DISEO DE ZAPATA AISLADA

1. METRADOS DE LA EDIFICACION INGRESAR DATOS


M= 1.645 m RESULTADOS
Area Tributaria
N= 2.9 m
Nro de pisos 4
Carga Muerta 800 kg/m2
Carga Viva 200 kg/m2
PD= 72.875 ton
PL= 33.125 ton Col=

2. DATOS S/C (kg/m2)= 400


PD= 72.875 ton
PV= 33.125 ton
terre= 2.5 kg/cm2 0.3
fc= 210 kg/cm2
fy= 4200 kg/cm2
Df= 1.6 m
hf= 1.9 m
S/c= 400 kg/m2
s= 1.8 ton/m3 d= 0.5
c= 2.4 ton/m3
m 2.1 ton/m3
COLUMNA 0.3 m
0.75 m

3. CALCULO DEL ESFUERZO NETO DEL SUELO =/

n= 20.61 ton/m2

4. AREA DE LA ZAPATA EN PLANTA =/


Pservicio= 106 ton
Az= 5.1431344008 m2 Requerida

Columna 0.75 0.3 m


Lv= 0.9 m
T= 2.55 m
S= 2.1 m
S Area Coloc= 5.355 m2
Diferencia 0.211865599 >>0 CUMPLE!!!
T
5. REACCION NETA ULTIMA DEL SUELO
=/
Pu= 158.3375 ton/m2
Pu
Wnu= 29.568160598 ton/m2

6.DIMENSIONAMIENTO EN ALTURA h
h=
Wnu 0.6 m
d= 0.5 m

7. VERIFICACION POR CORTANTE


= 0.85
Vc= 68.5478348537 ton
Vu= 24.837254902 ton
=0.53 , =

=()
21.1116666667 68.5478348537
CUMPLE!!!

d d
S

8. VERIFICACION POR PUNZONAMIENTO

= d/2

n
1=0.27(2+4/))
d/2

= 2=1.06 0.85 ELEGIR


EL
m= 1.25 m
MENOR = 2+2
n= 3=0.27(2+()/)
0.8 m
ELEGIR
EL
MENOR

bo= 4.1 m
Bc= 2.5 2
Vc1= 272.713218987 ton
Vc2= 267.66297419 ton
Vc3= 468.933705818 ton
Vu= 128.769339402 ton

109.4539384921 267.66297419
CUMPLE!!!

9. DISEO POR FLEXION


Wnu= 29.5681605976 ton/m2

Lv= 0.9 m
S= 2.1 m
Mu= 25.1477205882 ton*m
fc= 210 kg/cm2
fy= 4200 kg/cm2
phi= 0.9
b= 2.1 m
d= 0.5 m
w= 0.0257690911 = ^2/2
cuantia 0.0012884546 As requerido 13.5287728169 cm2
Cuantia minima 0.0018 As minimo 18.9 cm2
USAR= 18.9 cm2

ACERO EN LA DIRECCION LONGITUDNAL


Rec 7.5 cm
S= 2.1 m
T= 2.55 m

*Supongamos Acero 5/8"


Diam 1.59 cm
Ab= 2 cm2
Nro Varillas= 9.45
12
S ESP= 17.5827272727
20 COLOCAR 12

ACERO EN LA DIRECCION TRANSVERSAL


T r= 7.5 cm=(2)/(1)
Ast= 22.95 cm2
S= 2.1
T= 2.55
*Supongamos Acero 5/8"
Diam 1.6 cm
Ab= 2 cm2 =/
Nro Varillas= 11.475
14
S= 18.3384615385
S 14
20 COLOCAR
INGRESAR DATOS
RESULTADOS

0.75 x 0.3

Df= 1.6 hf= 1.9

h= 0.6

CUMPLE!!!
40 30 20

2+2 =
=/
=/

BARRA db(cm) Ab(cm2)


8 mm 0.8 0.5
3/8" 0.95 0.71
1/2" 1.27 1.29
5/8" 1.59 2
3/4" 1.91 2.84
7/8" 2.22 3.87
1" 2.54 5.1
1 3/8" 3.58 10.06

