Vous êtes sur la page 1sur 3

CRONOGRAMA DE DESEMBOLSOS

PROYECTO : REHABILITACION DE LA CARRETERA EMPALME PE-38 TARATA - CANDARAVE-EMP. PE-36A.


TRAMO : CANDARAVE-EMP. CARRETERA BINACIONAL KM 143+500.
UBICACIN : DPTO. TACNA, PROV. CANDARAVE, DIST. CANDARAVE
FECHA : JULIO 2013

ITEM PARTIDA UND. Metrado Precio (S/.) PARCIAL M1 M2 M3 M4 M5 M6 M7 M8


S/. S/. S/. S/. S/. S/. S/. S/. S/.
ADELANTO EFECTIVO 1,432,349.66 1,432,349.66
20.00%

01 TRABAJOS PRELIMINARES 196,240.55


01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 62,601.03 62,601.03 31,300.52 31,300.52
01.02 TRAZO Y REPLANTEO INICIAL km 56.20 1,281.67 72,029.85 9,796.06 9,796.06 9,796.06 9,796.06 9,796.06 9,796.06 9,796.06 3,457.43
01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRAS DE ARTE m2 1,160.20 1.42 1,647.48 352.56 352.56 352.56 352.56 237.24
01.04 LIMPIEZA DE TAJEAS Y/O ALCANTARILLAS EXISTENTES u 22.00 58.21 1,280.62 1,280.62
01.05 ROCE Y LIMPIEZA ha 33.72 1,740.26 58,681.57 32,274.86 26,406.71
02 MOVIMIENTO DE TIERRAS 1,832,930.98
02.01 EXCAVACION MATERIAL SUELTO m3 18,680.40 6.58 122,917.03 122,917.03
02.02 CONFORMACION DE RELLENOS CON MATERIAL PROPIO m3 10,845.50 9.40 101,947.70 101,947.70
02.03 CONFORMACION DE RELLENO CON MATERIAL DE CANTERA m3 75,675.50 15.52 1,174,483.76 375,834.80 516,772.85 281,876.10
02.04 PERFILADO Y COMPACTACION EN ZONA DE CORTE m2 282,000.00 1.50 423,000.00 118,440.00 160,740.00 143,820.00
02.05 REMOCION DE DERRUMBES m3 934.02 9.51 8,882.53 8,882.53
02.06 RELLENO CON MATERIAL PROPIO EN TERRAPLEN m3 207.06 8.21 1,699.96 1,699.96
03 PAVIMENTO 1,629,593.95
03.01 AFIRMADO GRANULAR DE E=0.15 M. m3 52,857.41 30.83 1,629,593.95 130,367.52 472,582.25 472,582.25 472,582.25 81,479.70
04 OBRAS DE ARTE Y DRENAJE 618,718.57
04.01 CUNETAS 397,351.93
04.01.01 CONSTRUCCION DE CUNETAS EN TERRENO SUELTO m 12,622.50 0.93 11,738.93 11,738.93
04.01.02 CONSTRUCCION DE CUNETAS - EMBOQUILLADO DE PIEDRA m 26,594.00 14.50 385,613.00 30,849.04 134,964.55 134,964.55 84,834.86
04.02 ALCANTARILLAS 156,281.44
04.02.01 REMOCION DE ALCANTARILLAS TMC u 3.00 247.79 743.37 743.37
04.02.02 DEMOLICION DE ESTRUCTURA (ALCANTARILLA) m3 10.61 145.56 1,544.39 1,544.39
04.02.03 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 460.20 33.26 15,306.25 2,755.13 10,102.13 2,449.00
04.02.04 ALCANTARILLA TMC D=36" m 32.10 492.98 15,824.66 15,824.66
04.02.05 ALCANTARILLA TMC D=48" m 9.38 753.49 7,067.74 7,067.74
04.02.06 RELLENO DE ESTRUCTURA CON MATERIAL DE PRESTAMO m3 32.80 22.76 746.53 746.53
04.02.07 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 550.50 71.78 39,514.89 23,708.93 15,805.96
04.02.08 CONCRETO CICLOPEO F`C=175 KG/CM2 + 30% DE PIEDRA GRANDE EN CIMENTACION m3 183.60 224.66 41,247.58 41,247.58
04.02.09 CONCRETO SIMPLE FC=175 KG/CM2 EN MUROS m3 96.00 288.07 27,654.72 27,654.72
04.02.10 ESCOLLERA DE ALBAILERIA DE PIEDRA m3 13.55 241.28 3,269.34 3,269.34
04.02.11 MATERIAL GRANULAR COMPACTADO EN ESCOLLERA m3 5.60 77.85 435.96 435.96
04.02.12 MANTENIMIENTO Y REHABILITACION DE ALCANTARILLAS TMC EXISTENTES m2 267.95 10.92 2,926.01 2,926.01
04.03 BADEN 64,109.73
04.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS / BADEN m3 214.00 33.26 7,117.64 2,135.29 4,982.35
04.03.02 ENCOFRADO Y DESENCOFRADO / BADEN m2 19.80 45.38 898.52 898.52
04.03.03 CONCRETO CICLOPEO F`C=175KG/CM2 + 30% P.G. EN BADEN m3 214.00 224.66 48,077.24 48,077.24
04.03.04 JUNTA DE DILATACION CON TEKNOPORT EN BADEN m2 28.20 7.37 207.83 207.83
04.03.05 JUNTAS DE DILATACION CON MORTERO EPOXICO EN BADEN m 94.00 55.01 5,170.94 5,170.94
04.03.06 MATERIAL GRANULAR COMPACTADO EN BADEN m3 33.88 77.85 2,637.56 2,637.56
04.04 CANALES 975.47
04.04.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2.42 33.26 80.49 80.49
04.04.02 ALBAILERIA DE PIEDRA m3 1.30 204.94 266.42 266.42
04.04.03 CONCRETO f'c=175 kg/cm2 m3 0.69 288.07 198.77 198.77
04.04.04 ACERO DE REFUERZO FY=4200 KG/CM2 kg 96.80 4.44 429.79 429.79
05 TRANSPORTE 2,462,402.76
05.01 TRANSPORTE DE MATERIAL GRANULAR (AFIRMADO) D<= 1 KM. M3/Km 51,737.17 5.28 273,172.26 62,829.62 94,244.43 94,244.43 21,853.78
05.02 TRANSPORTE DE MATERIAL GRANULAR (AFIRMADO) D> 1 KM. M3/Km 545,085.87 1.28 697,709.91 97,679.39 202,335.87 202,335.87 195,358.78
05.03 TRANSPORTE DE MATERIAL PARA RELLENO D<= 1 KM. M3/Km 73,230.71 5.28 386,658.15 150,796.68 150,796.68 85,064.79
05.04 TRANSPORTE DE MATERIAL PARA RELLENO D> 1 KM. M3/Km 847,786.18 1.28 1,085,166.31 455,769.85 455,769.85 173,626.61
05.05 TRANSPORTE DE ESCOMBROS D<1KM M3/Km 2,821.21 5.28 14,895.99 14,895.99
05.06 TRANSPORTE DE ESCOMBROS D>1KM M3/Km 3,750.11 1.28 4,800.14 4,800.14
06 BADEN PERMEABLE 204,997.15
06.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 45.85 33.26 1,524.97 1,524.97
06.02 ELIMINACION DE MATERIAL EXCEDENTE m3 52.73 6.59 347.49 347.49
CRONOGRAMA DE DESEMBOLSOS
PROYECTO : REHABILITACION DE LA CARRETERA EMPALME PE-38 TARATA - CANDARAVE-EMP. PE-36A.
TRAMO : CANDARAVE-EMP. CARRETERA BINACIONAL KM 143+500.
UBICACIN : DPTO. TACNA, PROV. CANDARAVE, DIST. CANDARAVE
FECHA : JULIO 2013

