Vous êtes sur la page 1sur 821

kers must trip: Breaker IN-2402 (52-01) and IN-2400 (52-02) and the Auto-

reclosing will be as follows:

1) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
2) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

1) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 2
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 3
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 4
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 5
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 6
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 7
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 8
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 9
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 10
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 11
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 12
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 13
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 14
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 15
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

3) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
4) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
5) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
6) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

1) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
2) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
3) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
4) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 16
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

1) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

2) Spring Failure to block the Breaker

3) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

1) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

2) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

1) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 17
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

2) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

1) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

2) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

2) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

3) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 18
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 19
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 20
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 21
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 22
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 23
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 24
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 25
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 26
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 27
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 28
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 29
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 30
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 31
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 32
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

7) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
8) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
9) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
10) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

5) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
6) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
7) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
8) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 33
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

4) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

5) Spring Failure to block the Breaker

6) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

3) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

4) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

3) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 34
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

3) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

4) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

4) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

5) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 35
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 36
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 37
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 38
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 39
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 40
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 41
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 42
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 43
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 44
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 45
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 46
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 47
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 48
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 49
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

11) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
12) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
13) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
14) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

9) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
10) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
11) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
If the fault is not Vizcarra 0.53 0.40
cleared, BAntamina X/R 7.0 6.6

371357618.doc 50
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64

371357618.doc 51
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

371357618.doc 52
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

371357618.doc 53
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

371357618.doc 54
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

371357618.doc 55
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

15) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
16) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
17) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
18) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

12) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
13) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
14) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
15) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

371357618.doc 56
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

The devices in the Circuit Breaker will perform the protection as follows:

7) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

8) Spring Failure to block the Breaker

9) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

5) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

6) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

5) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

6) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

5) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

6) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

371357618.doc 57
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

6) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

7) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 58
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 59
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 60
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 61
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 62
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 63
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 64
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 65
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 66
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 67
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 68
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 69
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 70
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 71
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 72
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

19) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
20) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
21) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
22) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

16) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
17) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
18) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
19) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 73
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

10) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

11) Spring Failure to block the Breaker

12) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

7) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

8) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

7) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 74
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

8) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

7) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

8) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

8) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

9) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 75
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 76
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 77
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 78
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 79
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 80
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 81
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 82
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 83
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 84
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 85
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 86
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 87
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 88
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 89
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

23) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
24) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
25) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
26) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

20) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
21) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
22) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
23) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 90
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

13) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

14) Spring Failure to block the Breaker

15) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

9) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

10) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

9) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 91
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

10) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

9) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

10) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

10) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

11) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 92
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 93
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 94
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 95
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 96
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 97
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 98
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 99
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 100
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 101
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 102
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 103
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 104
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 105
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 106
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

27) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
28) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
29) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
30) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

24) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
25) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
26) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
27) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 107
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

16) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

17) Spring Failure to block the Breaker

18) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

11) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

12) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

11) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 108
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

12) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

11) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

12) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

12) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

13) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 109
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 110
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 111
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 112
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 113
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 114
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 115
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 116
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 117
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 118
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 119
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 120
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 121
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 122
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 123
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

31) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
32) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
33) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
34) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

28) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
29) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
30) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
31) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 124
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

19) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

20) Spring Failure to block the Breaker

21) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

13) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

14) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

13) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 125
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

14) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

13) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

14) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

14) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

15) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 126
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 127
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 128
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 129
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 130
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 131
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 132
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 133
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 134
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 135
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 136
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 137
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 138
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 139
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 140
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

35) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
36) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
37) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
38) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

32) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
33) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
34) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
35) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 141
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

22) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

23) Spring Failure to block the Breaker

24) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

15) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

16) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

15) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 142
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

16) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

15) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

16) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

16) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

17) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 143
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 144
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 145
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 146
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 147
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 148
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 149
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 150
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 151
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 152
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 153
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 154
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 155
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 156
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 157
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

39) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
40) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
41) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
42) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

36) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
37) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
38) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
39) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 158
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

25) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

26) Spring Failure to block the Breaker

27) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

17) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

18) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

17) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 159
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

18) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

17) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

18) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

18) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

19) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 160
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 161
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 162
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 163
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 164
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 165
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 166
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 167
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 168
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 169
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 170
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 171
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 172
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 173
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 174
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

43) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
44) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
45) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
46) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

40) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
41) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
42) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
43) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 175
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

28) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

29) Spring Failure to block the Breaker

30) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

19) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

20) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

19) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 176
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

20) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

19) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

20) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

20) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

21) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 177
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 178
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 179
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 180
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 181
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 182
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 183
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 184
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 185
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 186
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 187
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 188
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 189
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 190
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 191
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

47) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
48) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
49) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
50) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

44) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
45) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
46) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
47) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 192
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

31) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

32) Spring Failure to block the Breaker

33) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

21) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

22) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

21) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 193
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

22) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

21) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

22) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

22) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

23) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 194
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 195
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 196
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 197
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 198
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 199
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 200
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 201
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 202
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 203
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 204
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 205
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 206
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 207
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 208
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

51) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
52) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
53) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
54) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

48) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
49) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
50) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
51) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 209
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

34) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

35) Spring Failure to block the Breaker

36) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

23) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

24) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

23) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 210
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

24) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

23) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

24) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

24) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

25) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 211
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 212
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 213
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 214
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 215
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 216
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 217
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 218
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 219
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 220
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 221
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 222
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 223
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 224
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 225
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

55) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
56) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
57) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
58) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

52) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
53) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
54) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
55) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 226
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

37) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

38) Spring Failure to block the Breaker

39) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

25) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

26) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

25) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 227
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

26) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

25) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

26) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

26) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

27) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 228
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 229
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 230
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 231
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 232
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 233
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 234
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 235
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 236
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 237
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 238
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 239
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 240
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 241
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 242
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

59) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
60) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
61) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
62) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

56) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
57) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
58) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
59) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 243
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

40) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

41) Spring Failure to block the Breaker

42) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

27) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

28) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

27) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 244
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

28) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

27) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

28) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

28) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

29) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 245
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 246
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 247
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 248
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 249
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 250
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 251
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 252
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 253
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 254
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 255
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 256
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 257
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 258
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 259
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

63) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
64) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
65) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
66) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

60) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
61) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
62) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
63) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 260
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

43) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

44) Spring Failure to block the Breaker

45) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

29) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

30) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

29) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 261
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

30) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

29) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

30) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

30) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

31) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 262
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 263
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 264
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 265
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 266
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 267
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 268
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 269
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 270
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 271
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 272
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 273
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 274
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 275
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 276
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

67) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
68) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
69) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
70) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

64) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
65) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
66) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
67) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 277
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

46) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

47) Spring Failure to block the Breaker

48) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

31) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

32) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

31) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 278
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

32) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

31) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

32) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

32) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

33) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 279
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 280
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 281
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 282
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 283
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 284
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 285
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 286
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 287
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 288
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 289
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 290
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 291
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 292
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 293
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

71) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
72) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
73) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
74) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

68) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
69) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
70) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
71) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 294
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

49) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

50) Spring Failure to block the Breaker

51) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

33) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

34) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

33) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 295
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

34) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

33) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

34) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

34) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

35) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 296
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 297
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 298
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 299
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 300
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 301
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 302
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 303
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 304
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 305
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 306
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 307
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 308
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 309
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 310
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

75) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
76) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
77) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
78) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

72) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
73) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
74) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
75) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 311
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

52) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

53) Spring Failure to block the Breaker

54) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

35) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

36) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

35) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 312
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

36) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

35) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

36) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

36) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

37) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 313
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 314
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 315
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 316
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 317
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 318
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 319
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 320
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 321
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 322
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 323
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 324
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 325
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 326
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 327
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

79) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
80) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
81) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
82) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

76) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
77) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
78) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
79) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 328
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

55) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

56) Spring Failure to block the Breaker

57) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

37) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

38) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

37) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 329
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

38) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

37) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

38) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

38) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

39) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 330
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 331
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 332
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 333
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 334
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 335
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 336
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 337
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 338
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 339
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 340
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 341
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 342
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 343
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 344
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

83) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
84) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
85) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
86) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

80) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
81) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
82) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
83) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 345
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

58) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

59) Spring Failure to block the Breaker

60) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

39) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

40) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

39) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 346
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

40) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

39) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

40) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

40) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

41) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 347
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 348
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 349
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 350
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 351
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 352
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 353
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 354
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 355
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 356
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 357
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 358
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 359
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 360
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 361
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

87) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
88) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
89) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
90) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

84) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
85) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
86) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
87) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 362
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

61) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

62) Spring Failure to block the Breaker

63) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

41) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

42) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

41) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 363
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

42) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

41) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

42) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

42) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

43) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 364
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 365
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 366
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 367
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 368
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 369
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 370
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 371
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 372
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 373
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 374
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 375
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 376
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 377
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 378
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

91) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
92) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
93) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
94) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

88) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
89) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
90) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
91) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 379
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

64) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

65) Spring Failure to block the Breaker

66) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

43) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

44) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

43) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 380
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

44) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

43) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

44) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

44) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

45) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 381
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 382
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 383
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 384
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 385
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 386
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 387
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 388
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 389
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 390
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 391
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 392
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 393
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 394
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 395
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

95) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
96) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
97) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
52-01 must be closed later by the Breaker Protection Relay.
98) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

92) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
93) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
94) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
95) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 396
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

67) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

68) Spring Failure to block the Breaker

69) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

45) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

46) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

45) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 397
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

46) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

45) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

46) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

46) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

47) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 398
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 399
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 400
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 401
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 402
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 403
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 404
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 405
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 406
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 407
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 408
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 409
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 410
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 411
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 412
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

99) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
100) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
101) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
102) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

96) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
97) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-2400
(52-02) will close.
98) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed. Breaker
IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
99) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 413
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

70) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

71) Spring Failure to block the Breaker

72) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

47) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

48) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

47) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 414
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

48) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

47) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

48) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

48) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

49) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 415
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 416
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 417
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 418
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 419
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 420
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 421
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 422
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 423
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 424
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 425
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 426
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 427
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 428
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 429
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

103) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
104) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
105) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
106) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

100) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
101) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
102) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
103) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 430
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

73) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

74) Spring Failure to block the Breaker

75) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

49) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

50) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

49) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 431
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

50) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

49) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

50) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

50) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

51) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 432
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 433
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 434
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 435
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 436
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 437
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 438
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 439
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 440
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 441
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 442
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 443
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 444
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 445
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 446
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

107) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
108) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
109) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
110) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

104) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
105) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
106) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
107) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 447
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

76) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

77) Spring Failure to block the Breaker

78) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

51) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

52) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

51) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 448
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

52) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

51) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

52) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

52) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

53) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 449
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 450
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 451
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 452
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 453
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 454
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 455
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 456
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 457
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 458
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 459
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 460
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 461
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 462
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 463
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

111) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
112) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
113) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
114) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

108) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
109) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
110) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
111) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 464
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

79) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

80) Spring Failure to block the Breaker

81) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

53) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

54) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

53) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 465
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

54) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

53) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

54) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

54) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

55) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 466
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 467
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 468
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 469
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 470
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 471
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 472
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 473
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 474
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 475
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 476
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 477
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 478
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 479
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 480
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

115) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
116) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
117) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
118) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

112) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
113) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
114) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
115) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 481
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

82) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

83) Spring Failure to block the Breaker

84) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

55) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

56) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

55) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 482
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

56) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

55) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

56) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

56) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

57) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 483
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 484
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 485
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 486
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 487
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 488
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 489
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner
The Relay will operate in two steps:

57) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

58) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

57) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

58) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

371357618.doc 490
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

57) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

58) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

58) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

59) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

nt/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management
https://www.scribd.com/document/221103628/Section-4-Energy-Management

371357618.doc 491
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

371357618.doc 492
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

371357618.doc 493
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 494
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 495
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 496
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 497
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 498
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 499
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 500
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 501
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

119) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
120) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
121) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
122) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

116) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
117) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
118) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
119) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 502
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

85) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

86) Spring Failure to block the Breaker

87) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

59) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

60) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

59) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 503
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

60) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

59) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

60) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

60) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

61) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 504
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 505
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 506
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 507
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 508
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 509
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 510
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 511
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 512
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 513
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 514
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 515
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 516
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 517
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 518
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

123) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
124) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
125) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
126) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

120) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
121) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
122) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
123) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 519
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

88) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

89) Spring Failure to block the Breaker

90) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

61) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

62) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

61) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 520
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

62) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

61) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

62) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

62) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

63) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 521
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 522
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 523
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 524
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 525
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 526
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 527
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 528
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 529
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 530
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 531
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 532
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 533
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 534
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 535
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

127) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
128) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
129) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
130) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

124) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
125) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
126) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
127) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 536
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

91) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

92) Spring Failure to block the Breaker

93) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

63) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

64) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

63) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 537
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

64) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

63) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

64) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

64) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

65) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 538
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 539
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 540
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 541
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 542
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 543
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 544
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 545
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 546
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 547
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 548
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 549
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 550
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 551
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 552
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

131) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
132) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
133) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
134) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

128) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
129) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
130) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
131) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 553
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

94) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

95) Spring Failure to block the Breaker

96) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

65) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

66) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

65) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 554
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

66) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

65) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

66) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

66) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

67) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 555
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 556
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 557
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 558
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 559
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 560
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 561
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 562
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 563
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 564
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 565
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 566
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 567
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 568
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 569
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

135) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
136) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
137) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
138) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

132) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
133) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
134) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
135) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 570
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

97) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

98) Spring Failure to block the Breaker

99) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

67) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

68) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

67) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 571
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

68) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

67) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

68) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

68) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

69) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 572
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 573
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 574
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 575
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 576
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 577
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 578
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 579
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 580
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 581
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 582
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 583
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 584
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 585
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 586
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

139) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
140) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
141) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
142) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

136) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
137) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
138) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
139) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 587
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

100) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

101) Spring Failure to block the Breaker

102) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

69) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

70) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

69) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 588
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

70) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

69) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

70) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

70) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

71) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 589
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 590
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 591
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 592
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 593
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 594
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 595
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 596
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 597
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 598
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 599
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 600
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 601
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 602
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 603
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

143) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
144) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
145) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
146) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

140) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
141) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
142) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
143) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 604
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

103) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

104) Spring Failure to block the Breaker

105) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

71) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

72) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

71) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 605
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

72) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

71) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

72) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

72) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

73) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 606
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 607
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 608
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 609
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 610
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 611
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 612
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 613
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 614
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 615
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 616
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 617
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 618
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 619
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 620
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

147) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
148) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
149) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
150) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

144) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
145) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
146) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
147) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 621
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

106) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

107) Spring Failure to block the Breaker

108) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

73) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

74) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

73) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 622
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

74) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

73) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

74) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

74) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

75) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 623
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 624
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 625
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 626
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 627
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 628
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 629
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 630
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 631
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 632
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 633
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 634
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 635
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 636
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 637
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 638
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

151) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
152) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
153) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
154) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

148) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
149) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
150) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
151) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 639
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

109) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

110) Spring Failure to block the Breaker

111) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

75) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

76) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

75) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 640
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

76) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

75) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

76) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

76) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

77) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 641
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 642
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 643
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 644
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 645
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 646
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 647
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 648
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 649
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 650
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 651
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 652
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 653
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 654
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 655
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

155) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
156) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
157) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
158) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

152) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
153) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
154) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
155) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 656
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

112) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

113) Spring Failure to block the Breaker

114) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

77) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

78) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

77) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 657
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

78) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

77) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

78) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

78) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

79) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 658
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 659
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 660
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 661
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 662
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 663
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 664
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 665
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 666
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 667
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 668
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 669
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 670
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 671
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 672
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

159) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
160) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
161) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
162) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

156) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
157) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
158) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
159) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 673
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

115) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

116) Spring Failure to block the Breaker

117) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

79) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

80) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

79) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 674
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

80) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

79) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

80) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

80) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

81) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 675
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

371357618.doc 676
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 677
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 678
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 679
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 680
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 681
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 682
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 683
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 684
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 685
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 686
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

163) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
164) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
165) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
166) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

160) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
161) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
162) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
163) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 687
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

118) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

119) Spring Failure to block the Breaker

120) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

81) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

82) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

81) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 688
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

82) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

81) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

82) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

82) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

83) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 689
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 690
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 691
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 692
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 693
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 694
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 695
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 696
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 697
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 698
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 699
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 700
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 701
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 702
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 703
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

167) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
168) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
169) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
170) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

164) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
165) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
166) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
167) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 704
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

121) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

122) Spring Failure to block the Breaker

123) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

83) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

84) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

83) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 705
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

84) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

83) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

84) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

84) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

85) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 706
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 707
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 708
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 709
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 710
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 711
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 712
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 713
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 714
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 715
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 716
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 717
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 718
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 719
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 720
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

171) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
172) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
173) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
174) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

168) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
169) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
170) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
171) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 721
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

124) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

125) Spring Failure to block the Breaker

126) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

85) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

86) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

85) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 722
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

86) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

85) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

86) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

86) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

87) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 723
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 724
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 725
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 726
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 727
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 728
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 729
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 730
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 731
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 732
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 733
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 734
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 735
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 736
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 737
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

175) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
176) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
177) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
178) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

172) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
173) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
174) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
175) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 738
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

127) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

128) Spring Failure to block the Breaker

129) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

87) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

88) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

87) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 739
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

88) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

87) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

88) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

88) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

89) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 740
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 741
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 742
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 743
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 744
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 745
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 746
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 747
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 748
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 749
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 750
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 751
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 752
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 753
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 754
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

179) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
180) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
181) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
182) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

176) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
177) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
178) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
179) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 755
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

130) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

131) Spring Failure to block the Breaker

132) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

89) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

90) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

89) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 756
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

90) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

89) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

90) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

90) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

91) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 757
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 758
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 759
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 760
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 761
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 762
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 763
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 764
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 765
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 766
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 767
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 768
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 769
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 770
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 771
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

183) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
184) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
185) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
186) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

180) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
181) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
182) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
183) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 772
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

133) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

134) Spring Failure to block the Breaker

135) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

91) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

92) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

91) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 773
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

92) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

91) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

92) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

92) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

93) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 774
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 775
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 776
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 777
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 778
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 779
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 780
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 781
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 782
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 783
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 784
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 785
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 786
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 787
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 788
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

187) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
188) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
189) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
190) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

184) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
185) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
186) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
187) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 789
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

136) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

137) Spring Failure to block the Breaker

138) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

93) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

94) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

93) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 790
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

94) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

93) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

94) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

94) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

95) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 791
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 792
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 793
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 794
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 795
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 796
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 797
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 798
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from V

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 799
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the

371357618.doc 800
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

191) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
192) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
193) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
194) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

188) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
189) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
190) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
191) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 801
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

139) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

140) Spring Failure to block the Breaker

141) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

95) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

96) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

95) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 802
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

96) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

95) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

96) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

96) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

97) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 803
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 1 CALCULATION SHEETS OF SETTINGS

Relay Protection Settings for Vizcarra-Paramonga Line (L-253)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Tingo Mara Line (L-252)


Sheet 1 /2 & 2 /2

Relay Protection Settings for Vizcarra-Antamina Line (L-255)


Sheet 1 /2 & 2 /2

371357618.doc 804
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 2 R-X DIAGRAMS

Figure 1.0 Vizcarra - Paramonga Line (L-253). Primary Protection

Figure 2.0 Vizcarra - Paramonga Line (L-253). Secondary Protection

Figure 3.0 Paramonga - Vizcarra Line (L-253). Primary Protection

Figure 4.0 Paramonga - Vizcarra Line (L-253). Secondary Protection

Figure 5.0 Vizcarra - Tingo Mara Line (L-252) . Primary Protection

Figure 6.0 Vizcarra - Tingo Mara Line (L-252). Secondary Protection

Figure 7.0 Tingo Mara - Vizcarra Line (L-252). Primary Protection

Figure 8.0 Tingo Mara - Vizcarra Line (L-252). Secondary Protection

Figure 9.0 Vizcarra Antamina Line (L-255). Primary Protection

Figure 10.0 Vizcarra Antamina Line (L-255). Secondary Protection

371357618.doc 805
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

Figure 1 Antamina Line & Breaker IN-2404 (52-04)

Figure 2 SVC & Breaker IN-2406 (52-03)

Figure 3 Paramonga Line & Breaker IN-2402 (52-01)

Figure 4 Tingo Mara Line & Breaker IN-2400 (52-02)

ANTAMINA PROJECT

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

371357618.doc 806
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Revised Approved Date

Report 21-30-26-E - Rev 1

371357618.doc 807
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

REVISION

REV DESCRIPTION DATE

A First Issue Oct. 18th, 1999

0 Approved Oct. 30th, 1999

1 Updating project data items 3.03, 3.04 and 3.05 12th Nov, 1999

371357618.doc 808
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES


PROTECTION RELAY SETTINGS

CONTENT

1.00 PURPOSE

2.00 STANDARDS & REFERENCES

3.00 PROJECT DATA


3.01 Scope of the Project
3.02 Network Data
3.03 Maximum Short-circuit currents
3.04 Minimum Short-circuit currents
3.05 Source Impedance
3.06 Fault Resistance
3.07 Instrument Transformers
3.08 Telecommunication Equipment

4.00 PROTECTION SYSTEM


4.01 Primary Protection
4.02 Secondary Protection
4.03 Backup Protection
4.04 Auto-reclosing

5.00 BREAKER PROTECTION


5.01 Devices in the Circuit Breaker
5.02 Breaker Protection Relays

ANNEX 1 CALCULATION SHEETS OF SETTINGS

ANNEX 2 R-X DIAGRAMS

ANNEX 3 TRIPPING SCHEMES ON THE 220 kV RING BUS

371357618.doc 809
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

220 kV SUBSTATION AND TRANSMISSION LINES

PROTECTION RELAY SETTINGS

1.00 PURPOSE

The purpose of this document is to provide the criteria for relay settings. On this
basis the calculations are performed to provide each setting.

2.00 STANDARDS & REFERENCES

The report is prepared on the basis of the following documents

ANSI/IEEE C37-93
IEC 255
Numerical Line Protection Type REL 316*4. Operating Instructions.
ABB Power Automation
Line Distance Protection Terminal REL 521*2.0. Technical Reference Manual.
ABB Network Partner
Breaker Protection Terminal REL 521*2.0. Users Manual.
ABB Network Partner

Project data is from the following documents

Initial Studies for the Interconnection of Ca Minera Antamina into Aguayta


Energy del Per SR Ltda. / SICN 220 kV System at Vizcarra Substation
Power Technologies, Inc., Report No. 34-99.

