Vous êtes sur la page 1sur 4

Client briefing note | 25 November 2016

Myanmars big LNG deal is slowly taking


shape. The World Bank organized a
workshop in Nay Pyi Taw to report on
the outcome of a pre-feasibility. Here in
our analysis.

We are a network of leading law and


tax advisory firms with offices in Myanmar LNG Project Update:
Cambodia, Indonesia, Laos, Myanmar
and Vietnam. Observations on the World Banks
Our general areas of practice are
corporate, finance and disputes.
Workshop of 10 November 2016
Our principal specialized areas Workshop organized as
of practice are energy and approximately 100 Expressions of Highlights of this note
infrastructure, real estate, telecom Interest were received
and taxation. Workshop organized as approximately
The World Bank organized a workshop in
There are three things you need to 100 Expressions of Interest were
know about our approach: Nay Pyi Taw on 10 November 2016 (the
Workshop) to report on the outcome of a received
1. We deliver the ultimate in pre-feasibility study done by MJM Energy
ground connectivity. for the World Bank. The study focused on This is a big, big deal
2. Our quality is trusted by the options for LNG purchase by Myanmar
And a complex deal
most discerning. and on the prima facie merits of three
designated possible LNG terminal sites. No long term LNG contracts to purchase
3. We never give up. The workshop comes after the newly
formed LNG Business Tender Committee LNG?
of the Ministry of Electricity and Energy
(MOEE) requested for Expressions of They seem focused on an FSRU, for
Interest (EOI) in the bulk supply and/or now
terminal of LNG in Myanmar (the Project).
Possible sites for the FSRU
By the deadline, which passed Friday
last week on 28 October 2016, the MOEE Its all about the pipeline
received approximately one hundred
How about the schedule for the Project?
EOIs from traders, upstream companies,
shipping companies, infrastructure How about the schedule for the Project?
providers and combinations of the above.
When can we expect the Request for
Although the Workshop was definitely
about the LNG project, it was not about the Proposal?
tender process. The World Bank executives
What about the integrated power angle?
did not want to entertain any questions
about commercial or timing aspects of the Some key Myanmar issues to consider
tender, which is not surprising since the
IFC will be taking the lead on that aspect of
the project. Nevertheless, the assumptions
and opinions expressed by the study
group do indicate some direction for the
forthcoming Project, although we do
need to understand that these are just
indications.
In this memo, we provide our observations
Page 1
on the World Bank Workshop and we supply gap needs to be taken up by No long term LNG contracts to
look ahead to the tender for the Project gas-fired power plants. That is a matter purchase LNG?
planned for next year. of Government policy, and it depends
on how many hydros and coal will get The invitation to submit an EOI did not
This is a big, big deal through. The existing energy plans betray whether the Project would be
(including the ones provided by E.GEN primarily about LNG supply or about
Officially, at this stage only a pre-feasibility and METI) assume that coal and hydro will infrastructure. It called for companies with
study has been done. So, we do not know provide the main source of generation. experience in both.
for sure what LNG volume we are talking It is now increasingly clear that those
about for the Project, and the World Bank plans are no longer current. Large scale At the Workshop this moved quite a bit
is not yet taking any position on actual hydropower projects may present social into the infrastructure direction. It was
demand. But the capacity of the FSRU challenges the likes of which are new to revealed that if it is up to the consultants,
which was featured in the study is 500 Myanmar. Plus, it seems coal projects are there is no need for Myanmar to procure
MMSCFD, which is nearly 3.5 MTPA. That all but dead in the water, until further LNG under long term contracts. Increasing
is larger than we expected and larger notice. So how much gas is needed to fill volumes of LNG are available on the spot
