Specification Report to Accompany the Estimate for the Work of Construction of Box Culvert at

Km 19/10 of Alathur-Ariyalur Road (MD-818)

Estimate Amount : Rs.384594.00


Name of Work :-

Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)

Proposal:
Alathur-Ariyalur Road is a important Major District Road. It is maintained by Kunnam
Highways C&M Sub-Division under the control of Perambalur Highways C&M Division. This
road is proposed to improvements which is sanctioned under CRIDP Scheme for the year of
2017-18 Rs. 134.00 lakhs.

EXISTING DETAILS:
The existing structure is Single row of 900mm dia RCC pipe. In this structure is partially
damaged condition . So.it is necessary to reconstruction.

PROPOSAL:
The Reconstruction of the Single cell box Culvert of 1.50 m clear width and 1.50m clear height
is proposed.

FOUNDATION:
The foundation level has been proposed to be fixed at 0.600 metres below the sill level. The
structures below sill level has been proposed with depth of 0.600 metres with M25 Grade
VRCC.below which Base course of 300 mm thick vibrated Cement Concrete M 15 Grade.

SUBSTRUCTURE:
The substructure will be of vibrated reinforced Cement Concrete M25 Grade and the height of
the substructure will be 2.300 metres.

SUPERSTRUCTURE:
TheTop Slab will be of vibrated Reinforced cement concrete of grade M25 to a thickness of

300 mm.

The steel of Fe-500 Grade has been proposed for all the R.C.C. items.

The wearing coat will be of vibrated cement concrete M30 Design Mix for a uniform thickness of
75mm over the Deck Slab.

GENERAL FEATURES:
Further the provisions for the following items have been made in this sub estimate.
Provisions :
1. Earthwork excavation in all classes of soil except hand rock requiring blasting etc., complete
as per relevant standard specification for box culvert.

2. Vibrated Cement Concrete M15 nominal mix 1:2:4 using 40mm ISS HBG graded metal for
levelling course below box culvert portion

3. Vibrated Reinforced Cement Concrete M25 DESIGN MIX using 20mm ISS HBG graded
metal for box culvert.

4. Vibrated Cement Concrete M30 DESIGN MIX using ISS HBG graded metal for wearing coat
over top slabs.

5. Vibrated Cement Concrete M15 nominal mix 1:2:4 using 40mm ISS HBG graded metal for
Parapet

6. Supply and fabrication of Fe-500 Steel for box culvert

7.Sand Filling behind the Abutments and Wings with good river sand

Rates:-

This estimate is prepared as per current schedule of rates for the year 2017-18. On sanction, the
work will be executed as per MORT & H and IRC Specifications and circular instructions by the
higher authorities from time to time.

Assistant Divisional Engineer Assistant Engineer


Highways, C&M, Kunnam. Highways, C&M, Kunnam.
LEAD STATEMENT

Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)

Sl. Cost of Loading


Name of Materials LEAD Conveyance TOTAL
No. Materials Charges

1 CEMENT --- 5318.00 257.53 5575.53

2 Steel --- 36825.00 1832.88 38657.88

3 40mm ISS Metal 23 Km 889.52 190.25 -- 1079.77

4 25mm ISS Metal 23 Km 764.76 190.25 -- 955.01

5 20mm ISS Metal 23 Km 1238.10 190.25 -- 1428.35

6 12mm ISS Metal 23 Km 1148.57 190.25 -- 1338.82

7 6mm ISS Metal 23 Km 572.38 190.25 -- 762.63

8 M-Sand 23 Km 434.29 190.25 -- 624.54

10 Gravel 26 Km 174.29 210.50 384.79


Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)

