Vous êtes sur la page 1sur 3

PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT CURRENT TRANSFORMER


MLDB IDCT - PMCC

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 1 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 27.6.17

1. Board Details

1 STATION NAME/BOARD Unit 3 & 4


2 AREA/LOCATION IDCT-PMCC
3 DRAWING NUMBER
4 RATING 200/1 A

2. Verification of Name Plate Details

Results (Ok/
Feeder No.
Sl. No. Make Ratio VA Class In.class Not Ok)
MLDB CT R=3189576 Precise 200/1 10 1 B OK
MLDB CT Y=3189592 Precise 200/1 10 1 B OK
MLDB CT B=3189583 Precise 200/1 10 1 B OK

Acceptance Criteria: Ratings, Make & Type shall be as per approved Drawing

3. Physical Verification of Wiring Tightness from Primary & secondary terminals to


Protective &Metering terminals

Wiring Tightness (Ok/Not Ok)

Feeder no. Protection/Metering R Y B Remarks

MLDB CT METERING OK OK OK

Acceptance Criteria: There shall not be any loose connections and Terminal connections
shall be as per approved Drg.

SIGNATURE
NAME DESIGNATION DATE

TEST ENGR. Rajesh S Testing Engr.


BGRESL Rathina Kumar D Dy.Manager
OPGCL
PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT CURRENT TRANSFORMER


MLDB IDCT - PMCC

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 2 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 27.6.17

4. Ratio test
Ratio
Protection/ R Y B Results(Ok/N Remarks
Feeder
Metering
No. Pri Sec Pri (A) Sec (A) Pri (A) Sec otOk)
(A) (A) (A)
50 0.248 50 0.249 50 0.251 OK

MLDB 100 0.501 100 0.499 100 0.499 OK


METERING
CT 150 0.701 150 0.749 150 0.749 OK

200 1.006 200 0.999 200 1.001 OK

Acceptance Criteria: Ratio Error at rated Current is +/- 1%

5. Measurement of Secondary Winding resistance for Protection CTs

Resistance in
Feeder No.
R Y B Remarks

MLDB CT 1.9 2.1 2.1 OK

Acceptance Criteria: There shall not be any abrupt difference from Factory value.

6. Measurement of Insulation Resistance for CTs

Resistance in
Feeder No. Reference Remarks
R Y B

Primary-Earth >1G >1G >1G OK

MLDB Sec-Earth 691 >1G 591 OK

Primary -Sec >1G 595 >1G OK

SIGNATURE
NAME DESIGNATION DATE

TEST ENGR. Rajesh S Testing Engr.


BGRESL Rathina Kumar D Dy.Manager
OPGCL
PROJECT: PROJECT: 2 X 660 MW IB THERMAL POWER STATION

TEST REPORT CURRENT TRANSFORMER


MLDB IDCT - PMCC

CLIENT ODHISHA POWER GENERATION CORPORATION LTD Page 3 of 3


EPC-BOP BGR ENERGY SYSTEMS LTD - POWER PROJECT DIVISION Date: 27.6.17

7.POLARITY

IDENTIFICATION R Y B

1S1 1S2 OK OK OK

7. Remarks

Test results of all the CTs in the board are found satisfactory.

SIGNATURE
NAME DESIGNATION DATE

TEST ENGR. Rajesh S Testing Engr.


BGRESL Rathina Kumar D Dy.Manager
OPGCL

Vous aimerez peut-être aussi