ITEM PARTIDA UND. Metrado Precio (S/.) PARCIAL M1 M2 M3 M4 M5 M6 M7 M8


S/. S/. S/. S/. S/. S/. S/. S/. S/.
06.03 ALCANTARILLA TMC 0=48" C=12 m 35.00 766.88 26,840.80 26,840.80
06.04 CONCRETO CICLOPEO F`C=175KG/CM2 + 30% P.G. EN BADEN PERMEABLE m3 733.60 224.66 164,810.58 98,886.35 65,924.23
06.05 JUNTA DE DILATACION CON TEKNOPORT EN BADEN PERMEABLE m2 39.90 7.37 294.06 294.06
06.06 JUNTAS DE DILATACION CON MORTERO EPOXICO EN BADEN PERMEABLE m 133.00 55.01 7,316.33 7,316.33
06.07 MATERIAL GRANULAR COMPACTADO EN BADEN PERMEABLE m3 49.62 77.85 3,862.92 3,862.92
CRONOGRAMA DE DESEMBOLSOS
PROYECTO : REHABILITACION DE LA CARRETERA EMPALME PE-38 TARATA - CANDARAVE-EMP. PE-36A.
TRAMO : CANDARAVE-EMP. CARRETERA BINACIONAL KM 143+500.
UBICACIN : DPTO. TACNA, PROV. CANDARAVE, DIST. CANDARAVE
FECHA : JULIO 2013