5/8" @ 20
5/8" @ 20
DISEO DE ZAPATA EXCENTRICA
DATOS
PD= 15.2656 ton AREA TRIBUTARIA COLUMNA EXCENTRICA
PV= 3.8164 ton M= 1.645 m
terre= 1 kg/cm2 N= 2.9
fc= 210 kg/cm2 Area= 4.7705
fy= 4200 kg/cm2 Pisos= 4
Df= 1.4 m Carga Muerta 800 kg/m2
hf= 1.5 m Carga Viva 200 kg/m3
S/c= 400 kg/m2
s= 1.8 PD= 15.2656 ton
c= 2.4 PL= 3.8164 ton
m 2.1 ton/m3

1. ESFUERZO NETO DE DISEO n


n= 6.45 ton/m

2. AREA DE LA ZAPATA EN PLANTA


Az= 2.9584496124 m2

Columna= 0.25 0.4


c= 1.25
L Area= 4.5375 m2
Dif= -1.579050388
B= 1.65
B L= 1.5
3. VERIFICACION DEL SUELO
M= 9.541 ton*m
P= 19.082 ton
en la zap con M 21.727897153 ton/m <<<terren= 10 ton/m2 NOCUMPLE
23.12969697
en la zap sinM 7.7098989899 ton/m <<<terren= 10 ton/m2 CUMPLE

4. REACCION NETA DEL SUELO Wu


Pu= 27.85972 ton
Wu= 11.256452525 ton/m2

5. DIMENSAMIENTO DE ALTURA h=
h= 0.6 m
d= 0.5 m

6. VERIFICACION POR CORTANTE d= 0.5


<
CORANTE RESISTENTE
0.85
L= 1.5 L= 1.5
Vc= 57.603222566 ton B= 1.65
Vc= 48.962739181 C= 1.25

CORTANTE ACTUANTE
VU= a d de la cara
VU= 12.663509091 ton <<Vc= CUMPLE ton/m2

7. VERIFICACIO POR PUNZONAMIENTO


CORANTE RESISTENTE
0.85
bo= 2.05 d/2= 0.25
Vc= 163.39027281 bo= 2.05
Vc= 138.88173189
CORTANTE ACTUANTE
Pu= 27.85972
Ao= 0.4875
Vu= 22.372199394 <<Vc= CUMPLE ton/m2

8. DISEO POR FLEXION


wu= 11.256452525 ton/m2
c= 1.25 m
L= 1.5 m
Mu= 13.191155303 ton*m
fc= 210
fy= 4200
phi= 0.9
b= 1.5
d= 0.5
w= 0.0188547813
cuantia 0.0009427391 As reque 7.0705429978 cm2
Cuantia minima 0.0018 As minim 13.5 cm2
USAR= 13.5 cm2
ACERO EN LA DIRECCION LONGITUDNAL
Rec 7.5 cm
L= 1.5 m
B= 1.65 m

*Supongamos Acero 5/8"


Diam 1.6 cm
Ab= 2 cm2
Nro Varillas= 6.75 =(2)/(1)
7
S= 22.233333333
20 COLOCAR 8 5/8"@25

ACERO EN LA DIRECCION TRANSVERSAL


=/
r= 7.5 cm
Ast= 14.85 cm2
L= 1.5
B= 1.65
*Supongamos Acero 5/8"
Diam 1.6 cm
Ab= 2 cm2 =(2)/(1)
Nro Varillas= 7.425
9
S= 18.55
20 COLOCAR 5 5/8"@20
XCENTRICA
DISEO DE ZAPATA DOBLE EXCENTRICA
DATOS
PD= 15.33 ton AREA TRIBUTARIA COLUMNA EXCENTRICA
PV= 3.83 ton M= 1.645 m
terre= 1.5 kg/cm2 N= 2.9 m
fc= 210 kg/cm2 Area= 4.7705 m2
fy= 4200 kg/cm2 Pisos= 4
Df= 1.4 m Carga Muerta 800 kg/m2
hf= 1.5 m Carga Viva 200 kg/m3
S/c= 400 kg/m2
s= 1.8 PD= 15.2656 ton
c= 2.4 PL= 3.8164 ton
m 2.1 ton/m3

