - - 0.00%
01.05.01.04.01.04 CURADO DE CONCRETO m2 17.60 1.06 18.66 18.66 - - 0.00% - - 0.00% - - 0.00% 10.56 11.20 60.00% 7.04 7.46 40.00% - - 0.00%
01.05.01.04.02 VIGAS 1,577.55 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.02.01 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 0.81 448.88 363.59 363.59 - - 0.00% - - 0.00% - - 0.00% 0.16 72.72 20.00% 0.65 290.87 80.00% - - 0.00%
01.05.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 9.50 53.62 509.39 509.39 - - 0.00% - - 0.00% - - 0.00% 1.90 101.88 20.00% 7.60 407.51 80.00% - - 0.00%
01.05.01.04.02.03 ACERO FY=4200 Kg/cm2 kg 147.14 4.72 694.50 694.50 - - 0.00% - - 0.00% - - 0.00% 29.43 138.90 20.00% 117.71 555.60 80.00% - - 0.00%
01.05.01.04.02.04 CURADO DE CONCRETO m2 9.50 1.06 10.07 10.07 - - 0.00% - - 0.00% - - 0.00% 1.90 2.01 20.00% 7.60 8.06 80.00% - - 0.00%
01.05.01.04.03 LOSAS 546.14 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.03.01 LOSA MACIZA 546.14 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.03.01.01 CONCRETO F'C=210 KG/CM2 PARA LOSAS MACIZAS m3 0.24 502.50 120.60 120.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.24 120.60 100.00% - - 0.00%
01.05.01.04.03.01.02 ENCOFRADO Y DESENCOFRADO PARA LOSAS MACIZAS m2 2.62 64.56 169.15 169.15 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.62 169.15 100.00% - - 0.00%
01.05.01.04.03.01.03 ACERO FY=4200 Kg/cm2 kg 53.73 4.72 253.61 253.61 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 53.73 253.61 100.00% - - 0.00%
01.05.01.04.03.01.04 CURADO DE CONCRETO m2 2.62 1.06 2.78 2.78 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.62 2.78 100.00% - - 0.00%
01.05.01.04.04 CISTERNA SUBTERRANEA 5,694.13 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.04.01 CONCRETO DE CISTERNA F'C=210KG/CM2 m3 4.34 502.50 2,180.85 2,180.85 - - 0.00% - - 0.00% - - 0.00% 4.34 2,180.85 100.00% - - 0.00% - - 0.00%
01.05.01.04.04.02 ENCOFRADO Y DESENCOFRADO DE CISTERNA m2 32.02 53.62 1,716.91 1,716.91 - - 0.00% - - 0.00% - - 0.00% 32.02 1,716.91 100.00% - - 0.00% - - 0.00%
01.05.01.04.04.03 ACERO DE CISTERNA FY=4200 Kg/cm2 kg 393.40 4.48 1,762.43 1,762.43 - - 0.00% - - 0.00% - - 0.00% 393.40 1,762.43 100.00% - - 0.00% - - 0.00%
01.05.01.04.04.04 CURADO DE CONCRETO m2 32.02 1.06 33.94 33.94 - - 0.00% - - 0.00% - - 0.00% 32.02 33.94 100.00% - - 0.00% - - 0.00%
01.05.01.04.05 TANQUE ELEVADO 3,014.85 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.01.04.05.01 CONCRETO DE TANQUE ELEVADO F'C=210KG/CM2 m3 1.56 507.86 792.26 792.26 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.56 792.26 100.00% - - 0.00%
01.05.01.04.05.02 ENCOFRADO Y DESENCOFRADO DE TANQUE ELEVADO m2 18.04 53.62 967.30 967.30 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.04 967.30 100.00% - - 0.00%
01.05.01.04.05.03 ACERO DE TANQUE ELEVADO FY=4200 Kg/cm2 kg 275.93 4.48 1,236.17 1,236.17 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 275.93 1,236.17 100.00% - - 0.00%
01.05.01.04.05.04 CURADO DE CONCRETO m2 18.04 1.06 19.12 19.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.04 19.12 100.00% - - 0.00%
01.05.02 ARQUITECTURA 6,797.79 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.01 MUROS Y TABIQUES DE ALBAILERIA 371.19 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 7.33 50.64 371.19 371.19 - - 0.00% - - 0.00% - - 0.00% 7.33 371.19 100.00% - - 0.00% - - 0.00%
01.05.02.02 REVOQUES Y ENLUCIDOS 1,896.51 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.02.01 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 11.28 19.46 219.51 219.51 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.28 219.51 100.00%
01.05.02.02.02 TARRAJEO EN MURO EXTERIORES MEZCLA 1:5, E=1.50CM m2 8.15 19.46 158.60 158.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.15 158.60 100.00%
01.05.02.02.03 TARRAJEO DE COLUMNA MEZCLA 1:5, E=1.5CM m2 16.00 23.33 373.28 373.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.00 373.28 100.00%
01.05.02.02.04 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 9.00 23.33 209.97 209.97 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.00 209.97 100.00%
01.05.02.02.05 TARRAJEO DE MUROS DE CONCRETO MEZCLA 1:5, E=1.50CM m2 9.90 14.73 145.83 145.83 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.90 145.83 100.00%
01.05.02.02.06 TARRAJEO CON IMPERMEABILIZANTES m2 32.27 24.46 789.32 789.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 32.27 789.32 100.00%
01.05.02.03 CIELO RASO 29.99 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.03.01 TARRAJEO DE CIELO RASO FROTACHADO Y PLANCHADO MEZCLAm2 2.21 13.57 29.99 29.99 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.21 29.99 100.00%
01.05.02.04 BRUAS EN TANQUE ALTO 31.75 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.04.01 BRUA DE 1/2" m 21.60 1.47 31.75 31.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.60 31.75 100.00%
01.05.02.05 PISOS Y PAVIMENTOS 644.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.05.01 VEREDA DE CONCRETO ACABADO FROTACHADO BRUADO m2 10.39 43.59 452.90 452.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.39 452.90 100.00%
01.05.02.05.02 PISO CON LADRILLO PASTELERO m2 4.48 42.72 191.39 191.39 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.48 191.39 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.05.02.06 CERRAJERIA 115.87 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.06.01 BISAGRA DE ACERO ALUMINIZADO DE 3 1/2" X 3 1/2" Y 1" und 3.00 13.69 41.07 41.07 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 41.07 100.00%
01.05.02.06.02 CERROJO DE 2" ALUMINIZADO PARA PUERTA und 1.00 15.45 15.45 15.45 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 15.45 100.00%
01.05.02.06.03 MANIJA DE BRONCE PARA PUERTAS und 1.00 35.85 35.85 35.85 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 35.85 100.00%
01.05.02.06.04 CANDADO MEDIANO und 1.00 23.50 23.50 23.50 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 23.50 100.00%
01.05.02.07 CARPINTERIA METALICA Y HERRERIA 2,850.32 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.07.01 PUERTA METALICA EN CASETA DE BOMBAS DE 0.80m x 2.00m m2 1.16 408.75 474.15 474.15 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.16 474.15 100.00%
01.05.02.07.02 ESCALERA MARINERA A TANQUE ELEVADO und 1.00 646.39 646.39 646.39 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 646.39 100.00%
01.05.02.07.03 ESCALERA DE GATO PARA TANQUE CISTERNA und 1.00 428.75 428.75 428.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 428.75 100.00%
01.05.02.07.04 ESCALERA DE GATO EMPOTRADO DE ALUMINIO PARA TANQUE CI und 1.00 440.68 440.68 440.68 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 440.68 100.00%
01.05.02.07.05 BARANDA METALICA m 5.20 92.38 480.38 480.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.20 480.38 100.00%
01.05.02.07.06 TAPA METALICA DE 0.80 x 0.80 m. EN CISTERNA und 1.00 200.31 200.31 200.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 200.31 100.00%
01.05.02.07.07 TAPA METALICA DE 0.70 x 0.70 m. EN TANQUE ELVADO und 1.00 179.66 179.66 179.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 179.66 100.00%
