Académique Documents
Professionnel Documents
Culture Documents
Paper 0480
VT
reliable islanding detection, even based on passive
methods like voltage phase angle-based methods or
voltage vector shift. The algorithm proposed in [2]
continuously ensures that there is enough reactive power
unbalance that the operation point remains constantly Figure 1. Equivalent circuit of a synchronous generator operating in
outside the NDZ of the used islanding detection method. parallel with the grid
Paper 0480
When the generator current Is is passing through the voltages (when all three phase voltage are used). The
generator reactance Xd, there is a voltage difference V vector shift algorithm is blocked, when any of the
between the terminal voltage VT and the generator internal measured voltages drop below or increase above the
voltage EI (Figure 1). Consequently, there is a threshold values.
displacement angle between the terminal voltage and START
generator internal voltage. The phasor diagram is shown in U_AB Signal
Figure 2(a). After the circuit breaker opens, the system U_BC Signal
AngDif_AB = ABS(FFT angle(U_AB)t=0 FFT angle(U_AB)t= 2cycles old)
AngDif_BC = ABS(FFT angle(U_BC)t=0 FFT angle(U_BC)t= 2cycles old)
consisting of the generator and load becomes islanded. At U_CA Signal AngDif_CA = ABS(FFT angle(U_CA)t=0 FFT angle(U_CA)t= 2cycles old)
U1 Signal AngDif_U1 = ABS(FFT angle(U1)t=0 FFT angle(U1)t= 2cycles old)
this same time instant, the synchronous generator begins Fm - Measured
to feed a larger (or smaller) load because the current IGr frequency
FN - Nominal IF {(Fm)t=0 (Fm)t=5 cycles old} < 0.001 FN, THEN FStable = (Fm)t=5 cycles old
frequency CorrectionAngle = (FN -FStable)x2x360.
provided by the grid is interrupted. Due to this, the angular
difference between VT and EI is suddenly increased (or
decreased) and the terminal voltage phasor changes its Fstable > FN + 2.5 Hz
YES
OR
position as shown in Figure 2(b). The sudden vector shift Fstable < FN 2.5 Hz
due to islanding can also be seen in the voltage waveform
NO
in Figure 2(c). VSAng_AB = AngDif_AB + CorrectionAngle
VSAng_BC = AngDif_BC + CorrectionAngle
VSAng_CA = AngDif_CA + CorrectionAngle
VSAng_U1 = AngDif_U1 + CorrectionAngle
U_BC Signal
U1 Signal
Out of three phases, if any one of the phase detects vector shift, the
Occurrence of LOM algorithm is initiated.
V(t)
Paper 0480
power load. The system line types and line parameters are vector shift angle behaviour and binary output signals
also presented in Figure 4. Simulations were done with a (operate and internal blocking) for vector shift algorithm
directly connected synchronous generator (SG) based DG are presented.
unit at the MV feeder and other DG units as well as de- Voltage magnitude in three phases
Voltage(pu)
centralized compensation coils were disconnected (Figure 1
U AB
U BC
4). U CA
0.8
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s)
Vector shift angle detected in three phases
Angle(Degrees)
30
VSAng AB
20
VSAng BC
10
VSAng CA
0
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s)
Vector shift algorithm Operate and Blocked signals
Binary outputs
1
OPERATE
0.5 INT BLKD
0
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s)
U AB
0.5 U BC
are simulated by opening the MV feeder CB (A in Figure U CA
4) or the recloser CB (B in Figure 4) at time 20.0 s and 0
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s)
by closing the CB 0.3 s later i.e. at 20.3 s. The faults and Vector shift angle detected in three phases
Angle(Degrees)
200
other network disturbances related simulation cases, i.e. VSAng AB
100 VSAng BC
cases where the algorithm should not operate, were done 0
VSAng CA
19.9 20 20.1 20.2 20.3 20.4 20.5
to test the stability of the algorithm. Time(s)
Vector shift algorithm Operate and Blocked signals
Binary outputs
a COMTRADE-file format. The proposed algorithm is Figure 6. Vector shift algorithm operation during islanding in large
tested with these voltage measurements from different power unbalance
simulated cases and the results are presented in the
following sections. During the testing, the algorithm pick- From Figure 6, one can see that after islanding at 20.0 s,
up value setting, i.e. vector shift angle, was 5 degrees and the vector shift angles start to increase in all three phases.
