PROJECT: MIP

WES DESIGN CALCULATION SUBMITTAL LIST & APPROVAL STATUS


MH ENGINEERING | ELECTRICAL DEPARTMENT Last Revised on |2016.12.08
SUBMITTED APPROVAL APP
SERIAL CALULATION CALC. SYSTEM
DATE DATE STATUS
REMARK
1ST 2ND
NO. DESCRIPTION ID NO. NAME 1ST 2ND 1ST 2ND
RESULT RESULT

1. PLEASE SUMIT DETAIL FOR 23GB /CA/DAY


STORAGE SIZE SPECIFING THE RECORDING
CCTV NVR CALCULATION
FRAME PER SECOND AND LIVE STREAMING
1 WORK SHEET - WES 2016.12.07 2016.12.08 RAR
2. THE NVR STORAGE SHALL BE SIZED WITH
(23GB/CA/DAY FOR 30 DAY)
25% ALLOWANCE FOR FUTURE CAMERA
3. PLEASE SPECIFY THE NUMBER OF NVR

OUTSIDE PVC GRID SZING THE NUMBER OF WES CABLE AT EACH


2 SHEET - WES 2016.12.07 2016.12.08 AAN MANHALL SHALL BE INDICTAED ON THE
(30% FILL FACTOR) INTEGRATED COMMUNICATION PIPE PLAN

PA SPEAKER SOUND PRESSURE


3 LEVEL - WES 2016.11.15 2016.12.08 APP
(80dB SPL)

CABLE TRAY SIZING


4 WORKSHEET - WES 2016.11.15 2016.12.08 APP
(25% FILL FACTOR)