01.05.02.08 PINTURA 857.87 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.02.08.01 PINTURA EN MUROS INTERIORES A LATEX AGRILICO 2 MANOS m2 11.28 13.91 156.90 156.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.28 156.90 100.00%
01.05.02.08.02 PINTURA EN MUROS EXTERIOR A LATEX AGRILICO 2 MANOS m2 8.15 8.54 69.60 69.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.15 69.60 100.00%
01.05.02.08.03 PINTURA EN COLUMNAS DE CONCRETO A LATEX AGRILICO 2 MA m2 16.00 13.91 222.56 222.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.00 222.56 100.00%
01.05.02.08.04 PINTURA EN VIGAS A LATEX AGRILICO 2 MANOS m2 9.00 13.91 125.19 125.19 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.00 125.19 100.00%
01.05.02.08.05 PINTURA EN MUROS DE TANQUE ALTO A LATEX AGRILICO 2 MANOm2 9.90 13.91 137.71 137.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.90 137.71 100.00%
01.05.02.08.06 PINTURA EN CAPINTERIA METALICA m2 13.56 10.76 145.91 145.91 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.56 145.91 100.00%
01.05.03 INSTALACIONES SANITARIAS 2,652.36 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.01 ACCESORIOS DE REDES DE AGUA GLB 1.00 511.61 511.61 511.61 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 511.61 100.00%
01.05.03.02 LLAVES Y VALVULAS GLB 1.00 301.28 301.28 301.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 301.28 100.00%
01.05.03.03 ALMACENAMIENTO DE AGUA 1,839.47 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.01 SUCCIN 53.82 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.01.01 TUBERA FG PARA SUCCION DE D=1 " m 2.09 25.75 53.82 53.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.09 53.82 100.00%
01.05.03.03.02 IMPULSIN 44.98 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.02.01 TUBERA FG PARA IMPLUSION DE D=1" m 2.00 22.49 44.98 44.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 44.98 100.00%
01.05.03.03.03 REBOSE Y LIMPIA 128.86 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.03.01 TUBERA PVC C-10 DE 2" m 8.85 14.56 128.86 128.86 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.85 128.86 100.00%
01.05.03.03.04 ALIMENTACIN A IEI 99.81 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.04.01 TUBERA PVC C-10 DE 1 " m 6.40 8.19 52.42 52.42 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.40 52.42 100.00%
01.05.03.03.04.02 TUBERA PVC C-10 DE 1" m 4.03 11.76 47.39 47.39 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.03 47.39 100.00%
01.05.03.03.05 VARIOS 12.44 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.05.01 TUBO DE VENTILACIN FO GALV. DE 2" m 0.70 17.77 12.44 12.44 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.70 12.44 100.00%
01.05.03.03.06 EQUIPOS Y OTRAS INSTALACIONES 1,499.56 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.03.03.06.01 BOMBA DE 1 HP SUCCIN 1 ", IMPUL. 1" und 2.00 514.45 1,028.90 1,028.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 1,028.90 100.00%
01.05.03.03.06.02 CANASTILLA DE BRONCE DE SUCCIN 1 1/4" und 2.00 92.50 185.00 185.00 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 185.00 100.00%
01.05.03.03.06.03 CONTROL DE NIVEL EN CISTERNA Y TANQUE ELEVADO und 2.00 142.83 285.66 285.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 285.66 100.00%
01.05.04 INSTALACIONES ELECTRICAS 1,747.49 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.01 SALIDAS ELCTRICAS 418.07 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.01.01 SALIDA DE CENTRO DE LUZ EN PARED, TIPO BRAQUET pto 1.00 65.59 65.59 65.59 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 65.59 100.00%
01.05.04.01.02 SALIDA DE INTERRUPTORES SIMPLES pto 1.00 71.95 71.95 71.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 71.95 100.00%
01.05.04.01.03 SALIDA PARA TOMACORRIENTE DOBLE C/LT A PRUEBA DE AGUA pto 1.00 78.72 78.72 78.72 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 78.72 100.00%
01.05.04.01.04 SALIDA P/LUZ DE EMERGENCIA pto 1.00 63.91 63.91 63.91 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 63.91 100.00%
01.05.04.01.05 SALIDA P/ELECTROBOMBA pto 2.00 68.95 137.90 137.90 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 137.90 100.00%
01.05.04.02 CAJAS DE PASE 35.87 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.02.01 CAJA DE PASE PRE FABRICADA DE 0.40M. x 0.50M. und 2.00 13.21 26.42 26.42 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 26.42 100.00%
01.05.04.02.02 CAJA DE PASE FG 100x100x75mm C/SELLO HERMTICO und 1.00 9.45 9.45 9.45 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 9.45 100.00%
01.05.04.03 CANALIZACIONES CONDUCTOS O TUBERAS 189.48 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.03.01 TUBERIA PVC-P 40mm m 12.00 15.79 189.48 189.48 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.00 189.48 100.00%
01.05.04.04 TABLEROS DE DISTRIBUCIN 742.91 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.04.01 TABLERO DE DISTRIBUCIN 12 POLOS und 1.00 319.32 319.32 319.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 319.32 100.00%
01.05.04.04.02 INTERRUPTOR TERMOMAGNETICO 2x10 A und 2.00 42.09 84.18 84.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 84.18 100.00%
01.05.04.04.03 INTERRUPTOR TERMOMAGNETICO 2x16 A und 1.00 42.09 42.09 42.09 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 42.09 100.00%
01.05.04.04.04 INTERRUPTOR TERMOMAGNETICO 2x20 A und 2.00 42.09 84.18 84.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 84.18 100.00%
01.05.04.04.05 INTERRUPTOR DIFERENCIAL 2x25A und 3.00 41.92 125.76 125.76 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 125.76 100.00%
01.05.04.04.06 TABLERO DE CONTROL DE ELECTROBOMBAS TC und 1.00 87.38 87.38 87.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 87.38 100.00%
01.05.04.05 ARTEFACTOS DE ILUMINACION 361.16 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.05.04.05.01 BRAQUET C/LAMP.2X26W-AHORRAD, SIMILAR A RSP-2 DE JOSFEL und 2.00 61.89 123.78 123.78 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 123.78 100.00%
01.05.04.05.02 LUCES DE EMERGENCIA - AUTONOMA 2HRS und 1.00 237.38 237.38 237.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 237.38 100.00%
01.06 OBRAS EXTERIORES 148,438.11 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01 ESTRUCTURAS 51,957.61 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01.01 TRABAJOS PRELIMINARES 1,380.75 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 742.34 1.36 1,009.58 1,009.58 - - 0.00% - - 0.00% - - 0.00% 742.34 1,009.58 100.00% - - 0.00% - - 0.00%
01.06.01.01.02 LIMPIEZA DE TERRENO MANUAL m2 742.34 0.50 371.17 371.17 - - 0.00% - - 0.00% - - 0.00% 742.34 371.17 100.00% - - 0.00% - - 0.00%
01.06.01.02 MOVIMIENTO DE TIERRAS 11,775.95 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01.02.01 PERFILADO MANUAL EN ZONA DE CORTE m2 742.34 2.35 1,744.50 1,744.50 - - 0.00% - - 0.00% - - 0.00% 742.34 1,744.50 100.00% - - 0.00% - - 0.00%
01.06.01.02.02 EXCAVACION DE ZANJA PARA CIMENTACION m3 150.50 23.66 3,560.83 3,560.83 - - 0.00% - - 0.00% - - 0.00% 150.50 3,560.83 100.00% - - 0.00% - - 0.00%