ITEM PARTIDA UND. Metrado Precio (S/.) PARCIAL M1 M2 M3 M4 M5 M6 M7 M8


S/. S/. S/. S/. S/. S/. S/. S/. S/.
07 SEALIZACION Y SEGURIDAD VIAL 153,652.78
07.01 SEALES INFORMATIVAS 153,652.78
07.01.01 PANELES DE SEALES INFORMATIVAS m2 3.48 788.07 2,742.48 2,742.48
07.01.02 CIMENTACION DE SEALES INFORMATIVAS u 17.00 875.30 14,880.10 14,880.10
07.01.03 TUBO D=3" m 69.72 157.55 10,984.39 10,984.39
07.02 SEALES PREVENTIVAS u 105.00 403.20 42,336.00 42,336.00
07.03 SEALES REGLAMENTARIAS u 19.00 551.95 10,487.05 10,487.05
07.04 POSTES DE KILOMETRAJE u 64.00 99.47 6,366.08 6,366.08
07.05 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 7.50 8,780.89 65,856.68 8,561.37 8,561.37 8,561.37 8,561.37 8,561.37 8,561.37 8,561.37 5,927.10
08 PROTECCION AMBIENTAL 63,211.57
08.01 PROGRAMA DE EDUCACION AMBIENTAL 1,525.50
08.01.01 EDUCACION AMBIENTAL A POBLADORES u 2.00 1,271.00 2,162.14 847.25 847.25 847.50
08.01.02 EDUCACION AMBIENTAL A TRABAJADORES u 1.00 1,271.00 939.44 1,271.00
08.02 SEALIZACION AMBIENTAL 3,101.58
08.02.01 CARTELES MAYORES u 2.00 1,081.07 2,162.14 2,162.14
08.02.02 CARTELES MENORES u 2.00 469.72 939.44 939.44
08.03 PROGRAMA DE SEGUIMIENTO Y/O VIGILANCIA 40,000.00
08.03.01 PROGRAMA DE SEGUIMIENTO Y/O VIGILANCIA mes 4.00 10,000.00 40,000.00 8,000.00 8,800.00 8,800.00 8,800.00 5,600.00
08.04 PROGRAMA DE CONTINGENCIAS 12,711.86
08.04.01 CONTINGENCIAS POR IMPACTO AMBIENTAL glb 1.00 12,711.86 12,711.86 2,542.37 2,796.61 2,796.61 2,796.61 1,779.66
08.05 PROGRAMA DE ABANDONO DE OBRA 3,585.13
08.05.01 REACONDICIONAMIENTO DEL AREA DEL CAMPAMENTO Y PATIO DE MAQUINAS ha 0.50 5,907.91 2,953.96 2,953.96
08.05.02 REACONDICIONAMIENTO DE CANTERAS Y ACCESOS ha 0.18 3,506.52 631.17 631.17
COSTO DIRECTO 7,161,748.31 224,034.06 149,333.25 1,436,658.63 1,762,526.31 1,522,112.35 922,484.57 843,116.78 301,482.41
GASTOS GENERALES 10.07% 721,188.05 22,560.23 15,037.86 144,671.52 177,486.40 153,276.71 92,894.20 84,901.86 30,359.28
UTILIDAD 8.00% 572,939.86 17,922.72 11,946.66 114,932.69 141,002.10 121,768.99 73,798.77 67,449.34 24,118.59
SUB TOTAL 8,455,876.22 264,517.01 176,317.77 1,696,262.85 2,081,014.81 1,797,158.05 1,089,177.53 995,467.98 355,960.29
IGV 18.00% 1,522,057.72 47,613.06 31,737.20 305,327.31 374,582.67 323,488.45 196,051.96 179,184.24 64,072.85
TOTAL VALORIZACION POR MES 9,977,933.94 312,130.07 208,054.97 2,001,590.16 2,455,597.47 2,120,646.49 1,285,229.48 1,174,652.22 420,033.14
PORCENTAJE 100.00% 3.13% 2.09% 20.06% 24.61% 21.25% 12.88% 11.77% 4.21%
AMORTIZACION 1,432,349.67 44,806.81 29,866.65 287,331.73 352,505.26 304,422.47 184,496.91 168,623.36 60,296.48
TOTAL DE DESEMBOLSO POR MES 9,977,933.94 1,699,672.92 178,188.32 1,714,258.43 2,103,092.21 1,816,224.02 1,100,732.57 1,006,028.86 359,736.66