Total price

no Item Breakdown unit Flag / price


(USD)
Installation site location KAPPANG southern Sulawesi
1 Installation ( first Tech Support 1 400 400
setup)
Co Tech support 1 250 250
Telco 1 50 50
Labor 2 50 100

2 Logistic Air Transportation 4 175 700


Ground / sea transportation 1 250 250
Accommodation 3 60 180
Tech logistic 2 75 150

3 material Installation material 1 30 30


Civil work If any reimburse

4 unexpected costs Equipment handling If any reimburse


Cable running / work permit If any reimburse
Building management permit If any reimburse
Delay due to unexpected situation (delays due If any reimburse
to the consumer or licensing issues and others)
installation on site without prior survey 1 200 200

Grand Total 2310


Maintenance site location KAPPANG southern Sulawesi (incidental)
1 Corrective Tech Support 1 200 200
Maintenance
Air Transportation 2 175 350
Ground / Sea Transportation 1 200 200
accommodation 3 60 180
Tech logistic + installation material 1 75 75
Total 1 1005
Preventive Maintenance + full year remote support, site location KAPPANG Southern Sulawesi
2 Preventive Tech Support 1 175 175
maintenance
Air Transportation 2 175 350
Ground / Sea Transportation 1 200 200
accommodation 2 60 120
Tech logistic + installation material 1 75 75
Total 2 920
Site Survey site location KAPPANG (Southern Sulawesi)
1 Site survey Tech Support 1 150 150
Air Transportation 2 175 350
Ground / Sea Transportation 1 200 200
accommodation 2 60 120
Tech logistic 2 30 60
880
Total price
no Item Breakdown unit Flag / price
(USD)
Installation for site location JAKARTA
1 Installation ( first Tech Support 1 400 400
setup)
Co Tech support 1 250 250
Telco 1 50 50
Labor 2 50 100

2 Logistic Air Transportation


Ground / sea transportation 1 100 100
Accommodation
Tech logistic 2 75 150

3 material Installation material 1 30 30


Civil work If any reimburse

4 unexpected costs Equipment handling If any reimburse


Cable running / work permit If any reimburse
Building management permit If any reimburse
Delay due to unexpected situation (delays due If any reimburse
to the consumer or licensing issues and others)
installation on site without prior survey 1 200 200

Grand Total 1280


Maintenance for site location JAKARTA (incidental)
1 Corrective Tech Support 1 200 200
Maintenance
Air Transportation
Ground / Sea Transportation 1 100 100
accommodation
Tech logistic + installation material 1 75 75
Total 1 375
Preventive Maintenance + full year remote support, for site location JAKARTA
2 Preventive Tech Support 1 175 175
maintenance
Air Transportation
Ground / Sea Transportation 1 100 100
accommodation
Tech logistic + installation material 1 75 75
Total 2 350
Site Survey site location JAKARTA
1 Site survey Tech Support 1 175 175
Air Transportation
Ground / Sea Transportation 1 100 100
accommodation
Tech logistic 2 30 60
325