Lead for Metal from Thuraimangalam Quarry

Way of Road Km 19/10

CT 0.60

NH-226 (Extn) P.M Road Km 0/4-0/0 0.40

NH-45 Km 268/2-274/8 6.60

Ayyalur-Kudikadu-Sathanur Road Km 0/0-13/650 13.65

Iluppaikudi-Sathanur Road Km 0/0-1/4 1.40

Alathur-Ariyalur Road Km 20/2-19/10 0.20

Total 22.85

OR 23.00

Lead for Gravel from Km 264/6 of NH 45

Way of Road Km 19/10

CT 0.40

NH-45 Km 264/6-274/8 10.20

Ayyalur-Kudikadu-Sathanur Road Km 0/0-13/650 13.65

Iluppaikudi-Sathanur Road Km 0/0-1/4 1.40

Alathur-Ariyalur Road Km 20/2-19/10 0.20

Total 25.85
OR 26.00
Lead for Carted Earth from Km 25/6 of Alathur-Ariyalur Road

Way of Road Km 19/10

CT 0.20

Alathur-Ariyalur Road Km 25/6-19/10 5.60

Total 5.80

OR 6.00

LEAD CERTIFICATE
The above Lead particulars are correct and shortest one to the best of my knowledge

Assistant Divisional Engineer, Assistant Engineer,


Highways, C&M, Kunnam. Highways, C&M, Kunnam.
Name of work
Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)

ABSTRACT ESTIMATE

Qty unit Item Description Rate Unit Amount

Earthwork excavation in all classes of soil except soft


disintegrated rock and medium rock not requiring
blasting and hard rock requiring blasting and depositing
on bank with all leads and lifts as per SS20B, including
cost of all labour, equipments and all incidental charges
such as baling our water, providing and maintaining
1 necessary cofferdams, sheeting, shoring bracing and
their subsequent removal, removal of all logs, stumps,
grubs and other deleterious matter and obstructions,
trimming bottom of excavation backfilling, and clearing
the site and disposal of all surplus materials etc.,
complete as per relevant standard specification for
FOUNDATION OF BOX CULVERT

78.72 Cum 115.72 Cum 9109.00

Vibrated cement concrete of grade M15 Nominal Mix


1:2:4 using 40mm ISS HBG metal including cost and
conveyance of all materials to site and cement at site
including cost of formwork, soft water,labour charges for
mixing, transporting, laying and curing concrete,
2
working at depths,Tools and Plants and incidental
charges such as maintaining of protective bunds,
cofferdams, shoring, strutting etc; complete as per
relevant standard specification for BASE COURSE
BELOW BOX PORTION

12.10 Cum 4025.38 Cum 48707.00


Qty unit Item Description Rate Unit Amount

Vibrated Reinforced Cement Concrete of grade M25


DESIGN MIX using ISS size graded HBG metal
including cost and conveyance of all materials to site
including cost of cement at site including cost of
formwork, soft water, labour charges for mixing,
3
transporting, laying and curing concrete , working at
depths , tools and plants and maintaining of protective
bunds, cofferdams, shoring, strutting etc., complete as
per relevant standard specifications, for BASE SLAB,
STEM AND TOP SLAB OF BOX CULVERT.

28.08 Cum 5846.54 Cum 164171.00

Vibrated cement concrete of grade M15 Nominal Mix


1:2:4 using 40mm ISS HBG metal including cost and
conveyance of all materials to site and cement at site
including cost of formwork, soft water,labour charges for
mixing, transporting, laying and curing concrete,
4
working at depths,Tools and Plants and incidental
charges such as maintaining of protective bunds,
cofferdams, shoring, strutting etc; complete as per
relevant standard specification for PARAPETS OVER
BOX culvert

1.05 Cum 4265.38 Cum 4479.00

Supply of fabrication of s-415 steel required for all RCC


items of works involved in the schedule cost of steel at
site fabrication,labour charges for cleaning the rods
straightening, cutting, bending, tying grills, including
5 overlapping to the required length whenever necessary
and placing the reinforcement in position as specified in
the drawings,including cost of binding wire, provision of
spacer bars, cover blocks and all other incidental
charges etc,complete, S-415 grade