01.06.01.02.03 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACIO m2 331.68 2.72 902.17 902.17 - - 0.00% - - 0.00% - - 0.00% 331.68 902.17 100.00% - - 0.00% - - 0.00%
01.06.01.02.04 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m3 59.18 11.79 697.73 697.73 - - 0.00% - - 0.00% - - 0.00% 29.59 348.87 50.00% 29.59 348.87 50.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.06.01.02.05 RELLENO, CONFORMACION Y COMPACTACION DE BASE E=10CM m2 197.64 8.46 1,672.03 1,672.03 - - 0.00% - - 0.00% - - 0.00% 98.82 836.02 50.00% 98.82 836.02 50.00% - - 0.00%
01.06.01.02.06 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 102.11 12.06 1,231.45 1,231.45 - - 0.00% - - 0.00% - - 0.00% 51.06 615.73 50.00% 51.06 615.73 50.00% - - 0.00%
01.06.01.02.07 ZARANDEO DE MATERIAL PROPIO PARA CAMA DE APOYO H=01Mm3 12.24 10.82 132.44 132.44 - - 0.00% - - 0.00% - - 0.00% 6.12 66.22 50.00% 6.12 66.22 50.00% - - 0.00%
01.06.01.02.08 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2.0m3 102.11 7.07 721.92 721.92 - - 0.00% - - 0.00% - - 0.00% 51.06 360.96 50.00% 51.06 360.96 50.00% - - 0.00%
01.06.01.02.09 SUBSTRATO TIERRA AGRICOLA (TIERRA NEGRA) m3 33.45 33.27 1,112.88 1,112.88 - - 0.00% - - 0.00% - - 0.00% 16.73 556.44 50.00% 16.73 556.44 50.00% - - 0.00%
01.06.01.03 OBRAS DE CONCRETO SIMPLE 33,260.94 - 0.00% 0.00% 0.00% - 0.00% 0.00% 0.00%
01.06.01.03.01 SOLADO DE 4" DE ESPESOR; MEZCLA 1:12 CEMENTO-HORMIGON m2 0.36 31.36 11.29 11.29 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.36 11.29 100.00% - - 0.00%
01.06.01.03.02 DADO DE CONCRETO F'C=175KG/CM2 5x5x10cm P/ ENCOFRAD m2 0.47 53.40 25.10 25.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.47 25.10 100.00% - - 0.00%
01.06.01.03.03 ENCOFRADO CARA VISTA Y DESENCOFRADO m2 422.77 59.63 25,209.78 25,209.78 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 422.77 25,209.78 100.00% - - 0.00%
01.06.01.03.04 CONCRETO PARA SARDINEL Y CANALETA F'C=175KG/CM2 m3 18.20 425.18 7,738.28 7,738.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.20 7,738.28 100.00% - - 0.00%
01.06.01.03.05 CURADO DE CONCRETO m2 260.84 1.06 276.49 276.49 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 260.84 276.49 100.00% - - 0.00%
01.06.01.04 OBRAS DE CONCRETO ARMADO 5,539.97 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01.04.01 BASE DEL ASTA DE BANDERA 5,539.97 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.01.04.01.01 ACERO FY= 4200 KG/CM2 EN BASE DE ASTA Y COLUMNAS kg 430.91 4.48 1,930.48 1,930.48 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 430.91 1,930.48 100.00%
01.06.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN LA BASE DEL ASTA Y COL m2 21.81 53.62 1,169.45 1,169.45 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.81 1,169.45 100.00%
01.06.01.04.01.03 CONCRETO EN BASE DE ASTA Y COLUMNAS CIRCULARES F'C= m3 4.83 500.00 2,415.00 2,415.00 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.83 2,415.00 100.00%
01.06.01.04.01.04 CURADO DE CONCRETO m2 23.62 1.06 25.04 25.04 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 23.62 25.04 100.00%
01.06.02 ARQUITECTURA 78,738.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.02.01 REVOQUES ENLUCIDOS Y MOLDURAS 203.25 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.02.01.01 TARRAJEO EN LA BASE DEL ASTA DE BANDERA MEZCLA 1:5, E=1. m2 11.90 17.08 203.25 203.25 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 11.90 203.25 100.00%
01.06.02.02 PISOS Y PAVIMENTOS 42,792.14 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.02.02.01 FALSO PISO CON CONCRETO F'C=140 KG/CM2 E=5CM m2 67.14 38.25 2,568.11 2,568.11 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 67.14 2,568.11 100.00%
01.06.02.02.02 CONCRETO F'C=175 KG/CM2 PARA PISO CON OCRE ROJO BRUA m2 192.39 158.64 30,520.75 30,520.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 192.39 30,520.75 100.00%
01.06.02.02.03 JUNTA DE DILATACION CON TEKNOPORT m2 29.05 3.52 102.26 102.26 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 29.05 102.26 100.00%
01.06.02.02.04 ADOQUINADO CON MORTERO m2 67.14 143.00 9,601.02 9,601.02 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 67.14 9,601.02 100.00%
01.06.02.03 CARPINTERIA METALICA Y HERRERIA 34,636.80 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.02.03.01 BARANDA METALICA m 28.00 92.38 2,586.64 2,586.64 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 28.00 2,586.64 100.00%
01.06.02.03.02 POSTE PARA FAROLAS und 5.00 662.35 3,311.75 3,311.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 3,311.75 100.00%
01.06.02.03.03 ASTA DE BARANDA METALICA und 1.00 720.10 720.10 720.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 720.10 100.00%
01.06.02.03.04 ABRAZADERAS METALICAS und 18.00 12.87 231.66 231.66 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.00 231.66 100.00%
01.06.02.03.05 REGILLA METALICA PARA LA CANALETA m 184.85 150.32 27,786.65 27,786.65 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 184.85 27,786.65 100.00%
01.06.02.04 PINTURA 1,105.99 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.02.04.01 PINTURA EN SARDINEL LATEX SATINADO, 2 MANOS m2 32.86 13.82 454.13 454.13 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 32.86 454.13 100.00%
01.06.02.04.02 PINTURA EN SEALECTICA ESMALTE ACRILICO pto 21.00 9.32 195.72 195.72 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.00 195.72 100.00%
01.06.02.04.03 PINTURA EN PATIO DE FORMACION ESMALTE ACRILICO pto 26.00 8.60 223.60 223.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 26.00 223.60 100.00%
01.06.02.04.04 PINTURA EN BASE DE ASTA DE BANDERA Y COLUMNA CIRCULA m2 26.04 8.60 223.94 223.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 26.04 223.94 100.00%
01.06.02.04.05 PINTURA EN ESTRUCTURA METALICA GLB 1.00 8.60 8.60 8.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 8.60 100.00%
01.06.03 INSTALACIONES SANITARIAS 7,740.41 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.03.01 DRENAJE PLUVIAL 4,041.17 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.03.01.01 ACERO FY=4200 Kg/cm2 PARA COLUMNETAS kg 52.20 4.72 246.38 246.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 52.20 246.38 100.00%
01.06.03.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETA m2 4.16 42.06 174.97 174.97 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.16 174.97 100.00%
01.06.03.01.03 CONCRETO EN COLUMNETAS DE BAJADA PLUVIAL F'C=175 KG/CMm3 0.18 425.18 76.53 76.53 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.18 76.53 100.00%
01.06.03.01.04 DESAGUE PLUVIAL CON TUBERIA PVC SAL DE 3" m 16.50 120.63 1,990.40 1,990.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.50 1,990.40 100.00%
01.06.03.01.05 CANALETA DE ZINC 4" INCL. SOPORTE EN U m 31.64 49.08 1,552.89 1,552.89 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 31.64 1,552.89 100.00%
01.06.03.02 INSTALACIONES DE RED DE AGUA 1,945.06 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.03.02.01 SALIDA PUNTO PARA MODULOS pto 10.00 60.27 602.70 602.70 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 10.00 602.70 100.00%
