CALENDARIO DE AVANCE DE OBRA

Obra: "RECONSTRUCCION I.E. N 82284 - CAJABAMBA - CAJAMARCA "


Consultor: SNCHEZ DVALOS MAGALY Plazo: 300 das calendarios
Propietario: GOBIERNO REGIONAL DE CAJAMARCA
Lugar: CAJABAMBA / CAJABAMBA / CAJAMARCA Fecha: Jun-13

MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10
Item Descripcin Parcial (S/.)

01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD


01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES
01.01.01 CONSTRUCCIONES PROVISIONALES 7,331.60 7,331.60
01.01.02 TRABAJOS PRELIMINARES 2,884.06 2,884.06
01.01.03 DEMOLICIONES 47,520.74 47,520.74
01.02 MOVILIZACIN DE CAMPAMENTO, MAQUINARIA Y HERRAMIENTAS 9,684.86 9,684.86
01.03 TRAZOS, NIVELES Y REPLANTEO 5,744.47 5,744.47
01.04 SEGURIDAD Y SALUD
01.04.01 ELABORACIN, IMPLEMENTACIN Y ADMINISTRACIN DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABA 23,545.18 23,545.18
02 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS 85,447.62 21,361.91 64,085.71
02.02 OBRAS DE CONCRETO SIMPLE 60,923.59 42,646.51 18,277.08
02.03 OBRAS DE CONCRETO ARMADO
02.03.01 ZAPATAS 211,673.60 211,673.60
02.03.02 VIGAS DE CIMENTACION 22,261.93 3,339.29 18,922.64
02.03.03 SOBRECIMIENTO ARMADO 17,128.91 17,128.91
02.03.04 MURO DE CONTENCIN 193,912.30 135,738.61 58,173.69
02.03.05 COLUMNAS 265,344.60 225,542.91 39,801.69
02.03.06 COLUMNETAS 30,218.49 24,174.79 6,043.7
02.03.07 VIGAS 285,132.88 35,641.61 220,977.98 28,513.29
02.03.08 VIGUETAS (CONFINAMIENTO) 11,874.77 11,874.77
02.03.09 LOSAS ALIGERADAS 184,757.59 31,408.79 153,348.80
02.03.10 LOSA MACIZA 27,126.51 27,126.51
02.03.11 ESCALERAS 15,318.90 9,957.29 5,361.6
02.03.12 PLACAS 9,372.90 1,405.94 7,966.96
02.03.13 CANAL DE EVACUACIN DE AGUAS DE LLUVIA 5,001.66 5,001.66
02.04 ESTRUCTURAS METALICAS 185,892.92 120,830.40 65,062.52
02.05 VARIOS 6,913.01 5,530.41 1,382.60
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10
Item Descripcin Parcial (S/.)

03 ARQUITECTURA
03.01 MUROS Y TABIQUES DE ALBAILERIA 93,479.19 93,479.19
03.02 REVOQUES ENLUCIDOS Y MOLDURAS 162,213.92 97,328.35 64,885.57
03.03 REVESTIMIENTO DE ESCALERAS 8,591.58 8,591.58
03.04 CIELORRASOS 54,445.68 46,278.83 8,166.85
03.05 PISOS Y PAVIMENTOS 75,125.42 75,125.42
03.06 JUNTAS DE DILATACION 3,039.73 3,039.73
03.07 CONTRAZOCALOS Y ZOCALOS 27,438.64 27,438.64
03.08 COBERTURAS 196,117.52 196,117.52
03.09 CARPINTERIA DE MADERA 72,989.95 43,793.97 29,195.98
03.10 CARPINTERIA METALICA 88,864.71 26,659.41 44,432.36 17,772.94
03.11 CERRAJERIA 6,698.59 6,698.59
03.12 VIDRIOS, CRISTALES Y SIMILARES 14,220.10 14,220.10
03.13 PINTURA 115,651.40 57,825.70 57,825.70
03.14 VARIOS, LIMPIEZA, JARDINERIA 10,446.88 10,446.88
03.15 OTROS 6,667.33 6,667.33
04 INSTALACIONES SANITARIAS
04.01 APARATOS Y ACCESORIOS SANITARIOS 17,010.73 9,355.90 7,654.83
04.02 SISTEMA DE AGUA FRIA 11,036.49 11,036.49
04.03 SISTEMAS DE DRENAJE PLUVIAL 25,539.61 25,539.61
04.04 SISTEMA DE DESAGUE Y VENTILACIN 8,922.28 8,922.28
05 INSTALACIONES ELECTRICAS
05.01 SALIDAS PARA ALUMBRADO, TOMACORRIENTES 121,704.45 73,022.67 48,681.78
05.02 INSTALACIN DE ALARMAS CONTRA INCENDIOS 6,280.04 6,280.04
06 INSTALACIN DE COMUNICACIONES Y RED DE DATOS 9,710.99 9,710.99
07 OBRAS COMPLEMENTARIAS
07.01 PLATAFORMA DEPORTIVA CON GRADERO 75,551.32 49,108.36 26,442.96
07.02 CERCO PERIMETRICO CON MALLA Y REJA 11,088.31 11,088.31
07.03 CERCO PERIMTRICO DE ALBAILERA 45,994.42 11,498.61 34,495.81
07.04 RAMPA, GRADAS Y VEREDA PRINCIPAL 50,191.13 30,114.68 20,076.45
08 MOBILIARIO 72,120.00 72,120.00
09 EQUIPAMIENTO 58,362.75 58,362.75
10 FLETES 60,614.11 9,092.12 48,491.29 3,030.70

