Académique Documents
Professionnel Documents
Culture Documents
Project Initiation Concept Selection FEED Detail Design Ready for Operations Asset Handover Project Evaluation
Next Phase Review Concept Selection Partner Approval & Agreement Asset Management Plan Project Update Asset Management Plan Update Stakeholder Analysis Project Documentation Archived
Preliminary PEP Stakeholder Analysis Update Stakeholder Analysis Update Stakeholder Analysis Update Communication Plan Lessons Learned Archived
Feasibility Report Communication Plan Update Communication Plan Update Communication Plan Lessons Learned
Commercial Proposal Insurance Plan Lessons Learned Recruit Operating Organization Peer Review
Project Team composition & leadership Document Control Plan Independent gate review Selection and training of operating staff Next Phase Review
Partner Strategy Document Control Applications in place Next Phase Review Lessons Learned
Preliminary Stakeholder Analysis Lessons Learned Peer Review
Preliminary Communication Plan Independent gate review Next Phase Review
Next Phase Review
Preliminary Document Control Plan
Peer Review
Change Management Framework
Lessons Learned
Next Phase Review
FEED Scope Defined FEED complete Detailed Design Complete Value Improvement Practices
Value Improvement Practices Value Improvement Practices Operability / Maintainability Review As-Built Drawings
Engineering &
Construction
Preliminary List of applicable standards List of applicable standards and codes Value Improvement Practices
and codes Decommissioning Plan incorporated into
Decommissioning Issueslan Design
Operability / Maintainability Review
Sparing Philosophy
Decommissioning Plan Updated
Key Deliverables
" Preliminary Logistics Strategy Transportation & Logistics Plan Update Transportation & Logistics Plan Start-up of Asset
Hand over/Start up Systems Identified Hand over/Start up Systems Finalized Update Construction Management Plan Deficiencies Managed
Operations
Environmental Impact Assessment (EIA) Audit Design Plan Audit Construction Plan Audit Operations & Maintenance Plan
Life Cycle Analysis (LCA) Hazard Operability Study (HAZOP) Hazard Operability Study (HAZOP) Update Project Quality Plan (PQP)
Legal Requirements identified Preliminary Project Quality Plan (PQP) Project Quality Plan (PQP) Emergency Response Plan completed
Preliminary Legal Strategy Legal Strategy Update Permitting Plan Sustainable Development Framework
Sustainable Development Framework Permitting Plan Permits & Permissions Obtained Update Risk Management Plan
Preliminary Risk Management Plan Legal Applications prepared License to Operate Obtained Update Risk Register
Sustainable Development Framework Sustainable Development Framework
Risk Management Plan Update Risk Management Plan
Update Risk Register Update Risk Register
Preliminary Risk Assessment Process Hazards Analysis (PHA)
Process Hazards Analysis (PHA)/ Safety complete
Integrity Levels (SIL) conducted
Preliminary Contracting Plan Contracting Plan Issue request for Quotes (RFQs) Contract Control
Procurement
Identify Long Lead Items Tender Board submission and approval of Purchase orders Issued
&
Apply/Secure Funding required for long Cost Control Plan Update Cost Control Plan Update Cost Control Plan Update Cost Control Plan
Planning
approved
lead procurement Cost saving potential Baseline Schedule level 3 Baseline Schedule level 4 Baseline Schedule level 4
Baseline Schedule level 1 Baseline Schedule level 3 Update Progress Control Plan Update Progress Control Plan Update Progress Control Plan
Budget request next phase approved Progress Control Plan Budget request next phase approved Budget request next phase approved
Budget request next phase approved