01.06.03.02.02 TUBERIA PVC SAP DE 1" m 50.38 3.34 168.27 168.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 50.38 168.27 100.00%
01.06.03.02.03 TUBERIA PVC SAP DE 1/2" m 41.07 2.03 83.37 83.37 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 41.07 83.37 100.00%
01.06.03.02.04 VALVULA DE COMPUERTA 1" und 3.00 82.25 246.75 246.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 246.75 100.00%
01.06.03.02.05 VALVULA DE COMPUERTA 1/2" und 5.00 73.86 369.30 369.30 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 369.30 100.00%
01.06.03.02.06 ACCESORIOS DE INSTALACION AGUA PARA EXTERIORES 1" GLB 1.00 42.21 42.21 42.21 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 42.21 100.00%
01.06.03.02.07 ACCESORIOS DE INSTALACION AGUA PARA EXTERIORES 1/2" GLB 1.00 42.21 42.21 42.21 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 42.21 100.00%
01.06.03.02.08 PRUEBA HIDRAULICA + DESINFECCION m 91.45 3.19 291.73 291.73 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 91.45 291.73 100.00%
01.06.03.02.09 CAJA PARA VALVULAS DE AGUA und 3.00 32.84 98.52 98.52 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.00 98.52 100.00%
01.06.03.03 INSTALACIONES DE RED DE DESAGUE 1,110.46 - 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.03.03.01 SALIDA DE DESAGUE 2", PARA ADMINISTRACION pto 1.00 42.29 42.29 42.29 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 42.29 100.00%
01.06.03.03.02 TUBERIA DE PVC SAL 4" m 83.91 12.73 1,068.17 1,068.17 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 83.91 1,068.17 100.00%
01.06.03.04 SUMINISTRO E INSTALACION DE LA CAJA DE REGISTRO DE CONCRETO 643.72 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.03.04.01 CAJA DE REGISTRO 30x60cm INCLUYE TAPA und 7.00 91.96 643.72 643.72 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.00 643.72 100.00%
01.06.04 INSTALACIONES ELECTRICAS 10,001.91 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.01 CONDUCTORES DE ENERGIA 607.59 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.01.01 CONDUCTOR (MEDIDOR A TG) m 4.50 4.71 21.20 21.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.50 21.20 100.00%
01.06.04.01.02 CONDUCTOR NYY 4mm2 + THW 10mm2 (TG A TD) m 102.91 4.71 484.71 484.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 102.91 484.71 100.00%
01.06.04.01.03 CONDUCTOR PUESTA A TIERRA m 1.81 22.51 40.74 40.74 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.81 40.74 100.00%
01.06.04.01.04 CAJA DE PASE FG 100x100x50mm und 2.00 30.47 60.94 60.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 60.94 100.00%
01.06.04.02 MEDIDORES Y TABLERO DE DISTRIBUCION 473.93 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.02.01 MEDIDOR DE ENERGIA TIPO I und 1.00 215.92 215.92 215.92 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 215.92 100.00%
01.06.04.02.02 TABLERO GENERAL METALICO TG und 1.00 258.01 258.01 258.01 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 258.01 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.06.04.03 INTERRUPTORES TERMOMAGNETICO SALIDA EN TG 515.55 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.03.01 INTERRUPTOR THERMOMAGNETICO TIPO RIEL DE 2X20A und 5.00 103.11 515.55 515.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 515.55 100.00%
01.06.04.04 INSTALACION PUESTA A TIERRA 366.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.04.01 PUESTA CONEXION A TIERRA und 1.00 366.18 366.18 366.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 366.18 100.00%
01.06.04.05 INSTALACION POSTES Y FAROLAS 503.36 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.05.01 INSTALACION DE POSTES und 5.00 45.76 228.80 228.80 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 5.00 228.80 100.00%
01.06.04.05.02 INSTALACIONES RED ALUMBRADO EXTERIOR CON FAROLAS pto 6.00 45.76 274.56 274.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 274.56 100.00%
01.06.04.06 PRUEBAS ELECTRICOS 509.42 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.06.01 PRUEBA NIVEL DE AISLAMIENTO pto 1.00 254.71 254.71 254.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 254.71 100.00%
01.06.04.06.02 PRUEBAS ELECTRICAS pto 1.00 254.71 254.71 254.71 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 254.71 100.00%
01.06.04.07 INSTALACION DE PARARAYOS 5,785.06 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.07.01 INSTALACION DEL SISTEMA DE PARARAYOS und 1.00 5,785.06 5,785.06 5,785.06 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 5,785.06 100.00%
01.06.04.08 RED ELECTRICA SEGUNDARIA Y ACOMETIDA 1,180.42 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.08.01 POSTES DE CONCRETO DE 9M INCLUYE IZADO Y RELLENO und 1.00 639.28 639.28 639.28 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 639.28 100.00%
01.06.04.08.02 CONEXION DE CABLES A RED SEGUNDARIA EXISTENTE und 1.00 43.83 43.83 43.83 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 43.83 100.00%
01.06.04.08.03 ACCESORIOS EN POSTES TIPOS E2 und 1.00 109.31 109.31 109.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 109.31 100.00%
01.06.04.08.04 CABLEADO EN POSTES m 50.00 7.76 388.00 388.00 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 50.00 388.00 100.00%
01.06.04.09 CONDUCTORES DE ENERGIA 60.40 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.06.04.09.01 CONDUCTOR ACOMETIDA DE LINEA DE ENERGIA - MEDIDOR m 8.00 7.55 60.40 60.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 8.00 60.40 100.00%
01.07 INSTALACIN DE REA DE JUEGOS 13,599.50 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.01 ESTRUCTURAS 4,419.48 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.01.01 TRABAJO PRELIMINAR 260.30 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 191.40 1.36 260.30 260.30 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 191.40 260.30 100.00%
01.07.01.02 MOVIMIENTO DE TIERRAS 3,182.49 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.01.02.01 EXCAVACION MANUAL DE TERRENO A NIVEL DE SUBRASANTE m3 13.16 28.14 370.32 370.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.16 370.32 100.00%
01.07.01.02.02 RELLENO, CONFORMACION Y COMPACTACION DE BASE 10CM m2 101.23 16.90 1,710.79 1,710.79 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 101.23 1,710.79 100.00%
01.07.01.02.03 RELLENO Y NIVELADO CON ARENA FINA (E=5 CM) m2 101.23 10.88 1,101.38 1,101.38 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 101.23 1,101.38 100.00%
01.07.01.03 INSTALACIN DE JUEGOS 976.69 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.01.03.01 DADO DE CONCRETO FC=140KG/CM2 PARA ANCLAJE m3 3.04 321.28 976.69 976.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.04 976.69 100.00%
01.07.02 ARQUITECTURA 9,180.02 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.02.01 INSTALACIN DE GRASS 3,842.69 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.02.01.01 COLOCACION Y EXTENDIDO DE CONFITILLO E=5CM m2 101.23 37.96 3,842.69 3,842.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 101.23 3,842.69 100.00%