COSTO DIRECTO 3,225,130.36 96,710.91 287,943.59 274,545.34 328,418.98 430,943.11 316,017.11 565,125.57 271,381.79 380,828.75 273,215.21

GASTOS GENERALES (12.70 %) 409,591.56 12,282.29 36,568.84 34,867.26 41,709.21 54,729.77 40,134.17 71,770.95 34,465.49 48,365.25 34,698.33

UTILIDAD (5.00 %) 161,256.52 4,835.55 14,397.18 13,727.27 16,420.95 21,547.16 15,800.86 28,256.28 13,569.09 19,041.44 13,660.77

SUB TOTAL 3,795,978.44 113,828.75 338,909.61 323,139.87 386,549.14 507,220.04 371,952.14 665,152.80 319,416.37 448,235.44 321,574.31

I.G.V (18.00 %) 683,276.12 20,489.17 61,003.73 58,165.18 69,578.85 91,299.61 66,951.39 119,727.50 57,494.95 80,682.38 57,883.37

TOTAL PRESUPUESTO 4,479,254.56 134,317.92 399,913.34 381,305.05 456,127.99 598,519.65 438,903.53 784,880.30 376,911.32 528,917.82 379,457.68

% AVANCE MENSUAL 3.00 8.93 8.51 10.18 13.36 9.80 17.52 8.41 11.81 8.47

% AVANCE ACUMULADO 3.00 11.93 20.44 30.62 43.98 53.78 71.31 79.72 91.53 100.00
CALENDARIO DE AVANCE DE OBRA
Obra: MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE E INSTALACION DE SANEAMIENTO BASIC0 EN EL CASERIO PAMPAS DE CHAMAN, DISTRITO DE ASUNCION - CAJAMARCA - CAJAMARCA
Consultor: UPN Plazo: 150 das calendarios
Propietario: UPN
Lugar: ASUNCION / CAJAMARCA / CAJAMARCA Fecha: Nov-17

MES 1 MES 2 MES 3 MES 4 MES 5


Item Descripcin Parcial (S/.)

01.01 OBRAS PROVISIONALES 869.09 869.09


01.02 MEJORAMIENTO DE RESERVORIOS (2 UNID) 3683.48 1,675.04 2,008.44
01.03 MEJORAMIENTO DE CASETA DE VALVULAS DE RESERVORIO (2 UNID) 1226.41 500.12 726.29
01.04 MEJORAMIENTO DE PASES AEREOS (3 UNID) 6864.15 2,521.12 4,343.03
01.05 CAPTACION (2 UNID) 11437.25 1,042.98 10,264.52 129.75
01.06 RED DE CONDUCCION 6535.13 685.41 3,843.09 2,006.63
01.07 RED DE DISTRIBUCION 61463.71 604.02 27,115.10 19,267.15 14,477.44
01.08 PASE AEREO L=7.5M (1 UNID) 1936.81 441.50 1,495.31
01.09 TUBO ROMPE CARGA (2 UNID) 399.48 366.82 32.67
01.10 CAMARA ROMPE PRESION (6 UNID) 14245.24 169.69 14,075.55
01.11 VALVULAS DE CONTROL (4 UNID) 2643.03 331.73 2,311.30
01.12 VALVULAS DE PURGA (3 UNID) 1386.65 141.82 1,244.83
01.13 SISTEMA DE CLORACION POR GOTEO (2 UNID) 12303.51 12,303.51
01.14 POZOS DE DRENAJE (69 UNID) 20598.24 576.12 4,043.69 7,731.30 8,247.13
01.15 SANEAMIENTO BASICO 350115.76 4,343.21 60,641.22 116,392.71 52,176.76 116,561.86
01.16 EXPEDIENTE TECNICO SOCIAL 46072.8 2,255.65 11,518.20 11,902.14 11,518.20 8,878.61
01.17 FLETE 60519.17 2,962.92 15,129.79 15,634.12 15,129.79 11,662.55

COSTO DIRECTO 602,299.91 19,487.24 171,096.54 173,063.80 101,549.32 137,103.02

GASTOS GENERALES (12.70 %) 76,492.09 2,474.88 21,729.26 21,979.10 12,896.76 17,412.08

UTILIDAD (5.00 %) 30,115.00 974.36 8,554.83 8,653.19 5,077.47 6,855.15

SUB TOTAL 708,907.00 22,936.48 201,380.63 203,696.09 119,523.55 161,370.25

I.G.V (18.00 %) 127,603.26 4,128.57 36,248.51 36,665.30 21,514.24 29,046.65

TOTAL PRESUPUESTO 836,510.26 27,065.05 237,629.14 240,361.39 141,037.79 190,416.90

% AVANCE MENSUAL 3.24 28.41 28.73 16.86 22.76

% AVANCE ACUMULADO 3.24 31.64 60.38 77.24 100.00