2.44 MT 56691.97 MT 138328.00


Qty unit Item Description Rate Unit Amount

Vibrated cement Concrete M30 design mix using ISS


size HBG graded metal including cost and conveyance
of all materials to worksite and cement at site including
all labour charges for fixing concrete, laying, vibrating,
hire charges for tools and plants, compacting, curing
6
with all leads for soft water, including all other incidental
charges formwork cost of remolded expansion joints
and fixing the same in position etc., complete for
wearing coat of 75mm uniform thickness over deck
slab

35.52 Cum 394.14 Cum 14000.00


Qty unit Item Description Rate Unit Amount

Filling behind Abutmants and wings with clean gritty


gravel including cost and conveyance of gravel
toworksite,laying,handling charges and filling in
layers,tamping under optimum moisture content to get
14.32 7 405.06 Cum 5800.00
the maximum density including watering,with all leads
for water and all other incidental charges etc,complete
for filling behind the abutment and wings as per
MORTH No. for filling box culvert Approach.

TOTAL Rs 384594.00

Assistant Divisional Engineer, (H), Assistant Engineer,


Highways, C&M, Kunnam. Highways, C&M, Kunnam.
DETAILED ESTIMATE
Name of work:
Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)
Sl.
Description of work Nos. L B D Contents Quantity
No.
1 2 3 4 5 6 7 8
1 Earthwork excavation in all classes of soil except soft disintegrated rock and
medium rock not requiring blasting and hard rock requiring blasting and
depositing on bank with all leads and lifts as per SS20B, including cost of all
labour, equipments and all incidental charges such as baling our water, providing
and maintaining necessary cofferdams, sheeting, shoring bracing and their
subsequent removal, removal of all logs, stumps, grubs and other deleterious
matter and obstructions, trimming bottom of excavation backfilling, and clearing
the site and disposal of all surplus materials etc., complete as per relevant
standard specification for FOUNDATION OF BOX CULVERT

1 x 1 12.30 3.200 2.00 78.72


78.72
(or) 78.72
Cum
2 Vibrated cement concrete of grade M15 Nominal Mix 1:2:4 using 40mm ISS
HBG metal including cost and conveyance of all materials to site and cement at
site including cost of formwork, soft water,labour charges for mixing,
transporting, laying and curing concrete, working at depths,Tools and Plants and
incidental charges such as maintaining of protective bunds, cofferdams, shoring,
strutting etc; complete as per relevant standard specification for BASE
COURSE BELOW BOX PORTION

RCC Box culvert portion 1 x 1 12.30 2.40 0.300 8.86

Culvert approach 1 x 2 12.00 0.30 0.45 3.24

12.10

(or) 12.10

Cum
Sl.
Description of work Nos. L B D Contents Quantity
No.
3 Vibrated Reinforced Cement Concrete of grade M25 DESIGN MIX using ISS
size graded HBG metal including cost and conveyance of all materials to site
including cost of cement at site including cost of formwork, soft water, labour
charges for mixing, transporting, laying and curing concrete , working at
depths , tools and plants and maintaining of protective bunds, cofferdams,
shoring, strutting etc., complete as per relevant standard specifications, for
BASE SLAB, STEM AND TOP SLAB OF BOX CULVERT.

Bottom Slab 1 x 1 12.00 2.10 0.30 7.56


Side Walls
1 x 2 12.00 0.300 1.500 10.80
Haunches (0.3/2)
2 x 2 12.00 0.150 0.30 2.16
Top slab
1 x 1 12.00 2.10 0.30 7.56

28.08
(or) 28.08
Cum
4 Vibrated cement concrete of grade M15 Nominal Mix 1:2:4 using 40mm ISS
HBG metal including cost and conveyance of all materials to site and cement at
site including cost of formwork, soft water,labour charges for mixing,
transporting, laying and curing concrete, working at depths,Tools and Plants and
incidental charges such as maintaining of protective bunds, cofferdams, shoring,
strutting etc; complete as per relevant standard specification for PARAPETS
OVER BOX culvert