01.07.02.02 IMPLEMENTACION CON JUEGOS 5,337.33 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.07.02.02.01 JUEGOS INFANTILES / INC INSTALACIN GLB 1.00 5,337.33 5,337.33 5,337.33 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 5,337.33 100.00%
01.08 CONSTRUCCION DE CERCO PERIMETRICO 135,106.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01 ESTRUCTURAS 71,437.05 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.01 TRABAJOS PRELIMINARES 265.30 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 195.07 1.36 265.30 265.30 - - 0.00% - - 0.00% 195.07 265.30 100.00% - - 0.00% - - 0.00% - - 0.00%
01.08.01.02 MOVIMIENTO DE TIERRAS 4,176.72 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.02.01 EXCAVACION PARA ZAPATAS m3 42.05 23.66 994.90 994.90 - - 0.00% - - 0.00% 42.05 994.90 100.00% - - 0.00% - - 0.00% - - 0.00%
01.08.01.02.02 EXCAVACION DE ZANJA PARA CIMIENTO CORRIDO m3 37.44 27.60 1,033.34 1,033.34 - - 0.00% - - 0.00% 37.44 1,033.34 100.00% - - 0.00% - - 0.00% - - 0.00%
01.08.01.02.03 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACIO m2 109.13 2.72 296.83 296.83 - - 0.00% - - 0.00% 109.13 296.83 100.00% - - 0.00% - - 0.00% - - 0.00%
01.08.01.02.04 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m3 7.01 16.90 118.47 118.47 - - 0.00% - - 0.00% - - 0.00% 7.01 118.47 100.00% - - 0.00% - - 0.00%
01.08.01.02.05 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 90.60 12.06 1,092.64 1,092.64 - - 0.00% - - 0.00% - - 0.00% 90.60 1,092.64 100.00% - - 0.00% - - 0.00%
01.08.01.02.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D= 2.0m3 90.60 7.07 640.54 640.54 - - 0.00% - - 0.00% - - 0.00% 90.60 640.54 100.00% - - 0.00% - - 0.00%
01.08.01.03 OBRAS DE CONCRETO SIMPLE 24,914.85 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.03.01 SOLADO PARA ZAPATAS Y MURO DE 4" DE ESPESOR; MEZCLA m2 17.52 31.36 549.43 549.43 - - 0.00% - - 0.00% 17.52 549.43 100.00% - - 0.00% - - 0.00% - - 0.00%
01.08.01.03.02 CONCRETO 1:10 +30% P.G. PARA CIMIENTOS CORRIDOS m3 50.80 244.74 12,432.79 12,432.79 - - 0.00% - - 0.00% - - 0.00% 50.80 12,432.79 100.00% - - 0.00% - - 0.00%
01.08.01.03.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 155.77 51.69 8,051.75 8,051.75 - - 0.00% - - 0.00% - - 0.00% 155.77 8,051.75 100.00% - - 0.00% - - 0.00%
01.08.01.03.04 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 11.68 318.13 3,715.76 3,715.76 - - 0.00% - - 0.00% - - 0.00% 11.68 3,715.76 100.00% - - 0.00% - - 0.00%
01.08.01.03.05 CURADO DE CONCRETO m2 155.77 1.06 165.12 165.12 - - 0.00% - - 0.00% - - 0.00% 155.77 165.12 100.00% - - 0.00% - - 0.00%
01.08.01.04 OBRAS DE CONCRETO ARMADO 42,080.18 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.04.01 ACERO EN SOBRECIMIENTO TRAMOS DE ENREJADO 427.71 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.04.01.01 ACERO FY=4200 KG/CM2 kg 95.47 4.48 427.71 427.71 - - 0.00% - - 0.00% - - 0.00% 95.47 427.71 100.00% - - 0.00% - - 0.00%
01.08.01.04.02 ZAPATAS 7,965.34 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.04.02.01 ACERO FY=4200 Kg/cm2 kg 230.94 4.72 1,090.04 1,090.04 - - 0.00% - - 0.00% - - 0.00% 230.94 1,090.04 100.00% - - 0.00% - - 0.00%
01.08.01.04.02.02 CONCRETO PARA ZAPATAS F'C=175 KG/CM2 m3 18.69 367.86 6,875.30 6,875.30 - - 0.00% - - 0.00% - - 0.00% 18.69 6,875.30 100.00% - - 0.00% - - 0.00%
01.08.01.04.03 COLUMNAS 27,952.94 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.04.03.01 ACERO EN COLUMNAS FY= 4200 KG/CM2 kg 933.32 4.72 4,405.27 4,405.27 - - 0.00% - - 0.00% - - 0.00% 933.32 4,405.27 100.00% - - 0.00% - - 0.00%
01.08.01.04.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 355.74 53.62 19,074.78 19,074.78 - - 0.00% - - 0.00% - - 0.00% 177.87 9,537.39 50.00% 177.87 9,537.39 50.00% - - 0.00%
01.08.01.04.03.03 CONCRETO EN COLUMNAS F'C=175 KG/CM2 m3 10.52 425.18 4,472.89 4,472.89 - - 0.00% - - 0.00% - - 0.00% 5.26 2,236.45 50.00% 5.26 2,236.45 50.00% - - 0.00%
01.08.01.04.04 VIGAS 5,734.19 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.01.04.04.01 ACERO FY=4200 Kg/cm2 kg 328.59 4.72 1,550.94 1,550.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 328.59 1,550.94 100.00% - - 0.00%
01.08.01.04.04.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 49.60 53.62 2,659.55 2,659.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 49.60 2,659.55 100.00% - - 0.00%
01.08.01.04.04.03 CONCRETO EN VIGAS F'C=175 KG/CM2 m3 3.46 425.18 1,471.12 1,471.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.46 1,471.12 100.00% - - 0.00%
01.08.01.04.04.04 CURADO DE CONCRETO m2 49.60 1.06 52.58 52.58 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 49.60 52.58 100.00% - - 0.00%
01.08.02 ARQUITECTURA 63,669.29 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.01 MUROS Y TABIQUES DE ALBAILERIA 34,638.78 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.01.01 MURO DE LADRILLO CORRIENTE TIPO CARAVISTA SOGA M:1:5 JUm2 372.50 92.99 34,638.78 34,638.78 - - 0.00% - - 0.00% - - 0.00% 223.50 20,783.27 60.00% 149.00 13,855.51 40.00% - - 0.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.08.02.02 REVOQUES, ENLUCIDOS Y MOLDURAS 11,630.83 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.02.01 TARRAJEO DE SOBRECIMIENTO MEZCLA 1:5 E=1.50CM m2 135.46 40.00 5,418.40 5,418.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 135.46 5,418.40 100.00% - - 0.00%
01.08.02.02.02 TARRAJEO DE COLUMNAS MEZCLA 1:5, E=1.5CM INC. VESTIDURA m2 189.60 22.60 4,284.96 4,284.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 189.60 4,284.96 100.00% - - 0.00%
01.08.02.02.03 TARRAJEO DE VIGAS MEZCLA 1:5, E=1.5CM m2 64.90 23.33 1,514.12 1,514.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 64.90 1,514.12 100.00% - - 0.00%
01.08.02.02.04 CURADO DE CONCRETO m2 389.95 1.06 413.35 413.35 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 389.95 413.35 100.00% - - 0.00%
01.08.02.03 CARPINTERIA METALICA 4,046.32 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.03.01 MURO DE REJA METALICA m2 22.80 177.47 4,046.32 4,046.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 22.80 4,046.32 100.00% - - 0.00%
01.08.02.04 JUNTA DE CONSTRUCCION 22.67 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.04.01 JUNTA DE CONSTRUCCION CON TEKNOPORT m2 6.44 3.52 22.67 22.67 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.44 22.67 100.00% - - 0.00%
01.08.02.05 PINTURA 13,330.69 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.08.02.05.01 PINTURA EN SOBRECIMIENTO ESMALTE ACRILICO m2 135.46 13.91 1,884.25 1,884.25 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 135.46 1,884.25 100.00%
01.08.02.05.02 PINTURA EN COLUMNAS LATEX SATINADO m2 323.40 13.82 4,469.39 4,469.39 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 323.40 4,469.39 100.00%
01.08.02.05.03 PINTURA EN VIGAS LATEX SATINADO m2 39.45 13.82 545.20 545.20 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 39.45 545.20 100.00%
01.08.02.05.04 PINTURA EN MURO DE LADRILLO CARA VISTA LATEX SATINADO m2 401.05 13.82 5,542.51 5,542.51 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 401.05 5,542.51 100.00%
