Proposal:
Alathur-Ariyalur Road is a important Major District Road. It is maintained by Kunnam
Highways C&M Sub-Division under the control of Perambalur Highways C&M Division. This
road is proposed to improvements which is sanctioned under CRIDP Scheme for the year of
2017-18 Rs. 134.00 lakhs.
EXISTING DETAILS:
The existing structure is Single row of 900mm dia RCC pipe. In this structure is partially
damaged condition . So.it is necessary to reconstruction.
PROPOSAL:
The Reconstruction of the Single cell box Culvert of 1.50 m clear width and 1.50m clear height
is proposed.
FOUNDATION:
The foundation level has been proposed to be fixed at 0.600 metres below the sill level. The
structures below sill level has been proposed with depth of 0.600 metres with M25 Grade
VRCC.below which Base course of 300 mm thick vibrated Cement Concrete M 15 Grade.
SUBSTRUCTURE:
The substructure will be of vibrated reinforced Cement Concrete M25 Grade and the height of
the substructure will be 2.300 metres.
SUPERSTRUCTURE:
TheTop Slab will be of vibrated Reinforced cement concrete of grade M25 to a thickness of
300 mm.
The steel of Fe-500 Grade has been proposed for all the R.C.C. items.
The wearing coat will be of vibrated cement concrete M30 Design Mix for a uniform thickness of
75mm over the Deck Slab.
GENERAL FEATURES:
Further the provisions for the following items have been made in this sub estimate.
Provisions :
1. Earthwork excavation in all classes of soil except hand rock requiring blasting etc., complete
as per relevant standard specification for box culvert.
2. Vibrated Cement Concrete M15 nominal mix 1:2:4 using 40mm ISS HBG graded metal for
levelling course below box culvert portion
3. Vibrated Reinforced Cement Concrete M25 DESIGN MIX using 20mm ISS HBG graded
metal for box culvert.
4. Vibrated Cement Concrete M30 DESIGN MIX using ISS HBG graded metal for wearing coat
over top slabs.
5. Vibrated Cement Concrete M15 nominal mix 1:2:4 using 40mm ISS HBG graded metal for
Parapet
7.Sand Filling behind the Abutments and Wings with good river sand
Rates:-
This estimate is prepared as per current schedule of rates for the year 2017-18. On sanction, the
work will be executed as per MORT & H and IRC Specifications and circular instructions by the
higher authorities from time to time.
CT 0.60
Total 22.85
OR 23.00
CT 0.40
Total 25.85
OR 26.00
Lead for Carted Earth from Km 25/6 of Alathur-Ariyalur Road
CT 0.20
Total 5.80
OR 6.00
LEAD CERTIFICATE
The above Lead particulars are correct and shortest one to the best of my knowledge
ABSTRACT ESTIMATE
TOTAL Rs 384594.00
12.10
(or) 12.10
Cum
Sl.
Description of work Nos. L B D Contents Quantity
No.
3 Vibrated Reinforced Cement Concrete of grade M25 DESIGN MIX using ISS
size graded HBG metal including cost and conveyance of all materials to site
including cost of cement at site including cost of formwork, soft water, labour
charges for mixing, transporting, laying and curing concrete , working at
depths , tools and plants and maintaining of protective bunds, cofferdams,
shoring, strutting etc., complete as per relevant standard specifications, for
BASE SLAB, STEM AND TOP SLAB OF BOX CULVERT.
28.08
(or) 28.08
Cum
4 Vibrated cement concrete of grade M15 Nominal Mix 1:2:4 using 40mm ISS
HBG metal including cost and conveyance of all materials to site and cement at
site including cost of formwork, soft water,labour charges for mixing,
transporting, laying and curing concrete, working at depths,Tools and Plants and
incidental charges such as maintaining of protective bunds, cofferdams, shoring,
strutting etc; complete as per relevant standard specification for PARAPETS
OVER BOX culvert
35.52 35.52
7 Filling behind Abutmants and wings with clean gritty gravel including cost and
conveyance of gravel toworksite,laying,handling charges and filling in
layers,tamping under optimum moisture content to get the maximum density
including watering,with all leads for water and all other incidental charges
etc,complete for filling behind the abutment and wings as per MORTH No. for
filling box culvert Approach.
Rs. 405.06
TOTAL 5846.54
Rate per cum Rs. 5846.54
6. Supply and fabrication of S-500 steel required
for all RCC items of works involved in the
schedule cost of steel at site fabrication,labour
charges for cleaning the rods straightening,
cutting, bending, tying grills, including
overlapping to the required length whenever
necessary and placing the reinforcement in
position as specified in the drawings, including
cost of binding wire, provision of spacer bars,
cover blocks and all other incidental charges
etc,complete, S-500 grade
2017-18
SIZE IRC ISS Crushed Stone Sand (M-Sand) 434.29
90mm 384.76 381.90 Rough stone moasonry work (p-16) 393.33
75mm 429.52 Rough stone for Revertment work (p-16) 340.95
63mm 556.19 493.33 Bondstone (p-17) 567.00
53mm 676.19 US Gravel (p-18) 174.29
46.5mm 907.62 Well Gravel (p18) 142.86
45.0mm 907.62 Sand for (M) & (F) (p-19) 168.00
40.0mm 889.52 Stone dust (p-19) 108.95
37.50mm 926.67 Earthwork (HGS) SS20A (p-24) 61.65
26.5mm 875.24 Earthwork (HGS) SS20B (p-25) 57.86
25.0mm 875.24 764.76 Earthwork (ordy soil) SS20A (p-24) 42.42
22.40mm 1270.48 Earthwork (ordy soil) SS20B (p-24) 38.64
20.0mm 1238.10 Shell lime (p-19) 1223.81
12.00mm 1148.57 Freshly Slaked lime (p-19) 901.90
13.20mm 1178.10 Heavy junglen (p-22) 4.21
11.2mm 800.00 Light jungle (p-22) 3.17
10.0mm 845.71 Scrub jungle (p-22) 2.89
6.70mm 593.33 Binding wire (p-21) 39.11
6.0mm 593.33 572.38 Dismantling Brick (p-22) 133.52
5.6mm 593.33 Dismantling Stone (p-22) 133.52
4.75mm 524.76 Dismantling Cutstone (p-22) 553.98
3.00mm 515.24 Dismantling PCC (p-23) 229.17
Laterite 40 - 75mm Dismantling RCC (p-23) 3475.38
Mix CM (By Manual) (p-32) 59.94