2017 Tunneling and TBM Method

TUNNEL BORING MACHINE (TBM) METHOD


There are two major shield methods around: earth pressure balanced (EPB) and slurry type shield machine. Selection of
shield method depends on ground conditions, surface conditions, dimensions of the tunnel section, boring distance,
tunnel alignment and construction period. Both are closed-face type shield machines, meaning the "head" part of machine
is "closed" and separated from the rear part of machine. The "head" has a working chamber filled with soil or slurry
between the cutting face and bulkhead to stabilize the cutting face under soil pressure . The EPB type shield machine
turns the excavated soil into mud pressure and holds it under soil pressure to stabilize the cutting face. It has excavation
system to cut the soil, mixing system to mix the excavated soil into mud pressure, soil discharge system to discharge the
soil and control system to keep the soil pressure uniform. Therefore, EPB may not be applicable for the rocky soil that is
difficult to turn the excavated soil into slurry. It can be used at ground predominated by clayer soil. The slurry type shield
machine, on the other hand, uses the external pressurized slurry to stabilize the cutting face, similar to bored piles or
diaphragm walls using bentonite to contain the trench wall. The slurry is circulated to transport the excavated soil by fluid
conveyance. Besides having excavation system, the slurry type shield machine has slurry feed and discharge equipment
to circulate and pressurize slurry and slurry processing equipment on the ground to adjust the slurry properties.

GENERAL KNOWLEDGE ABOUT TBM TUNNELS

A typical rail tunnel section with its components

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 1/27
03.11.2017 Tunneling and TBM Method

Schematic construction sequence for TBM

A shield machine at factory ready to transport out to the site

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 2/27
03.11.2017 Tunneling and TBM Method

Main components of a shield machine

EARTH PRESSURE BALANCED MACHINE (EPBM)

Schematic representation of EPBM

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 3/27
03.11.2017 Tunneling and TBM Method

Schematic representation of EPBM

Types of cutting face of EPBM

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 4/27
03.11.2017 Tunneling and TBM Method

EPBM circulation system

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 5/27
03.11.2017 Tunneling and TBM Method

Typical site utilization plan for EPBM including working shaft, gantry crane, segment stock yard, tanks, etc.

Section view of the EPBM site utilization

SLURRY TYPE TBM

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 6/27
03.11.2017 Tunneling and TBM Method

Schematic representation of a slurry type shield machine

Cutting head sketch of slurry type shield

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 7/27
03.11.2017 Tunneling and TBM Method

Types of cutting face of slurry type shield

Slurry type TBM: Slurry circulation system

Slurry type TBM: Slurry circulation system

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 8/27
03.11.2017 Tunneling and TBM Method

Slurry type TBM: Slurry circulation system

Slurry treatment plant

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 9/27
03.11.2017 Tunneling and TBM Method

Typical site utilization plan for slurry type TBM including working shaft, gantry crane, segment stock yard, tanks, etc.

Section view of the site utilization for the slurry type TBM

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 10/27
03.11.2017 Tunneling and TBM Method

SHAFT CONSTRUCTION

Shaft construction using diaphragm wall method (C905)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 11/27
03.11.2017 Tunneling and TBM Method

Shaft construction using diaphragm wall method (C905)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 12/27
03.11.2017 Tunneling and TBM Method

Shaft construction using diaphragm wall method (C902). Access stairs, ventilation and passenger hoist are provided.

LAUNCHING AND OPERATION

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 13/27
03.11.2017 Tunneling and TBM Method

Main body of the shield machine being lowered down into launching shaft. From there, the TBM system is to be
assembled and starts boring.