PCC Parapets 1 x 2 2.60 0.45 0.45 1.05


1.05
(or) 1.05
Cum
5 Supply of fabrication of s-415 steel required for all RCC items of works involved
in the schedule cost of steel at site fabrication,labour charges for cleaning the
rods straightening, cutting, bending, tying grills, including overlapping to the
required length whenever necessary and placing the reinforcement in position as
specified in the drawings,including cost of binding wire, provision of spacer bars,
cover blocks and all other incidental charges etc,complete, S-415 grade

For Box section As per steel schedule


1 x 1 2.440 2.44 2.44
M.T
Sl.
Description of work Nos. L B D Contents Quantity
No.
6 Vibrated cement Concrete M30 design mix using ISS size HBG graded metal
including cost and conveyance of all materials to worksite and cement at site
including all labour charges for fixing concrete, laying, vibrating, hire charges for
tools and plants, compacting, curing with all leads for soft water, including all
other incidental charges formwork cost of remolded expansion joints and fixing
the same in position etc., complete for wearing cost of 75mm uniform thickness
over deck slab

Over Deck Slab 1 x 1 11.10 3.20 35.52

35.52 35.52
7 Filling behind Abutmants and wings with clean gritty gravel including cost and
conveyance of gravel toworksite,laying,handling charges and filling in
layers,tamping under optimum moisture content to get the maximum density
including watering,with all leads for water and all other incidental charges
etc,complete for filling behind the abutment and wings as per MORTH No. for
filling box culvert Approach.

Culvert approach 1 x 2 11.10 0.30 2.15 14.32 14.32

Assistant Divisional Engineer, (H), Assistant Engineer,


Highways, C&M, Kunnam. Highways, C&M, Kunnam.
Name of Work:

Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)


DATA
Qty Unit Item Description Rate Unit Amount
CEMENT
PWD APPROVED RATE = 5318.00
Deduct for loading & unloading 83.71+83.71 = Rs. 167.42
= Rs. 5150.58
Storage Charges at 5% of basic cost 5,150.58x0.05 = Rs. 257.53
Cement Cost per MT = 5575.53
Rs. 5575.53/MT
STEEL
PWD APPROVED RATE = Rs. 36825.00
Deduct for loading & unloading 83.71+83.71 = Rs. 167.42
= Rs. 36657.58
Storage Charges at 5% of basic cost 36,657.6x0.1 = Rs. 1832.88
Steel Cost per MT = Rs. 38657.88
Rs. 38657.88/MT
CEMENT MORTAR 1:1.5 (M25) (using 20mm & 12mm)
1 Cu.m Sand 624.54 Cu.m 624.54
0.840 M.T. Cement 5575.53 M.T. 4683.45
TOTAL PER Cu.m Rs. 5307.99
CEMENT MORTAR 1:2 (Using 40mm) (M15)
1 Cu.m Sand 624.54 Cu.m 624.54
0.653 M.T. Cement 5575.53 M.T. 3640.82
TOTAL PER Cu.m Rs. 4265.36
Vibrated CEMENT CONCRETE 1:2:4. M15 Nominal Mixusing 40mm Metal.
9.00 Cu.m Cost of 40mm ISS metal 1079.77 Cu.m 9717.93
4.50 Cu.m Cost of C.M. 1:2 4265.36 " 19194.12
1.80 Nos. Mason II Class 462.12 No. 831.82
17.70 " Mazdoor I Class 322.92 No. 5715.68
14.10 " Mazdoor II Class 291.67 " 4112.55
10.00 Cu.m Vibration Charges 36.17 Cu.m 361.70
TOTAL PER 10 Cu.m Rs. 39933.80
Vibrated REINFORCED CEMENT CONCRETE M25 Design Mix.
6.30 Cu.m Cost of 20mm ISS metal 1428.35 Cu.m 8998.61
2.70 " Cost of 12mm ISS metal 1338.82 " 3614.81
4.50 " Cost of C.M. 1:1.5 5307.99 " 23885.96
3.50 Nos. Mason II Class 462.12 No. 1617.42
21.20 " Mazdoor I Class 322.92 No. 6845.90
35.30 Mazdoor II Class 291.67 No. 10295.95
DATA
Qty Unit Item Description Rate Unit Amount
10.00 Vibration Charges 48.67 Cu.m 486.70
TOTAL PER 10 Cu.m Rs. 55745.35
NAME OF WORK:- DATA FOR BOX CULVERT