than any of the existing LNG receiving the gap left by (possible delays in) hydro market. Myanmar could purchase LNG
terminals in Indonesia right now, to and coal? To illustrate the uncertainties, on the spot market or under 1 or 2 year
name a place (Nusantara Regas Satu has consultants at the workshop pointed out contracts. In due course, Myanmar could
a 3 MTPA capacity, Lampung FSRU has that the competing energy plans findings develop a portfolio of purchase contracts
1.8 MTPA and ArunRegas has 1.5 MTPA vary from 1.8 MTPA to 8.4 MTPA when it at various tenures in stages, like Pakistan,
capacity). comes to need for LNG import. As was the experts argued.
mentioned above, the World Bank did not
One of the key uncertainties, the study take a view on actual LNG demand. Separately from the supply, the
group explained, is that no one knows for Government (or the natural gas off-takers)
sure yet how much gas Myanmar will really Anyway, if this number ends up in the RFP, would conclude a tolling agreement with
need to generate power in the future. That this would be the largest energy project in the terminal for the regasification, and the
is to say, it is clear that (i) the demand for Myanmar, by far. At this kind of capacity, Government could build, or have built,
electricity far exceeds current supply, and including the storage and the needed the necessary pipelines.
will grow at least 15% per year and (ii) the pipelines (more on that see below),
production of domestic gas in Yadana and excluding any power infrastructure, Now, there is no way of knowing whether
Zawtika is already declining. But many of the World Bank consultants calculated the actual RFP will drop medium-to-long
the other elements we need to make an about up to a billion US$ in capex and term LNG supply in favor of spot. With gas
informed decision are unknowns, and discounted expenditure, much of which is taking over a large portion of the planned
some will stay that way for a while. For pipeline costs. electricity supply, the MOEE might choose
starters, when will recent discoveries in A6 for energy security.
and A7 translate into more domestic gas And a complex deal
becoming available, perhaps eliminating They seem focused on an FSRU, for
the need for imported LNG? It is hard to It is not only a big deal, it is also a complex now
predict when this will happen, and what deal. Much more complex than Myanmar
the volumes will be. is used to in the few years the country has The study looked both at an onshore
been opened to foreign investment in the terminal and at an FSRU solution. The FSRU
One factor we could actually narrow energy sector. This is project upon project solution came out as better in line with
down is how much of the electricity upon project. We have power generation the Governments timing expectations.
facilities, we have a pipeline (could be The discussion of the suitability of the
more than 500 km) and we have the possible sites from thereon focused on
terminal/FSRU (which will need marine the FSRU, most likely a lease. With these
facilities). kinds of volumes, that is perhaps not
surprising. The duration of the Project,
All of these three projects, needed to more than 5 year and less than 15 year,
match seamlessly, are still in the very early is also conducive of a temporary solution
stages. As for the power generation, the rather than a permanent one.
ones that need to purchase the natural
gas, we believe that more concessions The preliminary site studies all focused on,
will be needed than the ones currently for a large part, whether it was suitable to
granted. In other words, not all the place an FSRU there in terms of met-ocean,
offtakers have been given a license yet. navigation and weather conditions.
And for those that do have a license, most
did not yet reach financial close. So, they During the workshop some questions
might not exist yet by the time we kick off were raised by the attendants on
the tender. transmission versus pipeline, and smaller
quantities, but the experts could say little
This is all doable, but it is not easy. about it as these were outside of the
Especially not in Myanmar (see below for scope of this particular study.
more details).