the algorithm blocking settings for undervoltage was 0.80 When compared with the islanding in small power
pu and for overvoltage 1.2 pu. unbalance, the vector shift can now be detected faster as
expected. In this case, the algorithm issues an OPERATE
Real Islanding Cases pulse output at around 20.05 s.
Islanding in Small Power Unbalance Faults and Other Network Disturbances
When islanding in small power unbalance, the local Phase-to-Earth Fault
generation is a bit larger (or smaller) than the local load in In this case, the phase-to-earth (A-G) fault for 150 ms, is
the MV network. When the generation is larger than the applied in the middle of the same MV feeder (viii in
load, the power is exported to the utility grid. Respectively, Figure 4), i.e. 15 km from the recloser CB. Fault resistance
if the local generation is smaller than the local load, then Rf = 1000 . In Figure 7, phase-to-phase voltage
the deficit power is imported from the utility grid. magnitudes, voltage vector shift angle behavior and binary
However, results for the vector shift algorithm are similar output signals for vector shift Operate and blocking are
in both cases if the size of the power unbalance is equal. In presented.
Figure 5, phase-to-phase voltage magnitudes, voltage From Figure 7, it can be observed that during the A-G
Paper 0480
Voltage(pu)
1 U AB
phase-to-phase voltages (UAB, UCA). Because the detected 0.5 U BC
vector shift angles are less than the pick-up setting and the U CA
0
19.9 20 20.1 20.2 20.3 20.4 20.5
vector shift is not detected in all three phases, the Time(s)
Vector shift angle detected in three phases
Angle(Degrees)
developed vector shift algorithm is not operated. 80
VSAng AB
40 VSAng BC
Voltage magnitude in three phases
0.97 VSAng CA
Voltage(pu)
U AB 0
19.9 20 20.1 20.2 20.3 20.4 20.5
0.96 U BC Time(s)
U CA Vector shift algorithm Operate and Blocked signals
Binary outputs
0.95
19.9 20 20.1 20.2 20.3 20.4 20.5 1
Time(s)
OPERATE
Vector shift angle detected in three phases 0.5 INT BLKD
Angle(Degrees)
0.4 0
VSAng AB 19.9 20 20.1 20.2 20.3 20.4 20.5
0.2 VSAng BC Time(s)
VSAng CA
0
19.9 20 20.1 20.2 20.3 20.4 20.5
Figure 9. Vector shift algorithm behavior during A-B-C fault at the
Time(s) beginning of the adjacent MV feeder
Vector shift algorithm Operate and Blocked signals
Binary outputs
1
OPERATE From Figure 9, one can see that during the A-B-C fault, all
0 INT BLKD
-1
three phase-to-phase voltages vector shift angles are
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s) significantly above the pick-up setting (5 degrees). But the
Figure 7. Vector shift algorithm behavior during A-G fault in the three phase-to-phase voltage magnitudes are below the set
middle of the same MV feeder undervoltage value (0.8 pu), which caused activation of the
Phase-to-Phase Fault algorithm internal block (INT_BLKD). Due to this internal
In this case, the phase-to-phase (A-B) fault for 150 ms is blocking the developed vector shift algorithm is not
applied in the middle of the adjacent MV feeder (ix in operated.