Construction of Box Culvert at Km 19/10 of Alathur-Ariyalur Road (MD-818)

1. Earthwork excavation in all classes of soil


except soft disintegrated rock and medium rock
not requiring blasting and hard rock requiring
blasting and depositing on bank with all leads and
lifts as per SS20B, including cost of all labour,
equipments and all incidental charges such as
baling our water, providing and maintaining
necessary cofferdams, sheeting, shoring bracing
and their subsequent removal, removal of all logs,
stumps, grubs and other deleterious matter and
obstructions, trimming bottom of excavation
backfilling, and clearing the site and disposal of
all surplus materials etc., complete as per relevant
standard specification for FOUNDATION OF
BOX CULVERT

1 Cu.m SI. No. 62 Rs. 57.86 Cu.m Rs. 57.86


1 Cu.m Add 100% extra for narrow foundation. Rs. 57.86 Cu.m Rs. 57.86
TOTAL Rs. 115.72
2. Filling behind Abutmants and wings with clean
gritty gravel including cost and conveyance of
gravel toworksite,laying,handling charges and
filling in layers,tamping under optimum moisture
content to get the maximum density including
watering,with all leads for water and all other
incidental charges etc,complete for filling behind
the abutment and wings as per MORTH No. for
filling ubox culvert Approach.

1 Cu.m Cost of Gravel filling 384.79 Cu.m Rs. 384.79


1 Cu.m 20.27 " Rs. 20.27
Labour charges

Rs. 405.06

Rate per cum Rs. 405.06


DATA
Qty Unit Item Description Rate Unit Amount
3. Vibrated cement concrete of grade M15
Nominal Mix 1:2:4 using 40mm ISS HBG metal
including cost and conveyance of all materials to
site and cement at site including cost of formwork,
soft water,labour charges for mixing, transporting,
laying and curing concrete, working at
depths,Tools and Plants and incidental charges
such as maintaining of protective bunds,
cofferdams, shoring, strutting etc; complete as per
relevant standard specification for BASE
COURSE BELOW BOX PORTION
Cu.m Rate for Vib CC M15 nominal mix (1:2:4) 3993.38 Rs. 3993.38
Softwater L.S. Rs. 6.00
Curing Concrete L.S. Rs. 6.00
Hire charges for T&P L.S. Rs. 20.00

TOTAL Rs. 4025.38


Rate per cum Rs. 4025.38
4. Vibrated cement concrete of grade M15 Nominal
Mix 1:2:4 using 40mm ISS HBG metal including
cost and conveyance of all materials to site and
cement at site including cost of formwork, soft
water,labour charges for mixing, transporting,
laying and curing concrete, working at
depths,Tools and Plants and incidental charges
such as maintaining of protective bunds,
cofferdams, shoring, strutting etc; complete as per
relevant standard specification for PARAPETS
OVER BOX culvert
Cu.m Rate for Vib CC M15 nominal mix (1:2:4) 3993.38 Rs. 3993.38
Softwater L.S. Rs. 6.00
Curing Concrete L.S. Rs. 6.00