Page 2
Possible sites for the FSRU

The Government gave the consultants 3 potential areas to look at and compare. Each area
had two or more potential sites.

The Government gave the consultants 3 potential areas to look at and compare. Each area
had two or more potential sites.

1. Three sites in Rakhine


2. Two sites in Ayawaddy
3. Three sites in Mon state

After comparing metocean, navigation, weather, pipelines, local infrastructure and


environmental and social aspects, the consultants came to the preliminary finding that the
sites Rakhine and Mon State would both be suitable, and the sites in Ayawaddy somewhat
less so. However, for the site in Rakhine the pipeline would be very long, making that site
almost certainly more expensive from a capex perspective than the sites in Mon State. So,
that would leave one of the sites in Mon State as the better choice from the three for now.

However, the World Bank made it clear that alternative sites might be possible. We think it
is likely bidders can propose their own site as well.

Its all about the pipeline have to be granted.

The most important factor in the capex of the Project is the new pipeline which will be First of all, the MOEE would have to
needed. For a certain site access to the Shwe pipeline could be negotiated, but even then compensate for all but eliminating coal
a new 30 pipeline would have to be installed on existing routes to Yangon as the existing fired plants from the energy master
one is too small. The Mon State site offers the possibility of deploying a subsea cable, plans, if that is indeed what is happening.
which may be easier in terms of obtaining rights of way, and shorter, but it is also relatively Secondly, the volume of LNG to be
more expensive. imported which the MOEE and the World
Bank used in the pre-feasibility, although
just a working assumption, is aimed at
Site Length of pipelinein km
approximately 2,500MW. Assuming that
1 Rakhine Between 475 to 557 there will still be a significant portion
of domestic gas available as well in the
2 Ayawaddy 235 future, this is more than currently in the
works around Yangon.
3a Mon State (over land) 410
3b Mon State (subsea) 225 But whether an IPP would be included
in the tender itself, that is a whole other
How about the schedule for the Project? question. At this stage, it seems unlikely to
us. Based on what we know of the internal
The study group took the view that a solution could be in place within (at least) 3 years. workings of the MOEE, it would be more
One year for studies, permitting and financing and two years of engineering, procurement likely that new IPPs will be tendered by
and construction. That is if all goes well. the DEPP, or that the DEPP will simply take
up a newly negotiated proposal from an
Based on our experience, it is likely that more than one year is needed in Myanmar to IPP.
reach to financial close on a project of this nature. Lead times for land acquisition and land
permitting, port terminal permits and for obtaining the critical Government guarantee Some key Myanmar issues to consider
(which may require parliamentary approval, and a budget cycle in and of itself takes
nearly 1 year) are substantial. By comparison, the Myingyan gas-fired power project, also As I pointed out on the panel at the
with IFC support, took quite a bit more than one year to get through and that project is Workshop, there are a few key Myanmar
much smaller and less complex than what is contemplated here. legal issues that require particular
attention in connection with the Project,
When can we expect the Request for Proposal? at least the way it is (preliminarily) shaping
up.
The World Bank would not say. Based on what the MOEE tells us, mitigated with our own
experience with other MOEE tenders, our best guess is that the RFP might come out at the Government guarantees, more than
earliest in April 2017. As everything else right now, that date must be read with plenty of likely needed, are largely untested
flexibility. and may determine the schedule:
Actual Government guarantees (to
What about the integrated power angle? be distinguished from contractual
commitments) in Myanmar are
Of course, the Project is all about gas-to-power. But, in the site analysis, no mention was governed by the Public Debt
made of the need or the possibility to add an IPP near the terminal. Nevertheless, there are Management Law 2016 (PDML).
some indications that in the context of this Project, additional concessions for CCGTs will Such guarantees are largely untested

Page 3
in practice as the budget is now on a more promising. Related vDB LOI Publications
strictly cash basis. Under the PDML,
which confirmed a practice already Coordination with other Ministries will be Client Alert: Clock is ticking
in place with the annual National key: Many more state departments will to submit your proposal to
Budget Laws, the Ministry of Finance be needed to get a project of this nature the Myanmar Investment
can provide guarantees or something through, and it can be recommended Commission
resembling a guarantee for debt to to get them involved from the planning What Changes in Practice under
any person, association of persons or stage. Of particular note is the Myanma the New Investment Law?
project in accordance with such terms Port Authority and the Ship Registration
and conditions as may be approved Department, both of the Ministry of Myanmar Government Seeks
by the Government and the [National Transport and Communications, which LNG Partnership: Key Things
Assembly] (s. 30 PDML). Government will regulate the jetty, the terminal, the To Know for Your Expression of
debt means all the debt obligations FSRU and the vessels supplying the LNG. Interest
arising from the borrowing or the Also of note is the Ministry of Commerce
promise of payment by Central Bodies, which needs to issue the LNG import
Union Ministries and organizations licenses. Finally we should bring in the Download
in their charge, the Government or Customs Department and the Internal
government-guaranteed debt Revenue Department, needed to
Get to the point.