Aguaytia Tingo Mara Paramonga 220 kV Transmission Line.


Substation Project. Final Relay Settings

Drawing 21-31-30-E Vizcarra Substation.


Single Line Diagram

Drawing 21-31-32-E Vizcarra Substation.


Metering and Protection Diagram

Drawing 21-33-30-E Vizcarra Substation.


Telecommunications and Telephone System

371357618.doc 810
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.00 PROJECT DATA

3.01 Scope of the Project

At the present time, there is one transmission line from Paramonga Nueva to Tingo
Mara and the new Vizcarra Substation will be located along this line. There will be
one Static Var Compensator (SVC) in Vizcarra; also, there will be one new
Transmission Line from Vizcarra to Antamina Substation (L-255).

The relay settings are for the new Vizcarra Substation, where new Relays for the
lines to Paramonga Nueva and Tingo Mara Substations will be installed. At the
same time, the new settings will be determined for the existing Line Protection
Relays in both Paramonga Nueva and Tingo Mara substations. Nothing else will be
included in these substations. Also, the relay settings are for the new transmission
line from Vizcarra to Antamina (L-255).

The SVC will have differential protection, but it is out of the scope of this report.

3.02 Network Data

The data of the Transmission Line is the following

Impedance Impedance
Positive Sequence Zero Sequence
LINE DISTANCE [Ohm/phase] [Ohm]
[km]
R X Ro Xo
Paramonga
Vizcarra 144.211 8.298 72.833 39.736 212.284
L-253
Tingo Mara
Vizcarra 173.7 9.995 87.727 47.862 255.695
L-252
Vizcarra
Antamina 52.08 3.001 26.568 20.745 88.429
L-255
Aguayta
Tingo Mara 73.29 4.217 37.015 20.194 107.890

Paramonga
Chimbote 221.2 19.466 110.6 54.681 365.422
L-215
Paramonga
Zapallal 157.5 14.175 124.11 38.903 256.73
L-213

371357618.doc 811
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

3.03 Maximum Short-circuit currents

The maximum short-circuit currents will be with maximum dispatch.

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]

Tingo Mara Aguayta 1.32 0.94


SICN 0.27 0.20
Vizcarra 0.58 0.39
TOTAL 2.17 1.54
X/R 10.1 8.1

Vizcarra TingoMara 0.75 0.50


Paramonga Nueva 0.97 0.66
Antamina
TOTAL 1.72 1.15
X/R 8.0 6.8

Antamina Vizcarra 1.23 0.78


X/R 8.2 6.2

Paramonga Nueva Vizcarra 0.52 0.36


Zapallal 1.25 0.86
Chimbote 0.68 0.49
Paramonga 0.27 0.38
TOTAL 2.71 2.09
X/R 6.6 7.4

3.04 Minimum Short-circuit currents

The minimum short-circuit currents will be with minimum dispatch. The system
configuration is shown on Figure No. 2

Line to ground
BUS SOURCE Three-phase fault fault
[kA] [kA]
Tingo Mara Aguayta 1.32 0.95
SICN 0.27 0.21
Vizcarra
TOTAL 1.58 1.16
X/R 11.5 8.9

371357618.doc 812
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Vizcarra TingoMara 0.00 0.00


Paramonga Nueva 0.61 0.48
Antamina
TOTAL 0.61 0.48
X/R 6.9 7.0

Antamina Vizcarra 0.53 0.40


X/R 7.0 6.6

Paramonga Nueva Vizcarra


Zapallal
Chimbote 0.66 0.52
Paramonga 0.27 0.36
TOTAL 0.93 0.88
X/R 6.5 7.9

3.05 Source Impedance

On the basis of the maximum short circuit current the source impedance at each bus
will be as follows

BUS X/R R X
[Ohm] [Ohm]

Tingo Mara 10.1 5.774 58.61

Vizcarra 8.0 9.15 73.34

Antamina 8.2 12.49 102.4

Paramonga Nueva 6.6 7.04 46.29

3.06 Fault Resistance

The fault resistance will be the arc resistance plus the tower resistance. The first
value will calculated according to the formula

Rarc = 28707 L / I1.4

Where L is the length of the arc which is typically three times the conductor to
tower spacing and I is the minimum shortcircuit current (average value of both
ends). On this basis the fault resistance will be as follows