1. ESFUERZO NETO DE DISEO n


n= 11.45 ton/m

2. AREA DE LA ZAPATA EN PLANTA


Az= 1.6733624454 m2

Columna= 0.25 0.4


c= 1.4
L Area= 2.97 m2
Dif= -1.296637555
B= 1.8
B L= 1.65
3. VERIFICACION DEL SUELO
ex= 0.7 m
MY= 13.412 ton*m
ey= 0.7 m
MX= 13.412 ton*m
P= 19.16 ton
en la zap con M Y 21.503928171 ton*m <<<terren= 15 ton/m2 no cumple
en la zap con M X 22.872359963 ton*m
en la zap sinM 6.4511784512 ton/m <<<terren= 15 ton/m2 CUMPLE

4. REACCION NETA DEL SUELO Wu


Pu= 27.973 ton
Wu= 9.4185185185 ton/m2
5. DIMENSAMIENTO DE ALTURA h=
h= 0.6 m
d= 0.5 m

6. VERIFICACION POR CORTANTE d= 0.5


<
CORANTE RESISTENTE
0.85
L= 1.65 L= 1.65
Vc= 63.363544823 ton B= 1.8
Vc= 53.859013099 C= 1.4

CORTANTE ACTUANTE
VU= a d de la cara
VU= 13.9865 ton <<Vc= CUMPLE ton/m2
15.258 ton
7. VERIFICACIO POR PUNZONAMIENTO
CORANTE RESISTENTE
0.85
bo= 1.15 d/2= 0.25
Vc= 91.65795792 bo= 1.15
Vc= 77.909264232
CORTANTE ACTUANTE
Pu= 27.973
Ao= 0.325
Vu= 24.911981481 <<Vc= CUMPLE ton/m2

8. DISEO POR FLEXION


wu= 9.4185185185 ton/m2
c= 1.4 m
L= 1.65 m
Mu= 15.229744444 ton*m
fc= 210
fy= 4200
phi= 0.9
b= 1.65
d= 0.5
w= 0.0197991634
cuantia 0.0009899582 As reque 8.1671549053 cm2
Cuantia minima 0.0018 As minim 14.85 cm2
USAR= 14.85 cm2

ACERO EN LA DIRECCION LONGITUDNAL


Rec 7.5 cm
L= 1.65 m
B= 1.8 m

*Supongamos Acero 5/8"


Diam 1.6 cm
Ab= 2 cm2
Nro Varillas= 7.425 =(2)/(1)
7
S= 24.733333333
20 COLOCAR 7 5/8"@

ACERO EN LA DIRECCION TRANSVERSAL


=/
r= 7.5 cm
Ast= 16.2 cm2
L= 1.65
B= 1.8
*Supongamos Acero 5/8"
Diam 1.6 cm
Ab= 2 cm2 =(2)/(1)
Nro Varillas= 8.1
8
S= 23.342857143
25 COLOCAR 8 5/8"@
XCENTRICA
0.2 m

25 m
DISEO DE ZAPATA CONECTADA
1. METRADOS DE LA EDIFICACION INGRESAR DATOS
M= 3.1 m RESULTADOS
Area Tributaria
N= 3.23 m
Nro de pisos 3
Carga Muerta 800 kg/m2 COLUMNA 1
Carga Viva 200 kg/m2 0.4 0.25
PD= 24.0312 ton PD1= 24.0312
PL= 6.0078 ton PV1= 6.0078

DATOS
L= 6.46
L1= 6.06 m
PD1= 24.0312 ton
PV1= 6.0078 ton
Hf
PD2= 24.0312 ton
PV2= 6.0078 ton
terre= 1.5 kg/cm2
Df
fc= 210 kg/cm2
fy= 4200 kg/cm2
d1
Df= 1.5 m
hf= 1.6 m
S/c= 400 kg/m2
Y
s= 1.8 ton/m3 0.4
c= 2.4 ton/m3
m 2.1 ton/m3 X
COLUMNA 1 COLUMNA 2
0.4 0.25 0.4 0.25 m
x y x y