(s. 2 PDML). The budget cycle, with narrow down the current uncertainties Energy and Infrastructure

the financial year ending 31 March concerning the tax imposts on the
The energy and infrastructure team in our firm has one goal:
using the unique local knowledge and relationships we have
spent years building up, to give your deal the edge. We are the
ultimate in ground connectivity.

International financial institutions are confident in our

of each year, will have an impact on Project.


advice, choosing us for several of their largest-ever financing
transactions in our markets. Governments trust us to act for them
on their privatizations and private sector partnerships.

Our ability to navigate government administrations is

the schedule of the Project. So, the


exceptional, saving precious time on approval processes and
improving the transparency of infrastructure projects.

Ministry of Finance (now the Ministry Will the Government want an equity Cambodia
Indonesia
Laos

of National Planning and Finance) can stake? As we explained in our previous


Myanmar
Vietnam

indeed provide guarantees but within note on the Project, the MOEE, Commercially creative firm with very high standards. It has advised

yet to be drafted terms and conditions particularly the energy side, has
on the tender process and financing for various infrastructure projects,
as well as the privatisation of state-owned entities.
Legal 500

which need to be approved by the traditionally received an equity stake in Experience in Energy
National Assembly. its projects with foreign investors. The and Infrastructure
previous Union Minister even supported
https://goo.gl/BFMLEK
Securing land rights for the site and this practice by introducing regulations
for the pipeline may be challenging: under the Foreign Investment Law
Although nearly all the land in requiring foreign investors in certain
Our offices in Myanmar
Myanmar is state-owned, the MOEE energy sectors to conclude joint ventures
does not manage much of it. In most with the MOEE. One of the more recent
cases, land rights for sites must be such joint ventures is National Energy
secured from other state actors such Puma Aviation, a joint venture between
as states and regions (Myanmar is a one of the SOEs of the MOEE and Puma.
Union of 14 states and regions) or The Managing Director (MD) of the
other national ministries. This is very MOGE, U Myo Myint Oo, brought this
a long process. Furthermore, right of up when he joined the panel at the
way for pipelines and transmission has Workshop, raising speculation that there
become increasingly difficult in recent might be some expectations or plans in
years amid social opposition (not in this regard. The MD also touched upon YANGON
my backyard) and environmental possibly seeking financing to construct Level 8, Centrepoint Towers
concerns. We think that a subsea the pipeline as well as to fund the equity No. 65 Sule Pagoda Road & Merchant
pipeline solution is therefore all the stake into the Project company. Street, Kyauktada Township
T: +95 137 1902 / +95 137 1635
F: +95 124 1238

Contact
Edwin Vanderbruggen is the senior partner of VDB
Loi in Myanmar. He and his team assist the Myanmar
Government with transactions and privatizations in
the energy, transport and communications areas.
He has advised 4 of the supermajors on their oil and
gas interests, worked on several farm-ins in recent
years and is acting on the proposed purchase of a
producing gas and pipeline interest. NAY PYI TAW

Edwin Vanderbruggen Edwin is highly praised by peers and clients alike No. S-204, Tha Pyay Kone Ward
Partner, VDB Loi Zabu Thiri Township
as a seasoned and informed professional (Asia
edwin@vdb-loi.com T: +95 678 108 091
T: +95 137 1902 Law) with very high standards (Legal 500) while F: +95 678 108 092
+95 137 1635 the firm is widely considered a power house (Asia
www.vdb-loi.com Law).
Page 4

Vous aimerez peut-être aussi