Lowering down the main body of shield machine into launching shaft

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 14/27
03.11.2017 Tunneling and TBM Method

A receiving shaft to accommodate dismentle (right) and assemble (left) TBM at the same time (C902)

Assemble TBM (C902)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 15/27
03.11.2017 Tunneling and TBM Method

The shield machine at work

The function part of TBM (backup) at the rear (C902)

Work Sequece:
Lower main body, cutting head, segment erector, screw
conveyer, tail shield, thrust frame > Assemble TBM >
Erection of reaction frame > Connection of hose and cables
> Installation of 4 to 5 nos. of temp segments > Initial drive
> Completion of initial drive > Modification of TBM including
removal of reaction frame, cradle and temp rings, laying rail
> Main drive > Break through soft eye (reach receiving
shaft) > Dismantle TBM

Notes:
- Gantry crane (for example, 35ton, 45ton) is normally used
crossing the shaft.
- Lower down TBM components to the shaft needs heavy
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 16/27
03.11.2017 Tunneling and TBM Method

lifting. 600ton or 700ton crawler crane is needed.


- TBM production rate depends on soil condition. Normally
at 5-10 m/d.
- Ground improvement is necessary at receiving shaft end
for TBM to pass through (about 3-4m in length). Start end
depends on ground conditions.
- Grouting to the gap between shield skin and segment
following segment installation from ground surface.
- Dismantle TBM can be done in launch shaft after being
transporting back from receiving shaft end to the launching
shaft end, leaving behind shield skin at receiving shaft end.

LINING

The start end of tunnel lining (C902)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 17/27
03.11.2017 Tunneling and TBM Method

Lining segments are being lowered down from shaft to the locomotive

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 18/27
03.11.2017 Tunneling and TBM Method

Close view of segment lining. A typical ring of lining: 1.4m width with 6 segemnts to be joined by bolts. Note that the joint
of neighbouring rings to be staggered (C902)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 19/27
03.11.2017 Tunneling and TBM Method

Locomotive rail (C902)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 20/27
03.11.2017 Tunneling and TBM Method

The locomotive. It transports muck out and segments to and fro from shaft to the TBM (C902)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 21/27
03.11.2017 Tunneling and TBM Method

Completed tunnel with linings. From here, 1st stage concrete, rail track, ventilation, electrical and other cables, etc., starts
installation.

PIPE JACKING

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 22/27
03.11.2017 Tunneling and TBM Method

Pipe Jacking, a smaller scale "TBM" method to lay sewer lines

TBM VIDEO

Tunnel Boring Machine Breakthrough

TBM breaks through soft eye

TBM TERMINOLOGIES

Backfill Grouting (tailskin grout): Grouting to fill void between the lining and the ground (tail void) by grout injection
Cycle Time: Segment erection > excavation / backfill grouting > segment erection
EPB: Earth Pressure Balance (Shield Machine)
Goliath Crane: Gantry crane

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 23/27
03.11.2017 Tunneling and TBM Method

Segment, Ring and Lining:


Segment: a splice of precast concrete to form part of ring structure. This ring is also called primary lining. The inside
surface is sprayed with concrete, usually for waterproofing and finishing. Also called secondary lining. Segment > Lining
(primary, secondary), or ring
Shaft:
- To allow muck taken out, lining material brought in, TBM lowering in and assembly, reaction force at the start, operation
space
- Launching shaft, intermediate shaft, receiving shaft, turning shaft
Screw Conveyor: Carry excavated rocks and earth from cutting face to the rear of the completed tunnel
Muck: Soil slurry
Overburden: Distance from top point of tunnel to the surface of ground. Usually 1 - 1.5D
TBM: Tunnel Boring Machine

MAIN REFERENCES
1. Japanese standard for shield tunneling, third edition, 1996.
2. Mitsubishi Heavy Industries catalogue, 2005.
3. DTL 1 C902 (main contractor: Shanghai Tunnel), C905 (main contractor: Shimizu).

NEW AUSTRIAN TUNNELING METHOD (NATM)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 24/27
03.11.2017 Tunneling and TBM Method

The New Austrian Tunneling Method (NATM), an alternative and cheaper way for tunneling.

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 25/27
03.11.2017 Tunneling and TBM Method

NATM support tubes installation (double layer)

NATM support tubes installation (single layer)

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 26/27
03.11.2017 Tunneling and TBM Method

NATM support system sketch

MAIN REFERENCES
Basler&Hofmann's catalogue

http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 27/27