1. PREDIMENSIONAMIENT DE LA VIGA DE CONEXXION


L1= 6.06 m
h 0.87 USAR h= 0.6 m =1/7 =1/
b= 0.16 USAR b= 0.25 m (311)

2. ESFUERZ NETO
=/
n= 11.24 ton/m2

3. DIMENSIONAMIENTO DE LA ZAPATA EXTERIOR


1.20*P1= 36.05 ton =(1.21)/

Az= 3.21 m2 requerida
X Y
COLUMNA 1 0.4 0.25
Lv= 1.00 m
T T1= 2.30 m
S1= 1.40 m
Area Coloc= 3.22 m2
Diferencia 0.01 >>0 CUMPLE!

S
3. DIMENCIONAMIENTO DEFINITVO DE LA ZAPATA EXTERIOR 2 P1=
VIGA CIMENTA 0.25 0.6 m
Wviga= 0.36 ton/m
Distancias
1= 6.46 P1= 30.039 ton
2= 0.2 P2= 30.039 ton
3= 5.56 RN1= 31.2018 ton
4= 0.5 RN2= 31.2018 ton
5= 0.2 n= 11.24
6= 2.88
7= 0.7 =/
8= 0.35
9= 5.06 RN1

Az1= 2.78 Requerida Az2=


X Y
COLUMNA 1 0.4 0.25 COLUMNA 2
Lv= 0.930 m Lv=
T1= 2.11 m T2=
S1= 1.33 m S2=
Area Coloc= 2.81 m2 Area Coloc=
Diferencia 0.03 >>0 CUMPLE! Diferencia

4. DISEO DE LA VIGA DE CIMENTACION


Pu 1.4*PD+1.7*PL
PU1= 43.85694
PU2= 43.85694
Wvigau= 0.504 ton/m
Rnu1= 45.48486 ton
Rnu2= 45.48486 ton

4. REACCION NETA DEL SUELO POR UNIDAD DE LONGITUD


S= 1.35
Wnu1= 33.692488889 ton/m =/
S= 1.35
Wnu2= 33.692488889 ton/m

5. CALCULO DEL MOMENTO MAXIMO (ANALISIS ESTRUCTURAL)

=1/()
a) Cuando V=0 ===> Mma
x= 1.3214503422
M Max= -20.20599619

M (tonm) 20.21 BARRA db(cm) Ab(cm2)


b (cm) 0.25 8 mm 0.8 0.5
d (cm) 0.51 3/8" 0.95 0.71
fc (kg/cm2) 210 1/2" 1.27 1.29
fy (kg/cm2) 4200 5/8" 1.59 2
w= 0.1846 3/4" 1.91 2.84
p= 0.0092 7/8" 2.22 3.87
As cm2 11.77 1" 2.54 5.1
p minima= 0.0033 1 3/8" 3.58 10.06
Asmin 4.2500
INGRESAR DATOS
RESULTADOS

COLUMNA 2
0.4 0.25
PD2= 24.0312
PV2= 6.0078
L1= 6.06

L= 6.46

VIGA DE CIMENTACION d1

m 0.4 m

=1/ /2
11)

/
1.20*P1= 36.05 ton
Az= 3.21 m2 requerida

COLUMNA 2
Lv=
T T2=
S2=
Area Coloc=
CUMPLE! Diferencia

1
S
3 4 5
P2=

VIGA DE CIMENTACION

7
8
9
RN1 RN2

2.78 Requerida
X Y
0.4 0.25
0.930 m
2.11 m
1.33 m
2.81 m2
0.03 >>0 CUMPLE!
=()^2/21(/2)

USAR:
0 1/2" 1.29
3 5/8" 2
3 3/4" 2.84
0 7/8" 3.87
0 1" 5.1
Area Colocada 14.52
As inferior= 3.92
123.39648641
=(1.21)/

X Y
0.4 0.25
1.00 m
2.30 m
1.40 m
3.22 m2
0.01 >>0 CUMPLE!