1 sigma =68.

26%
2 Sigma =95.46%
3 Sigma =99.73%
6 Sigma = 99.99%
==============
Critical path of the project has 3 activities in sequence . Activity A has
optimistic estimate as 8,pessimistic as 16 and most likely as 12.Activity B has
optimistic estimate as5,Pessimistic estimates as15 and most likely estimate as
0.Activity C has optimistic estimate as 10,pessismistic estimate as 20 and most
likely as 15.What is the confidence that project would finish between 34-40 days?
-->
Confidence Interval= Project Mean +/- 1SD will give you a range at 68% confidence
Project Mean +/- 2SD will give you a range at 95.5% confidence
Project Mean +/- 3SD will give you a range at 99.97% confidence
================