371357618.doc 813
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

LINE Resistance Arc Resistance Tower Fault Resistance


[Ohm] [Ohm] [Ohm]
Vizcarra
Paramonga 24 25 49
L-253
Vizcarra
Tingo Mara 39 25 64
L-252
Vizcarra
Antamina 60 25 85
L-255

3.07 Instrument Transformers

The technical characteristics of Voltage and Current Transformers are the following

Instrument Transformer STATION


Paramonga Vizcarra Tingo Mara

Voltage Transformers
Primary [V] 220000 / 3 138000 220000 / 3

Secondary [V] 110 / 3 69 100 / 3

Current Transformers
Primary [A] 500 600 500

Secondary [A] 5 5 1

3.08 Telecommunication Equipment

Power Line Carrier will provide support for the Protection System. There will be
three telecommunication links: Vizcarra Paramonga, Vizcarra Tingo Mara and
Vizcarra Antamina. One channel will be installed on each link and there will be
one Teleprotection Signal Equipment over each channel. This equipment will
provide four signals named A, B C and D.

371357618.doc 814
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.00 PROTECTION SYSTEM

Protection will be carried by Multifunction Relays. Each protection zone will


include one Transmission Line (or the SVC) and one part of the 220 kV Ring Bus.
There will be two relays per protection zone; one is named Primary Protection and
the other is named Secondary Protection. Additionally, there will be one Breaker
Protection Relay. In the first stage when SVC is not in service, this relay will
provide overcurrent protection on the corresponding part of the Ring Bus.

SVC will not be in service at the first stage, therefore provisional connections must
be done in order to get the proper overlapping protection zones on the 220 kV Ring
Bus. For this reason, one interconnection between current transformer boxes will be
necessary to extent the Antamina Line zone; in the same way, Antamina line
protection will trip the corresponding circuit breaker also. Both provisional
interconnection cables will be installed at the switchyard.

Relay ABB - REL 521 will be used for Primary Protection and Relay ABB - REL
316 will be used for Secondary Protection. Relay ABB - REB 551 will be used for
Breaker Protection.

In Vizcarra Substation, Primary Protection Relays will work with Trip 1 in the
Circuit Breakers and Secondary Protection Relays will work with Trip 2. Each
Breaker Protection will operate with one Lockout Relay to trip and block the
corresponding breakers. These relays will work with Trip 1 and Trip 2.

4.01 Primary Protection

4.01.1 Vizcarra - Paramonga Nueva (L-253) and Vizcarra - Tingo Mara


(L-252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The communication scheme will be through the Teleprotection Equipment using


signal A. The logic will be Permissive Underreach Transfer Trip (PUTT) with the
following settings

First Zone : 85% of the line

Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Primary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

371357618.doc 815
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

4.01.2 Vizcarra Anatamina Line (L-255)

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal A.

4.02 Secondary Protection

4.02.1 Paramonga Nueva Vizcarra (L-253) and Vizcarra Tingo Mara (L-
252) Lines

Stepped impedance (21 & 21N) function in the Primary Protection Relays at both
ends of the line will be used to achieve fast fault clearance on all the transmission
line.

The first zone will operate to give direct trip the local breaker at each substation;
but one communication scheme will be used with the second zone. This scheme
will be trough the Teleprotection Equipment using signal B. The logic will be
Permissive Overreach Transfer Trip (POTT) to assure the fault is in the protected
line. The settings will be as follows

First Zone : 85% of the line


Second Zone : 120% of the line

Directional Earth Fault function (67N) in the Secondary Protection Relays will be
used also. It will work with the Teleprotection Equipment using signal C.
Permissive overreach logic will be used to assure that the fault is in the protected
line. The settings will be 15% in the residual current.

Secondary Protection will be carried out by Second Zone Impedance function (21
& 21N), which will operate with Permissive Overreach Transfer Trip (POTT)
scheme. The impedance setting will be 120% of the line in order to get the reach for
the full line.

4.02.2 Vizcarra Anatamina Line (L-255)

371357618.doc 816
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Stepped impedance (21 & 21N) function in the Primary Protection Relay will be
used to achieve fast fault clearance on all the transmission line. The setting will be
120% of the line in order to cover the full length.

Directional Earth Fault functions (67N) in the Primary Protection Relays will be
used also. The settings will be 15% in the residual current.

Primary Protection Relay will operate one Direct Transfer Trip trough the power
line carrier to trip both ends of the line. It will work with the Teleprotection
Equipment using signal B.

4.03 Backup Protection

4.03.1 Remote Protection

Backup Protection will be carried out by the second, third, fourth and fifth zones of
Impedance function in both Primary and Secondary Protection Relays.

