Start Installation

Safety briefing & Toolbox


Preparation Permit approval
meeting

Transfer personnel from AWB


to AHTS & SG101

Mob AHTS to SG101


Slacking Mooring Connect lower wire winch AHTS
Chain to mooring chain
AHTS repositioning, tied bow to
bouy, tied stern to bollard
SG101

Upper wire winch AHTS going


back (Goba) through snatchblock Yes
on SG101

No
Connect primary wire winch
SG101 to end of existing chain
Upper wire winch
AHTS going back Roll in wire AHTS to slack
Connect secondary wire winch (Goba) through chain in front of fairlead
SG101 to existing chain existing mooring
chain
Roll in wire winch SG101

Unlock pin 1st chain stopper

Transferring mooring chain


Roll out wire winch SG101
from SG101 to AHTS

Roll in wire winch AHTS

Rolling up mooring
Unlock chain from shark jaw
chain o/b AHTS

Roll in chain using winch


AHTS

AHTS sail away along DGPS


pattern

No
Cutting existing mooring chain and
Lock chain using shark jaw
connect to new mooring chain

Clean, inspect, and decide Witness by company,


chain to be cut contractor, and class

Cut existing chain using cutting


Yes
torch

Connect old chain with new


chain using d-shackle

Roll out mooring chain from


Unlock shark jaw
AHTS to approach SG101

Roll out wire winch AHTS

AHTS approach to SG101


follow DGPS pattern

Transferring and Hook-Up


Mooring chain from AHTS to Lock shark jaw
SG101

Connect wire winch from


SG101 to mooring chain o/b
AHTS

Roll in wire winch SG101

Roll out wire winch AHTS

Tensioning Roll in wire winch SG101

Mooring chain degree from


fairlead

Load test

SG101 position from DGPS

Lock 1st & 2nd chain stopper

Class Acceptance

Finish