Académique Documents
Professionnel Documents
Culture Documents
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 1/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 2/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 3/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 4/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 5/27
03.11.2017 Tunneling and TBM Method
Typical site utilization plan for EPBM including working shaft, gantry crane, segment stock yard, tanks, etc.
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 6/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 7/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 8/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 9/27
03.11.2017 Tunneling and TBM Method
Typical site utilization plan for slurry type TBM including working shaft, gantry crane, segment stock yard, tanks, etc.
Section view of the site utilization for the slurry type TBM
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 10/27
03.11.2017 Tunneling and TBM Method
SHAFT CONSTRUCTION
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 11/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 12/27
03.11.2017 Tunneling and TBM Method
Shaft construction using diaphragm wall method (C902). Access stairs, ventilation and passenger hoist are provided.
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 13/27
03.11.2017 Tunneling and TBM Method
Main body of the shield machine being lowered down into launching shaft. From there, the TBM system is to be
assembled and starts boring.
Lowering down the main body of shield machine into launching shaft
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 14/27
03.11.2017 Tunneling and TBM Method
A receiving shaft to accommodate dismentle (right) and assemble (left) TBM at the same time (C902)
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 15/27
03.11.2017 Tunneling and TBM Method
Work Sequece:
Lower main body, cutting head, segment erector, screw
conveyer, tail shield, thrust frame > Assemble TBM >
Erection of reaction frame > Connection of hose and cables
> Installation of 4 to 5 nos. of temp segments > Initial drive
> Completion of initial drive > Modification of TBM including
removal of reaction frame, cradle and temp rings, laying rail
> Main drive > Break through soft eye (reach receiving
shaft) > Dismantle TBM
Notes:
- Gantry crane (for example, 35ton, 45ton) is normally used
crossing the shaft.
- Lower down TBM components to the shaft needs heavy
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 16/27
03.11.2017 Tunneling and TBM Method
LINING
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 17/27
03.11.2017 Tunneling and TBM Method
Lining segments are being lowered down from shaft to the locomotive
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 18/27
03.11.2017 Tunneling and TBM Method
Close view of segment lining. A typical ring of lining: 1.4m width with 6 segemnts to be joined by bolts. Note that the joint
of neighbouring rings to be staggered (C902)
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 19/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 20/27
03.11.2017 Tunneling and TBM Method
The locomotive. It transports muck out and segments to and fro from shaft to the TBM (C902)
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 21/27
03.11.2017 Tunneling and TBM Method
Completed tunnel with linings. From here, 1st stage concrete, rail track, ventilation, electrical and other cables, etc., starts
installation.
PIPE JACKING
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 22/27
03.11.2017 Tunneling and TBM Method
TBM VIDEO
TBM TERMINOLOGIES
Backfill Grouting (tailskin grout): Grouting to fill void between the lining and the ground (tail void) by grout injection
Cycle Time: Segment erection > excavation / backfill grouting > segment erection
EPB: Earth Pressure Balance (Shield Machine)
Goliath Crane: Gantry crane
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 23/27
03.11.2017 Tunneling and TBM Method
MAIN REFERENCES
1. Japanese standard for shield tunneling, third edition, 1996.
2. Mitsubishi Heavy Industries catalogue, 2005.
3. DTL 1 C902 (main contractor: Shanghai Tunnel), C905 (main contractor: Shimizu).
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 24/27
03.11.2017 Tunneling and TBM Method
The New Austrian Tunneling Method (NATM), an alternative and cheaper way for tunneling.
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 25/27
03.11.2017 Tunneling and TBM Method
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 26/27
03.11.2017 Tunneling and TBM Method
MAIN REFERENCES
Basler&Hofmann's catalogue
http://www.p3planningengineer.com/productivity/tunneling/tunneling.htm 27/27