Second zone will reach part of the next line and will have time delay in the first
time step. Fourth zone will be used to reach the next line and third zone will be
used to reach line back. Third and fourth zones will have time delay in the second
time step. Fifth zone will reach the protected line plus shortest next line. The
settings and timing will be as follows

Zone Impedance Set Time Delay

Second 120% of the line 400 ms

Third -30% of the line 700 ms

Fourth 150% of the line 700 ms

Fifth 100% of the line plus 1500 ms


150% or 200% of next line
(the shortest)

4.03.2 Breaker Failure Protection

Besides the Remote Backup Protection, there will be a Local Backup Protection
carried out by Breaker Failure Relay.

Breaker Failure Protection will start with tha main protection and will sense current
in the current. The setting will be 50% of the nominal current. In this way it will
repeat in 150 ms the signal to trip the Circuit Breaker. 150 ms later, it will trip the
adjacent breakers in Vizcarra Substation and will send one direct transfer trip to the
opposite station connected with the faulted breaker.

371357618.doc 817
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

Transfer Trip will be through Teleprotection Equipment using signal D, which is


bidirectional. In this way, each reception will trip the corresponding breakers in
Vizcarra.

4.03.3 Overcurrent Protection

Overcurrent (51) function in Secondary Protection Relays will be used also as


Backup Protection. Definitetime characteristics will be selected in a way that for
the maximum overcurrent the time delay will be equal 2000 ms.

4.04 Auto-reclosing

4.04.1 Paramonga Nueva Vizcarra (L-253)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2402 (52-01) and IN-2400 (52-02) and the Auto-reclosing will be as follows:

195) Breaker IN-2402 (52-01) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
196) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
197) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker 52-01 must be closed later by the Breaker Protection Relay.
198) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.2 Vizcarra Tingo Mara Lines (L-252)

Automatic single-pole reclosing will be used with line protection. There will not be
three-pole reclosing. This function will be carried out by Breaker Protection Relay.
If there is a fault phase to ground in this line, two breakers must trip: Breaker IN-
2400 (52-02) and IN-2406 (52-03) and the Auto-reclosing will be as follows:

192) Breaker IN-2406 (52-03) will trip all the poles, but Breaker IN-2400 (52-02)
will trip only the pole corresponding to the faulted phase
193) Time delay for Auto-reclosing will be 500 ms and after this Breaker IN-
2400 (52-02) will close.
194) If the fault is cleared the Breaker IN-2400 (52-02) will remain closed.
Breaker IN-2406 (52-03) must be closed later by the Breaker Protection Relay.
195) If the fault is not cleared, Breaker IN-2400 (52-02) will trip the three poles

4.04.3 Vizcarra Antamina Line (L-255)

371357618.doc 818
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

There will not be auto-reclosing in this line. However, provisions for future
application will be included. Programming on the Relay will be switched OFF and
connection jumpers for the reclosing circuit will be removed.

5.00 BREAKER PROTECTION

Breaker Protection will be done by the devices incorporated in the equipment and
Breaker Protection Relay.

5.01 Devices in the Circuit Breakers

The devices in the Circuit Breaker will perform the protection as follows:

142) Low Pressure SF6 with two levels:


Refill Gas
Trip and Block the Breaker

143) Spring Failure to block the Breaker

144) Pole Disagreement to trip the Breaker. It will trip the breaker after 1000 ms.

5.02 Breaker Protection Relays

5.02.1 Breaker IN-2402 (52-01)

The Relay will operate in two steps:

97) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

98) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Paramonga.

5.02.2 Breaker IN-2400 (52-02)

The Relay will operate in two steps:

97) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

371357618.doc 819
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

98) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03). At the same time, one
direct transfer will be sent to Paramonga and Tingo Mara.

5.02.3 Breaker IN-2406 (52-03)

The Relay will operate in two steps:

97) If the main protection sends the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

98) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2404 (52-04) and Breaker IN-2400 (52-02). At the same time, one
direct transfer will be sent to Tingo Mara.

5.02.4 Breaker IN-2404 (52-04)

The Relay will operate in two steps:

98) If the main protection send the trip signal and 150 ms later the fault is not
cleared, Breaker Relay will repeat the trip signal

99) If 150 ms later (total 300 ms) the fault is not cleared, Breaker Relay will trip
Breaker IN-2402 (52-01) and Breaker IN-2406 (52-03).

371357618.doc 820
PROTECTION RELAY SETTINGS
21-30-26-E Rev 1

371357618.doc 821

Vous aimerez peut-être aussi