Total Price
No. Uraian Pekerjaan Qty. Unit Unit Price (Rp.) Remarks
(Rp.)
Profit 10 % 2,791,496.10
TOTAL 33,777,102.81
T O T A L (Pembulatan) 33,777,000.00
Page 1 of 2
EARTH WORK :
Excavation 10.90 m3
2.3
Backfill 2.90 m3
2.3
CONCRETE WORK : Lantai Kerja 0.2 m3
Concrete bagian bawah 0.69 m3
Concrete bagian samping 2.76 m3
Concrete bagian atas 0.69 m3
1.5 Total Concrete : 4.20 m3
RE-BAR WORK :
Dia-13 130 m
Dia-13 200 m
Total Dia-13 330 m 330 kg
Dia-16 136 m
Dia-16 136 m
Total Dia-16 272 m 376.2 kg
STEEL WORKS :
L-40X40X3 6.4 m
CNP 3.2 m
Ladder 6.2 m