Centering L.S. Rs. 240.00

Hire charges for T&P L.S. Rs. 20.00

TOTAL Rs. 4265.38

Rate per cum Rs. 4265.38


DATA
Qty Unit Item Description Rate Unit Amount
5. Vibrated Reinforced Cement Concrete of
grade M25 DESIGN MIX using ISS size graded
HBG metal including cost and conveyance of all
materials to site including cost of cement at site
including cost of formwork, soft water, labour
charges for mixing, transporting, laying and
curing concrete , working at depths , tools and
plants and maintaining of protective bunds,
cofferdams, shoring, strutting etc., complete as per
relevant standard specifications, for BASE SLAB,
STEM AND TOP SLAB OF BOX CULVERT.
1 Cum Rate for Vib RCC M25 Design Mix 5574.54 Cum 5574.54
sq.m Formwork and Centering Rs.240.00 Cu.m 240.00
Soft water LS " 6.00
Curing Concrete LS " 6.00
Hire charges for T&P LS " 20.00

TOTAL 5846.54
Rate per cum Rs. 5846.54
6. Supply and fabrication of S-500 steel required
for all RCC items of works involved in the
schedule cost of steel at site fabrication,labour
charges for cleaning the rods straightening,
cutting, bending, tying grills, including
overlapping to the required length whenever
necessary and placing the reinforcement in
position as specified in the drawings, including
cost of binding wire, provision of spacer bars,
cover blocks and all other incidental charges
etc,complete, S-500 grade

1.05 M.T Cost of Tor Steel 38657.88 M.T 40590.77

0.01 " Binding wire 39110.00 Rs. 391.10

35 Nos. Fitter I Class for Fabrication. 448.86 Rs. 15710.10

TOTAL Rs. 56691.97

Rate per tonne Rs. 56691.97


DATA
Qty Unit Item Description Rate Unit Amount
7

Vibrated Cement Concrete of grade M30 design


mix using ISS size graded HBG metal including
cost and conveyance of all materials to siteand
cement at site including all labour charges for
mixing concrete laying,vibrating Hire charges for
Tools and Plants, compacting, curing withall leads
of soft water,including and all other incidental
charges form work cost of premoulded expansion
joints and fixing the same in position etc.,
complete for wearing coat of 75mm uniform
thickness over deck slab and approach slab

0.45 Cum Cost of 25mm ISS 955.01 1 Cum Rs. 429.75


0.17 Cum Cost of 12mm ISS 1338.82 1 Cum Rs. 227.60
0.07 Cum Cost of 6mm ISS 762.63 1 Cum Rs. 53.38
0.34 Cum Cost of Sand 624.54 1 Cum Rs. 212.34
0.29 M.T Cost of Cement 5575.53 1 M.T Rs. 1616.90
1.88 No Mazdoor I Class 322.92 No Rs. 607.09
1.16 No Mazdoor II Class 291.67 No Rs. 338.34
0.43 No Carpenter I Class 504.73 No Rs. 217.03
0.36 No Mason I Class 516.10 No Rs. 185.80
Cost of Curing LS Rs. 6.00
0.75 Vibration charges Rs. 36.17 Rs. 27.13
Hire charges LS Rs. 20.00
Rs. 3941.36
Rate/m2 Rs. 394.14

Assistant Divisional Engineer Assistant Engineer


Highways, C&M, Kunnam. Highways, C&M, Kunnam.
HIGHWAYS DEPARTMENT
SCHEDULE OF RATE
Circle: Villupuram (H) C&M