Figure 4). Fault resistance Rf = 5 . The results are 30% Voltage Dip in HV Network
presented in Figure 8. In this case, the 3-phase 30 % voltage dip is simulated in a
Voltage magnitude in three phases 110 kV HV network (xi in Figure 4). The results are
1
Voltage(pu)
Time(s) U AB
Vector shift angle detected in three phases 0.8 U BC
Angle(Degrees)
10 U CA
VSAng AB 0.6
19.9 20 20.1 20.2 20.3 20.4 20.5
5 VSAng BC Time(s)
VSAng CA Vector shift angle detected in three phases
0
Angle(Degrees)
1 VSAng CA
OPERATE 0
0.5 INT BLKD 19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s)
0 Vector shift algorithm Operate and Blocked signals
Binary outputs
Paper 0480
U AB
U BC during various network disturbances like faults, capacitor
U CA
0.95
19.9 20 20.1 20.2 20.3 20.4 20.5
switching and connection of parallel transformer.
Time(s)
Vector shift angle detected in three phases Although the proposed vector shift algorithm guarantees
Angle(Degrees)
1.5
VSAng AB
1
VSAng BC
fast and reliable islanding detection in nearly all
0.5
0
VSAng CA operational conditions when the DG unit is running in
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s) parallel with the utility grid supply, certain cases may still
Vector shift algorithm Operate and Blocked signals
cause mal-operations. If the power unbalance before
Binary outputs
1
OPERATE
0 INT BLKD islanding is very small and the detected vector shift angle
-1
19.9 20 20.1 20.2 20.3 20.4 20.5
is therefore also small, the function may not operate. This
Time(s)
means that the vector shift algorithm, like many traditional
Figure 11. Vector shift algorithm behavior during capacitor switching
event
passive islanding detection methods, still has NDZ near a
power balance situation. Therefore, other passive methods
From Figure 11, it can be seen that during capacitor for detecting the islanding without NDZ should be further
switching, the voltage magnitudes are stable around 1 pu developed. Potential methods to deal with this NDZ issue
and the vector shift angles around 1 degree. The detected could be, for example, the multi-criteria based passive
vector shift angles are less than the setting and vector shift islanding detection method [1] or use of active MV
is not detected in all three phases. Due to these issues the network management [2].
proposed vector shift algorithm is not operated.
Connection of Parallel Transformer at HV/MV REFERENCES
Substation [1] H. Laaksonen, 2012, "New Multi-Criteria Based
In this case, parallel transformer at the HV/MV substation Algorithm for Islanding Detection in Smart Grids",
is connected to the system (v in Figure 4). The results are IEEE PES ISGT Europe 2012, Berlin, Germany.
presented in Figure 12. [2] H. Laaksonen, 2014, "Reliable Islanding Detection
Voltage magnitude in three phases with Active MV Network Management", CIRED
0.97
Voltage(pu)
1
VSAng AB
0.5 VSAng BC
18th International conference on electricity
VSAng CA distribution, 6-9 June 2005, Turin.
0
19.9 20 20.1 20.2 20.3 20.4 20.5
Time(s) [4] W. Freitas, Z. Huang, W. Xu, 2005, "A Practical
Vector shift algorithm Operate and Blocked signals
Binary outputs
1
OPERATE
Method for Assesing the Effectiveness of Vector
0 INT BLKD Surge Relays for Distributed Generation
-1
19.9 20 20.1 20.2 20.3 20.4 20.5 Applications", IEEE Transcations on Power
Time(s)
Delivery, vol. 20, no. 1
Figure 12. Vector shift algorithm behavior when connecting a parallel
transformer [5] W. Freitas, W. Xu, 2005, "Comparative Analysis
Between ROCOF and Vector Surge Relays for
From Figure 12, one can see that when connecting a Distributed Generation Applications", IEEE
parallel transformer, the voltage magnitudes are stable Transcations on Power Delivery, vol. 20, no. 2
around 1 pu and the vector shift angles around 0.5 degrees.
The detected vector shift angles are less than the setting
and therefore the proposed vector shift algorithm is not
operated.
CONCLUSIONS
In this paper a new advanced vector shift algorithm is
presented to improve the dependability and stability of the
voltage vector shift based islanding detection. The
developed algorithm can adaptively correct the measured
vector shift angle based on the steady-state frequency
variations, which makes the algorithm immune to steady-
state frequency variations. Based on the presented test
results, it can be concluded that the developed algorithm
successfully detects the islanding condition during small
and large power unbalances. In addition, the algorithm can