01.08.02.05.05 PINTURA EN ESTRUCTURAS METALICAS ESMALTE ANTICORROSI m2 75.24 11.82 889.34 889.34 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 75.24 889.34 100.00%
01.09 PUERTA DE INGRESO PRINCIPAL (01 UND) 27,823.82 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01 ESTRUCTURAS 15,656.90 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.01 TRABAJOS PRELIMINARES 39.33 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 28.92 1.36 39.33 39.33 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 28.92 39.33 100.00% - - 0.00%
01.09.01.02 MOVIMIENTO DE TIERRAS 1,111.11 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.02.01 EXCAVACION MANUAL DE ZAPATAS m3 3.90 28.14 109.75 109.75 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.90 109.75 100.00% - - 0.00%
01.09.01.02.02 EXCAVACION DE ZANJA PARA CIMENTACION m3 13.20 23.66 312.31 312.31 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 13.20 312.31 100.00% - - 0.00%
01.09.01.02.03 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACIO m2 39.91 2.72 108.56 108.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 39.91 108.56 100.00% - - 0.00%
01.09.01.02.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m3 22.23 13.80 306.77 306.77 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 22.23 306.77 100.00% - - 0.00%
01.09.01.02.05 RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO EN m3 4.60 16.90 77.74 77.74 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.60 77.74 100.00% - - 0.00%
01.09.01.02.06 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 16.25 12.06 195.98 195.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.25 195.98 100.00% - - 0.00%
01.09.01.03 OBRAS DE CONCRETO SIMPLE 2,585.20 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.03.01 SOLADO PARA ZAPATA DE ( e= 4") MEZCLA 1.10 CEMENTO - HOR m2 6.18 235.58 1,455.88 1,455.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.18 1,455.88 100.00% - - 0.00%
01.09.01.03.02 CONCRETO EN CIMIENTOS CORRIDOS; MEZCLA 1:10 CEMENTO m3 3.49 249.54 870.89 870.89 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.49 870.89 100.00% - - 0.00%
01.09.01.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTOS m2 2.23 51.69 115.27 115.27 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.23 115.27 100.00% - - 0.00%
01.09.01.03.04 CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTOS m3 0.45 318.13 143.16 143.16 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.45 143.16 100.00% - - 0.00%
01.09.01.04 SARDINEL EN PORTADA 2,879.76 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.04.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL m2 15.72 94.02 1,477.99 1,477.99 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.72 1,477.99 100.00% - - 0.00%
01.09.01.04.02 CONCRETO fc'= 175 kg/cm2 EN SARDINEL m3 3.43 403.13 1,382.74 1,382.74 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.43 1,382.74 100.00% - - 0.00%
01.09.01.04.03 CURADO DE CONCRETO m2 17.95 1.06 19.03 19.03 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 17.95 19.03 100.00% - - 0.00%
01.09.01.05 OBRAS DE CONCRETO ARMADO 9,041.50 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.05.01 ZAPATAS 1,240.24 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.05.01.01 ACERO FY=4200 Kg/cm2 kg 21.70 4.72 102.42 102.42 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.70 102.42 100.00% - - 0.00%
01.09.01.05.01.02 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 2.48 458.80 1,137.82 1,137.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.48 1,137.82 100.00% - - 0.00%
01.09.01.05.02 COLUMNAS 3,959.38 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.05.02.01 ACERO FY=4200 Kg/cm2 kg 325.24 4.72 1,535.13 1,535.13 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 325.24 1,535.13 100.00% - - 0.00%
01.09.01.05.02.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS m2 24.92 53.62 1,336.21 1,336.21 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 24.92 1,336.21 100.00% - - 0.00%
01.09.01.05.02.03 CONCRETO EN COLUMNAS F'C=210 KG/CM2 m3 2.58 411.48 1,061.62 1,061.62 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.58 1,061.62 100.00% - - 0.00%
01.09.01.05.02.04 CURADO DE CONCRETO m2 24.92 1.06 26.42 26.42 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 24.92 26.42 100.00% - - 0.00%
01.09.01.05.03 VIGAS 2,542.37 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.05.03.01 ACERO FY=4200 Kg/cm2 kg 208.62 4.72 984.69 984.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 208.62 984.69 100.00% - - 0.00%
01.09.01.05.03.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 18.39 53.62 986.07 986.07 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.39 986.07 100.00% - - 0.00%
01.09.01.05.03.03 CONCRETO EN VIGAS F'C=210 KG/CM2 m3 1.23 448.88 552.12 552.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.23 552.12 100.00% - - 0.00%
01.09.01.05.03.04 CURADO DE CONCRETO m2 18.39 1.06 19.49 19.49 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 18.39 19.49 100.00% - - 0.00%
01.09.01.05.04 LOSA MACIZA EN PORTADA 1,299.51 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.01.05.04.01 ACERO FY=4200 Kg/cm2 kg 33.99 4.72 160.43 160.43 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 33.99 160.43 100.00% - - 0.00%
01.09.01.05.04.02 ENCOFRADO Y DESENCOFRADO PARA LOSAS MACIZAS m2 4.80 64.56 309.89 309.89 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.80 309.89 100.00% - - 0.00%
01.09.01.05.04.03 CONCRETO F'C=210 KG/CM2 PARA LOSAS MACIZAS m3 1.64 502.50 824.10 824.10 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.64 824.10 100.00% - - 0.00%
01.09.01.05.04.04 CURADO DE CONCRETO m2 4.80 1.06 5.09 5.09 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 4.80 5.09 100.00% - - 0.00%
01.09.02 ARQUITECTURA 12,166.92 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.01 MUROS Y TABIQUES 843.75 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.01.01 MURO DE LADRILLO KK ARCILLA SOGA M:1:5 E=1.5 CM m2 16.54 50.64 837.59 837.59 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.54 837.59 100.00% - - 0.00%
01.09.02.01.02 JUNTA DE CONSTRUCCION CON TEKNOPORT m2 1.75 3.52 6.16 6.16 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.75 6.16 100.00% - - 0.00%
01.09.02.02 PISOS Y PAVIMENTOS 3,678.67 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.02.01 CONTRAPISO DE 48 MM. m2 21.85 25.36 554.12 554.12 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.85 554.12 100.00%
01.09.02.02.02 PISO ADOQUINADO m2 21.85 143.00 3,124.55 3,124.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 21.85 3,124.55 100.00%
01.09.02.03 REVOQUES Y ENLUCIDOS 979.62 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.03.01 TARRAJEO EN MURO INTERIOR MEZCLA 1:5, E=1.50CM m2 50.34 19.46 979.62 979.62 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 50.34 979.62 100.00%