2017-18
SIZE IRC ISS Crushed Stone Sand (M-Sand) 434.29
90mm 384.76 381.90 Rough stone moasonry work (p-16) 393.33
75mm 429.52 Rough stone for Revertment work (p-16) 340.95
63mm 556.19 493.33 Bondstone (p-17) 567.00
53mm 676.19 US Gravel (p-18) 174.29
46.5mm 907.62 Well Gravel (p18) 142.86
45.0mm 907.62 Sand for (M) & (F) (p-19) 168.00
40.0mm 889.52 Stone dust (p-19) 108.95
37.50mm 926.67 Earthwork (HGS) SS20A (p-24) 61.65
26.5mm 875.24 Earthwork (HGS) SS20B (p-25) 57.86
25.0mm 875.24 764.76 Earthwork (ordy soil) SS20A (p-24) 42.42
22.40mm 1270.48 Earthwork (ordy soil) SS20B (p-24) 38.64
20.0mm 1238.10 Shell lime (p-19) 1223.81
12.00mm 1148.57 Freshly Slaked lime (p-19) 901.90
13.20mm 1178.10 Heavy junglen (p-22) 4.21
11.2mm 800.00 Light jungle (p-22) 3.17
10.0mm 845.71 Scrub jungle (p-22) 2.89
6.70mm 593.33 Binding wire (p-21) 39.11
6.0mm 593.33 572.38 Dismantling Brick (p-22) 133.52
5.6mm 593.33 Dismantling Stone (p-22) 133.52
4.75mm 524.76 Dismantling Cutstone (p-22) 553.98
3.00mm 515.24 Dismantling PCC (p-23) 229.17
Laterite 40 - 75mm Dismantling RCC (p-23) 3475.38
Mix CM (By Manual) (p-32) 59.94

Extra lead (p-25) 7.15 Rate of labour for structures

Extra lift (P-25) 5.68 Mazdoor I class (p-12) 322.92

VCC (P-28) 36.17 Mazdoor II class (p-12) 291.67

VRCC (P-28) 48.67 Mason I class (p-11) 516.10

Filling the sand in Mason II class (p-11) 462.12

empty cement gunny 4.55 Carpenter I class (p-11) 504.73

bag(Labour only) (p-2 Carpenter II class (p-11) 462.12


Filter I class (p-11) 448.86
Filter II class (p-11) 416.67
Estimate
Cement & Steel Basic Rate Painter I Class (p-12) 412.88
Rate
Upto
16mm dia Painter II Class (p-12) 383.52
above 36825.00 38376.64
Steel 16mm dia Stone cutter I Class (p-12) 396.78

Binding 39.11 39.11/Kg Stone cutter II Class (p-12) 366.48


wire
Cement 5318.00 5517.93 Wodder (p-13) 334.28
Refiling with sand (p-25) 17.80

Refiling with soil (other than sand) (p-25) 20.27


Centering Rate for Culvert (Lumpsum) for 1cum. of Concrete
For footings of abutment,Wing in foundation
180
below Sill
For abutment, wing,parapet Above sill level 240

Bed block cum dirt wall Over abutments 360

Deck Slab 420

Centering Rate for Retaining Wall (Lumpsum) for 1 cum. of Concrete

Upto Sill level 120

Above Sill level 180

146th Meeting of the Board of Engineers held on 05.12.2012


@5.30. pm.Revision of Rates of the
Lumpsum provisions in the Bridges Data
SL.No. Description Rate
For Earthwork
1 Formation and maintaining of
30.00
protective bunds and coffer dams
2 Bailing out of water 30.00
3 Refilling sides 28.00
4 Shoring and strutting 25.00
5 Tools and plants 25.00
6 Removal of protective bunds and
20.00
clearing the sites
For concrete works
1 Water Charges for Curing concreate 20.00
2 Hire charges for tools and plants 84.00

Cost of seepage pipes 100mm


1 dia.including labour charges for fixing 180.00
(locale rate)
2 Cost of Kraft papper 55.00
3 Cost of PVC Expansion joint 3000.00
4 PIPE: RCC Pipe 1000mm dia NP3 - 2600.00

5 Cost of RCC Pipe 1000mm dia NP3


6500
(2.50m length)
FIXING PIPE 66.55
6
RCC 1000mm dia NP3 -
7 Cost of G.I Drainage Spout pipe
1250/1 No.
100mm dia.

Filter Media /1 Cum

53mm to 5.75mm IRC Metal


(53mm,46.5mm,45mm,37.5mm,26.5mm,
25mm, 849.76
22.4mm,13.2mm,11.2mm,6.7mm,6mm,5.
75mm)
Refilling labour Charge 20.27
Conveyance Charge
Total