DAFTAR PENAWARAN HARGA

Pekerjaan : Pengembangan Jaringan Distribusi Wilayah Jawa Bagian Barat


dan Sumatera Bagian Selatan 3
Sub Pekerjaan : Box Valve Tipe (a) ukuran 2.3 x 1.5 x 2.3 m

Total Price
No. Uraian Pekerjaan Qty. Unit Unit Price (Rp.) Remarks
(Rp.)

A PEKERJAAN BOX VALVE


1 Galian Tanah Keras 10.90 m 105,090.00 1,145,481.00
2 Urugan dan Pemadatan 2.90 m 45,800.00 132,820.00
3 Lantai Kerja Beton 1 : 3 : 5, tebal 50 mm 0.20 m 115,180.00 23,036.00 50 mm thickness
4 Beton Struktur K-250 4.20 m 1,692,500.00 7,108,500.00
5 Pembesian tulangan D13 - 120 330.00 Kg 23,020.00 7,596,600.00
6 Pembesian tulangan D13 - 120 376.20 Kg 23,020.00 8,660,124.00
7 Formwork 21.00 m2 135,500.00 2,845,500.00
8 L-40X40X3 6.40 m 25,500.00 163,200.00
9 CNP 3.20 m 25,500.00 81,600.00
10 Ladder 6.20 m 25,500.00 158,100.00

SUB TOTAL - A 27,914,961.00

Profit 10 % 2,791,496.10

SUB TOTAL - B 30,706,457.10

PPN 10% 3,070,645.71

TOTAL 33,777,102.81

T O T A L (Pembulatan) 33,777,000.00

Bogor, 01 December 2016


Disetujui oleh, Diperiksa oleh, Dibuat oleh,
PT. PGN (Persero) Tbk. KSO-BEC+SSA KSO-BEC+SSA
PMO Infrastruktur

( __________________ ) ( __________________ ) ( __________________ )

Page 1 of 2
EARTH WORK :
Excavation 10.90 m3
2.3

Soil Disposal 8.00 m3

Backfill 2.90 m3
2.3
CONCRETE WORK : Lantai Kerja 0.2 m3
Concrete bagian bawah 0.69 m3
Concrete bagian samping 2.76 m3
Concrete bagian atas 0.69 m3
1.5 Total Concrete : 4.20 m3

Tebal dinding : 0.2 m FORM WORK :


Bagian atas : 3.45 m2
Bagian samping : 17.48 m2
Total Form work : 21.00 m2

RE-BAR WORK :
Dia-13 130 m
Dia-13 200 m
Total Dia-13 330 m 330 kg

Dia-16 136 m
Dia-16 136 m
Total Dia-16 272 m 376.2 kg

STEEL WORKS :
L-40X40X3 6.4 m
CNP 3.2 m
Ladder 6.2 m

Page 2 of 2