01.09.02.04 COBERTURAS 608.36 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.04.01 COBERTURA CON TEJA ANDINA INDUSTRIAL m2 7.50 36.65 274.88 274.88 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.50 274.88 100.00%
01.09.02.04.02 CUMBRERA DE TEJA ANDINA INDUSTRIAL m 6.00 55.58 333.48 333.48 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 333.48 100.00%
01.09.02.05 CARPINTERIA METALICA Y HERRERIA 4,669.25 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.05.01 PUERTA METALICA VEHICULAR DOBLE HOJA 3.00M X 2.95M und 1.00 3,567.56 3,567.56 3,567.56 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 3,567.56 100.00%
01.09.02.05.02 PUERTA METALICA PEATONAL 1.20M X 2.95M und 1.00 1,101.69 1,101.69 1,101.69 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 1,101.69 100.00%
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
WISORE CONSULTORES Y CONTRATISTAS GENERALES SRL
PROYECTO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO
IE.I QOCHAPAMPA
% 03-10-2017 a 31-10-2017 01-11-2017 a 30-11-2017 01-12-2017 a 31-12-2017 01-01-2018 a 31-01-2018 01-02-2018 a 28-02-2018 01-03-2018 a 31-03-2018
Costo
ITEM DESCRIPCION Und Cantidad PARCIAL SUB TOTAL
Unitario INCID. METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO % METRAD0 COSTO %
01.09.02.06 PINTURA 1,035.99 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.06.01 PINTURA EN MUROS AL OLEO MATE EN EXTERIOR m2 16.54 20.30 335.76 335.76 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.54 335.76 100.00%
01.09.02.06.02 PINTURA EN VIGAS Y COLUMNAS INTERIOR LATEX ACABADO MA m2 50.34 13.91 700.23 700.23 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 50.34 700.23 100.00%
01.09.02.07 INSTALACIONES ELECTRICAS 351.28 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.09.02.07.01 SALIDA PARA CENTROS DE LUZ pto 2.00 65.59 131.18 131.18 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 131.18 100.00%
01.09.02.07.02 SALIDA DE INTERRUPTORES SIMPLES pto 1.00 71.95 71.95 71.95 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 71.95 100.00%
01.09.02.07.03 LAMPARA AHORRADORA DE 12W und 2.00 23.48 46.96 46.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 46.96 100.00%
01.09.02.07.04 SALIDA PARA TIMBRE pto 1.00 101.19 101.19 101.19 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 101.19 100.00%
01.10 TRATAMIENTO DE AGUAS SERVIDAS 16,249.83 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.01 BIODIGESTOR DE 7000LT 11,938.14 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.01.01 MOVIMIENTO DE TIERRAS 1,155.93 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.01.01.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 20.47 23.66 484.32 484.32 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 20.47 484.32 100.00% - - 0.00%
01.10.01.01.02 REFINE, NIVELACION Y COMPACTACION CON PISON MANUAL m2 0.95 1.66 1.58 1.58 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.95 1.58 100.00% - - 0.00%
01.10.01.01.03 RELLENO COMP.ZANJA CON MATERIAL PROPIO m3 7.26 36.40 264.26 264.26 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.26 264.26 100.00% - - 0.00%
01.10.01.01.04 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m3 16.51 13.80 227.84 227.84 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 16.51 227.84 100.00% - - 0.00%
01.10.01.01.05 CAMA DE APOYO m3 1.52 117.06 177.93 177.93 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.52 177.93 100.00% - - 0.00%
01.10.01.02 CONCRETO SIMPLE 2,059.82 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.01.02.01 CONCRETO f'c=140 kg/cm2 PARA SOLADOS Y/O SUB BASES m3 0.09 366.25 32.96 32.96 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 0.09 32.96 100.00%
01.10.01.02.02 CONCRETO F'C= 175 KG/CM2 m3 1.82 425.18 773.83 773.83 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.82 773.83 100.00%
01.10.01.02.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 15.15 50.86 770.53 770.53 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 15.15 770.53 100.00%
01.10.01.02.04 ACERO FY=4200 KG/CM2 kg 107.70 4.48 482.50 482.50 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 107.70 482.50 100.00%
01.10.01.03 SUMINISTRO E INSTALACIN DE BIODIGESTOR 8,722.39 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.01.03.01 SUMINISTRO E INSTALACIN DE BIODIGESTOR Y ACCESORIOS (70und 1.00 8,570.24 8,570.24 8,570.24 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 8,570.24 100.00%
01.10.01.03.02 TUBERIA PVC SAL 4" m 9.50 7.27 69.07 69.07 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.50 69.07 100.00%
01.10.01.03.03 TUBERIA PVC SAL 2" m 6.00 8.47 50.82 50.82 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.00 50.82 100.00%
01.10.01.03.04 ACCESORIOS PARA INSTALACION DE BIODIGESTOR GLB 1.00 32.26 32.26 32.26 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 32.26 100.00%
01.10.02 POZOS PERCOLADORES 4,311.69 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.02.01 OBRAS PRELIMINARES 16.00 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 6.25 2.56 16.00 16.00 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 6.25 16.00 100.00%
01.10.02.02 MOVIMIENTO DE TIERRAS 405.45 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.02.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 9.91 23.66 234.47 234.47 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 9.91 234.47 100.00%
01.10.02.02.02 ELIMINACION DE MATERIAL - MANUAL DISTANCIA PROMEDIO = 30 m3 12.39 13.80 170.98 170.98 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.39 170.98 100.00%
01.10.02.03 CONCRETO ARMADO 1,523.01 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.02.03.01 CONCRETO F'C= 175 KG/CM2 m3 3.08 425.18 1,309.55 1,309.55 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 3.08 1,309.55 100.00%
01.10.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 2.35 50.86 119.52 119.52 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.35 119.52 100.00%
01.10.02.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 19.49 4.82 93.94 93.94 - - 0.00% - - 0.00% - - 0.00% - - 0.00% - - 0.00% 19.49 93.94 100.00%
01.10.02.04 OTROS 2,367.23 - 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
01.10.02.04.01 MURO LADRILLO K.K DE ARCILLA DE CABEZA MEZCLA 1:4 m2 12.25 97.11 1,189.60 1,189.60 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 12.25 1,189.60 100.00% - - 0.00%
01.10.02.04.02 MATERIAL FILTRANTE m3 7.13 143.49 1,023.08 1,023.08 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 7.13 1,023.08 100.00% - - 0.00%
01.10.02.04.03 SALIDA DESAGUE POZO PERCOLADOR pto 2.00 19.70 39.40 39.40 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 2.00 39.40 100.00% - - 0.00%
01.10.02.04.04 ACCESORIOS GLB 1.00 115.15 115.15 115.15 - - 0.00% - - 0.00% - - 0.00% - - 0.00% 1.00 115.15 100.00% - - 0.00%
###
COSTO DIRECTO 1,129,926.03 48,939.85 100,289.33 149,501.55 218,481.05 271,629.22 341,085.04 ###
PROCENTAJE DE AVANCE MENSUAL 100% 4.33% 8.88% 13.23% 19.34% 24.04% 30.19% ###
48,939.85 149,229.17 298,730.72 517,211.78 788,840.99 1,129,926.03 ###
PORCENTAJE DE AVANCE ACUMULADO 4.33% 13.21% 26.44% 45.77% 69.81% 100.00% ###
CALENDARIO DE DESEMBOLSOS
PROYECTO:

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AY

Cliente
Lugar
Hecho por:
Item Descripcin SUB TOTAL % MES MES MES MES
INCID. N 01 N 02 N 03 N 04
01 OBRAS PRELIMINARES 0.00 #REF! 0.00 0.00 0.00 0.00

02 ALMACEN PROVISIONAL DE OBRA 2,695.20 #REF! 2,695.20 0.00 0.00 0.00


03 TRABAJOS GENERALES Y COMPLEMENTARIOS 0.00 #REF! 0.00 0.00 0.00 0.00
04 PERFILADO Y COMPACTADO DE LA SUBRRASANTE 2,112.00 #REF! 0.00 2,112.00 0.00 0.00
05 CONCRETO EN COLUMNAS F'C=210 KG/CM2 3,230.12 #REF! 0.00 1,292.05 1,938.07 0.00
06 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 10,226.30 #REF! 0.00 0.00 10,226.30 0.00
07 CONTRAPISO DE 48 MM. 3,247.35 #REF! 0.00 0.00 0.00 0.00
08 PINTURA EN CIELO RASO AL LATEX 2 MANOS 2,296.42 #REF! 0.00 0.00 0.00 0.00
09 LAVATORIO TIPO OVALIN PARA EMPOTRAR EN MESA DE CONCRETO 809.96 #REF! 0.00 0.00 0.00 0.00

10 NIVELACION Y COMPACTADO EN FONDO, ZANJAS DE EXCAVACION 388.87 #REF! 0.00 0.00 0.00 388.87
11 VIGAS DE CIMENTACION 2,927.78 #REF! 0.00 0.00 2,927.78 0.00
12 CURADO DE CONCRETO 0.00 #REF! 0.00 0.00 0.00 0.00
13 TARRAJEO DE CIELO RASO MEZCLA 1:5, E=1.50CM 1,636.01 #REF! 0.00 0.00 0.00 0.00
14 COBERTURAS #REF! #REF! #REF! #REF! #REF! #REF!
15 PRUEBA HIDRAULICA + DESINFECCION 32.84 #REF! 0.00 0.00 0.00 0.00
16 TABLERO DE DISTRIBUCION TD-2, 3,4... (20X40Cm) 0.00 #REF! 0.00 0.00 0.00 0.00
17 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. 743.20 #REF! 0.00 0.00 0.00 743.20
18 COLUMNETAS 362.07 #REF! 0.00 0.00 0.00 362.07

19 #REF! 226.20 #REF! 0.00 0.00 0.00 0.00


20 CANALIZACIONES CONDUCTOS O TUBERAS 189.48 #REF! 0.00 0.00 0.00 0.00
21 RED ELECTRICA SEGUNDARIA Y ACOMETIDA 5,785.06 #REF! 0.00 0.00 0.00 0.00
22 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
23 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
24 0 #REF! #REF! #REF! #REF! #REF! #REF!
25 #REF! #REF! #REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF! #REF!


PROCENTAJE DE DESEMBOLSO MENSUAL % #REF! #REF! #REF! #REF!
CALENDARIO DE DESEMBOLSOS
PROYECTO:

MEJORAMIENTO DEL SERVICIO EDUCATIVO EN 04 INSTITUCIONES EDUCATIVAS DEL NIVEL INICIAL DE LAS COMUNIDADES DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AY

Cliente
Lugar
Hecho por:
Item Descripcin SUB TOTAL % MES MES MES MES
INCID. N 01 N 02 N 03 N 04
PORCENTAJE DE DESEMBOLSO ACUMULADO % #REF! #REF! #REF! #REF!
E DESEMBOLSOS

DE QOCHAPAMPA, MAYOBAMBA, TAMBUCHA Y ROSASPATA, DISTRITO DE VINCHOS, PROVINCIA DE HUAMANGA- AYACUCHO

MES MES
N 05 N 06
0.00 #REF!

0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!
2,296.42 #REF!
809.96 #REF!

0.00 #REF!
0.00 #REF!
0.00 #REF!
818.01 #REF!
#REF! #REF!
32.84 #REF!
0.00 #REF!
0.00 #REF!
0.00 #REF!

226.20 #REF!
189.48 #REF!
5,785.06 #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

#REF! #REF!
#REF! #REF!
E DESEMBOLSOS